Department/Section: Module No: Issuance Date:

HV Transformer/I & QC

Issued By: Work Instruction No.: Superseding Date: WI-I&QC-04

MEASUREMENT OF CAPACITANCE AND DISSIPATION FACTOR

02 01 REV Date Prepared By Name Department Designation Signature Abdul Rehman I & QC Engineer Name Department Designation Signature Checked By Raza Aftab/Muhammad Shafiq I & QC Sr. Engineer/Test Field Engineer Nature of Change Approved & Controlled By Name Department Designation Signature Jahanzeb Ahmad I & QC Manager

Note: Copying of this document is strictly forbidden. Proprietary data. Company confidential. All rights reserved.

MEASUREMENT OF CAPACITANCE & DISSIPATION FACTOR


WORK INSTRUCTION W-I&QC-04 Revision: 00 Page 2 of 4

1.0

PURPOSE The Purpose of this document is to provide the guidelines to the Testing Engineer to check the quality of the insulation system of the transformer by measuring the capacitances and the dielectric losses at rated frequency. The test also indicates the ageing of the insulation and the contamination of the oil.

2.0

SCOPE This instruction applies to the in-house & final testing of the HV Transformer.

3.0

RECORDS Following items are recorded in the test reports (for both bushings & transformer): 1. 2. 3. 4. 5. 6. 7. 8. Applied Voltage Capacitances Dissipation Factor Power in watts Leakage current Ambient temperature Oil & winding temperature Humidity

4.0

ASSOCIATED DOCUMENTS The standard applicable for this test is IEC 60076-1.

5.0

DEFINATIONS NIL

6.0

RESPONSIBILITY Test will be performed under the supervision of Testing Engineer/Sub Engineer of I & QC section of the HV Transformer department.

7.0

EQUIPMENT/INSTRUMENTS Following equipments/instruments are required to perform this test: - Doble M4000-USA Insulation tester or equivalent, 10kV, 50/60 Hz.

MEASUREMENT OF CAPACITANCE & DISSIPATION FACTOR


WORK INSTRUCTION W-I&QC-04 Revision: 00 Page 3 of 4

8.0

SAFETY REQUIREMENTS 1. Safety Switches with the equipment should be pressed during the test. 2. Check all the connections, including earthing points.

9.0

MEASURING CIRCUIT

10.0

INSTRUCTIONS In a two-winding transformer, there are six measurements of capacitance: (1) CHL (2) CHL+HG (3) CHG (4) C LH+LG (5) C LG (6) C HG +LG (7) Capacitance of the HV bushings of three phases. All HV line terminals are connected together labeled (H) and all LV terminals are connected together labeled (L) and a connection is made to a ground terminal, usually a connection to

MEASUREMENT OF CAPACITANCE & DISSIPATION FACTOR


WORK INSTRUCTION W-I&QC-04 Revision: 00 Page 4 of 4

transformer tank, which is labeled (G). Leads from the measuring instrument or bridge are connected to one or both terminals and ground. Either grounded specimen measurements or grounded measurements are possible so that all the capacitance and dissipation factor values can be determined. 11.0 CALCULATIONS DISSIPATION CORRECTION FACTOR Tan Delta at 20 C = Tan Delta at Temp T C / Factor K 12.0 TOLERANCES NIL