Escolar Documentos
Profissional Documentos
Cultura Documentos
3. Secondary injection tests (But with relays isolated by test facility) Proof of isolated relay characteristic obtained Ref. for maintenance obtained (relay if necessary tested with system on load) Full primary injection/on load tests done on initial commissioning only
4. On load tests Checks that expected C.T. / V.T. quantities present at test facility Scheme stability for external faults Proof of correct directional characteristics
Summary
Arevas preference:1. Secondary injection (isolated relay) 2. Primary injection (incl. C.T. ratio, phasing and mag. curve) 3. On load tests
To assure ourselves, and the interested authorities, that the overall protective system functions correctly Resist pressures to take risks Study wiring diagrams and protection requirements Key diagram Delegate responsibilities Observe safety of self and others
Primary injection tests D.C. flick tests on C.T.s C.T. mag curve tests C.T. ratio and polarity tests Primary sensitivity tests Stability tests Test results
Mean D.C.
Faulty relays
Frequency of Maintenance (continued) f) The proven reliability of devices under identical site conditions g) The availability of built-in self-check features or semi-automatic test facilities, and the difficulties of alternative tests h) The interval of time an unexpected catastrophic failure, component or otherwise, that may go undetected and leave the system unprotected
Typically maintain every 12-18 months under ideal conditions and decrease frequency
Relays involving static (electronic) components Electro-static discharge (ESD) Wrist straps Modern static relays (K-SERIES, MiCOM etc.) Fault find to board level only Protect boards
A B C N To main VT
To main VT
Battery
C
A2
P2 S2
A1
Primary injection test set 250V AC supply
V1 V2 VN VL
V1
C
V
V2
A B C
Range adjusting CT
K1 250V AC supply K2
51
I Relay coil
Start timer Supply switch Backing transformer 10% control Injection transformer
Stop timer
Relay shortMedium circuiting switch control reactor Relay current I = Ammeter reading (A) x K1 K2
L1 10X 5X 2X 1X
220/250V AC Supply 50/60Hz
L2
50Hz 0.1A
60Hz
0.5A 1A 2A 5A
0.2A
Variac V1
50Hz
Output to Relay
10A
B OP
I1+I2
I1
A1 A2 R
I2
I1+I2
I1 A1
R1
I2 A2
R2
Sensitivity Test
Feeder isolated A B C Test plug Relay contact fingers
B
OP OP
Pilots
A To main current transformers Overcurrent test set Test plug in test block B
46
C N Filter network
Relay coil
A V
PA
67
Variable transformer for voltage control To other voltage coils of relay under test (if required)
A
51
B
51
C
51
64
51
51
64
PA
A B C
PA
A A V V PA PA
Ammeter Ammeter Voltmeter Voltmeter Phase angle Phase angle meter meter
20 19 18 17 16 15 14 13 12 11
9 10
IA
V1 V2
51 51 51
PA
VN
V PA
Generator
Isolating links A B C
87
87
87
Testing Sensitivity of Generator Differential Protection Using Generator to Supply Primary Current
87
87
87
Generator
A
87
A
87
A B C Bias coils
Operating coils
87
87
87
B C Bias coils
Operating coils
87
87
87
~
Bias coils
A
87
87
87
Operating coils
Instantaneous current distribution for three-phase short circuit with phase A current at maximum
A B C
64
64
Filter network
46
20 19 18 17 16 15 14 13 12 11
10
A B C
Primary injection test set
B
OP
A Ammeter
Instantaneous current distribution of three-phase balanced load with phase A current at maximum
B
OP
B
OP
Pilots
20 19 18 17 16 15 14 13 12 11
10
A1
A2
Test links
A1 and A2 Ammeters 87 Busbar Protection relay 95 Supervision relay 95X Bus wires short-circuiting relay
A B C N
95X
95 87 87 87
Test links
A B C N
95X
95 87 87 87
Test links
A B C N
Ammeter for ratio check Ammeter for polarity check 87 Busbar protection relay 95 Supervision relay 95X Bus wires shortcircuiting relay
A1 A2
A2
95X
95 87 87 87
A2
A2
A B C N
95X
V
95 87 87 87
Stability Test
A B C Test plug Test plug
B
OP
Pilots