B. TECHNICAL SPECIFICATION - PART-II B.

1 CLIMATIC/ENVIRONMENTAL CONDITIONS: The Machine/Plant shall be able to work under following site conditions at Dankuni Factory .1.1 AmbientTemp. Min. 0 degree C & Max. 50 degree C. 1.2 Humidity 98% (Max) 1.3 Atmosphere Dusty 1.4 Rainfall Heavy 1.5 Altitude 150 mts. above sea level B.2 RIGIDITY AND STABILITY:

B.2.1 The machine shall be robust, rigid and sturdy construction. it shall be designed to meet heavy duty demands of various operations on the machine under normal workshop environment for such machines. It shall be free from vibrations even when working at full capacity. B.2.2 All machine casting shall be made of close grained high grade cast iron like meehanite or equivalent materials meeting IS :210 Standards to ensure durability and rigidity. The casting shall be thermal stress relieved to ensure stability and continued accuracy. B.2.3 All machine fabrications of critical load bearing assemblies like beds, columns etc. shall be adequately strengthened and stress relieved. B.3 HYDRAULIC SYSTEM (WHERE APPLICABLE) B.3.1 Hydraulic circuit must be equipped with the following safety and inspection equipments: (a) Pressure gauges at all places, where pressure has to be set up or inspected. (b) Safety valves for hydraulic circuit, if relief valve dose not fulfill this function. (a) Equipment for checking of temperature in the circuit or in the pump wherever necessary. (c) Arrangement to show if the filters (including those in the pump set) are chocked and need cleaning. The filters shall be of reusable type and indigenously available. If reusable filter cannot be offered, the filter cartridge shall be readily available in India. Source of supply shall be indicated adequate no. of filters for 2 years working on double shift basis shall be offered as spare. (d) Alarm for low oil level. B.3.2 The sump aggregate shall have the following: (a) Oil level sight gauges or any other equipment showing the minimum and maximum oil levels in sump (tank).

(1)
(b) It shall be possible to drain the oil from the tank without disconnecting any pipes or other fittings.

B.3.3 The temperature of oil in hydraulic circuits shall not exceed 60 degree C in any case. Suitable arrangement shall be incorporated to ensure that the oil is not over heated under local weather conditions at continuous normal working of the machine. B.3.4 Facilities for bleeding of air in case of air-lock shall be provided. B.3.5 The hydraulic reservoir, pump and allied equipment shall be suitably segregated from the machine in order to remove major source of heat. B.3.6 Hydraulic oils used on the machine shall be available in India. Brand names of approved oils supplied by various Indian Oil Companies shall be indicated. B.3.7 First fill of hydraulic oils used on the machine shall be provided with the machine. B.3.8 The hydraulic system elements shall be from reputed Indian manufacturers like- M/s REXROTH, Vickers Systems, Yuken, L& T etc. The make of different element shall be dearly indicated. BA PNEUMATIC SYSTEM (WHEREAPPLICABLE) : B.4.1 The compressed air supply will be provided by the customer at the machine within pressure range of 4.5 to 5 kg/square cm. and.a moisture content of 1000 PPM. The pneumatic system of the machine should be designed accordingly. B.4.2 Suitable filter/moisture trap, air pressure regulator, pressure gauge shall be provided by the contractor in the system of pneumatic air intake. The filter shall be reusable type and indigenously available. If reusable filter can not be offered, the filter cartridge shall be easily available in India. Source of supply shall be indicated. Adequate no. of filter for 2 years working on double shift basis shall be offered as spare. An alarm for low air pressure shall be provided. B.4.3 The make of pneumatic control equipment shall be of reputed make. The make shall be Indicated. B.5 LUBRICATION SYSTEM (WHERE APPLICABLE): B.5.1 The machine shall be provided with a suitable lubricating system for ensuring delivery of adequate quantity for lubricant to areas requiring continuous lubrication. Suitable arrangements must be provided for indication of failure of the lubricating system. B.5.2 Reusable filters capable of filtering chips, dust particle etc. shall be provided. Indicators for showing clogged condition of filters shall be available. The filters shall be indigenously available. If reusable filters can not be offered, the filter cartridge shall be readily available in India. Source of supply shall be indicated. Adequate no. of filters for 2 years working on double shift basis shall be offered as spares. B.5.3 Lubrication and filter cleaning chart shall be displayed on a metal plate at a conspicuous location on the machine indicating:-

(2) (a) Specific location of points on the machine to be oil lubricated/greased. (b) Periodicityoflubricationsofthese points.

(c) Filters to be cleaned. (d) Periodicity of cleaning filters. (e) Periodicity of replenishing lubricating oil for the centralized system.
B.5.4 Points where manual lubrication is needed shall be separately indicated. Frequency of lubrication shall also be clearly mentioned. B.5.5 Lubricating oils used in the machine or their equivalents shall be available in India. Successful tenderer will be required to indicate brand names of approved oils manufactured by various Indian Oil Companies. B.5.6 First fill of lubricating oils used in the machine shall be provided with the machine. Details of lubricating system provided shall be indicated. B.6 COOLANT SYSTEM (WHERE APPLICABLE) : B.6.1 Suitable coolant system with pump, motor, tank, filter etc. shall be provided. The coolant pump shall be as per IS: 2161-1962. The filter shall be of reusable type and indigenously available. If reusable filter cannot be offered, the filter cartridge shall be readily available in India. Source of supply shall be indicated. B.6.2 Provision of re-circulation of the coolant in ample Volume shall be available. A chip and coolant tray shall be provided. The volume of coolantflow shall be indicated. It shall be adjustable. B.6.3 An enclosure shall be provided to prevent the coolant from splashing outside the machine zone. B.6.4 Specific requirements of coolant for grinding operation on the job, if any, shall be clearly indicated. B.7 ELECTRICAL SYSTEM (WHERE APPLICABLE) : B.7.1 The electrical equipment shall comply with the requirements of Indian Electricity Act and Rules. B.7.2 All equipments and material shall comply with appropriate Indian Standards (Latest) or National Standards of the country of origin provided the latter are equivalent to or better than the former. For items for which Indian standards are not published, National Standards shall be acceptable. The tenderer shall indicate the standards applicable. The following standards are applicable in particular, Corresponding international standards like ASA, NEMA, RSS, DIN etc. may also be quoted. IS :325-1979 (latest) Three phase induction motors (corresponding to IEC Pub-34-1) (latest) IS :1248-(latest) Direct acting indicating analogue electrical Measuring instrument and their accessories (corresponding to IEC Pub - 51) (latest) IS :1231-1974 (latest) Dimensions of three phase induction motors (corresponding to IEC-Pub 72-1) (latest)

(3)
IS : 1271-1985 (latest) : Classification of insulation material for electrical machinery and apparatus in relation to their thermal stability in service

corresponding to IEC-Pub-85) (latest) IS : 6875 - (latest): Push Buttons and related control switches (corresponding to IECPub-73) (latest) IS : 375-1963 (latest) : Marking and arrangement of switch gear, bus-bars, main connections and auxiliary wiring IS : 996-1979 (latest) : Single phase small A.C. and Universal electric motors. IS :1356 - (latest) : Electrical equipment of machine tools IS : 2516 - (latest) Circuit breakers: (corresponding to IEC-Pub-56) (latest) IS :9815-1981 (latest) : Servo motor operated line voltage correctors. IS :7752(Pt.1)-1975: Guide for the improvement of power factor in consumer's installation. B. 7.3 MOTORS: B.7.3.1 The motors and starters shall be of the following types, unless special conditions of working dictate otherwise which should be explained by the tenderer. TYPE OF MOTOR 1. A.C. motor, starting current of which doesn't exceed 75 amps. TYPE OF STARTER Direct on line Star delta or Auto Transformer

1. A.G. squirrel cage induction motor, starting


current of which is above 75 amps. started direct on line. A.C. slip ring type motor.

2.

Metallic Resistance Air cooled or Oil immersed type

3. A.C. Synchronous or synchronous induction motor. Suitable makers standard.


5. D.C. motor. Resistance Type/Thyristor type.

B.7.3.2 For main motor, class 'B' of better insulation shall be provided. B.7.3.3 The earthing terminals shall be provided on all electric motors including the control gear. B.7.4 CONTROL GEAR: B.7.4.1The control gear of AC/DC motors shall be provided with No voltage protection, short circuit protection, Overload protection and single phasing prevention.

(4)
B.7.4.2 Control equipment shall be mounted in separate drip proof enclosure having no ingress of dust oil, coolant or chips and its hinged covers shall be interlocked with the machine tool control to prevent operation of the machine when cover is open.

B.7.4.3 All instruments shall be of the industrial Grade 'A' (IS:1248) switch board type, the range of the instrument shall be such that the maximum load expected in the circuit shall produce a deflection of 60% to 80% of the full scale. B.7.5 POWER SUPPLY: (a) System: Three phase, Three Wire or Four Wire.

(b) Voltage: 415 Volts 10%. (c) Frequency: 50% Hz 3%


B.7.6 VOLTAGE STABILIZER: B.7.6.1 Tenderer should clearly indicate the voltage range in which the performance of machine will be satisfactory. He should clearly mention whether a Voltage stabilizer is required or not with the machine offered. B.7.6.2 Voltage stabilizer shall be provided for electrical motors having rated capacity upto 10 KW. The voltage stabilizer shall confirm to the following parameters. (i) Input Voltage (ii) Output Voltage (iii) Regulation (iv) Rate of correction (v) Wave from Distortion (vi) Efficiency (vii) Winding and class of insulation. -320 to 460 volts, 3 phase-4 wire unbalanced supply. -415 10 Volts - 1 % from No load to full load. - 20 Volt per second per phase. - NIL. - Not less than 97%. -Copper wire wound with 'B' class insulation or better.

B.7.6.3 Voltage stabilizer shall be provided with a protective relay to trip the AC power supply to the machine instantaneously with audio and visual indication to the operator. Setting of the protective relay for low and high voltage shall be 320 volts and 460 volts respectively. B.7.7 ISOLATION TRANSFORMER: Firm should clearly indicated whether Isolation Transformer is required for m/c or not, In case of machine equipped with NC, CNC. Thyristor controlled devices and other sophisticated electronic gadgets including microprocessors etc. which are susceptable to power line spikes and surges, a suitable Isolation Transformer of adequate capacity to cover for the entire electrical load of the machine shall be offered. The Isolation Transformer should confirm to following specifications:

(5) (i) Transformer ratio (i)


Winding - 1: 1 - Copper wire wound with 'B' class insulations or better.

(ii) Protection (iii) Common Mode Noise rejection. (iv) Isolation

- To arrest apikes and surges the order of 3 KV for 200400 Micro seconds duration. - 120dB. - Capacitance: 0.005 Pt. Resistance: Greaterthen 1000 Mega Ohms.

B.7.8 POWER FACTOR IMPROVEMENT DEVICE: Machine having electrical load of induction motors exceeding 20 KW or equipped with low power factor appliances shall be offered with adequate rating of Capacitor Bank as a concomitant accessory to improve power factor to a value of 0.90 lagging, in order to effect saving in Energy Bills. The capacitor Bank shall conform to IS: 7752 (Part-1) 1975. B.7.9 The supplier shall furnish four sets of complete electrical & electronic wiring diagrams in full details to enable the maintenance staff to locate fault in the electrical circuits, four sets of parts catalogue, maintenance manual, operating instructions with details of coils and windings used in the equipment to facilitate repairs and maintenance, should also be supplied. .6.7.10 Following technical data shall be submitted with the tender: a. a.1 a.2 a.3 a.4 a.5 a.6 a.7 a.8 a.9 a.10 a.11 a.12 a.13 MOTOR: Manufacturer's Name: Type of motor (AC/DC) : Type of enclosure: Type of duty (Ref: IS: 325) / (latest) : Starting/Excitation Mechanism: Rating-Continuous/Intermittent: Output(KW/BHP): Operating voltage across phases, no. phases & Freq.: Speed in RPM: Class of insulation.: Normal full load current: Starting current: Maximum current at the time of change over from lower speed to higher speed:

(6)

a.14

Type of Motor-Squirrel Cage/Slip ring (wound rotor): degree C :

a.15 Temperature rise of windings and other Parts allowed above an ambient temperature of 50 a.16 a.17 a.18 a.19 Frame size of motor: End use of motor: Speed control Mechanism: Standard Specification to which the motor (s) confirm:

b b.1 b.2 b.3 b.4

CONTROL GEAR: Manufacturer's Name: Type of control gear (Direct on Line/Star Delta/Auto-transformer etc.) : Rating of starting gear in KW and Amps. : Are the following provided : b.4.1. Short circuit protection. b.4.2. No volt trip. b.4.3. Overload trip. b.4.4. Delayed action, current sensitive single phasing prevention.

b.5 b.6

Standard specifications to which the motor, control gear and its ancillary offered, Special features, if any:

confirm to:

c c.1 c.2 c.3 c.4 c.5 c.6 c.7 c.8 c.9 c.10

VOLTAGE STABILIZER: Manufacturer's Name: Type of voltage Stabilizer viz DC servo Motor type, AC servo motor type, solid state: Rated capacity in KVA: Nos of phases &frequency : Type of input supply (balanced/unbalanced) : Input voltage range: Output voltage range: Rate of correction: Class of insulation & winding (only copper wound is acceptable) : Type of control circuitry :

(7)
c.11 Class of duty:

c.12 c.13 c.14 d d.1 d.2 d.3 d.4 d.5 d.6 e e.1 e.2 e.3 e.4 e.5

Type of cooling: Indicating instruments and their ranges: Safety features: ISOLATION TRANSFORMER: Manufacturer's Name: Rated capacity: Ratio of input/output voltage: Class of insulation: Arrangementfor suppression of power line surges, spikes, transients and noises: Type of cooling: POWER FACTOR IMPROVEMENT DEVICE: Manufacturer's Name: Rated capacity in KVAR: AC voltage across phases, No of phases and frequency: Mechanism of Power factor correction: Frame size:

B.8 WEAR COMPENSATION ADJUSTMENT: The original built in accuracy of the machine shall be capable of being maintained conveniently and economically by suitable adjustment for taking up wear on slides, bearing and lead screws. The system of adjustments incorporated shall be explained in the offer. B.9 SAFETY CONTROLS: B.9.1 The machine shall incorporate safety devices to provide protection to the operator and machine against all possible operational and machinery failures. B.9.2 Suitable interlock shall be provide to prevent machine operations in the event of:

(a) Faulty sequence of operation. (b) Fluctuation in supplyvoltage. (c) Resumption of power supply after power failure. (d) Not positioning of safety guards. (e) Failure of hydraulic system (Where applicable). (8) (f) Failure of pneumatic system (where applicable)

(g) Failure of lubricating system (in case of automatic lubrication) including drop in
pressure. B.9.3 A fault or damage in the control circuit or interruption, re-establishment after an interruption or fluctuation in whatever manner in the power supply to the machinery, must not lead to dangerous situations, in particular:(a) The machinery must not start unexpectedly. (a) The machinery must not be prevented from stopping, if command has already been given. (b) No moving part of the machinery or piece worked by the machinery should fall or be ejected. (b) The protection devices must remain effective. (c) The machine.tool/drive movement must immediately come to stand still or jump back to a safe clearance as soon as power supply interruption occurs. It should in no case be allowed to dig into the job or endanger the man/machine safety. B.9.4 The machine shall be fitted with an emergency stop device to enable actual or impending danger to be averted. This device must be:(a) Conveniently located. (b) Clearly identifiable. (a) Able to stop the machine as quickly as possible without causing additional hazards. (c) The emergency stop must remain engaged. It should be possible to disengage it only by appropriate operation. Disengaging the control must not restart the machinery but only permit restarting. B.9.5 Safety device shall also include:(a) Safety device against overloads for all mechanical and electrical items to the extent possible. (b) Safety stops against over running of slides. B.9.6 Guards and protection devices shall protect exposed persons against risks related to moving transmission parts (such as pulleys, belts, gears, rack an pinion, shafts etc.) and moving parts directly involved in the process to the extent possible. These shall meet the following requirements:(a) Be of robust construction. (b) Not give rise to any additional risk. (c) Not be easy to by pass or render non-operational. (d) Be located at an adequate distance from danger zone. (e) Cause minimum obstruction to the view of the production process. (f) Rigidly connected and not prone to rattling. (g) Enable essential work to be carried out without the guard or protection device having to be dismantled.

(9)

B.9.7 A load meter shall be provided to indicated the load on the machine. The meter shall

have a suitable mark to indicated the maximum load the machine can take. Full details of the above and other safety features indicating how each one functions must be explained in the offer.
B.10 MACHINE MAINTENANCE AND MAINTAINABILITY: 8.10.1 The machine shall be so designed as to require minimum possible maintenance and

to Give trouble free service and high reliability. The bidder should agree to undertake maintenance of machine even beyond warranty period for a sufficient time say 5 years. To do so should quote the annual maintenance charges per year for this period. The rate so quoted should remain firm. B. 10.2 All assemblies/parts of the machine shall be easily accessible for maintenance, periodical check up and replacement of parts.
B.1 0.3 The manufacturer must provide means of access e.g. stairs, ladders, cat walks etc. to allow safe access to all areas of machine used for production, adjustments and maintenance operations. B.10.4 Maintenance Spares :- Maintenance spare parts (Mechanical, Hydraulic, Electrical and Electronic spares) for 2 years normal working in double shift basis shall be quoted by the tenders separately giving part No and cost of each spare part. The spare parts ordered must be supplied with machine. For bought-out spares, addresses of Indian/Overseas manufacturers/suppliers shall be furnished to facilitate future procurements. B.11 FOUNDATION DRAWINGS AND SPACE REQUIREMENT: B.11.1 For each machine the supplier shall submit one copy of foundation drawing and related diagrams (Mechanical and Electrical) giving machine-weight space required for machine, overall dimensions, foundation details, electrical & pneumatic load and circuitry with the bid. B.11.2 The supplier shall furnish the detailed foundation drawing & general arrangement drawings including electrical & pneumatic load and circuit to Dy. CME/Plg/E.Rly/Kolkata, direct, in 6 (six) copies, within one month of the placement of Advance Acceptance of Tender, to enable necessary preparations to be made fortimely commissioning of machine. B.11.3 A penalty of 1/4% of the cost of the machine per week subject to maximum of 2% will be levied against the supplier for delay in supply of foundation drawings for the machine to Dy. CME/Plg. B.12 INSPECTION AND TESTING AT MANUFACTURER'S WORKS: B.12.1 Aload test shall be carried out at the manufacturers works. Rigidity of the machine shall be demonstrated to the satisfaction of appointed inspector/inspecting Agency of the purchaser. 8.12.2 Manufacturer must have suitable facilities at their works for carrying out various performance tests on the machine. The tenderers should clearly confirm while submitting the quotation that all the facilities exist and shall be made available to the inspecting Authority. 8.12.3 A sample inspection chart for inspecting the machine indicating all the test that are rried out during the machine manufacture should be supplied along with the bid. B. 12.4 The tenderers will submit quality assurance plan being followed at the manufacturer's works for ensuring quality of the products offered. (10)
B.12.5 Machine required to be supplied tooled up (where applicable) for components (as mentioned In the

specification) shall be proved out to demonstrate the claimed capability. Productivity, accuracy reliability. This proving out shall be done at the inspection stage at manufacturers premises and also at Dankuni Factory premises. The number of components needed for proving out should be indicated by the tenderer. DLW will provide the components which the supplier or his. agent will collect from DLW premises on submission of Bank Guarantee. B.12.6 At least four weeks clear notice shall be given by the contractor to the Inspecting Officer/Inspecting Agency while issuing call for inspection, which shall be sent directly to the Inspecting Officer. B.13 COLOUR: The machine and its accessories shall be painted in apple green colour No. 281 to IS-5 (1978) or its equivalent. B.14 JOINT INSPECTION AT CONSIGNEE'S PREMISES: B.14.1 The contractor or his agent shall attend joint inspection of the consignment after its receipt before unpacking, to avoid subsequent complaints regarding short supply or any transit damage. Inspection call shall be issued by Dy/CME(Plg)/E.Rly/Kolkata, on arrival of the machine at Dankuni. 8.14.2 For delay in attending joint inspection of the machine/plant on its arrival at Dankuni Factory beyond a period of 15 days from receipt of intimation by the contractor, a penalty of 1/4 % of the cost of the machine per week subject to maximum of 2% will be levied against the contractor. B.15 INSTALLATION AND COMMISSIONING AND PROVE OUT OF MACHINE: B.15.1 The contractor shall arrange for installation/erection and commissioning of the machine/plant at site by deputing their Technical Experts/Service Engineers. Necessary support facilities like crane, power, unskilled labour etc. if available, at site would however, be provided by Dankuni Factory Tools required, for installation and commissioning will be brought by firm's Technical Experts. Cranes of higher capacity/reach, than what is available at Dankuni Factory if required, for installation/erection shall be arranged by the contractor. The Technical Exports of the contractor will be required to be present immediately after the machine has been received and foundation is ready. B.15.2 The contractor or his agent shall commission the machine and prove out the same at Dankuni Factory in respect of capability, productivity, accuracy/repeatability within a period not exceeding 2 months for imported machines and 45 days for indigenous machines from the date of installation of the machine at site. 8.15.3 In the event of contractor's failure to have M&P commissioned by the time or times respectively specified in the letter of acceptance or contract, purchaser may withhold, deduct or recover from the contractor as penalty, a sum @ 2% (two percent) of the price of M&P which the contractor has failed to commission as aforesaid for each and every month (part of a month being treated as a full month) during which the M&P may not have been commissioned, subject to an upper limit of 10% (ten percent) of contract value. B.15.4 After successful prove out the machine performance shall be watched by Dankuni Factory for a period of one month (each working day, having two shifts of 8 hours), before final clearance of the balance 20% payment is given. B.15.5 Charges, if any, for the installation/erection and commissioning and prove out of machine as

(11)

defined in the scope shall be quoted on lump sum basis and not on per day basis. 8.15.6 The tender should also quote for installation/erection and commissioning of machine on turnkey basis, duly giving break up of cost for this portion of the work. 8.15.7 If an assembly/sub-assembly is required to be taken back to the manufacturer's premises for repairs/replacement either before commissioning or during warranty. The manufacturer or his agent would be required to submit an indemnity Bond. Incase the entire machine has to be taken back, a bank Guarantee would have to be submitted. The indemnity Bond/Bank Guarantee should be of adequate value so as to cover the cost of assembly/sub-assembely/paid up cost of the machine. B.16 TECHNICAL LITERATURE: 8.16.1 One copy of printed illustrative catalogue showing features of the machine and its elements must be enclosed with the bid. 8.16.2 The successful tenderer will also have to supply for each machine free of cost, 4 (Four) copies of following Technical Literature, in English language, directly to Dy. CME/Planning/Kolkata. , within 3 months of the placement of Advance Acceptance of Tender:-

(a) Operation Manual. (b) Maintenance Manual with trouble shooting guide. (c) Spare Parts Catalogue (For Mechanical, Hydraulic, Electrical & Electronic spares), giving the
part list number of each component with exploded views and assembly drawings. (d) Test Chart for leveling. Alignment & Geometric accuracies of the machine.

(e) All Electrical Circuit Diagrams including PCB Circuits. (f) For bought-out (i.e. purchased) Items/Equipments used/fitted on the machine, relevant
Technical Literature/Catalogues (specially Spare Parts Catalogue) from Indian/Overseas manufacturers of the Items, shall invariably be supplied with the above mentioned Technical Literature for the machine, giving complete address, Fax No./Telex No./Telephone No. of the manufacturers of the items. B.17 TRAINING: 8.17.1 Indigenous Machines :- The contractor shall arrange to provide free training for a period of four weeks at the manufacturer's works for three orfour persons in maintenance, operation and CNC programming (if applicable) of the machine. The boarding, lodging and travel expenses will be borne by the purchaser. However, bidders should quote for boarding and lodging charges (separately) per week per technician deputed for the training. In the event of the purchaser not being able to arrange for the boarding & lodging for their personnel for the period of training, the contractor may be required to arrange the same at quoted rates for which the payment will be made by the purchaser. B.17.2 Machine being imported:- In case of the Machines being imported two personnel per consignee (Three persons for CNC machines) shall be given training for a period of one month free of cost at the purchaser's end simultaneously with installation and commissioning.

(12)
8.17.3 The training will be in maintenance of the equipment ordered and include trouble shooting And repair of the machine and accessories. The training to be imparted will cover all

Mechanical equipment/electrical equipment/electronic equipment/part programming in case of CNC machines. B.17.4 The Training at manufacturer's works will be provided during stage of assembly and testing of machine. To ensure this supplier will give at least three months notice to E.Rly/Kolkata to enable deputing trainees in time. B.17.5 In addition to the above, technical experts from the manufacturer/supplier will fully and adequately train operators nominated by the consignee during commissioning of the machine. B.18 CREDENTIALS AND QUALIFYING REQUIREMENTS OF TENDERERS : B.18.1 The Tenderer shall furnish the following information along with his offer FAILING WHICH, HIS OFFER SHALL NOT BE CONSIDERED AND NO BACK REFERENCE SHALL BE MADE, in this regard. (a) Firm shall provide satisfactory evidence that he is a licensed manufacturer, who regularly manufacturers the item offered and has adequate technical knowledge and practical experience. In case, where a manufacturer is not ready to quote directly, the procurement can be made only from his authorised agents/authorised Indian agents. In case of foreign suppliers, the authorised agent should produce valid authorization (in original) directly from OEM, not older than six months, against the tender case. Any authorization, other than from original manufacturer against the tender case shall be accepted and the absence of this offer shall be summarily rejected. The authorization shall be as per "The Proforma For Authority From Manufacturers" (Annexure-1) (b) Firm shall confirm that it has adequate financial stability and status to meet the obligations under the contract for this purpose it should submit "Commercial Details & Past Performance" as per Annexure3. (c) Firm has adequate design and manufacturing capacity to manufacture and supply the items offered within the delivery schedule offered by his. For this purpose "Proforma For Details of Manpower organization" as perAnnexure-2, shall be submitted. (a) Firm has established quality control system and organization to adequate control at all stages of the manufacturing process. For this purpose details as per Annexure-4 for "Proforma For Equipment and Quality Control Employed by The manufacture" shall be submitted. B.18.2 For purpose of Clause No. 18.1, the tenderer shall also submit a reference to prove that the machine models quoted are latest and have been earlier installed at at least 5 locations and have been successfully operating for at least 2 years. A list of users with their name, address, Telex No./Fax No./Phone No. and name of the contact person must be furnished, indicating firms where the quoted similar and earlier models are working. A performance statement (as per annexure-3) giving a list of major supplies effected in last 5 years of the items offered by him, giving details of purchasers name, address, order No. and date and the quantity supplied and whether the supply was made within the delivery schedule. IN THE ABSENCE OF INFORMATION REFERRED IN PARA 18.1 A TO D & PARA 18.2, THE TENDER IS LIABLE TO BE REJECTED.

(13)

ANNEX-1

PROFORMA FOR AUTHORITY FROM MANUFACTURERS


Dated.......................... THE PRESIDENT OF INDIA Acting through the Controller of Stores, Eastern Railway. Kolkata. Sir, Sub :- Diesel Locomotive Works, Varanasi's TenderNo................................................. Dateof Opening......................................... We, M/S ..........................................................................................an established and reputable Manufacturersof ................................................................................................ .............having offices at authorizeM/s factories at.................................................................and do hereby ........................................................

............................................................................................

(Name and address of Agents) to represent us, to bid, negotiate and conclude the contract on our behalf with you against. TenderNo ................................................................................ ..................................................... No company/firm or individual other than M/s ...................................................................... are authorised to represent us in regard to this business against this specific tender.

Your's Faithfully Signature............................................. Name( ................................................) for& on behalf of M/s ............................

(Name of manufacturer's) Note :- This letter of authority should be on the Letter-Head of manufacturing concern and should be signed by a person competent and having the power of attorney to bid the manufacturer. (14) ANNEX - 2

PROFORMA FOR DETAILS OF MAN POWER ORGANIZATION


(To be submitted on Letter-Head of Firm) 1. 2. 3. 4. 5. Name and full address of the firm. Telephone No./Telex No./Fax No. Telegraphic address. Location of the manufacturing factory. Details of Man Power : No. of Persons 5.1 5.2 Managerial cadre: Technical Supervisory Staff in charge of 5.3 5.4 5.5 Production & quality control: Skilled labour: Un-skilled labour employed: Max. No. of workers (skilled & Un-skilled) employed on any day during the 18 months preceding the date of application. 6. 7. 8. No of shifts. Organization chart of managerial cadre. Organization chart of different department. (Organization forAfter Sales Service & Quality Assurance to be given separately) Note :- If there is more than one Unit, chartfor each Unit to be given. Signature................................................. Technical Qualification

(15)

Name (.................................................... Designation. For (Name of Firm) M/s......................... Seal. .......................................................

ANNEX-3 COMMERCIAL DETAILS & PAST PERFORMANCE


TenderNo .....................................................Date of Opening............................................ A (i) COMMERCIAL DETAILS Is the firm a small scale unit registered

with NSIC ? If so, a copy of the registration certificate should be enclosed. (ii) (iii) (iv) B Name and address of the Banker. Acopy of the Banker's report should enclosed. Last 5 years turn over. (Documentary evidence should be enclosed) Acopy of current valid ITCC should be enclosed. PAST PERFORMANCE Details of orders of quoted item executed during the past five years should be furnished in the following format. S. No. Full address Remarks Order No. Description Qty Value Date of

Signature:..................................................

Name:.................................................. Designation:.................................................. Note: A certificate from the purchaser should preferably be enclosed to indicated that the contract Was satisfactorily performed

(16)

ANNEX-4

PROFORMA FOR EQUIPMENT AND QUALITY CONTROL EMPLOYED BY THE MANUFACTURER


Tender No..............................................Date of Opening ..............................................................

1. 2. 2.1

NAME OF THE FIRM LOCATION Postal Address i) Head Office Telephone No. (with STD Code). 0 Head Office ii) Works/Factory

i)Works/Factory 2.2

2.3 i) i)

Telegraphic address & Telex/Fax Head Office Works/Factory

3. DESCRIPTION OF FACTORY/WORKS i) Total Land area (In Sq. meters) ii) Total Covered area (In Sq. meters) iii) Different sub-units (with details of covered/uncovered area, etc.)

iv) Special features, if any: 4. i) NO. OF PERSONNEL EMPLOYED (CATEGORY-WISE) Managerial *

ii) Supervisory* Hi) Skilled artisans: iv) Unskilled The qualification may also be indicated. (17) 5. 5.1 GENERAL INFORMATION-TECHNICAL Description of different department in the factory/Works and function of each department, along with an organizational chart. 5.2 Detailed description of machinery and plant in each department (make and year procurement/commissioning to be provided. For special type of equipment copy of pamphlets/Write ups to be furnished so as to supplement the description). 5.3 Details of raw-materials held is stock (state whether imported/indigenous). 5.4 i) 5.5 6. 6.1 6.2 7 7.1 7.2 7.3 8 8.1 Production capacity of the quoted items Per month List of other Items, which the firm regularly manufacturers and corresponding production capacity. DESIGN CAPABILITY Details of Qualified Personnel (indicating qualification and experience) Other facilities available. MANUFACTURING PROCESS Level of In-house Facilities Important Items of Work done by Outside vendors Brief details of manufacturing process relevant to the items quoted. QUALITYASSURANCE Is the firm certified for ISO 9000 or equivalent? If so, please give certification details. If firm is certified for ISO 9000 or equivalent, no further information on para 8 is required to be filled in. 8.1.1 If no, does the firm contemplate to obtain ISO 9000 certification? What steps have been taken by the firm in that direction ? 8.2 Does the factory have an established Quality Assurance programme? If yes, please enclose i) , Peryear

a copy of the write-up if not, what plans are there if any for setting it up? 8.3 Details of QualityAssurance Organization. Names of key personnel, their qualifications, designations and position in overall management structure (explain with organization chart, if necessary).

(18) 8.4 8.5 8.6 above. i) i) ii) iii) 8.7 How is the calibration done? Frequency of calibration. System to ensure that calibration of above equipments does not fall overdue. Action taken if such calibration has fallen overdue. Source of procurement of raw-materials. important bought-outs, and steps taken to ensure their quality. 8.8 Details of inspection/checks done on material during various stages of the above manufacturing process. 8.9 Have acceptable values for the parameters inspected during above stage checks been laid down? If yes, what is the action taken if value of the parameter inspected does not meet the desired laid down value. 8.10 System for documentation of the results of the above stage checks.
9. AFTER -SALES -SERVICE

Quality control testing Facilities and Laboratory equipment available. Availability of gauges (Please give details) Calibration of laboratory/test equipment/gauges, indicated in para 8.4 and 8.5

9.1 9.2

Facilities Available at works and Branch offices. Assessment of Quality of service including Response Times.

Signature ...................................................................... Name ......................................................................

Designation ......................................................................

(19)

B.19 WARRANTY: B. 19.1 a) Warranty period for M&P will be 24 (twenty four) months from the date of commissioning and proving out of M&P. A maximum period of 2 (two) weeks will be allowed for attending and rectification of fault during the warranty period. b) Maximum down time during the warranty period will be 2% (two percent) for online M&P and 10% (ten percent) for Offline M&P calculated on quarterly basis. c) A penalty of 0.5% (zero point five percent) per week of the contract value will be levied for delay in response time for attending and rectification of faults beyond specified during the warranty period as detailed above. d) Maximum penalty to be levied on account of warranty failure will be 5% (five percent) of the contrabt value calculated during whole of warranty period and after that if there is any delay on the part of supplier, purchaser shall be entitled for encashment of WG bonds. B.19.2 In the event of failure of the machine during the warranty period, the warranty period shall be extended afresh, from the date the machine is rectified. It is only if the machine works without failure fora period of one year continuously that the firm shall be free from the warranty. B. 19.3 The supplier shall clearly spell out in offer, the facilities available with him to maintain adequately the machine/plant free of cost, during warranty period and also to maintain the machine/plant afterwarranty period on chargeable basis. 8.19.4 The bidder should also confirm that the parts will be made available by him even beyond warranty period. B.20 MODE OF DESPATCH: B.20.1 By Indigenous Suppliers :-Transport of machine/plant from manufacturer's/supplier' premises to consigned at site will be arranged by supplier. The machine/plant will be despatched by road for free delivery at site at Dankuni Factoey. The machine shall be despatched after proper inspection and issue of inspection Certificate by Inspecting Authority, duly packed

in proper (secure) packing, suitable for rough conditions of transit and shall be duly insured for safe arrival at DLWNaranasi. 8.20.2 By Overseas Suppliers :- For Overseas Supplies Conditions specified in Bid Document Part 1, Para 16 (Shipping Arrangement) will apply.

(20)

C. SPECIAL CONDITIONS OF CONTRACTS


Tenderer shall please note that Special condition shall override the similar conditions, if any, appearing in Bid Documents/Advertised Tender Documents/IRS Conditions of Contract. C.1. SECURITY DEPOSIT/PERFORMANCE BANK GUARANTEE: C.1.1 For the performance of the contract, Performance Guarantee (PG)/Security Deposit in cash or through Bank Guarantee. Equivalent to 10% of value of the contract, is required to be submitted by the contractor within 30 days of issue of "Advance Acceptance" (as per proforma enclosed in Annexure-1). This Bank Guarantee shall remain valid till the machine is Commissioned and provedout. C.1.2 A Warranty Guarantee (WG) through Bank Guarantee equivalent to 10% of value of the contract towards warranty obligations (as per proforma enclosed in Annexure-2), is required to be submitted to cover the warranty period, before claiming balance 20% payment. It may be noted that 20% payment shall not be released without execution of the requisite and valid WG. C.2 PAYMENT TERMS: i) Payment to foreign suppliers: Payment against foreign supplies shall be made through Letter of Credit. All charges, including the confirmation charges of L.C. levied by foreign Banks, shall be borne by the supplier. The standard payment terms subject to recoveries if any, under the liquidated damages clause and general conditions of contract, will be as under: a) 80% of the payment against irrevocable L.C. on proof of inspection certificate and shipping documents within 30 days of receipt of shipping documents as specified. b) Balance 20% payment within 90 days after installation/ commissioning and proving test of M&P subject to submission of bank guarantee for an amount of 10% of contract value, as warranty security. ii) Payment against indigenous supply: The standard payment terms subject to recoveries if any, under the liquidated damages clause and general conditions of contract, will be as under: a) 80% of the payment on proof of inspection certificate and Receipted challan signed by Dy. CME/Plg/E.Rly/Kolkata or indenter regarding correct receipt of materials in good

condition at site. b) Balance 20% payment within 90 days after satisfactory installation/ commissioning and proving test of M&P subject to submission of bank guarantee for an amount of 10% of contract value, as warranty security. (21)

C.3

PENALTIES:

In case of failure on the part of the contractor liquidated damages shall be levied on him as under: C.3.1 For delay in supply of foundation drawings and related information to Dy.CME/Plg/E.Rly/Kolkata. Varanasi beyond a period of one month of placement of purchase order/issue of Advance Acceptance, a penalty or 1/4% of the cost of the machine per week subject of maximum of 2% will be levied against the supplier. C.3.2 For delay in attending joint inspection of the machine/plant on its arrival at Dankunmi Factory beyond a period of 15 days from receipt of intimation by the contractor a penalty of 1/4% of the cost of the machine per week subject to maximum of 2% will be levied against the supplier. C.3.3 For delay in commissioning and proving out of the machine by the time specified in the letter of acceptance or contract, purchaser may withhold, deduct or recover from the contractor as penalty, a sum @ 2% (two percent) of the price of M&P which the contractor has failed to commission as aforesaid for each and every month (part of a month being treated as a full month) during which the M&P may not have been commissioned, subject to an upper limit of 10% (ten percent) of contract value. C.3.4 For delay in responding/attending to repairs and replacement of parts during warranty period within 15 days from the date of receipt of intimation by the supplier/contractor a penalty of 0.5% of the value of the contract per week will be imposed subject to maximum of 6%. (22)

ANNEXURE-1 PROFORMA OF BANK GUARANTEE FOR CONTRACT PERFORMANCE GUARANTEE BOND Ref................................................................................................................. ......................................................................................................................Date ...................................................................................................................... Bank Guarantee No . To, THE PRESIDENT OF INDIA Acting through the FA& CAO Eastern Railway Kolkata 700 001. 1. Against contract vide Advance Acceptance of the Tender No........................................ ..................................dated...........................covering supply of......................... ..................................................................................................................(hereinafter called the said 'contract') entered into between the President of India and............................................. (hereinafter called the Contractor) this is to certify that at the request of the Contractor we ................................ ................................................Bank Ltd. are holding in trust in favour of the President of India, the Amount of ..............................(write the sum here in words) to indemnity and keep indemnified the President of India, (Govt. of India) against any loss or damage that may be caused to or suffered by the President of India (Govt. of India) by reason of any breach by the Contracts of any of the terms and conditions of the said contract and / or the performance thereof. We agree that the decision of the President of India (Govt. of India), whether any breach of any of the terms and conditions of the said contract and / or in the performance thereof has been committed by the Contractor and the amount of loss or damage that has been caused or suffered by the President of India (Govt.of India) shall be final and binding on us and the amount of the said loss or damage shall be paid by us forthwith on demand and without demur to the President of India (Govt. of India). 2. We......Bank Ltd., further agree that the guarantee herein contained shall remain in full force and effect during the period that would be taken for satisfactory performance and fulfilment in all respects of the said contract by the Contractor i.e. till.................. ..........(viz. the date upto 12 months after the date of last shipment / delivery of the goods ordered) hereinafter called the 'said date' and that if any claim accrues or arises against us............................. ....................................Bank Ltd., by virtue of this guarantee before the said date the same shall be inforceable against us.....................................................Bank Ltd., notwithstanding the fact that the same is enforced within six months after the said date, provided that notice of any such claim has been given to us...............................................Bank Ltd., by the President of India (Govt. of India) (23)

before the said date, Payment under this letter of guarantee shall be made promptly upon our receipt of notice to that effect from the President of India (Govt. of India) 3. It is fully understood that this guarantee is effective from the date of the said contract andthat we .................................................................Bank Ltd., undertake not to revoke this guarantee during its currency without the consent in writing of the President of India (Govt. of India) 4. We undertake to pay that Government any, money so demanded notwithstanding any dispute or disputes raised by the Contractor in any suit or proceeding before any court or Tribunal relating thereto our liability under this present being absolute and unequivocal. The payment so made by us under this bond shall be valid discharge of our liability for payment thereunder and the Contractor shall have no claim against us for making such payment. 5. We ...............................................Bank Ltd., further agree that the President of India (Govt. of India) shall have fullest liberty, without affecting in any manner our obligations hereunder to vary any of the terms and conditions of the said contract or to extend time of performance by the Contractor from time to time or to postpone for any time or from time to time any powers exercisable by the President of India (Govt. of India) against the said Contractor and to forebear or enforce any of the terms and conditions relating to the said contract and We..................................................................................................Bank Ltd. shall not be released from our liability under this guarantee by reason of any such variation or extension being granted to the said Contractor or for any forbearance and /or omission on the part of the President of India or any indulgence by the President of India to the said Contractor or by any other matter or thing what-so-ever,which under the law relating to sureties, would, but not for this provision have the effect of so releasing us from our liability underthis guarantee. 3. This guarantee will not be discharged due to the change in the constitution of the Bank or the Contractor. Date.............................. Place.............................. Witness.............................. Signature...................................

PrintedName ........................ ..... (Designation)


...................................I ...........

(Bank's Common Seal)

(24)

ANNEXURE-2

PROFORMA OF BANK GUARANTEE FOR 10% CONTRACT VALUE TOWARDS WARRANTY GUARANTEE
To, THE PRESIDENT OF INDIA Acting through the FA& CAO. Eastern Railway, Kolkata-700 001. Sub:- Guarantee No.................................................for...............................(Amount) Covering equipment (s) Serial No..............................................................supplied to (Consignee/s) Ref. Contract No....................................................................dated............................ Placed on M/s.............................................................................................................. 1. WHEREAS M/s.................on of our constituents. (hereinafter called the "Seller") have agreed to you (hereinafter referred to as the "Government'). No of......(give description) as per contract No.......... date....................................(hereinafter called "the said contract"). 2. AND WHEREAS according to the terms of said contract, it has been stipulated that payment of 10% of the value of the stores would be made. provided that the Seller furnish to the Purchaser a Bank Guarantee from a recognized bank, acceptable to the Purchaser for 10 percent of the value of the said contract, valid for a period covering in full the Guarantee period as per the warranty clause of the said conditions of the contract, being the conditions attached to and forming part of the said contract 3. AND WHEREAS the Sellers have approached us to give the said Bank

Guarantee on their behalf in your favour for an amount representing 10 percent of the value of the stores despatched which you have agreed to accept. 4. That in consideration of the promises and at the request of the said Sellers, we (Bank Ltd.) hereby irrevocably undertake and guarantee to pay to the Government of India or at such other place as may be determined a by you forth-with on demand and without any demur, any sum upto a maximum amount of.... (Rs ) representing 10 percent of the value of the stores despatched under the said contract in case the sellers make default in paying the said sum or make any default in performance, observance of discharge of the guarantee contained in the said contract. 5. We ......... (Bank Ltd.) agree that the decision of the Government, whether any default has occured of has been committeed by the Sellers in the performance, observance of discharge of the guarantee aforesaid shall be conclusive and binding on M/s

(25) 6. Government shall be at liberty, from time to time, to grant or allow extension of time or give other indulgerce to the said Sellers or to modify the terms and conditions of the contract with the said Sellers without affecting or imparin this guarantee or our liability hereunder. 7. We ....................... (Bank Ltd.) undertake to pay to the Government any money so demanded notwithstanding any dispute of disputes raised by the Sellers in any suit or proceeding pending before any court or Tribunal, relating thereto our liability under this present being absolute and unequivocal. The payment so made by us under this bond shall be a valid discharge of our liability for payment thereunder and the Sellers shall have no claim against us for making such payment. 8. This bank guarantee comes into force when the balance twenty percent of the value of the stores, shipped pervessel ..............................................vide Bill of Lading No.......................................... dated................................................or R/R No...........................................dated.................................... (in the case of indigenous contract) under the said contract, has been paid will remain in full force and effectupto ..................................................i.e. for......................................................months counted from the date of commissioning, shall continue to be enforceable for further five months i.e. upto (date), hereinafter called the said date. 9. This guarantee will not be discharged due to the change in the

constitution of the Bank of the Sellers 10. That no claim under this guarantee shall be entertained by us unless the same has been prefereed by the Government wthin the said date. 11. BG(s) being furnished will be honoured under all conditions. Any doubt about the genuineness of stamp-paper used in BG will not render BG invalid because stamp-paper has been purchased by the vendor/contractor of Eastern Railway namely M/s........................................................... ...........................for contract no.......................................................... dated........................................... and, therefore, is responsible for the genuineness. Date Signature................................... Place Name ............................. Witness (Designation) Printed

.............................................. (Bank's Common Seal) (26)