Você está na página 1de 30

City of Coweta Building Permit Fees 2009

New Residential Construction Enter your data here


Plan Check Fee
Inspection Fee Total Floor area =.. 1500
(Floor area includes garage & upper floors,but excludes unfinished areas & porches)

Building Permit Sub Total =


Contractors do not require permits for each individual trade, as all inspections are included in the above fee. Plumbin
mechanical contractors must hold valid State & City of Coweta licenses.

Additional costs for new residential construction


Park & Recreation Fee ($50.00 + $25.00 per bedroom)

Number of rooms capable of use as a bedroom = 3


Sewer Tap Fee
Number of connections onto City Sewer, Inside City limits = 1
Number of connections onto City Sewer, Outside City limits = 0
Water Tap Fee (including 3/4" water meter)
Number of connections onto City Water, Inside City limits = 1
Number of connections onto City Water, Outside City limits = 0

Total New Residential Construction Fees

Accessory Buildings
Buildings less than 120 sq ft do not require building permits. Buildings 750 sq ft+ need to matc
structure in appearance & materials. All buildings must meet City setback requirements & must
utility easements.
Enter your data here

Building Permit Fee 240

Accessory buildings that include any mechanical, plumbing or electrical work require a $25.00
relevant trade per building. Each of these trades must hold a valid City of Coweta contractor's li

Mechanical Permit 0
Plumbing Permit 0
Electrical Permit 1

Total Accessory Building Permit Fee


Residential Remodel
Enter your data here

Building Permit Fee


Floor area of the area being remodelled = 240

Residential remodels that include any mechanical, plumbing or electrical work require a $25.00
relevant trade per building. Each of these trades must hold a valid City of Coweta contractor's li

Mechanical Permit 1
Plumbing Permit 1
Electrical Permit 1

Total Residential Remodel Permit Fee

New Commercial Construction Enter your data here


Plan Check Fee

Inspection Fee Total floor area = 4000


0.4% x valuation of construction cost
Estimated cost estimate per sq ft* = $70.00
*Value as determined by the latest ICC Building Valuation Data Table

Building Permit Sub Total *

*Contractors do not require permits for each individual trade, as all inspections are included in the above
both fire & landscape sprinklers, fire & security alarms, data infrastructure & any other low voltage system
electrical and mechanical work must be carried out by Oklahoma State & City of Coweta licensed contrac

Additional costs for new commercial construction


Park & Recreation Fee
$0.01 x floor area =
Sewer Tap Fee
Number of connections onto City Sewer, Inside City limits = 1
Number of connections onto City Sewer, Outside City limits = 0
Water Tap Fee
Number of connections onto City Water, Inside City limits = 1
Number of connections onto City Water, Outside City limits = 0
Total New Commercial Construction Fee *
*This fee excludes any water meters, which are the cost of materials plus 15%

Commercial Remodel Enter your data here

Plan Check Fee


Commercial remodels that include any mechanical, plumbing or electrical work require a $25.00 fee for each relevan
of these trades must hold a valid City of Coweta contractor's license.

Mechanical Estimated number of inspections required 2


Plumbing Estimated number of inspections required 2
Electrical Estimated number of inspections required 2

Total Commercial Remodel Fee

Other Building Permits


In Ground Swimming Pools
Total Fees, including all inspections =

Demolition Permits
Total Fee for demolition of building or structure

Mobile Home Permit


New Mobile Home, including all inspections =
Existing Mobile Home Inspection

Mover's Permit
Oversized Load
Building or Structure
2009

your data here


$250.00

sq ft @ $0.22/ sq ft = $330.00

$580.00
e included in the above fee. Plumbing, electrical and

.= $125.00

.@ $750 per tap = $750.00


.@ $950 per tap = $-

.@ $850 per tap = $850.00


.@ $1050 per tap = $-

$2,305.00

ngs 750 sq ft+ need to match the principal


setback requirements & must not encroach into

your data here

sq ft @ $0.15/ sq ft = $36.00

trical work require a $25.00 fee for each


City of Coweta contractor's license.

mechanical permit = $-
plumbing permit = $-
electrical permit = $25.00

$61.00
your data here

sq ft @ $0.15/ sq ft = $36.00

ctrical work require a $25.00 fee for each


City of Coweta contractor's license.

mechanical permit = $25.00


plumbing permit = $25.00
electrical permit = $25.00

$111.00

your data here

.=.. $500.00

sq ft Valuation = $280,000

Inspection fee = $1,120.00

$1,620.00

ctions are included in the above fee. This includes


e & any other low voltage systems. Plumbing,
City of Coweta licensed contractors.

.= $40.00

.@ $750 per tap = $750.00


.@ $950 per tap = $-

.@ $750 per tap = $750.00


.@ $950 per tap = $-
$3,160.00

your data here

$115.00
equire a $25.00 fee for each relevant trade inspection. Each

$50.00
$50.00
$50.00

$265.00

$75.00

$50.00

$100.00
$25.00

$25.00
$100.00