Você está na página 1de 4

Activity ID

Activity Name

Original Duration 1 2 3 4 5 6 7 8 9 10 11 12 13

Month 14

15

16

17

18

19

20

21

22

23

24

25

26

27

AL MUSSAFAH AHALIA HOSPITAL A


PROJECT BENCHMARK DATES BEN
XXX-0000 XXX-0010 XXX-0020 XXX-0030 XXX-0040 XXX-0050 XXX-0060 XXX-0070 XXX-0080 Commencement Date/Site Possession Receipt of Contract Documents & IFC Drawings Receipt of Building Permit Completion of Sub-Structure Completion of Superstructure Completion of MEP Works Completion of Finishes Project Completion Power On 0 0 0 0 0 0 0 0 0 Commencement Date/Site Possession Receipt of Contract Documents & IFC Drawings Receipt of Building Permit Completion of Sub-Structure Completion of Superstructure Completion of MEP Works Completion of Finishes Project Completion Power On

GENERAL WO WORKS
MOBILIZATION AN D P REPERATORY WORKS
PRE-0010 PRE-0020 PRE-0030 PRE-0040 PRE-0050 PRE-0060 Mobilization Installation of Temp. Site O ffices and Facilities Pre-Construction Survey and Site Setting Out Geotechnical Soil Investigation Demolish Existing Building and Site Clearance Install Tower Cranes 62 55 5 18 31 27 Mobilization Installation of Temp. Site O ffices and Facilities Pre-Construction Survey and Site Setting Out Geotechnical Soil Investigation Demolish Existing Building and Site Clearance Install Tower Cranes

TECHNICAL SU SUBMITTALS & APPROVALS


SUBMITTALS
PRE-1010 PRE-1020 PRE-1030 PRE-1040 PRE-1050 PRE-1060 PRE-1070 PRE-1080 PRE-1090 PRE-2010 PRE-2020 PRE-2030 PRE-2040 PRE-2050 PRE-2060 PRE-2070 PRE-2080 PRE-2090 Prepare and Submit QC/QC and Safety Plans Prepare and Submit Construction Schedule Prepare and Submit Construction Methodologies Prepare and Submit Civil/Structural Materials Prepare and Submit MEP Materials and Equipment Prepare and Submit Conveying System Prepare and Submit Finishing Materials Prepare and Submit Shop Drawings Prepare and Submit As-Built Drawings Review and Approval of QC/QC and Safety Plans Review and Approval of Construction Schedule Review and Approval of Construction Methodologies Review and Approval of Civil/Structural Materials Review and Approval of MEP Materials and Equipment Review and Approval of Conveying System Review and Approval of Finishing Materials Review and Approval of Shop Drawings Review and Approval of As-built Drawings 31 31 289 304 304 61 151 389 250 31 31 289 304 304 61 151 389 250 Review and Approval of Conveying System Review and Approval of Finishing Materials Review and Approval of Shop Drawings Review and Approval of As-built Drawings Review and Approval of QC/QC and Safety Plans Review and Approval of Construction Schedule Review and Approval of Construction Methodologies Review and Approval of Civil/Structural Materials Review and Approval of MEP Materials and Equipment Prepare and Submit Conveying System Prepare and Submit Finishing Materials Prepare and Submit Shop Drawings Prepare and Submit As-Built Drawings Prepare and Submit QC/QC and Safety Plans Prepare and Submit Construction Schedule Prepare and Submit Construction Methodologies Prepare and Submit Civil/Structural Materials Prepare and Submit MEP Materials and Equipment

REVIEW AND APPROVALS A

PROCUREMENT PROCUREMEN OF LONG LEAD ITEMS


XXX-1020 Procurement of Conveying Systems 209 Procurement of Conveying Systems

CONSTRUCTION CONSTRUCTIO
STRUCTURAL WORKS
SUB-0000 SUB-0005 Start Structural Works Finish Structural Works 0 0 Start Structural Works Finish Structural Works

SUBSTRUCTURE SUBSTRUCTU
PILING WORKS WOR SUB-0010 Exacavate to Platform Level for Bored Piling Operation SUB-0015 SUB-0020 SUB-0030 SUB-0040 SUB-0050 SUB-0060 SUB-0070 SUB-0080 Mobilization of Drilling Rigs (by Sub-Contractor. Bored Piling Operation and Pile Test Excavate up to Bottom of Pile Caps Trimming and Treatment of Pile Heads Fill/Compact Working Platform for Secant Piling Operation Secant Pile Retaining Walls Construct Capping Beam for Secant Pile Retaining Walls Parking Area - Install Suitable De-watering System (If Required) 12 12 60 30 30 12 40 40 16 Exacavate to Platform Level for Bored Piling Operation Mobilization of Drilling Rigs (by Sub-Contractor. Bored Piling Operation and Pile Test Excavate up to Bottom of Pile Caps Trimming and Treatment of Pile Heads Fill/Compact Working Platform for Secant Piling Operation Secant Pile Retaining Walls Construct Capping Beam for Secant Pile Retaining Walls Parking Area - Install Suitable De-watering System (If Required)

CAR PARKING AREA - BASEMENT 2 SUB-1010 Excavation Inside Cofferdam SUB-1020 SUB-1030 SUB-1040 SUB-1050 SUB-1051 SUB-1052 SUB-1053 SUB-1054 SUB-1060 SUB-1070 SUB-1080 Spray Gunite on Secant Pile Retaining Wall Surfaces Blinding and Waterproofing under Base Slab Water proofing on Retainin g Walls Construct Base Slab Construct Base Slab (Part 1) Construct Base Slab (Part 2) Construct Base Slab (Part 3) Construct Base Slab (Part 4) Construct Perimeter Walls, Inter nal Walls and Columns Construct Water Tank Walls and Columns (1st Lift) Construct Water Tank Walls and Columns (2nd Lift)

26 20 12 16 20 7 7 7 7 20 10 12

Excavation Inside Cofferdam Spray Gunite on Secant Pile Retaining Wall Surfaces Blinding and Waterproofing under Base Slab Water proofing on Retaining Walls Construct Base Slab Construct Base Slab (Part 1) Construct Base Slab (Part 2) Construct Base Slab (Part 3) Construct Base Slab (Part 4) Construct Perimeter Walls, Inter nal Walls and Columns Construct Water Tank Walls and Columns (1st Lift) Construct Water Tank Walls and Columns (2nd Lift)

Actual Work Remaining Work Critical Remaining Work Milestone Actual Milestone

Critical Milestone

AMAH-1

Date 30-Nov-11 ISSUED FOR TENDER

Revision

Checked

Approved

AL MUSSAFAH AHALIA HOSPITAL PRELIMINARY SCHEDULE


1 of 4

Activity ID

Activity Name

Original Duration 1 2 3 4 5 18 10 10 10 10 16 16 10 10 8 10 20 28 15 30 22 22 15 18 18 16 10 10 8 20 28 24 6 7 8 9 Construct Beams and Deck Slab @ -2.55 Level 10 11 12 13

Month 14

15

16

17

18

19

20

21

22

23

24

25

26

27

SUB-1090 SUB-1091 SUB-1092 SUB-1100

Construct Beams and Deck Slab @ -2.55 Level Construct Beams and Deck Slab @ -2.55 Level (Part 1) Construct Beams and Deck Slab @ -2.55 Level (Part 2) Construct Stairways and Ramp (from -5.55 to -2.55 Level)

Construct Beams and Deck Slab @ -2.55 Level (Part 1) Construct Beams and Deck Slab @ -2.55 Level (Part 2) Construct Stairways and Ramp (from -5.55 to -2.55 Level) Water proofing on Retainin g Walls Construct Perimeter Walls, Inter nal Walls and Columns Construct Beams and Deck Slab @ +0.55 Level Construct Beams and Deck Slab @ +0.55 Level (Part 1) Construct Beams and Deck Slab @ +0.55 Level (Part 2) Construct Water Tank Roof Slab @ +0.55 Level Construct Stairways and Ramp (from -2.55 to +0.55 Level) Water Pr oofing to Water Tank External and Internal Surfaces Backfilling & Compaction Around Parking Aea to Finish Level Blinding and Waterproofing under Pile Caps Construct Pile Caps Water Pr oofing at the Sid es of Pile Caps Backfilling upto Bottom of Floor Slab Blinding and Waterproofing under F loor Slab Construct Basement Floor Slab Construct Perimeter Walls, Inter nal Walls and Columns Construct Beams and Deck Slab @ +0.60 F.F.L. Construct Beams and Deck Slab @ +0.60 F.F.L. (Part 1) Construct Beams and Deck Slab @ +0.60 F.F.L. (Part 2) Construct Beams and Deck Slab @ +0.60 F.F.L. (Part 3) Water Pr oofin g at External Surfaces of Perimeter Walls Backfilling & Compaction Around Basement Floor to Finish Level Construct Stairways and Ramp (from -3.25 to +0.60 Level)

CAR PARKING AREA - BASEMENT 1 SUB-2010 Water proofing on Retainin g Walls SUB-2020 SUB-2030 SUB-2031 SUB-2032 SUB-2040 SUB-2050 SUB-2060 SUB-2070 Construct Perimeter Walls, Inter nal Walls and Columns Construct Beams and Deck Slab @ +0.55 Level Construct Beams and Deck Slab @ +0.55 Level (Part 1) Construct Beams and Deck Slab @ +0.55 Level (Part 2) Construct Water Tank Roof Slab @ +0.55 Level Construct Stairways and Ramp (from -2.55 to +0.55 Level) Water Pr oofin g to Water Tank External and Internal Surfaces Backfilling & Compaction Around Parking Aea to Finish Level

MAIN BUILDI BUILDING - BASEMENT FLOOR SUB-3010 Blinding and Waterproofing under Pile Caps SUB-3020 SUB-3030 SUB-3040 SUB-3050 SUB-3060 SUB-3070 SUB-3080 SUB-3081 SUB-3082 SUB-3083 SUB-3090 SUB-3100 SUB-3110 Construct Pile Caps Water Pr oofin g at the Sides of Pile Caps Backfilling upto Bottom of Floor Slab Blinding and Waterproofing under F loor Slab Construct Basement Floor Slab Construct Perimeter Walls, Inter nal Walls and Columns Construct Beams and Deck Slab @ +0.60 F.F.L. Construct Beams and Deck Slab @ +0.60 F.F.L. (Part 1) Construct Beams and Deck Slab @ +0.60 F.F.L. (Part 2) Construct Beams and Deck Slab @ +0.60 F.F.L. (Part 3) Water Pr oofin g at External Surfaces of Perimeter Walls Backfilling & Compaction Around Basement Floor to Finish Level Construct Stairways and Ramp (from -3.25 to +0.60 Level)

SUPERSTRUCTURE SUPERSTRUC
CAR PARKING AREA - GROUND FLOOR SUP-0010 Construct Lift Shaft, Pump Room and Medical Gas Room SUP-0020 SUP-0030 SUP-0040 Construct Columns at Service Block Area Construct Roof Slab at Sevice Block Area Construct Roof Parapet Wall s at Sevice Block Area 30 12 18 10 18 18 10 10 8 14 18 18 10 10 8 14 18 18 10 10 8 14 18 18 10 10 8 14 18 18 10 10 8 14 18 Construct Lift Shaft, Pump Room and Medical Gas Room Construct Columns at Service Block Area Construct Roof Slab at Sevice Block Area Construct Roof Parapet Wall s at Sevice Block Area Construct Internal Walls and Columns Construct Beams and Deck Slab @ +5.40 Level Construct Beams and Deck Slab @ +5.40 Level (Part 1) Construct Beams and Deck Slab @ +5.40 Level (Part 2) Construct Beams and Deck Slab @ +5.40 Level (Part 3) Construct Stairways Construct Internal Walls and Columns Construct Beams and Deck Slab @ +9.60 Level Construct Beams and Deck Slab @ +9.60 Level (Part 1) Construct Beams and Deck Slab @ +9.60 Level (Part 2) Construct Beams and Deck Slab @ +5.40 Level (Part 3) Construct Stairways Construct Internal Walls and Columns Construct Beams and Deck Slab @ +13.80 Level Construct Beams and Deck Slab @ +13.80 Level (Part 1) Construct Beams and Deck Slab @ +13.80 Level (Part 2) Construct Beams and Deck Slab @ +13.80 Level (Part 3) Construct Stairways Construct Internal Walls and Columns Construct Beams and Deck Slab @ +18.00 Level Construct Beams and Deck Slab @ +18.00 Level (Part 1) Construct Beams and Deck Slab @ +18.00 Level (Part 2) Construct Beams and Deck Slab @ +18.00 Level (Part 3) Construct Stairways Construct Internal Walls and Columns Construct Beams and Deck Slab @ +22.20 Level Construct Beams and Deck Slab @ +22.20 Level (Part 1) Construct Beams and Deck Slab @ +22.20 Level (Part 2) Construct Beams and Deck Slab @ +22.20 Level (Part 3) Construct Stairways Construct Internal Walls and Columns

MAIN BUILDI BUILDING - GROUND FLOOR SUP-1010 Construct Internal Walls and Columns SUP-1020 SUP-1021 SUP-1022 SUP-1023 SUP-1030 Construct Beams and Deck Slab @ +5.40 Level Construct Beams and Deck Slab @ +5.40 Level (Part 1) Construct Beams and Deck Slab @ +5.40 Level (Part 2) Construct Beams and Deck Slab @ +5.40 Level (Part 3) Construct Stairways

MAIN BUILDI BUILDING - 1ST FLOOR SUP-2010 Construct Internal Walls and Columns SUP-2020 SUP-2021 SUP-2022 SUP-2023 SUP-2030 Construct Beams and Deck Slab @ +9.60 Level Construct Beams and Deck Slab @ +9.60 Level (Part 1) Construct Beams and Deck Slab @ +9.60 Level (Part 2) Construct Beams and Deck Slab @ +5.40 Level (Part 3) Construct Stairways

MAIN BUILDI BUILDING - 2ND FLOOR SUP-3010 Construct Internal Walls and Columns SUP-3020 SUP-3021 SUP-3022 SUP-3023 SUP-3030 Construct Beams and Deck Slab @ +13.80 Level Construct Beams and Deck Slab @ +13.80 Level (Part 1) Construct Beams and Deck Slab @ +13.80 Level (Part 2) Construct Beams and Deck Slab @ +13.80 Level (Part 3) Construct Stairways

MAIN BUILDI BUILDING - 3RD FLOOR SUP-4010 Construct Internal Walls and Columns SUP-4020 SUP-4021 SUP-4022 SUP-4023 SUP-4030 Construct Beams and Deck Slab @ +18.00 Level Construct Beams and Deck Slab @ +18.00 Level (Part 1) Construct Beams and Deck Slab @ +18.00 Level (Part 2) Construct Beams and Deck Slab @ +18.00 Level (Part 3) Construct Stairways

MAIN BUILDI BUILDING - 4TH FLOOR SUP-5010 Construct Internal Walls and Columns SUP-5020 SUP-5021 SUP-5022 SUP-5023 SUP-5030 Construct Beams and Deck Slab @ +22.20 Level Construct Beams and Deck Slab @ +22.20 Level (Part 1) Construct Beams and Deck Slab @ +22.20 Level (Part 2) Construct Beams and Deck Slab @ +22.20 Level (Part 3) Construct Stairways

MAIN BUILDI BUILDING - 5TH FLOOR SUP-6010 Construct Internal Walls and Columns

Actual Work Remaining Work Critical Remaining Work Milestone Actual Milestone

Critical Milestone

AMAH-1

Date 30-Nov-11 ISSUED FOR TENDER

Revision

Checked

Approved

AL MUSSAFAH AHALIA HOSPITAL PRELIMINARY SCHEDULE


2 of 4

Activity ID

Activity Name

Original Duration 1 2 3 4 5 6 7 8 9 10 18 10 10 8 14 18 18 10 10 8 14 18 18 10 10 8 14 8 9 8

SUP-6020 SUP-6021 SUP-6022 SUP-6023 SUP-6030

Construct Beams and Deck Slab @ +26.40 Level Construct Beams and Deck Slab @ +26.40 Level (Part 1) Construct Beams and Deck Slab @ +26.40 Level (Part 2) Construct Beams and Deck Slab @ +26.40 Level (Part 3) Construct Stairways

Month 11 12 13 14 Construct Beams and Deck Slab @ +26.40 Level

15

16

17

18

19

20

21

22

23

24

25

26

27

Construct Beams and Deck Slab @ +26.40 Level (Part 1) Construct Beams and Deck Slab @ +26.40 Level (Part 2) Construct Beams and Deck Slab @ +26.40 Level (Part 3) Construct Stairways Construct Internal Walls and Columns Construct Beams and Deck Slab @ +30.60 Level Construct Beams and Deck Slab @ +30.60 Level (Part 1) Construct Beams and Deck Slab @ +30.60 Level (Part 2) Construct Beams and Deck Slab @ +30.60 Level (Part 3) Construct Stairways Construct Internal Walls and Columns Construct Beams and Deck Slab @ +34.80 Level Construct Beams and Deck Slab @ +34.80 Level (Part 1) Construct Beams and Deck Slab @ +34.80 Level (Part 2) Construct Beams and Deck Slab @ +34.80 Level (Part 3) Construct Stairways Construct Internal Walls and Columns Construct Beams and Deck Slab @ +38.30 Level Construct Stairways

MAIN BUILDI BUILDING - 6TH FLOOR SUP-7010 Construct Internal Walls and Columns SUP-7020 SUP-7021 SUP-7022 SUP-7023 SUP-7030 Construct Beams and Deck Slab @ +30.60 Level Construct Beams and Deck Slab @ +30.60 Level (Part 1) Construct Beams and Deck Slab @ +30.60 Level (Part 2) Construct Beams and Deck Slab @ +30.60 Level (Part 3) Construct Stairways

MAIN BUILDI BUILDING - 7TH FLOOR SUP-8010 Construct Internal Walls and Columns SUP-8020 SUP-8021 SUP-8022 SUP-8023 SUP-8030 Construct Beams and Deck Slab @ +34.80 Level Construct Beams and Deck Slab @ +34.80 Level (Part 1) Construct Beams and Deck Slab @ +34.80 Level (Part 2) Construct Beams and Deck Slab @ +34.80 Level (Part 3) Construct Stairways

MAIN BUILDI BUILDING - ROOF AND TOP ROOF FLOOR SUP-8040 Construct Internal Walls and Columns SUP-8050 SUP-8060 Construct Beams and Deck Slab @ +38.30 Level Construct Stairways

CIVIL/ARCHITECTURAL WORKS CIVIL/ARCHITE


CIV-0000 CIV-0005 CIV-0010 CIV-0020 CIV-0030 CIV-1010 CIV-1020 CIV-1030 CIV-2010 CIV-2020 CIV-2030 CIV-2040 CIV-2050 CIV-2060 CIV-2070 CIV-3010 CIV-3020 CIV-3030 CIV-3040 CIV-3050 CIV-3060 CIV-4010 CIV-4020 CIV-4030 CIV-4040 CIV-4050 CIV-4060 CIV-4070 CIV-4080 CIV-4090 CIV-4100 Start Civil/Architectural Works Finish Civil/Architectural Works Blockworks and Plastering Works Boundary Walls Installation External Curb Stone and Paving Blocks Water proofing Works to Wet Areas (i.e. Kitchen, Toilet, etc..) Water proofing Works to External Surfaces Water proofing Works to Roof Areas Install Curtain Walls (C omposite Aluminum Section and Glazing) Wall Finishes Ceiling Finishes Floor Finishes Painting Works Install Sanitary Fittings (Sanitary ware and Tapware) Other External Finishing Works Install Powder Coated Aluminun Doors Install Fire Rated Wooden Doors Install Powder Coated Aluminum Windows Install Aluminum Louver Doors Install Electrically Operated Sliding Doors Instal Door Ironmongery Install Epoxy Coated Aluminum Pipe Handrails Install Aluminum Powder Coated Ramp Railing Install Aluminum Ladder Stair for Basement Floor Install Galvanized Ladder Stair from Roof to Top Roof Install Access Panel for Services Type SD1 and SD2 Install Aluminum Kitchen Cabinet Install Epoxy Coated Wrought Iron for External Fence Install Barrier for External Access to Basement Electrical Operator Install Automatic Barrier and Electrical Operated Steel Gates Install External Galvanized Flag Pipe Install Bumper Guards and Corner Protection Install Counters for Reception and Nurse Station Install Corridor Handrail 0 0 201 61 31 231 234 61 214 214 214 214 214 153 132 214 214 214 138 107 91 214 31 30 31 123 122 61 30 61 20 78 200 153 Install Bumper Guards and Corner Protection Install Counters for Reception and Nurse Station Install Corridor Handrail Install Aluminum Powder Coated Ramp Railing Install Aluminum Ladder Stair for Basement Floor Install Galvanized Ladder Stair from Roof to Top Roof Install Access Panel for Services Type SD1 and SD2 Install Aluminum Kitchen Cabinet Install Epoxy Coated Wrought Iron for External Fence Install Barrier for External Access to Basement Electrical Operator Install Automatic Barrier and Electrical Operated Steel Gates Install External Galvanized Flag Pipe Install Aluminum Louver Doors Install Electrically Operated Sliding Doors Instal Door Ironmongery Install Epoxy Coated Aluminum Pipe Handrails Blockworks and Plastering Works Boundary Walls Installation External Curb Stone and Paving Blocks Water proofing Works to Wet Areas (i.e. Kitchen, Toilet, etc..) Water proofing Works to External Surfaces Water proofing Works to Roof Areas Install Curtain Walls (Composite Aluminum Section and Glazing) Wall Finishes Ceiling Finishes Floor Finishes Painting Works Install Sanitary Fittings (Sanitary ware and Tapware) Other External Finishing Works Install Powder Coated Aluminun Doors Install Fire Rated Wooden Doors Install Powder Coated Aluminum Windows Start Civil/Architectural Works Finish Civil/Architectural Works

MASONRY WO WORKS

THERMAL AND MOISTURE PROTECTION

FINISHING WO WORKS

DOORS AN D W DOWS WIN

MISCELANEUOUS METAL WORKS MISCELANEUO

WOOD WORKS
CIV-5010 CIV-5020 CIV-5030

MEP WORKS
MEP-0000 MEP-0010 MEP-0020 MEP-0030 MEP-0040 Start MEP Works Chilled Water and Air Distribution System Install Galvanized Steel Sheet Rectangular Duct Works. Install Ventillation System Install Building Managemenrt System (BMS) 0 242 242 242 214 Start MEP Works Chilled Water and Air Distribution System Install Galvanized Steel Sheet Rectangular Duct Works. Install Ventillation System Install Building Managemenrt System (BMS)

AIR-CONTIONING AND VEN TILATION SYSTEM AIR-CONTIONI

Actual Work Remaining Work Critical Remaining Work Milestone Actual Milestone

Critical Milestone

AMAH-1

Date 30-Nov-11 ISSUED FOR TENDER

Revision

Checked

Approved

AL MUSSAFAH AHALIA HOSPITAL PRELIMINARY SCHEDULE


3 of 4

Activity ID

Activity Name

Original Duration 1 2 3 4 5 6 7 8 9 10 11 12 13 92 61 61 61 242 242 242 137 92 92 92 92 92 92 242 242 92 76 76 242 242 242 245 92 92 199 199 242 242 242 242 242 90 184 184 184

Month 14

15

16

17

MEP-0050 MEP-0060 MEP-0070 MEP-0080 MEP-1010 MEP-1020 MEP-1030 MEP-1040 MEP-1050 MEP-1060 MEP-1070 MEP-1080 MEP-1090 MEP-1100 MEP-2010 MEP-2020 MEP-2030 MEP-2040 MEP-2050 MEP-3010 MEP-4010 MEP-4011 MEP-4020 MEP-4030 MEP-4031 MEP-4040 MEP-4060 MEP-4070 MEP-4080 MEP-4090 MEP-4100 MEP-4110 MEP-4120 MEP-4140 MEP-4150 MEP-4160

Install Air-Cooled Water Chillers and Pumps Install Fresh Air Handlling Units Roof Mounted Exhaust Fans Motor Control and Supply Distribution Panel Installation of Internal Cold Water Pipes, F ittings and Valves Installation of Internal Hot Water Pipes, F ittings and Valves Installation of Internal Drainage Pipes and Fittings Installation of Drain Water Pipes and Manholes Install CWS Transfer Pump Set Install of Electric Water Heaters Install HWS Circulation Pump Set & CWS Booster Pump Set Install Central Water F ilter in cl. Pipes, Filter Pumps Automatic Control Panel Install Water Tanks Including Related Piping Works Install Drainage Pump Set Install Fire Sprinkler System Install Fire Alarm and Fire Detection System Install FM-200 Clean Agent System Install Fire Water Pumps and Control Panels Install Portable Fire Extinguishers Installation Medical Gases Install Power/Lighting Cables, Supports & Trays Install Electrical Service to Mechanical Works Install Main and Sub Distribution Boards including MCC Install 1500KVA Dr y Type Transformer Install Stand by Generator Install Final Sub-Circuit, Fixtures and Accessories Install Lighting Fixtures Install Public Address & Voice Evacuation System Install SMATV System Telephone, Data (Structure Cabling) and CATV System Install Uninterruptable Power Supply (UPS) Install Earthing System Install Lightning Ptotection Install Nurse Call System Install IPTV System and Audio System Install CCTV System and Access Control System

18 19 20 21 Install Air-Cooled Water Chillers and Pumps Install Fresh Air Handlling Units Roof Mounted Exhaust Fans Motor Control and Supply Distribution Panel

22

23

24

25

26

27

DRAINAGE AN PLUMB ING WORKS AND


Installation of Internal Cold Water Pipes, F it tings and Valves Installation of Internal Hot Water Pipes, F it tings and Valves Installation of Internal Drainage Pipes and Fittings Installation of Drain Water Pipes and Manholes Install CWS Transfer Pump Set Install of Electric Water Heaters Install HWS Circulation Pump Set & CWS Booster Pump Set Install Central Water F il ter incl. Pipes, Filter Pumps Automatic Control Panel Install Water Tanks Including Related Piping Works Install Drainage Pump Set Install Fire Sprinkler System Install Fire Alarm and Fire Detection System Install FM-200 Clean Agent System Install Fire Water Pumps and Control Panels Install Portable Fire Extinguishers Installation Medical Gases Install Power/Lighting Cables, Supports & Trays Install Electrical Service to Mechanical Works Install Main and Sub Distribution Boards including MCC Install 1500KVA Dr y Type Transformer Install Stand by Generator Install Final Sub-Circuit, Fixtures and Accessories Install Lighting Fixtures Install Public Address & Voice Evacuation System Install SMATV System Telephone, Data (Structure Cabling) and CATV System Install Uninterruptable Power Supply (UPS) Install Earthing System Install Lightning Ptotection Install Nurse Call System Install IPTV System and Audio System Install CCTV System and Access Control System

FIRE FIGHTING SYSTEM

MEDICAL GAS GASES ELECTRICAL W WORKS

CONVEYING SY SYSTEM
CON-0000 CON-0010 CON-0020 CON-0030 CON-0040 Start Installation of Conveying System Install Parking Lift Type (L3) Install Bed Lifts Type (L1) Install Passenger Lifts Type (L2) Install Service Lifts Type (L4) 0 60 183 183 183 Start Installation of Conveying System Install Parking Lift Type (L3) Install Bed Lifts Type (L1) Install Passenger Lifts Type (L2) Install Service Lifts Type (L4)

SPECIAL CONS CONSTRUCTION


SPC-0010 SPC-0015 SPC-0020 SPC-0030 SPC-0040 SPC-0060 Install Car park Shade from Steel Pipe & Polypropylene Cover Install Swimming Pool System in 7th Floor Install Window Washing System Install Kitchen Equipment with Freezer, Fridge and Oven Install Laundry Equipment incl. Shelves, Racks and Free Standing Washing Machine Install Stainless Steel Design Space Frame for Building Facade' 101 150 101 101 101 71 Install Car park Shade from Steel Pipe & Polypropylene Cover Install Swimming Pool System in 7th Floor Install Window Washing System Install Kitchen Equipment with Freezer, Fridge and Oven Install Laundry Equipment incl. Shelves, Racks and Free Standing Washing Machin e Install Stainless Steel Design Space Frame for Building Facade'

PROVISIONAL ITEMS - INDICATIVE ONLY

TESTING, COM COMMISSIONING AND POWER ON


TST-0000 TST-0010 TST-0020 TST-0030 TST-0040 TST-0050 TST-0060 Install Temporary Power & Water Supply Testing and Commissioning Inspection/Snags and Approvals Temporary Power ON Final Inspection and Approval Connection to Main Services (by Statutory) Building Completion Certificate 20 24 14 0 6 6 6 Install Temporary Power & Water Supply Testing and Commissioning Inspection/Snags and Approvals Temporary Power ON Final Inspection and Approval Connection to Main Services (by Statutory) Building Completion Certificate

Actual Work Remaining Work Critical Remaining Work Milestone Actual Milestone

Critical Milestone

AMAH-1

Date 30-Nov-11 ISSUED FOR TENDER

Revision

Checked

Approved

AL MUSSAFAH AHALIA HOSPITAL PRELIMINARY SCHEDULE


4 of 4

Você também pode gostar