Você está na página 1de 61

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

PETROBRAS Strategic & Business Plan 2009-2013


Opportunities for foreign suppliers

Houston, May 5th 2009 OTC 2009

Paulo Srgio Rodrigues Alonso D.Sc. Materials Engineering Manager


1

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

DISCLOSURE
The presentation may contain forecasts about future events. Such forecasts merely reflect the expectations of the Company's management. Such terms as "anticipate", "believe", "expect", "forecast", "intend", "plan", "project", "seek", "should", along with similar or analogous expressions, are used to identify such forecasts. These predictions evidently involve risks and uncertainties, whether foreseen or not by the Company. Therefore, the future results of operations may differ from current expectations, and readers must not base their expectations exclusively on the information presented herein. The Company is not obliged to update the presentation/such forecasts in light of new information or future developments. Cautionary Statement for US investors The United States Securities and Exchange Commission permits oil and gas companies, in their filings with the SEC, to disclose only proved reserves that a company has demonstrated by actual production or conclusive formation tests to be economically and legally producible under existing economic and operating conditions. We use certain terms in this presentation, such as oil and gas resources, that the SECs guidelines strictly prohibit us from including in filings with the SEC. 2

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

PRESENTATION OUTLINE
Main objectives; PETROBRAS Overview; Strategic and Business Plans Highlights: E&P; Downstream; Petrochemical; Gas and Energy;

Critical Goods and Services and equipment quantities; PETROBRAS Strategies for purchasing goods and services; Register Requirements for Foreign Suppliers; PROMINP Governmental Program and Local Content; Conclusions.
3

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

MAIN OBJECTIVES

To provide a broad overview of PETROBRAS main investment programs, included in the Strategic and Business Plan for the period 2008-2012, aiming to expand the basis of selected goods and services foreign suppliers interested to come to Brazil and register with the Company in order to participate in the projects Vendor Lists.

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

Petrobras Overview

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

A WORLD-CLASS, PUBLIC, INTEGRATED ENERGY COMPANY


Among its peers, Petrobras has the:

4th largest Proven Reserves; 5th largest Oil & Gas Production;

6th largest Refining Capacity; 6th largest Market Value.

STRATEGIC VISION: TO BE ONE OF THE WORLDS FIVE LARGEST PUBLICLY TRADED OIL PRODUCERS
30,000
Production Target: 2020

25,000

Reserves(mmboe)

20,000
Production Target: 2009

Production Target: 2013

XOM BP

15,000

PBR
10,000

TOT

COP

CVX

RDS

5,000 2,000 2,500 3,000 3,500 4,000 4,500 5,000 5,500

Production(mboe/d)

2007 (SEC) reserves and production


Source: Bloomberg and Company Reports (2007 SEC Proven Reserves Data, 9M08 Oil & Gas Production data, 2008 Refining Capacity data and 2008 Market Value data)

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

DOMINANT POSITION IN A LARGE AND GROWING EMERGING MARKET

2007 Total Oil Consumption by Country (mmbo/d)


20.7 7.9

Brazil is worlds eighthlargest oil consumer

Total Oil Consumption mb/d (index)


160 150 140 Brazil OECD World

Brazil oil consumption growing at 2.4% p.a.


130

OECD oil consumption growing at 1% p.a.

120 110 100 1998 1999 2000 2001 2002 2003 2004 2005 2006 1990 1991 1992 1993 1994 1995 1996 1997 2007

Source: BP Statistical Review 2008, PFC Energy

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

HIGH-POTENTIAL PORTFOLIO IN ONE OF THE WORLDS MOST EXCITING PROVINCES...

Kashagan

Sakhalin II Sakhalin I

Thunder Horse

Shah Deniz Khurais Roncador Marlim Albacora Iara Jupiter Tupi Carioca

Kurmangazi Azadega n Anaran

Agbami Akpo Dalia Kizomba Girassol, Jaz, Rosa

82% of our total crude production currently comes from Campos Basin

Development of the Santos Basin sub-salt play will drive our longterm production growth

Significant light oil and gas discoveries have been made in the Espirito Santo Basin

Circle size indicates estimated reserves

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

Strategic and Business Plans highlights

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

VISION 2020 AND CHARACTERISTICS

Vision 2020
We will be one of the largest integrated energy companies in the world and the preferred choice among our stakeholders

Vision 2020 Characteristics


Our operations will be notable for: Strong international presence; World scale prominence in biofuels; Operational excellence in management, technology and human resources; Profitability; Benchmark in social and environmental responsibility; Commitment to sustainable development.
10

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

AND A CAREFULLY CRAFTED SPENDING PROGRAM TO SUPPORT THAT VISION

International Investments US$ 15.9 billion Business Plan 2009-2013 US$ 174.4 billion
3% 7% 2%
5.6

5% 1% 8% 7%

2%

2%
E&P

3.0 2.8 3.2


RTC G&E Petrochemicals Distribution

11.8

43.4

25%

104.6 (*)

59%

Biofuels Corporate

79% E&P Distribution RTCP Corporate G&E

(*) US$ 17.0 billion allocated to Exploration

11

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

CENPES

Total Area:114.000 m2 Building:75.000 m2 137 Laboratories 30 Pilot plants

CENPES Expansion and

Expansion

Dataprocessing integrated Center: Total Area: 190.000 m2 Building: 114.000 m2

Partnership with over 120 universities and research centers in Brazil, and 70 Institutions abroad
Investments in Technology 2009-2013

Technological programs

US$ 4.0 billion


25%

1.0
5%

0.2 0.9

1.9

47%

Frontier Areas

Basin Modeling

Deep and Ultra-deep Waters

Heavy Oil

Enhanced Oil Recovery

Pre-salt

Refining

23% E&P G&E

Downstream Corp.(Cenpes)

Optimization & Reliability

Fuel Innovation

Transportatio n

Natural Gas

Renewable Energy and Bio Fuels

Environment

Climate Changes

12

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

E&P Business Segment

13

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

E&P: FOCUSED & DISCIPLINED INVESTMENT

Total Investments

Total Investments of US$ 104.6 billion in E&P through 2013, of which US$ 92 billion will be spent in Brazil

12%

13%
Expected Costs of Production*
140

17%

Production costs (US$/bbl-2008)

120 100 80 60 40 20
Produced MENA

Deepwater and Ultra-deep water

Oil Shales

Gas to liquids

Coal to liquids

CO EOR EO R Arctic
Other conventi onal oil

58%
Exploration Development

Heavy oil and bitumen

Petrobras expected maximum break-even cost

Santos Pre-salt

International

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

Reserves (bn bbls)

* Source: IEA Outlook 2008

14

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

PRE-SALT PROVINCE

Total area of the Province: 112,000 km2 Area under concession: 41,000 km2 (38%) Area not under concession: 71,000 km2 (62%) MINA GERAIS Area with Petrobras interest: 35,000 km2 (31%)

ESPIRITO SANTO

SO PAULO

RIO DE JANEIRO

PARAN

Tested wells Campos HC Exploratory Blocks Pre-Salt reservoirs 15

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

SANTOS BASIN PRE-SALT CLUSTER

50 km

Rio de Janeiro

BM-S-10 BR 65%

BM-S-11 BR 65%

Major discoveries include: Tupi, Iara, Carioca, Guara, Jupiter, Parati, Bem-te-vi and Caramba Multi-billion barrel reserves potential Good oil quality: medium-light

BM-S-8 BR 66%

Seismic activity and appraisal wells underway


Iara
Parati Tupi Carioca Bem-te-vi Guara

Recoverable resources announced: 5-8 bn boe in Tupi and 3-4 bn boe in Iara Three production systems by 2014: Tupi, Iara and Guara

BM-S-21 BR 80%
Caramba

Azulo BM-S-9 BR 45%

BM-S-24 BR 80%

BM-S-22 BR 20%

16

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

ESPRITO SANTO PRE-SALT

UTG Cacimbas
Linhares Rio Doce

MG

Cango

Pero

Infrastructure in-place P-34 at Jubarte field, first pre-salt production: excellent results, prod. up to 18 k b/d FPSO Seillean started in dec/08 as pilot system of Cachalote (CHT) field FPSO Capixaba will move from Golfinho field to Cachalote/Baleia Franca (BFR) in 1H10 FPSO Pipa II will start in 2H10 as Baleia Azul (BAZ) pilot system Baleia Azul first definitive production unit by 4Q12 Natural gas production transported via pipeline

UPGN Lagoa Parda 24 66 km 25 MM m3/d


Camarupim Canapu Golfinho VITRIA
Vila Velha

Aracruz

Terminal Barra do Riacho

Carap

UTG Sul Capixaba


Guarapari

Anchieta Presidente Kennedy Marataizes

Sul Capixaba Gas pipeline 12 83 km 4,5 MM m3/d

Sul-Norte Capixaba Gas pipeline 12 a 24 160 km 7 a 15 MM m3/d

CHT JUB

ARG Baleia Franca NAU PRB Catu OST ABA

RJ

Baleia Azul CXR

17

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

MAJOR OIL PROJECTS


Marlim Sul Module 2 SS P-51 180,000 bpd 24/jan/09 Marlim Leste FPSO Cidade de Niteri 100,000 bpd 26/feb/09 Badejo FPSO Cidade Rio das Ostras 15.000 bpd 31/mar08 Tupi TLD FPSO BW Cidade de S.Vicente 30,000 bpd FPSO Frade 100,000 bpd Tupi Pilot FPSO Cidade de Angra dos Reis 100,000 bpd Marlim Sul SS P-56 Module 3 100,000 bpd

Thousand bpd

2800

Anticipation of Baleia Azul FPSO Espadarte 100,000 bpd

2,680
Roncador FPSO P-62 Module 4 100,000 bpd Roncador SS P-55 Module 3 180,000 bpd Papa-Terra TLWP P-61 & FPSO P-63 150,000 bpd Guar 1 Pilot FPSO 100,000 bpd

2600

2,580

2400

2,430
Jubarte FPSO P-57 180,000 bpd

2200
Marlim Leste FPU P-53 180,000 bpd 30/nov/08

2,250
Cachalote e Baleia Franca FPSO Capixaba 100,000 bpd

2000

2,050
Parque das Conchas FPSO Esprito Santo 100,000 bpd

1800

1,855
Cachalote FPSO Seillean 25,000 bpd 16/dec/08

1600

Pre-Salt Projects

1400 2008 2009 2010 2011 2012 2013 PN 2009-2013

18

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

CIDADE DO RIO DE JANEIRO FPSO(CAPACITY 100 .000 BPD), PRODUCTION ON 06/01/07 AT ESPADARTE FIELD

19

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

PIRANEMA FPSO (CAPACITY 30 .000 BPD), PRODUCTION ON 10/10/07

20

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

P-52 DECK MATING

21

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

P-52 - BRASFELS SHIPYARD- ANGRA DOS REIS

22

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

P-54 - MAU JURONG SHIPYARD- NITERI

23

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

P-54 LEAVING THE SHIPYARD ON 19-Out-2007

24

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

P-54 LEAVING THE SHIPYARD ON 19-Out-2007

25

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

Downstream Business Segment

26

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

DOMESTIC CRUDE THROUGHPUT (THOUSAND BPD)


Downstream Investments US$ 47.8 billion
Refining Pipelines&Terminal 8% Transport ShipTransport Petrochemicals
73%
Premium I 300 tho. bpd 1st Phase: 2013 2nd Phase: 2015 Premium II 300 tho. bpd 1st Phase: 2014 2nd Phase: 2016

12% 7%

Adding values to domestic crude and producing diesel and gasoline in-line with international standards Investment targets Fuel Quality, Conversion and Expansion
3,012

UPB 150 tho. bpd Dez/2012

2,270

1,779

1,791

RNE 230 tho. bpd 2011


REPLAN Revamp 33 tho. bpd 2010 REPAR Revamp 25 tho. bpd 2011

2008

2009

2010

2011

2012

2013

2020

27

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

NEW INVESTMENTS

NEW REFINERIES
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017

Start up:end of 2.012 Start up: 1 st quarter 2.011

Start up 2013 and 2015 Start up: 2013 and 2015

28

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

NEW INVESTMENTS - PREMIUM REFINERIES

LPG PETROCHEMICAL NAPHTHA

5% 20% 11% 50% 8% 3%

Feedstock oil basis: Marlim 20

AVIATION QUEROSENE DIESEL PETROCHEMICAL COKE BUNKER

Premium I MA

Premium II - CE 300 mil bpd 2013 e 2015 (2 phases)

Capacity Operation

600 mil bpd 2013 e 2015 (2 phases)

Market

GLP, Nafta e QAV (Brasil) e Diesel 10 ppm (Europa)

29

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

REFINERIES INVESTMENTS

done

present

planned

30

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

TERMINALS

26 water terminals, operated by means of monobuoys or buoy arrays 20 onshore terminals.

INVESTMENTSINLOGISTICS PIPELINESANDTERMINALS

Os investimentos previstos atendem s necessidades da carteira exploratria e de desenvolvimento da produo Total Investments: US$ 3.7 billion between 2009-2013; da Petrobras
Main Projects:
Storage extension in Santos and Paranagu ports; Increase in effluents treatment in So Sebastio (TEBAR), So Fransisco do Sul (TEFRAN), Cabinas, Ilha Grande (TEBIG) and TEDUT Terminals; Implantation of the Program Adequao de Suprimento de Petrleo (PASP) and the Plano Diretor de Dutos, in So Paulo State, through interventions in the OSVAT and OSCAN Systems, and new pier for the So Sebastio Terminal; Improvements in the oil product outflow system in Santos and Paranagu ports and Madre de Deus Terminal(TEMADRE).

31

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

Petrochemical Business Segment

32

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

COMPERJ

Site: Itabora - RJ; Capacity: 1300 kta ethylene; 700 kta P-Xylene; 881 kta Propylene; 608 kta Benzene; 157 kta Butadiene Total Investment: US$ 8.5 billion; Feedstocks: Heavy crude oil from Campos basin; Start up: 2012.

33

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

COMPERJ OUTPUTS

Products UPB

Production (kta)

Production (kta)

1st Generation

Products UPA
2nd Generation

Diesel
Fuels (UPB)

535 284 700 1.300 881 608


157
Polypropylene (PP)

Naphtha Coke Ethylene Propylene

850

Poliethylene (PE)

800

Styrene

500

Petrochemical Feedstocks (UPB)

Benzene
Butadiene

Ethylene glicol

600

PTA p-Xylene Sulfur 700 45 PET

500

600

34

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

COMPERJ MAP LOCATION

Itabora

35

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

Gas and Energy Business Segment

36

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

G&E INVESTMENTS

G&EInvestments US$10.6billion20092013
1,477 926 4.528 3.692
US$million Natural Gas US$ 8.2 billion Energy US$ 2.4 billion

ProjectsinPortfolio ProjectsinPortfolio

NewInvestmentsProposed NewInvestmentsProposed

37

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

MAIN PROJECTS: GAS & ENERGY

US$ million

Main Projects

Gas Pipelines: Gasene, Northeast and Southeast Network, South Section of Gasbol, Urucu-Coari-Manaus and Gasduc III LNG Liquefied Natural Gas Thermo-Electrics: Cubato, Trs Lagoas, Canoas and Termoau Wind Power Generation G&E in Argentina and Other Countries
Total investments US$ 10.6 billion

38

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

Critical goods and services and equipment quantities

39

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

E&P CRITICAL EQUIPMENT: OPPORTUNITIES FOR FOREIGN SUPPLIERS


Production pipelines alloy coatings (13 Cr, Super 13 Cr); Turbo compressors (6-10 Mw ); Polyester Mooring cables; Mooring systems; Drilling pipelines; Fiber glass pipelines; Electrical cables for CSP; Control Systems for well control, oil and gas metering systems, drilling activities; Offshore drilling rigs; Gravel packing; Drilling bits; Steam generators (25-50 x 106 BTU/d); Special submarine valves.
40

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

CRITICAL SERVICES FOR E&P ACTIVITIES: OPPORTUNITIES FOR FOREIGN SUPPLIERS

Drilling; Workover services; Flexible lines and umbilicals laying services; Support to diving; Support to ROV; Support to mooring activities; Special vessels; Submarine interconnection services.

41

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

CRITICAL EQUIPMENT AND SERVICES FOR REFINING ACTIVITIES: OPPORTUNITIES FOR FOREIGN SUPPLIERS

Equipment HCC Reactors (250-300 mm wall width, 200 Kgf/cm2); Boiler works with special alloys (reactors, towers, pressure vessels); Boilers (steam generators); Heat exchangers working with H2S traces (ASTM A 387 degree 11); API pumps; Structural packing for refining process towers;

Services Basic Design; Thermal Projects Design.

42

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

CRITICAL EQUIPMENT FOR G&E ACTIVITIES: OPPORTUNITIES FOR FOREIGN SUPPLIERS

Pipelines in the range of 14-42 inches diameter with longitudinal welding. Petrobras standards do not accept helicoidal welding.

43

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

NEW EQUIPMENTS TO BE CONTRACTED


Drillingshipsandsemisubmersibledrillingplatforms 29RIGSCONTRACTEDPLUS28TOBELEASEDUPTO2017,MAKINGATOTALOF57DRILLINGRIGS 17beingdeliveredbetween2009and2011 12willbecharteredviainternationalbidding,beingdeliveredin2012 MeetingPetrobrasshorttermneeds,while thenationalindustrypreparesitselffortheremainingunits 28willbebuiltinBrazilandoperatedbyBraziliancompanies,beingdeliveredbetween2013and2017 Items Wet Christmas Tree Well Head Flexible Lines Manifolds Producing pipes Umbilical Dry Christmas Tree Onshore well head Items Reactors Oil and water splitter Storage Tankers Turrets Un. un un km un t km un un Un. un un un un TOTAL 500 500 4.000 30 42.000 2.200 1.700 1.700 TOTAL 280 50 1.800 550 Items Pumps Compressors Winch Crane Engines Turbines Structure Steel (Hull) Un. un un un un un un t TOTAL 8.000 700 450 200 1.000 350 940.000

Items Power Generators Filters Flares

Un. un un un

TOTAL 500 300 30

44

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

Petrobras supply strategies for goods and services

45

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

SUPPLY STRATEGIES FOR GOODS AND SERVICES

Manufacturers

Equipment Chemicals Spare parts Etc. Seismic

US$ 7.0 Bi

Distributors Retailers

US$ 25.8 Bi

Service providers

Drilling Transport Etc. Platform Refinery Revamps Etc. 46

EPC

US$12.4 Bi
As per 2008

Shipyards Constructors

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

Up-dated Petrobras Vendor Register Requirements

47

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

REGISTER OF GOODS AND SERVICES SUPPLIERS


Requirements, Concepts and Ranking

MANDATORY REQUIREMENTS and RANKING REQUIREMENTS 5 CRITERIA

SOCIAL TECHNICAL RESPONSIBILITY

HSE

ECONOMIC

LEGAL

48

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

REGISTRATION FOR MATERIAL SUPPLIERS

TECHNICAL REQUIREMENTS FOR MATERIALS

Depending on the material or equipment, the supplier must comply with the following requirements:

Tradition (Main Sales, Reference Letters); Facilities for Technical Assistance (Automation Systems, Rotating Machinery, etc); Mandatory Product Certification (API, ASME, ...); Other Specific Requirements.

49

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

REGISTRATION FOR SERVICES SUPPLIERS

TECHNICAL REQUIREMENTS FOR SERVICES Depending on services criticality, the supplier must comply with the following requirements:

Tradition (List of Services Provided continuity and Reference Letters); List of Equipment relating to services provided; Main personnel curricula vitae; Other specific requirements.

50

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

SUPPLIERS REGISTRATION
LEGAL REQUIREMENTS
MATERIALS & SERVICES

Brazilian companies: Proof of being legally constituted in Brazil; Proof of being regular with Brazilian taxes; See details on registration website. Foreign companies: Proof of being legally constituted in its home country, issued by a Governmental Authority; Legal Representative in Brazil (mandatory); Commercial Representative (is not registered, but only indicated by and linked to the supplier):
Not mandatory (may be the own company); May be the same or other than the Legal representative.

51

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

SUPPLIERS REGISTRATION

ECONOMICAL REQUIREMENTS MATERIALS & SERVICES Annual Reports with Audited Financial Statements; Proof that the company is not bankrupt (bank statement or company declaration by its president).

52

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

SUPPLIERS REGISTRATION

MANAGEMENT and SOCIAL RESPONSIBILITY MATERIALS ISO-9001 - certification mandatory for suppliers of material & equipment which require technical qualification. SERVICES Compliance with some requirements of ISO-9001 for special services. MATERIALS & SERVICES Petrobras stimulates suppliers to improve Social Responsibility actions.

53

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

SUPPLIERS REGISTRATION

HELTH, SAFETY and ENVIRONMENT SERVICES ISO-14001 and OSHAS-18001: Certification is not mandatory; Petrobras evaluates how does the suppliers implement these standards requirements (0 to 10). MATERIALS PETROBRAS requires supplier formal declaration of compliance with legal requirements. Petrobras evaluates how the suppliers implement some standards requirements of ISO 14001 and OSHAS 18001 (not mandatory) (0 to 10).
54

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

REGISTER OF SUPPLIERS OF GOODS AND SERVICES

General

information

is

obtained

at

Petrobras

website:

www.petrobras.com.br Options (icons): English; Business, Material Channel, Registration Guide.

Corporate registration process must be carried out in Petrobras headquarters, in Rio de Janeiro.

55

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

PROMINP Governmental Program and Local Content

56

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

PROMINP BRAZILIAN OIL & GAS NATIONAL INDUSTRY MOBILIZATION PROGRAM

MINISTRY OF MINES AND ENERGY (MME) Programs promoter and manager PETROBRAS Leading operator in Brazil BRAZILIAN PETROLEUM INSTITUTE (IBP) Coordinator for the participation of the other operators NATIONAL ORGANIZATION OF THE INDUSTRY (ONIP) Coordinator for participation of class associations (suppliers) OIL the

BNDES ABIMAQ

ABEMI SINAVAL

ABDIB

ABCE

PROMINP
IBP
ONIP

57

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

COMPETITIVE NATIONAL SUPPLY OF GOODS AND SERVICES Adequacy of The National Supply Industrial Complex
GOOD AND SERVICES SUPPLY PATH
5. Incentive for international companies to establish operations in Brazill 4. Incentive for association between national and international companies 3. Incentive for new national entrants 2. Develop competition among medium competitive sectors

imports

Increase in National Supply Capacity of G&S imports

National Industry

1. Increase productivity capacity of highly competitive sectors

Current Demand
Source: Promimp, 2008

Future Demand 57

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

GLOBAL LOCAL CONTENT 4TH QUARTER 2008

PROMINP

$ Target National $ Accomplished Total

$ Target Total $ Accomplished National

Target LCI Accomplished LCI (US$bi)

58

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

CONCLUSIONS

Huge Strategic Plan for the period 2009-2013; Plenty of opportunities for foreign suppliers planning to establish in Brazil and address the Latin America Market; Strong industrial basis in Brazil, for the Oil and Gas segment representing today 15% of GDP; Opportunities shall be focused on critical goods and services not available in a competitive basis in local market; Foreign suppliers must be aware of the specific laws framework and Local Content requirements; incentives should be assigned by Government Offices once the intention to manufacture in Brazil is assured; Partnership with a local supplier operating in the same business area should be considered. .
59

2020 PETROBRAS STRATEGIC & BUSINESS PLAN

PETROLEO BRASILEIRO S.A. PETROBRAS


The Challenge is our Energy
Paulo Sergio Rodrigues Alonso D.Sc. Materials Engineering Manager alonso@petrobras.com.br

60

Você também pode gostar