Escolar Documentos
Profissional Documentos
Cultura Documentos
MAIN STAGES IN POWER STATION ERECTION READINESS OF SITE FOR ERECTION ( RAILWAY SIDING , STORAGE FACILITY , LABOUR COLONY,ERECTION TOOLS AND TACKLES) METHODS / TECHNICS OF ERECTION
PREPERATORY WORKS
DE-VEGITATION OF SITE AREA LEVELLING AREA GRADING TO BRING IT TO PLANNED BLOCK LEVEL TO MAKE THE SITE READY FOR START OF CIVIL WORK EXCESS EARTH DISPOSAL
CIVIL WORKS
PILING WORK
PILING DESIGN AS PER LOAD DATA FROM EPC CONTRACTOR PILING PILE TESTING PILE CAP AND FOUNDATION FOR STRUCTURE ( FDN CASTING AFTER JOINT CHECKING WITH STRUCTURAL ERECTOR)
STRUCTURAL ERECTION
TAKING OVER OF FOUNDATION
CHECK FOR LOCATION CHECK FOR LEVEL CHECK FOR BOLT/POCKET LOCATION
STRUCTURAL ERECTIONCONTD
STRUCTURAL ERECTION
BLUE MATCHING OF PACKER PLATES WITH FDNS FIRST STAGE COLUMN ERECTION & ROUGH ALIGNMENT FURTHER STAGES COLUMNS , FRAME BEAMS AND BRACINGS ERECTIONerecn photos\chp str.jpg INTERMEDIATE AND FINAL ALIGNMENT FLOOR BEAMS AND RELEASE OF FRONT FOR FLOOR CASTINGerecn photos\typical floor in str.jpg
EQUIPMENT ERECTION
TAKING OVER OF FOUNDATION
CHECK FOR LOCATION CHECK FOR LEVEL CHECK FOR BOLT/POCKET LOCATION
DEVISING HOISTING STRATAGY AND SELECTION OF HOISTING T&P FOR PLACEMENT OF EQUIPMENT
EQUIPMENT ERECTION
EQUIPMENT PLACEMENT AND ROUGH LEVELLING WITH BOLT GROUTINGerecn photos\Picture placemnt of id fan.jpg/erecn photos\tg box up.jpg FINAL LEVELLING AND GROUTINGerecn photos\mill erection.jpg ALIGNMENT OF ROTARY EQUIPMENTS ERECTION OF PIPING AND DUCTINGerecn photos\flue gas ducting.jpg PRESSURE /LEAKAGE TEST OF PIPING AND DUCTING
ELECTRICAL ERECTION
TAKING OVER OF FRONT FROM STRUCTURAL ERECTOR / EQUIPMENT ERECTOR ERECTION OF CABLE TRAY SUPPORT STRUCTUREerecn photos\cross country cable tray.jpg CABLE TRAY ERECTION FOR POWER AND CONTROL CABLEpipe rack.jpg CABLING AS PER CABLE SCHEDULE
C&I ERECTION
ERECTION OF FIELD INSTRUMENTS AND JBS PLC / CONTROL PANEL ERECTION CABLING BETWEEN INSTRUMENTS , I/O PANELS & PLC / CONTROL PANELS CABLING BETWEEN MCC AND PLC/ CONTROL PANELS
COMMISSIONING PHASE
RECHECKING OF ERECTION PRECOMMISSIONING CHECKS POWERING UP OF PANELS AND EQUIPMENTS NO LOAD RUN OF MOTORS COMMISSIONING OF FIELD INSTRUMENTS AND CONTROL SYSTEMS CHECKING OF LOGICS AND INTERLOCKS INITIAL RUN AND CHECK FOR HEALTHINESS OF THE SYSTEMS
MAJOR MILESTONES
Starting from Zero date( award of main plant pkg) Boiler erection start11 months Drum Lifting 17 months Start of Cond erction 21 months Start of TG erect 23 months Boiler hydro test 29 months TG box up 32 months BLU and AVO 35 months Compln of TG oil flushing35 months Steam blowing Compln 37 months Synchronization 39 months Coal firing 39 months Trail operation 42 months
ERECTION SCHEDULING
TYPES OF PROJECT SCHEDULES
MASTER NETWOR SCHEDULE OR L-1 NETWORK PACKAGE SCHEDULE OR L-2 SCHEDULE L-3 SCHEDULE QUANTITATIVE SCHEDULE
PACKAGE SCHEDULE OR L-2 SCHEDULE CONTD IT IS CONTRACTUALLY BINDING DOCUMENT BETWEEN NTPC AND THE CONTRACTOR IT ALSO SHOWS THE INTERRELATION BETWEEN VARIOUS ACTIVITIES AND DATE OF RELESE OF FRONTS TO THE CONTRACTOR
L-3 SCHEDULE
THIS SCHEDULE IS ACTIVITY SPECIFIC PREPARED AT PROJECT LEVEL FOR CLOSE MONITORING OF CRITICAL ACTIVITIES. SAMPLEL3_mech_1 CT.xls
QUANTITATIVE SCHEDULE
MAINLY FOR THE ITEM RATE CONTRACTS THIS SCHEDULE SHOWS QUANTITY FOR DIFFERENT ARES OF THE PACKAGE AND THEIR COMPLETION SCHEDULE. QUANTITIES ARE SPREAD OUT IN THE COMPLETION SCHEDULE.
RECORDING OF OUTPUT
RECORDING FOR THE PURPOSE OF BILLING IS DONE AS PER BILLING BREAK UP FOR THE ERECTION OF EQUIPMENT COMPLETED FOR ITEM RATE CONTRACTS , INSTEAD OF BBU THERE IS BOQ ( BILL OF QUANTITIES)
REPORTING
PROGRESS REPORTING
MONTHLY PROGRESS REPORT WEEKLY PROGRESS REPORT DAILY PROGRESS REPORT
THANK YOU
.