Escolar Documentos
Profissional Documentos
Cultura Documentos
Contents
Introduction ................................................................................................................... 3 1 2 3
3.1 3.2
Introduction ...................................................................................................... 3 Developing a view of required transmission ..................................................... 3 Transmission cost estimates ............................................................................ 3
High Voltage AC (HVAC)............................................................................................ 4 High Voltage DC (HVDC) ........................................................................................... 6
Disclaimer ..................................................................................................................... 7
Page 2 of 7
Introduction 1 Introduction
The document sets out the approach and assumptions that the Australian Energy Market Operator (AEMO) will use in developing a view of the transmission network and its cost that will support the 100 per cent renewables study.
http://www.nationalgrid.com/NR/rdonlyres/437A1BD2-4650-45D4-8A92-C1A358808FD0/39230/ODISAppendicesFinal_0110.pdf Page 3 of 7
500 kV double circuit transmission line (Capacity per circuit 2500 MVA-3500 MVA) 500 kV single circuit transmission line (Capacity per circuit 2500 MVA - 3500 MVA) 220 kV, 275 kV or 330 kV double circuit transmission line (Capacity per circuit 800, 1100, 1300 MVA) 220 kV, 275 kV or 330 kV single circuit transmission line (Capacity per circuit 800, 1100, 1300 MVA) 220 kV double circuit transmission line (Capacity per circuit 500 MVA) 132 kV double circuit transmission line (Capacity per circuit 100- 250 MVA) 132 kV single circuit transmission line (Capacity per circuit 75, 100, 150 175 MVA) Table 2 Transformers
Plant
1.8 1.4 1.1 0.7 0.75 0.7 0.4 Multiply by two for length < 20 km
Comments
1000 MVA 500/330 kV transformer 370 MVA 500/275 kV transformer 1000 MVA 500/220 kV transformer 750 MVA 500/220 kV transformer 600 MVA 500/220 kV transformer 700 MVA 330/220 kV transformer 400 MVA 330/220 kV transformer 225 MVA 330/220 kV transformer 150 MVA 220/110 kV transformer Table 3 Switch bays
18 11 18 16 15 12 9 8 5
3 x 1 phase units
3 phase units
Cost estimate ($M) Switch bay 500 kV 330 kV 275 kV 220 kV 132 kV
3 Breaker Diameter - 3CBs 3 Breaker Diameter - 2CBs 3 Breaker Diameter - 1CBs 2 Breaker Diameter - 2CBs 2 Breaker Diameter -1CBs 1 Breaker Diameter - 1CBs
Page 4 of 7
7 8 10 13 16 19 22 25
3 Breaker Diameter - 3CBs 3 Breaker Diameter - 2CBs 3 Breaker Diameter - 1CBs 2 Breaker Diameter - 2CBs 2 Breaker Diameter - 1CBs 1 Breaker Diameter - 1CBs
SVC -100 / +300 MVAr (220 kV, 275 kV or 330 kV) Series capacitors 1000MVA (220 kV, 275 kV or 330 kV) Shunt cap bank 200MVAr (330 kV) Shunt cap bank 200MVAr (275 kV) Shunt cap bank 200MVAr (220 kV) Shunt cap bank 120MVAr (220 kV, 275 kV or 330 kV) Shunt cap bank 100MVAr (110 kV or 132 kV) Shunt cap bank 25 - 50MVAr (110 kV or 132 kV) Table 7 High Voltage AC submarine cable
Plant
SVC with CB Capacitor bank with 1CB diameter 1 CB Capacitor bank with 1CB diameter 1 CB Capacitor bank with 1CB diameter 1 CB Capacitor bank with 1CB diameter 1 CB Capacitor bank with 1CB diameter 1 CB Capacitor bank with 1CB diameter 1 CB
3 core 132 kV 189 MVA cable 3 core 220 kV 314 MVA cable
1.70 2.18
Page 5 of 7
150kV 352 MW bipole submarine cable 300kV 704 MW bipole submarine cable 300kV 1306 MW bipole submarine cable 300kV 770 MW bipole on-shore cable 300kV 1253 MW bipole on-shore cable
200kV DC, 230/138kV AC, 400 MW with voltage source converter 170-300 Table 10 - Offshore platforms Offshore platform, water depth of 30-40m Platform for 500 MW HVDC with voltage source converter Platform for 1000 MW HVDC with voltage source converter Platform for 132/33 kV AC Platform for 220/33 kV AC
$150
68 108 44 54
Page 6 of 7
Disclaimer
Purpose - This document is provided by AEMO as at 18 September 2012 for general information purposes only. No Reliance or warranty - This document or the information in it may be subsequently updated or amended. While AEMO has made every effort to ensure the quality of the information in this document, AEMO does not warrant or represent that it is accurate, reliable, complete or current or that it is suitable for particular purposes. You should not rely on this document as a substitute for obtaining detailed advice about the National Electricity Law, the National Electricity Rules, or any other applicable laws, procedures or policies. Limitation of liability - To the maximum extent permitted by law, AEMO and its advisers, consultants and other contributors to this document (or their respective associated companies, businesses, partners, directors, officers or employees) are not liable (whether by reason of negligence or otherwise) for any errors, omissions, defects or misrepresentations in this document, or for any loss or damage suffered by persons who use or rely on the information in it.
2012 Australian Energy Market Operator Limited. The material in this publication may be used in 2 accordance with the copyright permissions on AEMOs website.
http://www.aemo.com.au/en/About-AEMO/Copyright-Permissions Page 7 of 7