<Author> May 19, 1999 May 28, 1999 <Document Reference Number> DRAFT 1A
Document Control
Change Record
4
Date 19-May99
Author <Author>
Versio n Draft 1a
Reviewers
Name
Position
Distribution
Copy No. 1 2 3 4
Note To Holders: If you receive an electronic copy of this document and print it out, please write your name on the equivalent of the cover page, for document control purposes. If you receive a hard copy of this document, please write your name on the front cover, for document control purposes.
Legacy Data Clean-up and Normalization (v. DRAFT 1A ) Company Confidential - For internal use only
Contents
Document Control.......................................................................................ii Introduction................................................................................................1 Purpose.................................................................................................1 Background...........................................................................................1 Scope and Application...........................................................................1 Audience...............................................................................................1 Business Object Description.......................................................................2 Business Object To Be Manually Converted: <Business Object To Be Converted>...........................................................................................2 Data Elements To Be Converted/Not Converted.........................................3 Data Elements To Be Converted...........................................................3 Data Elements Not Converted...............................................................4 Legacy Data Clean-up and Normalization...................................................5 Data Clean-up.......................................................................................5 Data Normalization...............................................................................5 Century Date Compliance.....................................................................5 Conversion Responsibility and Timeline.....................................................6 Conversion Responsibility.....................................................................6 Conversion Dates..................................................................................6 Conversion Procedures...............................................................................7 <Form Name>......................................................................................7 <Zone Name> Zone.............................................................................7 Open and Closed Issues for this Deliverable...............................................8 Open Issues...........................................................................................8 Closed Issues.........................................................................................8
Legacy Data Clean-up and Normalization (v. DRAFT 1A ) Company Confidential - For internal use only
Doc Ref:
Introduction
Purpose
The purpose of the Manual Conversion Procedures document is to describe the procedure to be followed and the values to be entered when manually converting legacy data for <Business Object To Be Converted>. Use the following information as a detailed guide for converting <Business Object To Be Converted> legacy data that requires manual entry into <Target Application>. The information provided below includes: a description of the business object a listing of the related legacy data elements that will be converted or not converted data clean-up and normalization requirements responsibilities and timelines conversion procedures
Background
The information in this document has been defined as the result of discussions between project staff, <Company Short Name> technical staff, and <Consulting Services Provider> consultants.
Audience
This document is intended for the following individuals: <Company Short Name> conversion project staff outside consultants reviewers of data conversion deliverables
(v. )
Legacy Data Clean-up and Normalization Company Confidential - For internal use only
Doc Ref:
(v. )
Legacy Data Clean-up and Normalization Company Confidential - For internal use only
Doc Ref:
(1) Ref. #
(4)
(5)
(10) Validation
(11) Rule #
(v. )
Legacy Data Clean-up and Normalization Company Confidential - For internal use only
Doc Ref:
(v. )
Legacy Data Clean-up and Normalization Company Confidential - For internal use only
Doc Ref:
Data Clean-up
Below is a description of the data clean-up efforts required for the conversion of <Business Object To Be Converted>:
Data Normalization
Below is a description of the data normalization that will occur for the conversion of <Business Object To Be Converted>:
(v. )
Legacy Data Clean-up and Normalization Company Confidential - For internal use only
Doc Ref:
Conversion Responsibility
The Manager responsible for the manual conversion of <Business Object To Be Converted> is <Name of Responsible Manager>. Additional resources devoted to this effort include:
Conversion Dates
The start date for the manual conversion of <Business Object To Be Converted> is as follows:
The end date for the manual conversion of <Business Object To Be Converted> is as follows:
(v. )
Legacy Data Clean-up and Normalization Company Confidential - For internal use only
Doc Ref:
Conversion Procedures
To manually convert <Business Object To Be Converted>, navigate using the following Oracle <Target Application> menu path:
<Navigation Path>
<Form Name>
The purpose of this form is to:
Form Name
Field Name
Recommended Value <Enter the legacy system data element or the word Default if a default value will be entered in this field>
Default Value <Enter the default value that has been listed in a previous component of this deliverable>
Notes <Additional Comments to help the person who is manually entering this data element>
(v. )
Legacy Data Clean-up and Normalization Company Confidential - For internal use only
Doc Ref:
ID
Issue
Resolution
Responsibility
Target Date
Impact Date
Closed Issues
ID
Issue
Resolution
Responsibili ty
Target Date
Impact Date
(v. )