TRANSMITTAL

(1) Contract No. (2) Project Name (3) Contractor (4) To (5) COPY to (6) Subject

: CPEPIICBIO1 : Colombo Port Expansion Project : Hyundai Engineering & Construction Co., Ltd.

: CRE, Scott Wilson : Project Director, Sri Lanka Ports Authority : Method Statement 48 for Sand Compaction, HDPE Sheet and

Amour Rock (Sea Side) Placing - Rev.1 (7) Conb.actors File No. : HDEC/CPEP/11/4129 The following islare submitted :
Description (8) Document Date (9) Transmittal No. (10) No. Copies (1 1)

1. Method Statement 48 for Sand Compaction, HDPE Sheet and Amour Rock (Sea Side) Placing- Rev. 1

08'~ March 201 1

One (1) Copy

(12) Remarks : Further to our transmittal ref. No. HDEC/CPEP/1114078 dated 23rd February 2011. we hereby submit the revised "Method Statement for Sand Compaction,

(13) Signed (15) Name

: Hvung Kim

(14) Date : Osth March 201 1 (16) Title : Proiect Director

" Having checked this submission, I certifi that it confirms to the requirements o f the Contract in all respects, expect as otherwise indicated."
Employer's Representative's Comments/Response:

Attach additional sheets as necessary. Signed : Name : Date : Title :

* Note :
M
D C Management Design Construction Environmental Survey FI UR CR FS FC For information and by the Employer's Representative Upon Request For Contract Records For Approval For consent by the Engineer's Representative

Method Statement Register


[Colombo Port Expansion Project I S r i Lanka] Submission I Revision No. Method No. Method Description Ref. No. Method Statementsfor CoreLoc Crack Repairing Using Epoxy HDECICPEPH012265
0

1 Date 9.Jan.10

Ref. No.

Date

2 Ref. No. Date

3
Ref. No. Date

Remarks

HDECICPEPH012451 10.Feb.10 No Response

Method Statements for Backfillingof Submarine Pipeline Trench Method Statements for Submarine Pipeline Trench Badmlling for Hydro Test Method Statements for Demolitionof Chain Link Fence

HDECICPEP/l0/2280

12.Jan.10 No Response HDECICPEPH012657 13.Mar.10

1 HDECICPEPHOR711
I

2O.Mar.10

1
I 1

No Response Wolk Finished

Method Statements for Demolitionof Existing SAGT Boundary Wall

+HDECICPEPH012750 27.Mar.10 HDECICPEPH012822 10Apr.10 HDECICPEPHOI3178 23.Jun.10 HIWI80101H136 HDECICPEPHOI3178 HIWi80101H140 3.Aug.10 10.Ju1.10 5.Aug.10 28.Ju1.10 10.Sep.10

HDECICPEPHOR731 24.Mar.10

HDECICPEPHOI3129 16.Jun.10 HIWi85107101147 10.Aug.10 7.Aug.10

-+
I
Wolk Finished No Resoonse Conditionally Approved Conditionally Approved

59

COLPOIMS1038

Method Statements for Core-Loc Crack Repair Using Epoxy Filling r y Method Statements for Secondary ~ e a b a t e~ u a Wall ~ l m k Fabrication
~e.~d statements for Secondary ~ ~ ~ k ~ w c placing (up to o a t ~ ~ k Ch.5m,

HDECICPEPH013386

60

COLPO(MS1039

1 1
61
62 63

COLPOiMSRlO

HDECICPEPH114022

7.Feb.11

I
HDECICPEPHOI3439 19.Aug.10

Conditionally Approved

COLPOIMS,D41

Method Statements for Secondary Breakwater Quay Wall Blod; Foundation ~ ~ t hstatements for ~ ~ ~ i l of^^^^ ~~~d to secondary ~ , j i t & ~ ~ BreakwaterConstructionSite ~ ~ t statements fw ~~~~~~l ~ ~~, j (~ r ~i a 21 within h ~ d o f ~ ~ t 1 ~~l ~ Appmach Channel Method Statements for Secondary Breakwater Quay Wall Block Repair Method Statements for Quarry Run Filling under Wave Wall

HDEC1CPEPfi013345 HIWi80101101186

Rivision Requested

HDECICPEPHOl3405 11.Aug.10 HIW152iU1151 12.Aug.10

C0LP01MS1042

Conditionally Approved HDECICPEPHOI3641 19.0ct.10 Approved Add. Inform Required

C0LP01MS1043

fHDEClCPEPHOi3437 19.Aug.10 HIWI81102/01209 HDEC1CPEPH013438 HIW180101101181 HDECICPEPHOI3609 HIWI80102101252 6.0ct.10 lgAug.10 2.Sep.10 9.0ct.10 10.Dec.10

65

COLPOIMS1044

HIWi81102/01251

10.Dec.10

66

COLPOIMSB45

Conditionally Approved

I
Approved

Method Statements for Secondary Breakwater Construction(from

Method Statement Register.xls

-414-

201 1-03-08

AHYUNDAI

IWWER~)~~~TRC~MCOLTII

Method Statement for Document No. : COLPOIMS1048 Rev.1 Date : 2011.03.08 Sand Compaction, HDPE Sheet and Armour Rock Page : 1 of 31 (Sea Side) Placing

Method Statements
for

Sand Compaction, HDPE Sheet And Armour Rock (Sea Side) Placing
Colombo Port Expansion Project Habour Infrastructure Works, Sri Lanka

Docu. No. Rev. No. Prepared Date. Effective Date. Department.

Planning I Construction Division.

Method Statement for Sand Compaction, HDPE Sheet and Armour Rock (Sea Side) Placing

Document No. : COLPO/MS/048 Rev.1 Date : 2011. 03. 08 Page : 2 of 31

Revision Control Table.


Rev. Date
2011.02.23.

Rev. No.
0

Description of Revision.
First Issue. 2.3.2 Grid of Vibro Compaction (page 9) Grid pattern changed from isosceles triangle to equilateral triangle 2.4.8 (page 16) Field Welding Test changed into Field Welding Inspection 5.1 ITP (page 23,24) No. 2 & 4 Revised 5.1 ITP (page 25) No.9 Air pressure test changed into Field welding inspection

Remarks

2011.03.08

Method Statement for Sand Compaction, HDPE Sheet and Armour Rock (Sea Side) Placing

Document No. : COLPO/MS/048 Rev.1 Date : 2011. 03. 08 Page : 3 of 31

CONTENTS
1 2 Introduction .................................................................................................................... 4
1.1 Purpose ........................................................................................................................................................ 4

Work Method ................................................................................................................. 5


2.1 2.2 2.3 Work Sequence .......................................................................................................................................... 5 Sand Compaction Sequence .................................................................................................................... 6 Sand Compaction Method ......................................................................................................................... 8 2.3.1 2.3.2 2.3.3 2.3.4 2.4 Deep Vibro Compaction .............................................................................................................. 8 Grid of Vibro Compaction ............................................................................................................ 9 Pattern of Probe Insertion and Pull-out ................................................................................... 10 Records........................................................................................................................................ 11

HDPE Sheet Placing ................................................................................................................................ 11 2.4.1 2.4.2 2.4.3 2.4.4 2.4.5 2.4.6 2.4.7 2.4.8 Preparation of Sand Slope and Geo-textile ............................................................................ 11 Roll Reception and Storage of HDPE Sheet .......................................................................... 12 Preparation of HDPE Sheet before Placing ........................................................................... 12 Deployment of HDPE Sheet Placing ....................................................................................... 13 Trial Welding ............................................................................................................................... 13 Field Welding Fusion (Hot Wedge) Welding System ......................................................... 13 Field Welding Extrusion Welding System ............................................................................ 15 Field Welding Inspection ........................................................................................................... 16

2.5

Bedding Layer, Rock (0.3~1.0 ton) and Armour Rock (3.5~6.5 ton) Placing ................................... 17 2.5.1 2.5.2 2.5.3 Material Requirement ................................................................................................................ 17 Bedding Layer and Rock (0.3~1.0 ton) Placing ..................................................................... 18 Armour Rock (3.5~6.5 ton) Placing ......................................................................................... 18

3 4

Quality Control ............................................................................................................. 19 Safety .......................................................................................................................... 20


4.1 General Safety .......................................................................................................................................... 20 4.2.1 4.2.2 Heavy Equipments. .................................................................................................................... 20 Vibrators / Generators / Water Pumps / Power Tools ........................................................... 20

Inspection & Test Plan ................................................................................................. 22


5.1 Inspection & Test Plan ............................................................................................................................. 23

Attachment Attachment

#. 1 ............................................................................................................... 27 #. 2 ............................................................................................................... 29

Method Statement for Sand Compaction, HDPE Sheet and Armour Rock (Sea Side) Placing

Document No. : COLPO/MS/048 Rev.1 Date : 2011. 03. 08 Page : 4 of 31

Introduction
1.1 Purpose
This document outlines the work methods for sand compaction for road construction up to main breakwater Ch.4,200 and, HDPE sheet & armour rock (sea side) placing.

Method Statement for Sand Compaction, HDPE Sheet and Armour Rock (Sea Side) Placing

Document No. : COLPO/MS/048 Rev.1 Date : 2011. 03. 08 Page : 5 of 31

Work Method
2.1 Work Sequence
Below is a flow chart of normal work procedure for sand compaction, HDPE sheet and armour rock placing.

Start of Work

Sand Compaction (Vibro-Hammer) Compaction Test Preparation of Sand Slope

HDPE Sheet Placing

Bedding Layer Placing

Rock (0.35~1.0 ton) Placing

Rock (3.5~6.5 ton) Placing

Process Finish

Method Statement for Sand Compaction, HDPE Sheet and Armour Rock (Sea Side) Placing

Document No. : COLPO/MS/048 Rev.1 Date : 2011. 03. 08 Page : 6 of 31

2.2 Sand Compaction Sequence


The compaction is required within the road boundary of breakwater up to Ch.4,216 which is consist of wide road and narrow road as shown in Fig.2-1. The wide road section is up to Ch.2,000 and the narrow road section is from Ch.2,000 to Ch.4,216.

[ Fig. 2-1 ] Plan of Breakwater and Compaction Sequence The subgrade and fill material beneath the pavement should be compacted up to required degree of compaction to support traffic load on the pavement and prevent additional long term settlement. The hatched compaction areas in Fig. 2-2 and Fig. 23 sufficiently cover the traffic load distribution area beneath the load area. The compaction will be carried out in the order described in Fig. 2-1 Ch.800 ~ Ch.1,500 Ch.1,500 ~ Ch.1,900 CWA ~ Ch.800 Ch.1,900 ~ Ch.3,100 Ch.3,100 ~ Ch.4,216

Method Statement for Sand Compaction, HDPE Sheet and Armour Rock (Sea Side) Placing

Document No. : COLPO/MS/048 Rev.1 Date : 2011. 03. 08 Page : 7 of 31

[ Fig. 2-2 ] Sectional View of Compaction Area for Wide Road (~Ch.2,000)

[ Fig. 2-3 ] Sectional View of Compaction Area for Narrow Road (Ch.2,000~Ch.4,216) For Area 1 (Sequence and ), the area is filled with sand up to around +4.5 m ~ +5.0 m level and used for the access road. As for each 100 meters from Ch.1,500 toward Ch.800, one half (sea side) of full width will compacted and the other half (land side) will be used for access road. After sea side half is compacted, it will be used for access road and land side will be compacted contrarily. It will be repeated by turns for each 100 meter. For Area 2 (CWA~Ch.800, Sequence ), the area is filled up to +3.0 m and the CoreLoc units are stored at both sides of access road. The stored units will be removed from existing location for placing before the compaction of area 1 is finished.

Method Statement for Sand Compaction, HDPE Sheet and Armour Rock (Sea Side) Placing

Document No. : COLPO/MS/048 Rev.1 Date : 2011. 03. 08 Page : 8 of 31

Then sand which was pumped and stored within CWA will be transported by dump truck and the sand embankment will be prepared for compaction up to the level below the final road surface by 0.2 m for one half of the full width. After the compaction for one half up to Ch.800 is finished, the other half will be filled with sand up to the level below the final road surface by 0.2 m and compacted. For Area 3 and 4 (Sequence and ), there are rock stockpiles along the road line. When the stored rock is removed, the sand will be filled up to the required level by pumping of dredgers. When the sand embankment is prepared, it will be compacted.

2.3 Sand Compaction Method


Deep compaction by vibrating H-beam will be carried out at the formation level after hydraulic filling. There are several factors affecting efficiency of vibro-compaction such as capacity of vibro-hammer, frequency of vibration, shape of vibrating probe, time period of vibration, number of penetration and extraction, spacing of compaction point and so forth. In order to determine the factors, the trial compaction was carried and proposal for compaction method and alternative acceptance criteria of sand compaction was submitted with transmittal No. HDEC/CPEP/11/4103. Top 45 cm surface layer will be compacted by vibrating roller at formation level. The requirement of insitu density for this layer will be discussed further with the Engineer. The capacity of roller and number of trips also will be decided through trial compaction and discussion with the Engineer. CPT (Cone Penetration Test) will be used to check the degree of compaction for deep sand compaction area. The correlation between the cone tip resistance (qc) of CPT and relative density was developed through trial compaction and proposed as a alternative acceptance criteria of sand compaction. 2.3.1 Deep Vibro Compaction The deep vibro compaction work will be carried out using land based equipment as follows and in the photograph below; Vibro-hammer : weight 11 ton, electric power capacity 340 kW Crawler Crane : 70 ton Generator : 200 kVA Water Pump : 3 H-Beam : 55 X 64 X 13, 6 m

Method Statement for Sand Compaction, HDPE Sheet and Armour Rock (Sea Side) Placing

Document No. : COLPO/MS/048 Rev.1 Date : 2011. 03. 08 Page : 9 of 31

Vibro-Hammer

Generator Crane H-Beam

Water Supply

2.3.2 Grid of Vibro Compaction At the beginning, the compaction work will be carried out with 2.5m spacing in equilateral triangular patterns as below.

[ Fig. 2-4 ] Grid of Vibro Compaction

Method Statement for Sand Compaction, HDPE Sheet and Armour Rock (Sea Side) Placing

Document No. : COLPO/MS/048 Rev.1 Date : 2011. 03. 08 Page : 10 of 31

To form a vibro compaction point, the H-beam gripped with vibro-hammer will be placed over the selected position by means of a crawler crane. After starting the motor of the vibro-hammer, water will be discharged from 4 pipes which are installed on each side of the H-beam and the beam will be slowly lowered. In the immediate vicinity of the beam head, the sand will be saturated with water inducing local and temporary liquefaction of the soil under the influence of the vibration. 2.3.3 Pattern of Probe Insertion and Pull-out When the desired depth of penetration is reached, the downward movement of the beam will be stopped and upward movement started. When the embedded length of beam reaches 1 m, downward movement of beam will resume and pulled out after beam touches the desired depth. The patter of probe insertion and pull-out is given in the sketch below.

[ Fig. 2-5 ] Pattern of Probe Insertion and Pull-out The compaction duration at each compaction point will be min. 4 minutes and the water will be jetted continuously during compaction. Generally the effect of the compaction becomes visible at the ground surface in the form of a cone shaped depression. The depression formed around the compaction point will be leveled by trimming and grading up to the level slightly higher than the sand formation (+4.5m) and compacted with vibro-roller.

Method Statement for Sand Compaction, HDPE Sheet and Armour Rock (Sea Side) Placing

Document No. : COLPO/MS/048 Rev.1 Date : 2011. 03. 08 Page : 11 of 31

For the proper compaction of both slope areas, there will be additional filling by 0.5m width and it will be trimmed to the design profile by back-hoe after vibro compaction is finished. 2.3.4 Records Daily report and daily compaction record will be kept and submitted to the Engineer for information and review. Daily compaction record form is attached as attachment #.1

2.4 HDPE Sheet Placing


2.4.1 Preparation of Sand Slope and Geo-textile The surface will be prepared with back-hoe, prior to the HDPE sheet installation, according to the executive design guidelines. The surface shall be smooth and free of sharp objects and stones, free of all foreign and organic material and debris of any kind.

[ Fig. 2-6 ] Preparation of Sand Slope

Method Statement for Sand Compaction, HDPE Sheet and Armour Rock (Sea Side) Placing

Document No. : COLPO/MS/048 Rev.1 Date : 2011. 03. 08 Page : 12 of 31

The geotextile shall be unfolded and spread over the slope. spread on the slope shall be more than one (1) meter.

The length of geotexte

One recommends that the HDPE sheet be installed immediately after slope preparation to avoid deterioration caused by rain, wind, lost of moisture or local traffic. 2.4.2 Roll Reception and Storage of HDPE Sheet The rolls unloading shall be done with equipment that ensures its security transportation. When the rolls delivered and unloaded at the site, they will be inspected visually. The external roll side shall be free of holes, tears and bubbles. The technical data of HDPE sheet (Geomembrane) is attached as Attachment #.2 The rolls shall be stored on the smooth ground without excessively hot or moist condition. Sharp objects or anything which may puncture the sheet shall be removed. Under standard weather condition, the storage of HDPE sheet does not require special treatment. 2.4.3 Preparation of HDPE Sheet before Placing The required length of each chainage of breakwater is summarized as below;
Chainage Ch.0 ~ Ch. 1,100 Ch. 1,100 ~ Ch. 1,780 Ch. 1,780 ~ Ch. 2,570 Ch. 2,570 ~ Ch. 4,250 Kerb Level 5.00 5.00 5.83 5.50 Kerb Height 0.575 0.575 0.575 0.575 HDPE upper level 4.425 4.425 5.255 4.925 HDPE lower level 1.5 1.5 1.0 2.0 HDPE Height 2.925 2.925 4.255 2.925 HDEP Slope Length 5.896 5.896 8.576 5.896 HDPE upper Length 0.7 0.7 0.7 0.7 HDPE Length 6.596 6.596 9.276 6.596 Remarks

The width of HDPE sheet delivered to the site is 6 meter. Therefore, before placing the sheet on the slope, additional length shall be welded at the storage yard or on the embankment near the slope. The HDPE sheet will be delivered with 7 meter length in the future to minimize welding joint.

Method Statement for Sand Compaction, HDPE Sheet and Armour Rock (Sea Side) Placing
2.4.4 Deployment of HDPE Sheet Placing

Document No. : COLPO/MS/048 Rev.1 Date : 2011. 03. 08 Page : 13 of 31

Initially, the HDPE sheet will be placed at 30m interval, longitudinally and the interval may be adjusted later. All machines or equipment to be used for HDPE sheet placing shall be in appropriate manner to prevent the sheet from any damage, extension or wrinkles. Adequate temporary anchoring (sand bags or tires), that cause no damage to the HDPE sheet, may be placed to prevent uplift by the wind. Welding should be performed as soon as possible after the sheet is placed. 2.4.5 Trial Welding Trial welding will be done to verify the equipment and the operator. This verification shall be made prior to the main field welding. Trial welding will be done under the same conditions as actual welding. The trial welding will be carried out under the supervision of manufacture. The welding overlap shall be over 10 cm for hot wedge welding and over 7.5 cm for extrusion welding. In cases of fish mouths or wrinkles at the seam overlaps, they shall be cut along the ridge of the wrinkle, in order to achieve a flat overlap. The HDPE sheet portion cut shall be welded and any portion where overlap is inadequate shall be patched with an oval or round patch of the same HDPE sheet, extending a minimum of 15cm beyond the cut in all directions. 2.4.6 Field Welding Fusion (Hot Wedge) Welding System There are several different types of field welding equipment available. The fusion (hot wedge) and the extrusion welding methods are used for HDPE sheet welding. Hot wedge welding is the primary method for panel seam and extrusion for HDPE insert liners and repairs. Fusion (Hot Wedge) welding is the primary welding method. Hot metal wedge shall be heated to the required temperature and used to melt the overlapped facing surfaces then they are pressed together with two nip/drive rollers to create a permanent bonding structure. Welding temperature setting is recommended at 325~400, upon the thickness of HDPE sheet. Weather condition (e.g. temperature, sunshine, and wind) shall be taken into consideration as well.

Method Statement for Sand Compaction, HDPE Sheet and Armour Rock (Sea Side) Placing

Document No. : COLPO/MS/048 Rev.1 Date : 2011. 03. 08 Page : 14 of 31

Turn off the motor before placing the overlap in the wedge and roller. After the overlap to be welded is properly positioned, turn on the motor and lock the seam in position. The welding machine shall be aligned and set to the adequate temperature, the travel speed of welding machine is set depending on the thickness of sheet and weather condition.

[ Fig. 2-7 ] Typical double fusion hot wedge weld detail The welding operator shall take care of welding machine for temperature and speed control to maintain a consistent weld. A small amount of squeeze-out is a good indication that the proper welding temperature has been set. The melted material will lately be extruded out of the welding area. If there appears an excessive amount of hot extrusion, it indicates that the temperature or pressure is too high and needs adjustment. For the 1mm or less thickness sheet, if there shows a long, low, sinusoidal wavelength pattern in the direction of the welding, it indicates the proper seaming. If the wave peaks are too close, the seaming speed shall be increased until an acceptable pattern appears. The absence of the wave length indicates that the seaming speed shall be decreased. There will be no wave pattern for the thickness greater than 1mm because of the inherent stiffness. Nip/Drive roller marks will always show on the welding track surface, they are noticeable and slightly embossed.

Method Statement for Sand Compaction, HDPE Sheet and Armour Rock (Sea Side) Placing

Document No. : COLPO/MS/048 Rev.1 Date : 2011. 03. 08 Page : 15 of 31

Daily checking and cleaning of welder are required. 2.4.7 Field Welding Extrusion Welding System Extrusion welding is primarily used for repairs, details (e.g. piping or trench) and T welding. The welding rods, with 4mm or 5mm diameter, which are made of the same material as the HDPE sheet, are extruded by the extrusion welder and pasted along the overlapped seam. Preheating of the sheet in the welding area is performed by the extrusion welder.

[ Fig. 2-7 ] Typical Extrusion weld detail The welding area shall be dry and clean. The HDPE sheet surface shall be slightly ground to remove the oxidized layer or other foreign materials. Grinding depth shall not exceed 10% of sheet thickness. Grinding width shall match extruder, and not exceed either side of the extruded. Welding shall be conducted right after grinding, no more than 30 minutes. Use hot air welder or other equipment to tack two sheets binding together. heat could damage the upper sheet and shall be avoided. Excess

The extrusion welder shall purge all degraded material in the barrel for approximately 30 seconds before welding. The purge material shall not be discharged on the surface of the sheet.

Method Statement for Sand Compaction, HDPE Sheet and Armour Rock (Sea Side) Placing

Document No. : COLPO/MS/048 Rev.1 Date : 2011. 03. 08 Page : 16 of 31

The overlap thickness shall be approximately twice of the sheet thickness, measuring from the upper surface of the bottom sheet to the top of the extrusion. A small amount of squeeze-out appearing on two sides of welding track is allowed. If the amount of squeeze-out is too much, lower the extrusion welder temperature setting or increase the welding speed. If interruption is necessary during the welding process, trial-off the extrusion shall be applied gradually instead of stopping instantly. To re-launch the welding process, the continued area shall be ground before welding. To perform repairs, piping, other accessories, T welding and Y welding, follow the above procedures. The welding shall be done vertically up and down the slope. The overlaps between panels shall be over 10 cm for fusion welding and over 7.5 cm for extrusion welding. Before welding start the overlaps shall be dry and clear. 2.4.8 Field Welding Inspection All field welding shall be inspected by the engineer visually. The clear nip/drive roller marks certify the quality of welding and the Engineer can check the roller marks run out of the overlap edge.

Method Statement for Sand Compaction, HDPE Sheet and Armour Rock (Sea Side) Placing

Document No. : COLPO/MS/048 Rev.1 Date : 2011. 03. 08 Page : 17 of 31

2.5 Bedding Layer, Rock (0.3~1.0 ton) and Armour Rock (3.5~6.5 ton) Placing
After HDPE sheet is placed and tested, remaining rock such as bedding layer, rock (0.3~1.0 ton) and armour rock (3.5~6.5 ton) will placed as per the drawing and specification.

[ Fig. 2-9 ] Rock Placing Sequence 2.5.1 Material Requirement Quarried rock to be used in armour, underlayers shall be free from any defects which could lead to breakage during loading, unloading or placing. All Quarry stones shall be prismoidal in shape. Within each class, no stones shall have a length to thickness (l/d) ratio greater than 3 and not more than 50% of stones shall have a l/d ration greater than 2, where the length (l) is defined as the greatest distance between two points in the stone and the thickness (d) as the minimum distance between two parallel straight lines between which the stone can just pass. Quarried rock to be used in armour, underlayers shall be subject to the following limits; Apparent Relative Density (BS812 : Part 2) > 2,650 kg/m3

Method Statement for Sand Compaction, HDPE Sheet and Armour Rock (Sea Side) Placing
Water Absorption (BS812 : Part 2) Soundness (BS812 : Part 121) MgSO4 Or : Los Angeles Abrasion (ASTM C-535)

Document No. : COLPO/MS/048 Rev.1 Date : 2011. 03. 08 Page : 18 of 31

<2% < 12 % < 18 %

Either : Aggregate Abrasion (BS 812 : Part 113) < 15 %

2.5.2 Bedding Layer and Rock (0.3~1.0 ton) Placing After HDPE sheet is placed and the test result is accepted, the 0.5 m thick bedding layer and 1.0 m thick rock (0.3~1.0 ton) will be placed by back-hoe from sand embankment layer by layer. The HDPE sheet shall not be damaged during the bedding layer and rock placing. The profile of each layer will be inspected respectively. 2.5.3 Armour Rock (3.5~6.5 ton) Placing After Rock (0.3~1.0 ton) profile is accepted, the armour rock (3.5~6.5 ton) will placed. Initially, armour rock will be supplied to the placing location, over the surface of rock (0.3~1.0 ton) layer by crane using wire net. Then, standard back-hoe will climb over the armour rock and place the armour rock as per the drawing.

Method Statement for Sand Compaction, HDPE Sheet and Armour Rock (Sea Side) Placing

Document No. : COLPO/MS/048 Rev.1 Date : 2011. 03. 08 Page : 19 of 31

Quality Control
The construction engineer will be responsible for maintaining QA/QC aspect and he will manage overall construction according to the approved drawings, specifications, method statement and programme. Prior to every special activity, Inspection/surveying will be arranged for the consent to approval of Engineers representative.

Method Statement for Sand Compaction, HDPE Sheet and Armour Rock (Sea Side) Placing

Document No. : COLPO/MS/048 Rev.1 Date : 2011. 03. 08 Page : 20 of 31

Safety
The Contractor has submitted Health and Safety Plan and will carry out safety control according to the health and safety plan

4.1 General Safety


All land-based equipment to be used at the site shall have obtained a suitable certificate. All personnel will be instructed in safe working procedures by the Safety Officers. The Construction Engineer is responsible for the implementation of the approved safety procedures throughout the construction period and ensures that all personnel are issued with the proper safety gears/instructions. Safety Supervisor will be nominated to ensure the implementation of safety aspects by all employees when performing their duties.

4.2 Sand Compaction


4.2.1 Heavy Equipments. All construction equipment and vehicles will be inspected before each use and all deficiencies corrected, prior to operate. Safe working Loads, recommended operating speed within HDEC and special hazard warning will be conspicuously posted on all equipment and be visible from the operators station. Prior to initial use and on a daily basis, all lifting accessories will be inspected and defected equipment removed from service immediately. Where manual (hand) signals may be used, only one person will be designated to give signals to the operator and called rigger. A flag person (signalman) will be provided when operations or equipments on or adjacent to a highway create a traffic hazards. 4.2.2 Vibrators / Generators / Water Pumps / Power Tools Tools having defects or render those unsafe will be removed from service. Portable power tools require industrial socket. Completed electrical installations must be inspected and tested prior to use Ensure all power supply systems are completely safe.

Method Statement for Sand Compaction, HDPE Sheet and Armour Rock (Sea Side) Placing

Document No. : COLPO/MS/048 Rev.1 Date : 2011. 03. 08 Page : 21 of 31

Earthling rods, must be used to prevent electrical shock from the cables of machines

4.3 HDPE Sheet placing


All welding equipment will be inspected daily. Defective equipment will be removed from site. High temperature works (Hot Work) will be supervised by Safety Staff and permission must be obtained from the HSE manager. Each welding or cutting will be equipped with compatible fire extinguishers. Suitable eye protection will be worn to prevent eye injuries while welding and cutting.

4.4 Amour (Rock Sea Side ) Placing


All outside dump truck may be good condition. All personnel working near shoreline will wear the life jacket. When transporting amour rock loads they will be adequately secured against displacement. Established job site speed limits, posted speed limits and traffic control signs will be strictly obeyed. All vehicles and equipment must have a back up alarm installed. A flagman (signalman) is required to aid in reversing vehicles or equipment.

Method Statement for Sand Compaction, HDPE Sheet and Armour Rock (Sea Side) Placing

Document No. : COLPO/MS/048 Rev.1 Date : 2011. 03. 08 Page : 22 of 31

Inspection & Test Plan


Inspection and Test Plan for sand compaction, HDPE sheet and armour rock placing is attached as below.

Method Statement for Sand Compaction, HDPE Sheet and Armour Rock (Sea Side) Placing 5.1 Inspection & Test Plan
ITP reference: TITLE: Revision: DRAWING Nos/ DOCUMENT REFERENCES:

Document No. : COLPO/MS/048 Rev.1 Date : 2011. 03. 08 Pate : 23 of 31

Date of issue: Test and Inspection Codes:

Page

S = Surveillance Record as Diary Entry etc. I =Inspection work continues Signed Record WORK BY: Method Statement and the Specification W = Witness inspection or test Signed Record H = Hold Point Stop work until seen Signed Record R = Records Review Signed Record per package
OP. No. Operation to be inspected or tested Operation Controlled by: (position) 1 Approval of Vibrating hammer Minimum weight 11 tons, Minimum electric power capacity 340kW 2.5m x 2.5m equilateral triangle Before initial use Accept / Reject Criteria Frequency of inspection or test Reference to Standard, Specification, Procedure, Method Statement etc. Method Statement Quality Records required (Certifying document) Manual of the machine HYUNDAI SCOTT WILSON Test/ Inspection Codes

Hyundai

Marking of the grid before compaction

Hyundai

Every section before compaction Every point

Method statement

RISC I I

Time recording during compaction

Hyundai

Minimum of 240 seconds

Method statement

Recording sheet I S

Method Statement for Sand Compaction, HDPE Sheet and Armour Rock (Sea Side) Placing
OP. No. Operation to be inspected or tested Operation Controlled by: (position) 4 CPT for check the compaction (+0.40m +4.05m) Hyundai Depth(m) 0.5~1.0 1.0~2.0 2.0~3.0 3.0~4.0 4.0~5.0 To be decided Hyundai qc (Mpa) 6.0 8.0 10.0 12.0 15.0 For wide road 1 test for 18.82m x 30m section For narrow road 1 test for 18.14m x 30m section To be decided Accept / Reject Criteria Frequency of inspection or test

Document No. : COLPO/MS/048 Rev.1 Date : 2011. 03. 08 Pate : 24 of 31

Reference to Standard, Specification, Procedure, Method Statement etc. Method statement

Quality Records required (Certifying document) RISC, and test report

Test/ Inspection Codes

HYUNDAI

SCOTT WILSON

Compaction check at Top 0.45m layer

RISC and Test reports

Preparation of sand slope before placing HDPE sheet Geo-textile placing over the slope before HDPE sheet placing

Slope should be 7:4 Hyundai Free from sharp objects Spread on slope more than 1 m

HDPE sheet to be placed in every section Every section

Design Drawings and Method statements Method statements

RISC H I

RISC H I

Hyundai

Overlap for sheet welding

Hyundai

For Hot wedge welding Over 10 cm For Extrusion welding Over 7.5 cm

Every welding section

Method statements

RISC H I

Method Statement for Sand Compaction, HDPE Sheet and Armour Rock (Sea Side) Placing
OP. No. Operation to be inspected or tested Operation Controlled by: (position) Field Welding Inspection (Visual) Clear nip/drive roller marks certify the quality Accept / Reject Criteria Frequency of inspection or test

Document No. : COLPO/MS/048 Rev.1 Date : 2011. 03. 08 Pate : 25 of 31

Reference to Standard, Specification, Procedure, Method Statement etc. Method statements

Quality Records required (Certifying document) RISC

Test/ Inspection Codes

HYUNDAI

SCOTT WILSON

Hyundai

10

Armour Rock Material Approval

Grading Test Shape Test Density > 2650 Kg/m3 Water absorption<2.5% Hyundai Point load >5 Mpa LAAV<18% MBA < 0.7/100g Soundness < 12%

Every 25000 ton Every 5000 ton Every 25000 ton Every 50000 ton Every 50000 ton Every 25000 ton Every 50000 ton Every 50000 ton Every section before proceed next step

Specification 7.031

Test Report and RISC

11

Final Inspection of Bedding material layer Hyundai

Slope and thickness according to the design Drawings

Design Drawings

RISC H I

12

Final inspection of 0.35~1.0 ton layer Hyundai

Slope and thickness according to the design Drawings

Every section before proceed next step

Design Drawings

RISC H I

Method Statement for Sand Compaction, HDPE Sheet and Armour Rock (Sea Side) Placing
Operation to be inspected or tested Operation Controlled by: (position) Accept I Reject Criteria Frequency of inspection or test

Document No. :COLPOIMS1048 Rev.1 Date :2011.03.08 Pate : 26 of 31

Procedure, Method Statement etc. Slope and thickness according to the design Drawings Every section before proceed next step Design Drawings

specification,

Referenceto Standard,

Quality Records required (Certifying document) RlSC

Test1 InspectionCodes

HYUNDAI

SCOTT WILSON

13

Final inspection of

3.5-6.5ton layer
Hyundai

Prepared by: J.S. Y u

Checked by:

Approved by:

/
Date: Construction Engineer

Date:

K.C. Kim

J. S. Kim

~b*f+
-11
Date: Construction Manager

06 pflc

Quality Control Manager

Method Statement for Sand Compaction, HDPE Sheet and Armour Rock (Sea Side) Placing

Document No. : COLPO/MS/048 Rev.1 Date : 2011. 03. 08 Page : 27 of 31

Attachment

#. 1

Daily Compaction Record Form

Method Statement for Sand Compaction, HDPE Sheet and Armour Rock (Sea Side) Placing

Document No. : COLPO/MS/048 Rev.1 Date : 2011. 03. 08 Page : 28 of 31

Method Statement for Sand Compaction, HDPE Sheet and Armour Rock (Sea Side) Placing

Document No. : COLPO/MS/048 Rev.1 Date : 2011. 03. 08 Page : 29 of 31

Attachment

#. 2

HDPE Sheet Technical Sheets

Method Statement for Sand Compaction, HDPE Sheet and Armour Rock (Sea Side) Placing

Document No. : COLPO/MS/048 Rev.1 Date : 2011. 03. 08 Page : 30 of 31

Method Statement for Sand Compaction, HDPE Sheet and Armour Rock (Sea Side) Placing

Document No. : COLPO/MS/048 Rev.1 Date : 2011. 03. 08 Page : 31 of 31