Você está na página 1de 1

HATCH MOTT.

qxd:Layout 1 1/19/09 10:30 AM Page 194

UPPER NORTHWEST INTERCEPTOR SECTIONS 1 AND 2 TUNNEL PROJECT


The Upper Northwest Interceptor
Sections 1 and 2 Tunnel project
features PVC liner inside each
segment, providing significant
cost savings for the owner.

Sacramento’s Tunnel Vision


The Upper Northwest Interceptor Sections 1 and 2 Tunnel in Sacramento will provide the final 3.6 miles
of a 20-mile wastewater pipeline project serving California communities.

By Kate Burrows unique solution using segmental pipe lined with PVC on

W hen San Francisco-based engineering firm URS


Corp. commenced work on the Upper North-
west Interceptor Sections 1 and 2 Tunnel proj-
ect, even the most experienced professionals in the industry
were intrigued by its unique design. The 3.6-mile-long tunnel
the interior face of each segment,” Gambino continues.
Using PVC will help ensure the project is completed on
time and within budget, URS Regional Tunnel Practice
Manager Galen Klein says. Traditional tunneling projects pro-
vide corrosion protection by first constructing the tunnel
will become the first tunnel of its kind to feature concrete with a temporary lining and then installing a pipe that
segments with integral PVC corrosion protection. already includes some form of corrosion protection within
According to URS Project Geotechnical Engineer Sam the tunnel.
Gambino, employing a PVC liner significantly reduces risk “This process would require the tunnel to be larger,” Klein
for the client. “When we first began the design of the proj- says. “It would require a second stage of construction to
ect, it was conceived that it would be constructed with pipe install the pipe and provide the backfill grouting, which
jacking, which would require the con- is much more expensive. Using PVC on segments has been a
Upper Northwest Interceptor struction of multiple shafts adjacent to a huge benefit to the client.”
Sections 1 and nearby levee,” Gambino explains. “Since
2 Tunnel project this method would increase the client’s Achieving its Goals
www.srcsd.com/prj-unwi-1-
2.php risk on the project, we looked at alterna- Although the project is on its way to meeting its expected
Project value: $100 million tive methods of construction.” completion date in 2010, maintaining scheduling goals has
Location: Sacramento, Calif. The tunnel will require only one work- not been easy.
Employees at peak: 100
Patrick Doig: “We’ve had a great ing shaft at each end, rather than multiple The project team encountered a number of environmen-
team on this project.” shafts along the way. “URS proposed a tal challenges that required adjustments to the schedule.

194 ■ WWW.CONSTRUCTION-TODAY.COM ■ FEBRUARY 2009

Você também pode gostar