Escolar Documentos
Profissional Documentos
Cultura Documentos
Method study Method Improvement Time Study Idle Time Creative Production Planning Factory Production Capacity Special Machine Production Capacity
METHOD IMPROVEMENT
Once the method study is done , one looks for better ways to save time and less effort by the operator . this could be done by improving work motions / provide work aids like gauges , folders , attachments , trolleys , movers , tracks or machine automation.
POTENTIAL CAPACITY:
Maximum capacity adjusted for efficiency.
COMMITED CAPACITY:
Total hours previously allocated for production during a certain time period.
REQUIRED CAPACITY :
Sam or SAH necessary to produce a specified volume in a certain time period .
EXCESS CAPACITY :
Difference between potential capacity and required capacity .
What is the potential capacity of united garments company for the 10 working days ?
Ans. 10 machines x 7 hours /day = 70 hours/day x 90% efficiency = 63 potential
production hours /day. Potential capacity for 10 days = 10 days x 63 hours = 630 hours potential capacity.
Require more time from buyer to accommodate the 170 hours . Work overtime to cover the 170 hours. Increase more machines and operators . Find way to increase efficiency level to 100 % . Use creative production technique to increase productivity . Try to eliminate idle time within production to decrease throughput time .
Assess the performance of individual operators.
DATE
01-Jul
BUYER
J.C.P.
P.O. #
2442
ITEM
L.S. TOP
QTY
2000
SAM / UNIT
12 SAM
TOTAL SAH
400
AVAIL SAH
8960
02-Jul
04-Jul
SEARS
GAP
1123
G-07
S.S. TUNIC
BLOUSE
4000
12,000
10 SAM
15 SAM
667
3000
8293
5293
15-Jul
17-Jul
JCP
SEARS
2443
1124
L.S. DRESS
S.S TUNIC
15,000
4000
20 SAM
10 SAM
5000
667
293
-374
DATE 01/07
BUYER J.C.P.
P.O. # 2442
ITEM # 1 B.S.
QTY 2000 10
SAM / UNIT
02/07
04/07 15/07 17/07
SEARS
J.C.P. JCP SEAR
1123
G-07 2443 1124
B.S
FR.B Q.C CUSH
4000
3000 6000 3000
10
20 15 20
667
1000 1500 1000
ITEM-2
QTY
SAM
SAH
ITEM-3
QTY
SAM
SA H
ORDER SAH
AVAIL SAH
Fitted
2000
10
334
Pc
3000
250
928
8432
Fitted
4000
10
667
Pc
6000
500
1834
6598
Fr.Fit
3000
20
1000
Fr.Pc.
5000
10
833
2833
3765
Sham -
8000 -
10 -
1333 -
2833 1000
932 -68
Estimate the rate or time for completion of each operation. Determine the required capacity for an order or style. Determine the production start dates and completion dates for orders. Plan the daily volume that should have been completed. Determine the backup inventory needed to support the work flow. Determine how many operaqtors and machines should be performing on each operation. Schedule specialized equipment . Monitor daily production delays.
QUIZ
QUESTION ONE.
Plant capacity is :
A projection of the total hours available for production in a given time period. Number of garments a plant can produce in a certain time period Number of machines available to meet the capacity of orders
Committed capacity is :
The orders which P.O. Still not received Orders waiting for confirmation Total hours previously allocated for production in certain time
Available capacity is :
The volume which can be still produced in a plant The styles which orders can be taken and ship on time The difference between plant capacity and committed capacity for a certain time period
If a garment has Sam = 6 min . the plant capacity is 4800 min/day . efficiency of plant at 100% . how many days will it take to produce 12000 garments ? how many machines does the plant own ?
10 days . 10 machines 2.5 days . 20 machines 5 days . 40 machines 15 days . 10 machines
QUIZ
QUESTION TWO . What will be plant potential capacity ? If the plant has: 125 machines 6 working hours / day 5 working days / week Efficiency level 80% Answer : Plant capacity / day:_____________________ Plant capacity / week:____________________
QUESTION THREE. What will be the required order capacity ? If the order details are : Order quantity : 30,000 garments Sam / garment = 15 Mins Answer : Required capacity total hours :______________________ Days required to complete order:___________________
Answer: A- Total Sam/garment:________________________________________ B-Total machines required to produce 320 garments/day? _______________ C-How many days required to produce 2880 garments? _________________ D- how many machines required to produce 24,000 in 20 days? ______________
OP#
OPERATION
SAM
PROD/DAY
EQUIP
T.EQUIP
N.PROD
N.EQP
1-
JOIN SHLD JOIN/TU RN/SET COL S. SLV/CLS SIDE JOIN/TURN/ S. CUFFS JOIN/TURN/ S.W.BA ND
0.34
1411
O/L
1411
23-
1.647 1.5
291 320
O/L O/L
4 3
378 320
3 3
4-
2.78
172
O/L
210
5-
2.3 8.567
208 1000
O/L ----
5 -
-0.40= 1.90 19
253 7.290
4 16
TOTAL SAM =
Operation
SAM
Prod/day
Manpower Req.
1-Turn cuff(2) 0.50 960 1 2-Turn Col 0.37 1297 1 3-Turn W Band 0. 40 1200 1 Productivity increase: 8.567 7.290 = 1.277 / 8.567 = 15 % Separating indirect labor resulted into : 15% productivity increase. 1000+150 = 1150 output 19 machines-16 machines = 3 less machines Indirect labor cost the operator cost saved. 3 machines less inline . less space. 3 less machine . machine cost saved.
Plant capacity is :
Projection of the total hours available for production in a given time period. Number of garments a plant can produce in a certain time period Number of machines available to meet the capacity of orders
Committed capacity is :
The orders which P.O. Still not received Orders waiting for confirmation Total hours previously allocated for production in certain time
Available capacity is :
The volume which can be still produced in a plant The styles which orders can be taken and ship on time The difference between plant capacity and committed capacity for a certain time period
If a garment has Sam = 6 min . the plant capacity is 4800 min/day . efficiency of plant at 100% . how many days will it take to produce 12000 garments ? how many machines does the plant own ?
10 days . 10 machines 2.5 days . 20 machines 5 days . 40 machines 15 days . 10 machines
QUESTION TWO .
WHAT WILL BE PLANT POTENTIAL CAPACITY IN SAHS ? IF THE PLANT HAS: 125 MACHINES 6 WORKING HOURS / DAY 5 WORKING DAYS / WEEK EFFICIENCY LEVEL 80% PLANT CAPACITY / DAY:_125 X 6HR X80%= 600 HRS PLANT CAPACITY / WEEK: 600 HRS X 5 = 3000 HRS
ANSWER :
QUESTION THREE.
WHAT WILL BE THE REQUIRED ORDER CAPACITY ? IF THE ORDER DETAILS ARE ORDER QUANTITY : 30,000 GARMENTS SAM / GARMENT = 15 MINS
ANSWER : REQUIRED CAPACITY TOTAL HOURS : 30,000 X 15 SAM/PC / 60 = 7500 HRS DAYS REQUIRED TO COMPLETE ORDER: 7500 HRS -------------= 12.5 DAYS 600 HRS/DAY
Question four. Garment breakdown sheet Product description : Fleece top L/S with neck band / cuff & w. Band all sewn on over lock machines. Fill in blanks. 8 hours work time /day. 26days/month. 100% efficiency. Op No Operation Sam Prod/day Machine Type Machine Qty 1 Join Shld 3.00 160 O/L 2 2 Close/set n.Band 4.50 106 O/L 3 3 Set sleeve 3.00 160 O/L 2 4 Close side 1.50 320 O/L 1 5 Close/set cuff 6.00 80 O/L 4 6 Close/set w.Band 3.00 160 O/L 2 Answer: A- Total Sam / garment : 16 Sam B- Total machines required to produce 320 garments/day ? 14 machines C- How many days required to produce 2880 garments ? 2880 / 320pcs/day= 9 days D-How many machines required to produce 24,000 in 20 days ? ? 24,000 / 20 days = 1200 units Req./day. 1200 units x 16 Sam = 19200 Sam/ 480mins= 40 machine
CASE STUDY
A company called blue grass industries in Kentucky , USA was producing Men's turtle neck pullovers in Velor fabric for sears catalog . The company had 280 machines in production and was producing approximately 15,000 units per day. At the time of my visit , the prevailing Sam / unit was established as follows :
Op#
123456-
Operation
Sew neck label Join shoulder Join/turn/set collar Set slv/close side Join/turn/set cuffs Join/turn/set w.Band
Sam
0.313 0.340 1.647 1.500 2.780 2.300
Prod/day
1534 1411 291 320 172 208
Equip
S/n O/l O/l O/l O/l O/l
Total Equip
1 x10= 10 1x10= 10 5x10=50 5x10=50 9x10=90 7x10=70
Total Sam = 8.880 1534 Equipment requirement : S/N = 10 O/l = 270 Total = 280 Production output target = 15,000 units per day.
-----
28x10=280
The segregation of indirect labor from direct labor would improve operator productivity and less machines would be required to meet the designated target.
Due to less machine requirement , less work space would be required in production line . investment in machine would also be a saving to the company.
Turner crew would clip . turn and stack ready for operator to attach on to the garment.
Time study results were as follows :
Collar clip / turn & stack Sam = 0.085 + 0.315 = 0.400 Cuffs (2) clip / turn & stack Sam =0.333+ 0.934 = 1.267 W.Band clip / turn & stack Sam = 0.117 + 0.583 = 0.700
RESULTS:
After Application Of The Logical Theory , The Final Results Were Alarming !!!!!!
Total Sam = 7.491 1534 Equipment Requirement : S/N = 10 O/L = 230 Total = 240
TOTAL SAM
2.367
1500
---------
76
TOTAL INDIRECT LABOR = 76 PRODUCTION OUTPUT TARGET = 15,000 UNITS PER DAY.
Test
Question One : If The Factory Continue Using 280 Machines In Production , What Would Be The Output With New Sam Derived ? Answer ; ______________________ Units/Day Question Two : In The Above Case In Q-1 , How Much Indirect Labor Would Be Required With 280 Machines In Production ? Answer :__________________ Labor Force Question Three : If Minimum Wage /Hour Is $ 4.00 . What Be The Labor Cost Per Garment ? Answer : $____________ / Garment
Test
Question Four : If The Operator Wage Is $8.00/Hour , Calculate : Total Cost Of Garment At Time When No Improvement Was Executed. Answer : $____________ / Garment
Cost Of Garment After Improvement Including Direct & Indirect Labor . 8 Hour / Day Work Time.
Answer : $_____________ / Garment Question Five :
In The Above Case Study , Calculate Following Comparing Before And After Method Improvement . Productivity Increase % = ____________________ % Cost Savings / Garment In Dollars = $________________ . % Savings In Dollars =___________________ %
Answers
Test Paper Answers : Question One: Total Machine = 280 New Sam = 7.491 Production Minutes Available = Machine X 480 Min = 280x480=1,34,400 Production Output= Available Mins = 1,34,400 = 17,942 Units/Day Sam 7.491
Question Two : New Output = 17,942 Units Labor Sam = 2.367 Production Output = Available Mins (Laborx480) Sam Labor Req = Output X Sam = 17,942 X 2.367 = 88.48 Labor/Day 480 480 = 89 Labor / Day Question Three : Labor Wage / Hour = $ 4.00 Wage / Min = 0.066 Labor Sam = 2.367 Cost Of Labor /Garment = Sam X Cost /Min = 2.367 X 0.0666 = $ 0.1576 / Garment = $ 0.16 / Garment
Question Four:
Operator Wage / Hour = $ 8.00 Operator Wage/Min = $ 0.1333 Cost / Garment = Cost / Min X Sam / Garment = $0.1333 X 8.88 = $ 1.184 / Garment Operator Wage / Min = $0.1333 Labor Wage / Min = $ 0.0666 Cost Of Labor = Sam X Wage / Min = 2.367 X 0.0666 = $ 0.16 Cost Of Operator = Sam X Wage / Min = 7.491 X 0.1333 = $ 0.998 Total Cost / Garment = $ 1.158
Question Five:
A- % Productivity Increase = New Output Previous Output X 100 Previous Output = 17,942 - 15,000 X 100 = 19.61 % 15,000 B-cost Savings/ Garment = Previous Cost New Cost = $ 1.184 - $ 1.158 = $ 0. 026 / Garment C- % Savings In Dollar = Cost Savings / Garment Previous Cost/Garment = $ 0.026 = 2.19 % $ 1.184