EARTHING (100mm Dia, 13 mm thick CI Pipe 3.0 Mtrs) with Funnel & wiremesh I.

Providing earthing as per IS 3043/ 1987 with 100mm (ID), 13mm thick C.I. Pipe of 3.0 mtr. length after excavating an earth pit of top chamber size1.05 m X 1.05 M X 1.50 M & bottom chamber 0.75 M X 0.75 M X 1.20 M and filling with a homogenous layer of 40 Kgs. of Coke/ Char Coal, 20 Kgs. of Salt and the required quantity of sand around 100mm pipe from the bottom of the pipe to a height of 2.7mtr. and filling the remaining excavated portion with earth and consolidation/ Settlement of the trench should be done by filling with sufficient quantity of water. A concrete bed of size 0.8 M X 0.8 M X 0.1 M thick and an inspection chamber having inside measurements of 0.4 M X0.4 M X 0.4 M with wall thickness of 100 mm with cement concrete CC 1:3:6 using 20 mm HBG Metal is to be constructed with side wall 100 mm above ground level and plastering the exposed walls neatly with CM 1:5 with 12 mm thick.. The Top of the Inspection Chamber is to be provided with reinforced precasted RCC Slab with 40mm thick with lifting hook. The top of C.I. Pipe is to be fixed & welded with suitable G.I. Wire mesh funnel 50mm x 6mm G.I. Strip having length of 200mm is to be fixed to the top of C.I. Pipe with G.I. Clamps fabricated with 50 x 3mm G.I. Flats with necessary bolts and nuts and necessary welding to be done to the clamps and C.I. Pipe. 2 Nos. of holes are to be drilled on either side of G.I. Flat for Extending earth connections. 65mm dia PVC Pipe is to be embedded at the pit entry for earth. After laying earth from earth conductor bus to Electrode trough PVC Pipe, the surface should be covered with bitumen and grease. The cost of GI/Copper flat to be run from CI Pipe electrode to the equipment is to be made separately on running meter basis. The work shall be executed strictly as per IS 3043 - 1987. (Note:- Necessary meggaring testing is to be carried out in the presence of concerned Engineers and measurement of resistance shall be as per ISI standards) Total Quantity 4 2.32 Cum Rate Tpt 5 97.85 109.60 Tml TPT Amount 6 227.01 TML Amount 7 254.27

S.no 1 a) Material 1

Description 2 Earth work excavation, ordinary soil manual means upto 3 M depth
top: 1.05 M X 1.05 M X 1.50 M bottom: 0.75 M X 0.75 M X1.20 M

Unit 3 cum

Qty

2.32

1.65 0.67 2.32 cum 0.14 0.14 Cum 3233.90 3237.55 452.75 453.26

(Rate as per Item No.5.1 (a) Civil SSR, Vol-I,2011-12) 2 Laying of bed concrete & inspection chamber with C.C 1:3:6 , 20 mm HBG Stone Metal
Bed : 0.8M X 0.8 MX 0.1 M walls : 2.00 M X 0.10 MX 0.40 M

0.06 0.08

(Rate as per Item No.6.1.3 Civil 0.144 SSR, Vol-I,-2011-12) Cement plastering inside through sqm with 1:5 Cement mortar, 12 mm thick (Civil SSR).

1.08

1.08 Sq.mtr

79.50

90.10

85.86

97.31

Inside: 1.60 X0.40 top : 2.00 X 0.10 outside:2.40 X 0.10 (Rate as per Item No.11.1.4 Civil SSR, Vol-I,-2011-12) cover 40 mm precasted RCC slab thick using 10 mm graded aggregate of HBG crushed metal (0.45 X 0.45)

0.64 0.20 0.24 1.08 sqm

0.2

0.20 Sq.mtr

171.4

188.4

34.28

37.68

c/o

799.90

842.52

100 mm dia, 13 mm thick C.I pipe (Rate as per Item.21.99.3 of Civil SSR, vol. II, 2011-12

Mtr

3.00

3.00 Rmt

454.67

B/f 454.67

799.90 1364.01

842.52 1364.01

G.I Funel covered with wire mesh 1/2" x 4" (Rate as per Item No.1274 / 8.136 of R&B SSR-2010-11)

Each

1.00

1.00 No.

75.00

75.00

75.00

75.00

7 8

50 mm x 6mm of 0.2 M length G.I Flat 50 mm X 3 mm of 0.2 M length GI strip to connect GI flat to CI pipe at top side fabrication charges for GI strip & drilling 12 mm holes 6 Nos, to GI flat & 2 Nos. to strip or as per direction G.I Bolts, Nuts and Washers. (Rate as per R&B 2010-11 Item Sl.No.1302/Elec 8.1.64) Hard Coke. (Rate as per R&B 2010-11 Item Sl.No.1254/Elec 8.1.16) Salt. (Rate as per R&B 2010-11 Item Sl.No.1255/Elec 8.1.17)

Each Each

1.00 1.00

1.00 No. 1.00 No.

LS LS

LS LS

20.00 20.00

20.00 20.00

Each

1.00

1.00 No.

LS

LS

20.00

20.00

10 11 12 13 14 15 16

Set

6.00

6.00 Set

10.00

10.00

60.00

60.00

kg

4.00

40.00 Kg

8.00

8.00

320.00

320.00

kg

20.00

20.00 Kg

4.00

4.00

80.00

80.00

Sand Cu.Mtr (Rate as per Civl SSR-2010-11. Item No.2.6.Vol-I / 10-11 Sundries Saddles. such as Lugs and

0.16

0.16 Cu.Mtr

230.57

468.11

36.89

74.90

17

LS

LS

120.00 2915.80

120.00 2996.42 29.96

1% TML Handling Charge (Exclude the cost of Item No. 1 to 6) labour charges for fixing pipe ring and connections with necessary bolts,& nuts and necessary welding to be done to GI pipe to flat. 1 No. Skilled Electrician
1 No. Semi Skilled Electrician

18

TPT

TML

(a) (b)

day day

1.00 1

1.00 Nos 1 No

387.50 325.00

434.00 364.00

387.50 325.00 3628.30

434.00 364.00 3824.39

Rate per Each = C / 2 Note: Labour charges considered for 2 Nos /day