Você está na página 1de 57

A PROJECT TO STUDY PRODUCTION AND OPERATIONS OF NTPC SIMHADRI USING PRODUCTION AND OPERATION MANAGEMENT FUNCTIONS

INDEX

S.NO. 1. 2. 2.1. 2.2. 2.3. 2.4. 2.5. 2.6. 2.7. 2.8. 2.9 3. 3.1. 3.2. 3.3. 3.4. 3.5. 4. 4.1. 4.2. 4.3. 5. 6. 7. 8.

CONTENTS POWER SECTOR IN INDIA INTRODUCTION TO NTPC MAJOR ACHIEVEMENTS OF NTPC HISTORY OF NTPC VISION AND MISSION OF NTPC NTPC: CULTURE Simhadri NTPC NTPC: CORE VALUES &OBJECTIVES SWOT ANALYSIS DIVERSIFICATION SUBSIDIARIES BUSINESS MODEL OF NTPC OPERATIONS OF THE BUSINESS OPERATING STRATEGIES OF NTPC ORGANIZATION STRUCTURE CORPORATE OBJECTIVE SUPPLY CHAIN MANAGEMENT ISSUES AND CHALLENGES HUMAN RESOURCES FUTURE CAPACITY ADDITIONS CHALLENGES WITH COAL RESOURCES ARTICLE CASE STUDY CONCLUSIONS/RECOMMENDATIONS BIBLIOGRAPHY

PAGE NO. 2 4 7 6 10 11 12 14 14 17 18 20 21 29 30 34 34 34 34 38 40 43 48 50 50

1.

POWER SECTOR IN INDIA:-

Power development in India is the key to economic development. The power sector has been receiving adequate priority ever since the process of planned development in 1950. Hydro power and coal based thermal power have been the main sources of generating electricity. Nuclear power development is at slower pace, which was introduced in late 60s. The concept of operating power systems on a regional basis crossing the place, the power supply industry have been under constant pressure to bridge the gap between supply and demand. Since Independence in 1947, Indian Power sector progress has been rapid. From mere 1713 MWs of Installed capacity in 1950 the capacity at the end of March 2007 rose to 124569 excluding capacity of renewable energy. Total generation in April 2006- March 2007 was 659419 GWs in the utility sector. The per capita consumption of electricity increased from 15 KWHs in 1950 to 619 in 2006-07. Decades of economic planning in India following independence placed significant emphasis on the development of the power sector. Electricity generation capacity with utilities in India had grown from 1713 MW in December 1950 to over 124,287 MW by March 2006. However, per capita electricity consumption remains much lower than the world average and even lower than some of the developing Asian economies. Investment in the sector has not been able to improve access and keep pace with the countrys growing demand for electricity. India has the fifth largest generation capacity in the world with an installed capacity of 152 GW as on 30 September 2009, which is about 4 percent of global power generation. The top four countries, viz., US, Japan, China and Russia together consume about 49 percent of the total power generated globally. The average per capita consumption of electricity in India is estimated to be 704 kWh during 2008-09. However, this is fairly low when compared to that of some of the

developed and emerging nations such US (~15,000 kWh) and China (~1,800 kWh). The world average stands at 2,300 kWh. The Indian government has set ambitious goals in the 11th plan for power sector owing to which the power sector is poised for significant expansion. In order to provide availability of over 1000 units of per capita electricity by year 2012, it has been estimated that need-based capacity addition of more than 100,000 MW would be required. This has resulted in massive addition plans being proposed in the sub-sectors of Generation Transmission and Distribution. India is world's 6th largest energy consumer, accounting for 3.4% of global energy consumption. Due to Indias economic rise, the demand for energy has grown at an average of 3.6% per annum over the past 30 years. In March 2009, the installed power generation capacity of India stood at 147,000 MW while the per capita power consumption stood at 612 kWh. The country's annual power production increased from about 190 billion kWh in 1986 to more than 680 billion kWh in 2006. The Indian government has set an ambitious target to add approximately 78,000 MW of installed generation capacity by 2012. The total demand for electricity in India is expected to cross 950,000 MW by 2030. About 75% of the electricity consumed in India is generated by thermal power plants, 21% by hydroelectric power plants and 4% by nuclear power plants. More than 50% of India's commercial energy demand is met through the country's vast coal reserves. The country has also invested heavily in recent years on renewable sources of energy such as wind energy. As of 2008, India's installed wind power generation capacity stood at 9,655 MW. Additionally, India has committed massive amount of funds for the construction of various nuclear reactors which would generate at least 30,000 MW. In July 2009, India unveiled a $19 billion plan to produce 20,000 MW of solar power by 2020.

The

Power

sector

in

India

is

predominantly

controlled

by

the Government of India's public sector undertakings (PSUs). Major PSUs involved in the generation of electricity are National Thermal Power Corporation (NTPC), National Hydroelectric Power Corporation (NHPC) and Nuclear Power Corporation of India (NPCI). Besides PSUs, several state-level corporations, such as Maharashtra State Electricity Board (MSEB), are also involved in the generation and intra-state distribution of electricity. The Power Grid Corporation of India is responsible for the inter-state transmission of electricity and the development of national grid. The Ministry of Power is the apex body responsible for the generation and development of power in India. This ministry started functioning independently from 2 July, 1992; earlier, it was known as the Ministry of Energy. The Union Minister of Power at present is Sushilkumar Shinde, who took charge of the ministry on the 28th of May, 2009.

2.

INTRODUCTION TO NTPC :-

NTPC Limited is the largest thermal power generating company of India. A public sector company wholly owned by Government of India, it was incorporated in the year 1975 to accelerate power development in the country. Within a span of 30 years, NTPC has emerged as a truly national power company, with power generating facilities in all the major regions of the country. Recognizing its excellent past performance and its vast potential, the Govt. of the India has identified NTPC as one of the 'Navratnas'- a potential global giant and also it is going to be identified as one of the Maharatna- giant among the 'Navratnas'. NTPC Limited is the largest thermal power generating company of India. A public sector company, it was incorporated in the year 1975 to accelerate power development in the country as a wholly owned company of the Government of India. At present, Government of India holds 89.5% of the total equity shares of the company and the balance 10.5% is held by FIIs, Domestic Banks, Public and others. Within a span of 30 years, NTPC has emerged as a truly national power company, with power generating facilities in all the major regions of the country. Based on 1998 data, carried out by Data monitor UK, NTPC is the 6th largest in terms of thermal power generation and the second most efficient in terms of capacity utilization amongst the thermal utilities in the world. The Group's principal activity is to generate and sell power to state utilities. It also provides consultancy to power utilities and maintains power stations. The Group operates in two segments, namely, Power Generation and Others. The Power generation segment includes generation and sale of bulk power to SEBs/State utilities. Other business includes providing consultancy, project management and supervision, oil and gas exploration and coal mining.

In the Forbes list of World's 2000 largest companies, 2008, NTPC occupies 317th place. With a current generating capacity of 30,144 MW, NTPC has embarked on plans to become a 75,000 MW company by 2017.

Presently, Government of India holds 89.5% equity in the company and the balance 10.5% is held by FIIs, Domestic Banks, Public and others. As on date, NTPC's total installed capacity is 27, 904 MW. NTPC's coal based power stations are at: Singrauli (Uttar Pradesh), Korba (Chattisgarh), Ramagundam (Andhra Pradesh), Farakka (West Bengal), Vindhyachal (Madhya Pradesh), Rihand (Uttar Pradesh), Kahalgaon (Bihar), NTCPP (Uttar Pradesh), Talcher (Orissa), Unchahar (Uttar Pradesh), Simhadri (Andhra Pradesh), Tanda (Uttar Pradesh), Badarpur (Delhi), and Sipat (Chattisgarh). NTPC's Gas/Liquid based power stations are located at: Anta (Rajasthan), Auraiya (Uttar Pradesh), Kawas (Gujarat), Dadri (Uttar Pradesh), Jhanor-Gandhar (Gujarat), Rajiv Gandhi CCPP Kayamkulam (Kerala), and Faridabad (Haryana). NTPC's Power Plants with Joint Ventures are located at Durgapur (West Bengal), Rourkela (Orissa), Bhilai (Chhattisgarh), and RGPPL (Maharastra). Indias largest power company, NTPC was set up in 1975 to accelerate power development in India. NTPC is emerging as a diversified power major with presence in the entire value chain of the power generation business. Apart from power generation, which is the mainstay of the company, NTPC has already ventured into consultancy, power trading, ash utilisation and coal mining. NTPC ranked 317th in the 2009, Forbes Global 2000 ranking of the Worlds biggest companies. The total installed capacity of the company is 31,134 MW (including JVs) with 15 coal based and 7 gas based stations, located across the country. In addition under JVs, 3 stations are coal based & another station uses naptha/LNG as fuel. By 2017, the power generation portfolio is expected to have a diversified

fuel mix with coal based capacity of around 53000 MW, 10000 MW through gas, 9000 MW through Hydro generation, about 2000 MW from nuclear sources and around 1000 MW from Renewable Energy Sources (RES). NTPC has adopted a multi-pronged growth strategy which includes capacity addition through green field projects, expansion of existing stations, joint ventures, subsidiaries and takeover of stations. NTPC has been operating its plants at high efficiency levels. Although the company has 18.79% of the total national capacity it contributes 28.60% of total power generation due to its focus on high efficiency. In October 2004, NTPC launched its Initial Public Offering (IPO) consisting of 5.25% as fresh issue and 5.25% as offer for sale by Government of India. NTPC thus became a listed company in November 2004 with the government holding 89.5% of the equity share capital. The rest is held by Institutional Investors and the Public. The issue was a resounding success. NTPC is among the largest five companies in India in terms of market capitalization. At NTPC people before Plant Load Factor is the mantra that guides all HR related policies. NTPC has been awarded No.1, Best Workplace in India among large organizations and the best PSU for the year 2009, by the Great Places to Work Institute, India Chapter in collaboration with The Economic Times. The concept of Corporate Social Responsibility is deeply ingrained in NTPC's culture. Through its expansive CSR initiatives NTPC strives to develop mutual trust with the communities that surround its power stations. Right from social to developmental work of the community and welfare based dependence to creating greater self reliance; the constant Endeavour is to institutionalize social responsibility on various levels.

2.1 MAJOR ACHIEVEMENTS OF NTPC

Largest thermal power generating company of India.

Sixth largest thermal power generator in the world. Second most efficient utility in terms of capacity utilization. One of the nine PSUs to be awarded the status of Navratna. Provides power at the cheapest average tariff in the country.

2.2 HISTORY OF NTPC


1975 Incorporated in November 1977 TPC acquired the first patch of land at Sanghrauli The first batch of executive trainees joined the company

1978 Takeover of management of the Badarpur project. Construction of the first transmission network Sanghrauli- Korba- Kanpur of 400 KV systems started. 1982 Power Management Institute, Delhi, a centre for education was established 1983 In the very first year of commercial operation , NTPC earned a profit of Rs 4.51 crore in the financial year 1982-83

1985

This year marked the completion of decade (1975-1985) of NTPCs existence. NTPC achieved a generating capacity of 220 MW by commissioning 11 units of 200 MW each at its various projects in country. The government of India approved the setting of three gas based combine cycle projects by NTPC in Kawat in gujrat, Auraiya in Uttar Pradesh and Anta in Rajasthan. For these projects, the World Bank agreed to provide US$ 485 million, which was the largest single loan in the history of bank. 1987 Crossed the 5000 MW capacity mark. 1989 Consultancy division launched 1990 Total installed capacity crossed 10000MW 1992 Acquisition by the company of Feroz Gandhi Unchahar Thermal Power Station (2x210 MW) from Uttar Pradesh Rajya Vidyut Utpadan Nigam Of Uttar Pradesh 1994 Crossed 15000 MW of installed capacity. 1995

NTPC celebrated 20 yrs of its existence.

A new logo was adopted. NTPC took over the 460 MW Talcher Thermal power Station from Orrisa State Electricity Board. 1997 Achieved 100 million units generation in one year. 1998 Commissioned the first Naphtha based plant at Kayamkulam with a capacity of 350 MW. 2000 Commenced construction of a first hydro- electricity power project of 800 MW capacity in Himachal Pradesh 2002 Three wholly owned subsidiaries viz. NTPC Electric Supply Company Limited, NTPC Hydro Limited, NTPC Vidyut Vyapar Nigam Limited incorporated. 2004 NTPC became a listed company. NTPC made its debut issue of euro bonds amounting to USD 200 million in international market. 2005

The company rechristened as NTPC Limited in line with its changing business portfolio and transforms itself from a thermal power utility to an integrated power utility. 2008 National Thermal Power Corporation is the largest power generation company in India. Forbes Global 2000 for 2008 ranked it 411th in the world.

2.3 VISION AND MISSION OF NTPC


VISION: To be one of the worlds largest and best power utilities, powering Indias growth. To realize this vision, NTPC has drawn up a detailed Corporate Plan for the period 1997-2012 which represents the company's collective optimism and enthusiasm, inspired by a glorious past, a vibrant present and a brilliant future. The Plan has been prepared in-house in consultation the committed, competent and confident members of the NTPC family. The road map that has been charted out was after a thorough scan of the strengths and weaknesses within the organization as well as opportunities and threats in the environment. Considering multidimensional opportunities in the energy sector, NTPC will adopt a multi-pronged growth strategy for capacity addition through Greenfield sites, expansion of existing stations, takeovers and joint ventures. The capacity addition plans that NTPC have drawn up for the fifteen-year period using all the above strategies to enable the corporation to become a 40,000 MW company by 2012 A.D.

MISSION: Develop and provide reliable power, related products and services at competitive prices, integrating multiple energy sources with innovative and ecofriendly technologies and contribute to society"

Make available reliable and quality power in increasingly large quantities at competitive prices and ensure timely realization of revenues. Adopt a broad based capacity portfolio including Hydro Power, LNG, Nuclear Power, and non conventional and eco-friendly fuels Plan and speedily implement power projects using state-of- the art technologies. Be an integrated utility by implementing strategic diversifications in areas such as power trading distribution, transmission, coal mining, coal beneficiation etc. Develop a strong portfolio of profitable businesses in overseas markets including technical services, generation assets etc. Continuously attract and develop committed human resources to match world standards. Lead fundamental and applied research for adoption of the state-of-theart technologies, breakthrough efficiency improvements and new fuels. Lead developmental efforts in the Indian power sector including assisting state utility reform, policy recover etc.

Be a socially responsible corporate entity with thrust on environment protection, ash utilization, community development, and energy conservation.

2.4 NTPC: CULTURE


Core values are both intensely and widely shared Climate of high behavioral control Low employee turnover High agreement among the employees, for what NTPC stands for. All these point to the fact that strong cohesiveness, loyalty and organization commitment exist in NTPC lowering he attrition Rate.

2.5 Simhadri

NTPC:

Address Telephone Fax Email Location Govt. approved date Approved Capacity/Installed Capacity Plant Configuration Land Availability Coal Source Water Source Beneficiary States Approved Investment Associated Transmission System Units Commissioned

P.O. Simhadri-531 020, Dist. Vishakhapatnam, Andhra Pradesh (STD-08924,STD-Vizag-0891) - 243001 243092 Near Pittavanipalem Village,Dist. Vishakhapatnam, Andhra Pradesh 24.07.1997 (Zero date 8.7.1997) 1000 MW 2X500 MW 3384.24 acres (entire land) Kalinga Block of Talcher Coal fields in Orrisa Yeluru canal for sweet water, Sea water for CW system. Andhra Pradesh (100%). Rs.3650.79 Cr. (I Qtr.97). Implemented by APTRANSCO. Unit-I Commissioning: Feb 2002

Unit-II Commissioning: Aug 2002 International Assistance JBIC Simhadri is the ambitious project of the National Thermal Power Corporation (NTPC) intended to provide the ever growing power needs of the state of Andhra Pradesh. Infact, NTPC comes to the rescue of about 20 million units of power consumed every day in Andhra Pradesh. The construction work of the project is under way. Mr. R.C. Srivatsav has been appointed as the General Manager for the Simhadri Project Operations. With the completion of the project, the total power generation capacity of NTPC will reach to 3600 MW in

Andhra Pradesh with NTPC Ramagundum already generating 2100 MW a day. The Project was developed near Parawada and 3384 acres of land was allocated for the construction of the Thermal plant. The height of the Chimney is 275-feet - a record in Asia for being the tallest factory chimney. Near to this are the 165meter two cooling towers. The Coal for the project will be coming to the plan with a special rail line setup for this. Coal will be drawn from the Mahanadi Coal Fields in Orissa drawing over 6 Million tones of coal every year. The Coal transport for the NTPC Simhadri Project is expected to begin in December 2002. The water intake for the project for cooling is done by sea water drawn from 8.9 kms away from the Bay of Bengal through an intake-well sized 9100 cubic meters. This intakewell is again the biggest well constructed in the entire India. The project also gets Sweet water from the Yeluru canal. The power generated at NTPC Simhadri will be bought by AP Transco - the power distribution arm of the Electricity Board in the state. The approximate selling price of power is expected to be at Rs. 2.10 as against to the price from private power generation companies which was at Rs. 3 - 4 per unit. The 500 MW First Boilers at the NTPC Simhadri, Boiler was ignited on November 6, 2001. This is a mile stone in the history of NTPC Simhadri. The commencement of the 500 MW first units was expected to begin in March 2002 while the second unit is expected to begin by December 2002. To save the environment from pollution, NTPC Simhadri has taken ample steps. Towards this is the project of planting trees and maintaining greenery around the site.

2.6 NTPC: CORE VALUES &OBJECTIVES

CORE VALUES This corporate plan provides details of the overall agenda for NTPC. The successful delivery of this agenda would require a committed work force that identifies with and supports the vision. To ensure realization of this corporate agenda, a set of core values should be central to, and govern each activity of the organization. Known as one of the NAVRATAN S of the PSUS NTPC has its following core values. They are known as (BCOMIT) as follows:B-Business Ethics C-Customer Focus O-Organizational & Professional pride M-Mutual Respect and Trust I- Innovation & Speed T-Total quality for Excellence

2.7 SWOT ANALYSIS

STRENGTHS Largest market share in domestic power generation and a broad customer portfolio across the country. Excellent track record of performance in project

implementation and plant operation.

Diversified thermal generation portfolio multiple sizes and

fuel types. Highly skilled and experienced human resources, exposed to

state-of-the art technologies in project execution and power generation. Navaratna status High brand equity among shareholders. Strong balance sheet ability to raise low cost debt. Engineering skills in project configuration and package design. Turnaround ability for old plants demonstrated in the

takeover plants of Talcher, Tanda & Unchahar. High credit rating that is indicative of the confidence of

lenders. In-house training facility (PMI), CENPEEP, R&D etc that assist growth strong execution of Resettlement and

in development of the sector. Thrust on reducing social costs of capacity rehabilitation plans.

WEAKNESS Low risk-diversification of business portfolio consists primarily of generation assets. Poor financial health of customers. Functional orientation hampering cross functional perspective in decision making.

Long and multi layered procurement process leading to long lead times and process delay. Fragmented IT architecture. Gaps in HR systems such as performance management, rewards and incentives and career development. Inadequate deployment of a strong knowledge management system that could assist in improving efficiency and effectiveness in all aspects of the business. Hierarchy for decision making that affects responsiveness. Role ambiguity and dilution within different lends of the organization. OPPORTUNITIES Expand generation capacities by putting up thermal and hydro capacities; maintain the position of a dominant generating utility in the Indian Power sector. Broad base fuel mix by considering imported coal, gas, domestic coal, nuclear power etc with a view to mitigate fuel risks and maintain long run competitiveness. Expand services for EPC, R&M and O&M activities in the domestic as well as international markets.

Backward integrate into fuel management to exercise greater control and understanding of supply economics. Lead the development and commercial deployment of nonconventional energy sources especially in the distributed generation mode. Improve collections by trading, direct sale to bulk customers and the active role in allocation in new plants. Execute increased number of power plants that classify for Mega Power Projects status, thereby reducing the cost of the projects and power and power generated. Forward integrate into the distribution business in India.

THREATS Limited experience of operating in a truly liberalized environment with competition. Limited experience of operating in an independently regulated

system. Redirecting power may be constrained by inter-regional

connectivity. Downward regulatory and competitive pressure on tariffs. Stringent norms for approval of increase in capital costs for

projects in event of time overrun. Stringent environmental norms in the future may add to the

cost of generation.

Absence of an independent regular for coal industry and the

delay in private investments lending to the risk of low availability of coal in the future

2.7 DIVERSIFICATION
NTPCs quest for diversification started with its foray into Hydro Power. It has, since then, been moving towards becoming a highly diversified company through backward, forward and lateral integration. The company is well on its way to becoming an Integrated Power Major, having entered Hydro Power, Coal Mining, Power Trading, Equipment Manufacturing and Power Distribution. NTPC has made long strides in developing its Ash Utilization business. In its pursuit of diversification, NTPC has also developed strategic alliances and joint ventures with leading national and international companies.

Hydro Power: In order to give impetus to hydro power

growth in the country and to have a balanced portfolio of power generation, NTPC entered hydro power business with the 800 MW Koldam hydro projects in Himachal Pradesh. Two more projects have also been taken up in Uttarakhand. A wholly owned subsidiary, NTPC Hydro Ltd., is setting up hydro projects of capacities up to 250 MW.

Coal Mining: In a major backward integration move to create

fuel security, NTPC has ventured into coal mining business with an aim to meet about 20% of its coal requirement from its captive mines by 2017. The Government of India has so far allotted 7 coal blocks to NTPC, including 2 blocks to be developed through joint venture route. Coal Production is likely to start in 2009-10.

Power Trading: 'NTPC Vidyut Vyapar Nigam Ltd.' (NVVN), a

wholly owned subsidiary was created for trading power leading to optimal utilization of NTPCs assets. It is the second largest power trading company in the country. In order to facilitate power trading

in the country, National Power Exchange Ltd., a JV between NTPC, NHPC, PFC and TCS has been formed for operating a Power Exchange.

Ash Business: NTPC has focused on the utilization of ash

generated by its power stations to convert the challenge of ash disposal into an opportunity. Ash is being used as a raw material input for cement companies and brick manufacturers. NVVN is engaged in the business of Fly Ash export and sale to domestic customers. Joint ventures with cement companies are being planned to set up cement grinding units in the vicinity of NTPC stations.

Power Distribution: NTPC Electric Supply Company Ltd.

(NESCL), a wholly owned subsidiary of NTPC, was set up for distribution of power. NESCL is actively engaged in Rajiv Gandhi Gramin Vidyutikaran Yojanaprogramme for rural electrification and also working as 'Advisor cum Consultant' for Ministry of Power for implementation of Accelerated Power Development and Reforms Programme (APDRP) launched by Government of India.

Equipment

Manufacturing: Enormous augmentation of

growth in power

power

sector

necessitates

equipment

manufacturing capacity. NTPC has formed JVs with BHEL and Bharat Forge Ltd. for power plant equipment manufacturing. NTPC has also acquired stake in Transformers and Electricals Kerela Ltd. (TELK) for manufacturing and repair of transformers.

2.8 SUBSIDIARIES:NTPC Electric Supply Company Ltd. (NESCL) The company was formed on August 21, 2002. It is a wholly owned subsidiary company of NTPC with the objective of making a foray into the

business of distribution and supply of electrical energy, as a sequel to reforms initiated in the power sector. NTPC Vidyut Vyapar Nigam Ltd. (NVVN) The company was formed on November 1, 2002, as a wholly owned subsidiary company of NTPC. The companys objective is to undertake sale and purchase of electric power, to effectively utilize installed capacity and thus enable reduction in the cost of power. NTPC Hydro Ltd. (NHL) The company was formed on December 12, 2002, as a wholly owned subsidiary company of NTPC with an objective to develop small and medium hydroelectric power projects of up to 250 MW. Pipavav Power Development Co. Ltd. (PPDCL) A memorandum of understanding was signed between NTPC, Gujarat Power Corporation Limited (GPCL) and Gujarat Electricity Board (GEB) in 2004 for development of a 1000 MW thermal power project at Pipavav in Gujarat by forming a new joint venture company between NTPC and GPCL with 50:50 equity participation. Pursuant to the decision of Gujarat Government, NTPC Ltd. has dissociated itself from this company. PPDCL is under winding up. Kanti Bijlee Utpadan Nigam Limited, (formerly known as Vaishali Power Generating Company Limited) To take over Muzaffarpur Thermal Power Station (2*110MW), a subsidiary company named Vaishali Power Generating Company Limited (VPGCL) was incorporated on September 6, 2006 with NTPC contributing 51% of equity and balance equity was contributed by Bihar State Electricity Board. This company was formed to renovate the existing unit and run the plant. The second unit has been successfully re-synchronized on October 17, 2007 after 4 years of being idle. Renovation and modernization of the first unit is under progress. The company was rechristened as Kanti Bijlee Utpadan Nigam Limited on April 10, 2008. Bharatiya Rail Bijlee Company Limited (BRBCL)

A subsidiary of NTPC under the name of Bharatiya Rail Bijlee Company Limited was incorporated on November 22, 2007 with 74:26 equity contribution from NTPC and Ministry of Railways, Govt. of India respectively for setting up of four units of 250 MW each of coal based power plant at Nabinagar, Bihar. Investment approval of the project was accorded in January, 2008.

3.
1.

BUSINESS MODEL OF NTPC

Efficiency improvement includes both improvements in the existing process and through improvement in the technology used to increase the productivity of the company. Research & Development Centre is ISO 17025 accredited and provides high end scientific services to all the companys stations as well as many outside stations resulting in improving availability and reliability of stations by providing condition assessment, failure analysis, solving and analyzing specific problems, and helping our stations in increasing the availability and reliability of their units.

2. Cost efficiency i.e. providing power at reasonable prices so that they could provide power to all in need. Their ultimate aim is to reduce the cost because without being the cost leader they cant dominate the market. So as a market leader they are always aiming at reducing the cost. 3. Technology enhancement i.e. to stay in competition they have to continuously enhance their technology. Technology enhancement is also a part of cost efficiency. That means by applying the new technologies the company can reduce the cost as well as improve the efficiency. 4. Eco friendly system: Driven by its commitment for sustainable growth of power, NTPC has evolved a well defined environment management policy and sound environment practices for minimizing environmental impact arising out of setting up of power plants and preserving the natural ecology.

3.1 OPERATIONS OF THE BUSINESS

LOCATION OF FACILITY FOR NTPC

The purpose of the location of NTPC in Visakhapatnam is to

find an optimal location which will result in the greatest advantage to the organization. There is minimal wastage of resources because of this BHEL is the major supplier of equipment for NTPC Simhadri. It HPCL is the major supplier of FUEL. It is located at a distance The plant is quite near to Sea ports, Railway station (to handle It distributes power to Power Grid which is just 10 Km away location. is located at a distance of 20 Kms from the plant. of 20 Kms. coal from Australia and Talcher) and Airport. from the location of the plant and hence there is no wastage of power during transmission. Nearest water source is Yeleru Canal. 5 Kms from Seashore as it uses sea water as coolant in

cooling towers.

PLANT LAYOUT AND MATERIAL HANDLING

NTPC SIMHADRI OVERALL LAYOUT

Coal is handled and processed. It is then sent to the units 1,2,3,4. Units 1 and 2 are linked with chimney 1 which consists of 2 chimneys internally. Similarly units 3 and 4 are linked with chimney 2. Each unit is linked with cooling towers in order to cool the steam. Sea water pump house links with cooling towers in order to supply Sea water as a coolant. DM plant links all the units in order to supply DM water. Yeleru Reservoir Canal is linked with DM plant to supply water. Every unit is linked with power handling and transmission station where power is transmitted to the power grid. Also, each unit is linked with Ash pond through Ash dispenser.

GENERAL THERMAL POWER PLANT LAYOUT

1. Cooling Tower 2. Cooling Water Pump 3. Transmission Line (3-

10. Steam Control Valve 19. Superheated 11. High Pressure Steam 20. Forced Turbine 12. Deaerator 13. Feedwater Heater 14. Coal Conveyor 15. Coal Hopper 16. Coal Pulverizer 17. Boiler Steam Drum 18. Bottom Ash Hopper (Draft) Fan 21. Reheater

Draught

Phase) 4. Step-Up Transformer (3Phase) 5. Electrical Phase) 6. Low Generator (3Pressure Steam

22. Combustion Air Intake 23. Economizer 24. Air Preheater 25. Precipitator 26. Induced (Draft) Fan 27. Flue Gas Stack Draught

Turbine 7. Condensate Pump 8. Surface Condenser 9.Intermediate

Pressure Steam Turbine

COAL PROCESS LAYOUT

a Coal is imported from Talcher and Australia which is transported to the plant through rail. a Coal wagons are handling at the Coal handling station. a From the coal handling station, coal is either stored in Stock Yard or directly sent to Coal Crushing mill, which crushes coal to 20mm size. a Through Conveyor belts, coal is sent to bunkers. a From bunkers it is sent to Coal mill where coal is milled to powdered state.

a The powdered coal is mixed with air and sent to Coal Gun. a From Coal Gun, it is sent to the Coal Furnace.

UNIT LAYOUT 1(IN ORDER TO KNOW THE INTERNAL OPERATION OF COAL FURNACE)

The coal furnace is surrounded by water walls which consist of DM water. DM water is supplied from Boiler Drum to Coal Furnace which is more than 165 meters high from Coal Furnace. Coal is supplied through coal gun. Initially, the coal is burnt with the help of Diesel. Two kinds of Diesel are used: HSD (High Speed Diesel) and LSD (Low Speed Diesel). First LSD is used and then HSD is used. Later, Oil supply is stopped and coal is left for burning. In order to ignite the furnace, DC supply is given by the DC inverters. The heat generated by the coal furnace is more than 1200 degrees centigrade.

When water comes through the water walls, it gets heated upto 540 degrees and turns into steam. This steam flows to turbines at various pressures. These turbines are linked with generators which generate power and these generators supply power to power stations from where it is sent to power grid. After the Coal is burnt, it turns into Ash. Bottom Ash is collected at Bottom Ashing and the Fly ash at the Induction Fans (IDF). Ash flows through IDF to ESP (Electro Static Priscribrators). In this ESP, 99% of Ash is sent to bottom Ashing. Less than 1% of the Fly ash goes through Chimneys which is 275 meters high. So, there is very less Air pollution.

UNIT LAYOUT 2(IN ORDER TO KNOW THE INTERNAL OPERATION AND PROCESS OF TURBINE)

Steam generated in the coal furnace is supplied to the Economizer.

From there, it is sent to the Super heater which has an elaborate setup of tubing where the steam vapour picks up more energy from Hot Flue gases outside the tubing and its temperature is now super heated above the saturation temperature. The super heater steam is then piped through the main steam lines to the walls before the high pressure turbines. From High Pressure turbines (HP) steam is transferred to Super Heater again and then to IP (Intermediate pressure) turbine.

The turbines are connected to generators where power is generated and sent to power grid. After this, the steam loses its pressure and hence is sent to low pressure turbine (LP). Then, steam has very low pressure which cannot be used for the turbines. Hence, it is sent to condenser which is in Vaccum.

The condenser is a shell and tube heat exchanger in which cooling water is circulated through the tubes. The exhaust steam from the LP turbines enters the shell where it is cooled and converted to condensate (water) by falling over the tubes. Such condensers use steam ejectors for continuous removal of air and gases from the steam side to maintain vaccum. This condensated steam is converted to water by the cooling towers in which coolant is sea water.

The water from the cooling tower is sent to hot well. From hot well, the water will go through condenser pumps through low pressure temperature heater, then through High pressure temperature heaters. This is called Re-heating or Re-cycling system (Deaerator system) to Boiler speed pump. Each boiler speed pump consumes 10MW in 500MW generated power.

Deaerators to boil speed pumps and to HP heaters and to FRS (Feed Regulating Station) to Boiler Drum. Hence whatever DM water was vaporized is again De-vaporized to DM water again. This comes back to Boiler Drum again. In cyclic process, this water goes down from Boiler drum to Furnace.

In between the process of vaporizing and de-vaporizing of water, 10% of water is lost. This lost water is made up by make up pumps which are connected to the DM plant.

DE-MINERALIZATION PLANT LAYOUT

Water is supplied from Yeleru Canal to the reservoir. From here, this This water is purified with the help of Aulum and Chlorine in the first Filter water is sent through gravity filters by which we get pure

water is pumped to DM plant. stage. This water is called Filter water. drinking water.

This pure water is sent to Cat-ion vessel and then to Cat-ion

exchanges from here to the Degasser and then to An-ion exchanger and to mixed bed. The water coming out of the mixer bed is 100% pure Dematerialized DM water is stored in DM water tank. The DM water tank is linked with DM water make up pump which is water (DM).

again linked to boiler drum.

POWER STATION LAYOUT

The power generated through the generators is 18 Kv. This 18 Kv power is stepped up by step-up generator to 400 Kv. This is done in order to avoid heavy Cabling for transmission of power. This is sent to power grid.

From Power grid, the power distributions are 400 Kv which is given to factories. In the same way 33 Kv, 11 Kv are stepped onto 440v and again stepped onto 230v which is used to household purpose.

3.2 OPERATING STRATEGIES OF NTPC


Maintain its position as the leader: As the largest power Generation Company in India NTPC Ltd is looking to increase its capacity to 75000 MW by 2017. Adopt the new technology: NTPC Ltd is also looking to utilize other sources of power generation in the next 5 years namely Hydel power and nuclear energy to generate electricity. Resource management : The company will look to continue with their stringent recruitment and retention policy which has provided it with the best minds in the country. Environment management : Being the leader in its trade the company will look towards fulfilling its corporate social responsibility and contributing towards the environment.

3.3 ORGANIZATION STRUCTURE:

3.4 CORPORATE OBJECTIVE


BUSINESS PORTFOLIO GROWTH To further consolidate NTPCS position as the leading thermal power generation company in India and establish a presence in hydro power segment. risks. To diversify across the power value chain in India by considering To broad base the generation mix by evaluating conventional

sources of energy to ensure long run competitiveness and mitigate fuel-

backward and forward integration into areas such as power trading, transmission, distribution, coal mining, coal beneficiation, etc. To develop a portfolio of generation assets in international markets.

To establish a strong brand in the domestic & international market. CUSTOMER FOCUS To foster a collaborative style of working with customer To expand the relationship with existing customers by trading, energy consulting, distribution consulting,

e.g.

growing to be a preferred brand for supply of quality power. offering a bouquet of services in addition to supply of power management consulting, management practices. To expand the future customer portfolio through

profitable diversification into downstream business, inter alia retail distribution and direct supply. To ensure rapid commercial decision making, using

customer specific information with adequate concern for the interests of the customer. AGILE CORPORATION To ensure effectiveness in business decisions and

responsiveness to change in the business environment by Adopting a portfolio approach to new business development. Continuous and coordinated assessment of the business

environment to identify and respond to opportunities and threats. To develop a learning organization having knowledge based

competitive edge in current and future businesses. To effectively leverage information technology to ensure

speedy decision making across the organization. PERFORMANCE LEADERSHIP To continuously improve on project execution time and cost in

order to sustain long run competitiveness in generation.

To operate & maintain NTPC stations at par with the best-run utilities in the world with respect to availability, reliability, efficiencies. To aim for performance excellence in the diversification

businesses. To embed quality in all systems and processes. HUMAN RESORUCE DEVELOPMENT To enhance organizational performance by institutionalizing

an objective and open performance management system. To align individual and organizational needs and develop business leaders by implementing a career development system. To enhance commitment of employees by recognizing and

rewarding high performance. To build and sustain a learning organization of competent

world-class professionals. To institutionalize core values and create a culture of team

building, empowerment, equity, innovation and openness which would motivate employees and enable achievement of strategic objectives.

FINANCIAL SOUNDNESS To maintain and improve the financial soundness of NTPC by

prudent management of the financial resources.

To continuously strive to reduce the cost of capital through

prudent management of deployed funds, leveraging opportunities in domestic and international financial markets. To develop appropriate commercial policies and processes

this would ensure remunerative tariffs and minimize receivables. To continuously strive for reduction in cost of power

generation by improving operating practices.

SUSTAINABLE DEVELOPMENT To contribute to sustainable power development by

discharging corporate social responsibilities. To lead the sector in the areas of resettlement and peripheral development and energy conservation

rehabilitation and environment protection including effective ashutilization, practices. To lead developmental efforts in the Indian power sector

through efforts at policy advocacy, assisting customers in the operations and management of power plants etc. RESEARCH and DEVELOPMENTS To pioneer the adoption of reliable, efficient and cost-effective technologies by carrying out fundamental and applied research in alternate funds and technologies. To carry out research and development of breakthrough techniques in power plant construction and operation that can lead to more efficient, reliable and environment friendly operation of power plants in the country.

To disseminate the technologies to other players in the sector and in the long-run generating revenue through proprietary technologies.

3.5 SUPPLY CHAIN MANAGEMENT


Coal is supplied from Talcher and Australia which is stored and maintained very well at the Coal Stock yard. There are no retailers or distributors. Everything is taken care by the government since it is a State-owned company. Supply of electric products are done by BHEL which is also a government owned enterprise. Chief water source is Yeleru canal.

4. ISSUES AND CHALLENGES 4.1 HUMAN RESOURCES


People before PLF (Plant Load Factor)' is the guiding philosophy behind the entire gamut of HR policies at NTPC. NTPC are strongly committed to the development and growth of all our employees as individuals and not just as employees. NTPC currently employ approximately 24500 people at NTPC. Competence building, Commitment building, Culture building and Systems building are the four building blocks on which our HR systems are based.

RECRUITMENT NTPC believe in the philosophy of 'Grow your own timber'. Our 'Executive Trainee' scheme was introduced in 1977 with the objective of raising a cadre of home grown professionals. First Division Graduate Engineers/ Post graduates are hired through nation-wide open competitive examinations and campus recruitments. Hiring is followed by 52 weeks of fully paid induction training.

CAREER ADVANCEMENT AND OPPORTUNITIES NTPC have a well established talent management system in place, to ensure that NTPC deliver on our promise of meaningful growth and relevant challenges for our employees. Our talent management system comprises PERFORMANCE MANAGEMENT, CAREER PATHS and LEADERSHIP DEVELOPMENT. REWARDS AND RECOGNITIONS We have, from inception, created a culture of rewards and recognitions through celebration of various achievements and events and recognizing the contributions behind such success. INNOVATE, CREATE, COMPETE We have introduced numerous initiatives which seek to enhance the

creativity, innovation, functional aptitude and teamwork of our employees. These initiatives include National Open Competition for Executive Talent (NOCET), Professional Circles, Quality Circles, Business Minds and Medha Pratiyogita (a quiz for our employees). A management journal called Horizon is published quarterly to enable the employees to share their ideas and experiences across the organization.

QUALITY OF WORK-LIFE NTPC is proud of its systems for providing a good quality of work-life for its employees. In addition to providing beautiful and safe work places, NTPC encourages a culture of mutual respect and trust amongst peers, superiors and subordinates. Away from hectic city life, NTPC townships provide an environment of serenity, natural beauty and close community living. Numerous welfare and recreation facilities including schools, hospitals and clubs are provided at the townships to enhance quality of life & the well being of employees and their families. An entire range of benefits, from child care leave to post retirement medical benefits are extended to employees to meet any exigency that may arise in a person's life. KNOWLEDGE MANAGEMENT IN NTPC To meet our ultimate objective of becoming a learning organization, an integrated Knowledge Management System has been developed, which facilitates tacit knowledge in the form of learning and experiences of employees to be captured and summarized for future reference. TRAINING AND DEVELOPMENT NTPC subscribes to the belief that efficiency, effectiveness and success of the organization, depends largely on the skills, abilities and commitment of the employees who constitute the most important asset of the organization. Our Training Policy envisages a minimum of 7 man days of training per

employee per year. NTPC have developed our own comprehensive training infrastructure. EDUCATION UP-GRADATION SCHEMES To meet the academic aspirations of employees and match them with the needs of the organization, NTPC has tie-ups with institutes of repute like MDI, Gurgaon; IIT Delhi; BITS Pilani, etc. NTPC sponsors fixed size batches of employees who are inducted into these courses based on their performance rating in the company and their performance in the entrance exam conducted by the respective institute. Unlike other study leave and sabbaticals, employees undergoing these courses do not forego their salary or growth during the duration of the course. SEEKING FEEDBACK NTPC actively seek and encourage employee feedback to ensure that our HR interventions and practices remain relevant and meaningful. NTPC regularly conduct Employee Satisfaction and Organizational Climate Surveys. AWARDS NTPC derive immense satisfaction from the awards NTPC receive and the resulting recognition they bestow. The awards are key indicators and milestones on our HR journey, and reinforce our HR philosophy and practices. NTPC has been awarded No.1, Best Workplace in India among large organizations for the year 2008, by the Great Places to Work Institute, India Chapter in collaboration with The Economic Times.

4.2 FUTURE CAPACITY ADDITIONS


NTPC has formulated a long term Corporate Plan up to 2017. In line with the Corporate Plan, the capacity addition under implementation stage is presented below: PROJECT Coal 1. NCTPP II ( 2 x 490) 2 Korba III ( 1 x 500) 3 Sipat I (3 x 660) 4. Farakka III ( 1 x 500) Indira Gandhi STPP- JV 5. HPGCL ( 3 x 500) 6. Simhadri II ( 2 x 500) 7. Vallur I -JV with TNEB ( 2 Vallur Stage-I Phase-II 8. ( 1 x 500) 9. Bongaigaon(3 x 250) 10 Mauda ( 2 x 500) . 11 Rihand III(2X500) . 12 Vindhyachal-IV (2X500) . 13 Nabinagar TPP-JV with . 250) 14 Barh II (2 X 660) . 15 Barh I (3 X 660) . Hydro 1. Koldam HEPP ( 4 x 200) STATE Uttar Pradesh Chhattisgarh Chhattisgarh West Bengal with IPGCL & Haryana MW 980 500 1980 500 1500

x 500) -JV with TNEB

Andhra Pradesh 1000 Tamilnadu 1000 Tamilnadu Assam Maharashta Uttar Pradesh Madhya Pradesh 500 750 1000 1000 1000 1000 1320 1980 800

Railways (4 x

Bihar Bihar Bihar Himachal

2. Loharinag Pala HEPP ( 4x 150) 3. Tapovan Vishnugad HEPP (4 x 130) Total

Pradesh Uttarakhand Uttarakhand

600 520 179 30

NTPC Limited, countrys largest power generating company having an installed capacity of 30,144 Mw, is adding 6,500 Mw in the southern region. Of this, 1,000 Mw is for the Simhadri Super Thermal Power Station at Visakhapatnam, according to NTPC regional executive director (south) Ambarish N Dave. Of the two 500 Mw units planned to be added at Simhadri, one unit would be ready by November 2010 while the second would come up in the subsequent phase. The Simhadri power plant expansion is estimated to cost about Rs 5,130 crore. Andhra Pradesh would get about 35 per cent power from the new capacity addition at Simhadri. The remaining would be distributed in the southern region according to the agreements with the respective states. The entire power currently generated by the 1,000 Mw Simhadri plant is being used by the state. In Tamil Nadu, the company would add another 500 Mw once its 1,000 Mw plant at Vallur is complete. The plant is being set up at an estimated cost of Rs 5,123 crore in joint venture with the Tamil Nadu Electricity Board. This apart, the company is also in the process of conducting feasibility studies for the 4,000 Mw power plant at Kudgi in Bijapur district of Karnataka. The project would be executed together with Power Company of Karnataka Limited for which a memorandum of understanding was signed in January this year. The project would have three units of 800 Mw each in Stage I and two units of similar capacity in Stage II.

Feasibility studies for multiple locations for a 500Mw wind power project in Karnataka too would be conducted soon. NTPC was in talks with Gas Authority of India Limited for supply of liquefied natural gas (LNG) to the Rajiv Gandhi Combined Cycle Power Project at Kayamkulam in Kerala. The company would take up Stage II expansion of the project upon availability of fuel (LNG) at a viable cost. The proposed expansion would not require additional land. The southern region achieved the highest-ever generation of 32,067.76 million units (mu) during the financial year 2008-09, surpassing the target of 29,775 mu.

4.3 CHALLENGES WITH COAL RESOURCES


The policy changes in coal sector provide an opportunity to NTPC to enter captive coal mining business. Production is expected by 2010 in one coal block already allotted (Pakri Barwadih in the state of Jharkhand). Five more blocks (~40MTPA) have been allotted to NTPC, including two in JV with CIL. In addition to development of its own domestic coal mines NTPC is exploring various other options including acquisition of stake in coal mines abroad for sourcing of thermal coal for addressing fuel security concerns. Ash Utilization is one of the key concerns at NTPC. The Ash Utilization division, set up in 1991, strives to drive maximum usage from vast quantities of ash produced at its coal based stations. The division proactively formulates policies, plans and programmes for Ash Utilization. It further monitors the progress in these areas and works at developing new fields of Ash Utilization.

The quality ash produced conforms to the requirements of IS 3812 2003. The fly ash generated at NTPC stations is ideal for use in cement, concrete, concrete products, cellular concrete, light weight aggregates, bricks/blocks/ tiles etc. this is attributed to very low loss on ignition value. To facilitate availability of dry ash to end users, all the new units of NTPC are provided with the facility of dry ash collection system. Partial dry ash collection systems have also been set up at the existing stations where these facilities did not exist earlier. Augmentation of these systems to 100% capacity is in under progress. As the emphasis on gainful utilization of ash grew, its usage over the years also increased. From 0.3 million tons in 1991 1992, the level of utilization during 2008 09 stood at over 24.40 million tons. The various segments of Ash Utilization currently includes use by a number of Cement, Asbestos Cement products & Concrete manufacturing industries, Land development, Road & Embankments, Ash Dyke Raising and Building Products. Such as bricks / blocks / tiles, as a soil amender and source of micro nutrients in agriculture and backfilling of mines.

AREA WISE BREAK-UP OF UTILISATION FOR THE YEAR 2008-09 IS AS UNDER: Area of Utilization Cement Quantity Million Tons) 7.04 (in

Industries Ready

0.33 Concrete Asbestos 0.20 Clay Ash/ Fly Ash 1.64 Bricks Land Fill 5.74 Ash Dyke Raising 6.24 Road/ 1.30 Embankments Mine Filling 1.14 Agriculture 0.002 Export 0.73 Others 0.02 Total 24.40 MAJOR INITIATIVES TAKEN BY NTPC TOWARDS ASH UTILISATION NTPC continually strives to evolve innovative and diverse means of Ash Utilization to further broaden the scope. Prominent among the methods devised so far are: Dry Flyash Extraction Systems Use in cement & concrete Use in Ash based products including setting up of o Ash Technology Park o Land Development/Wasteland Development, Roads &

Mix

Embankments, Raising Ash Dykes' Mine filling / Stowing Agriculture

NTPC Ash Utilization Division has published multiple literatures on the use of ash in various applications in the form of books & promotional brochures and documentary films to create awareness among the prospective users & entrepreneurs for use of ash. The booklets/ brochures/ films are: BROCHURES:
a a a a

Fly Ash Bricks Clay Ash bricks Clay Ash Bricks with 60% Fly Ash Coal ash Environment friendly material - For fills, Embankments and Road pavement Construction

a a

Fly Ash - a Resource for Cement & Concrete Use of Ash in agriculture (In Hindi)

FILMS:
a a a a

Clay Ash Bricks Fly Ash Bricks Use of Fly Ash in Mine Filling Coal Ash As Fill Material

5.

ARTICLE

Assembly Lines Past and Present Scenario wrt Effective Cost Objective of Study: Analysis of past and present trends used in

Assembly Lines and the cost factor associated with it. 1. History In earlier times, prototypes of assembly lines were used. In the 19thcentury meat-packing industry in Cincinnati, Ohio, and in Chicago, overhead trolleys were employed to convey carcasses from worker to worker. When these trolleys were connected with chains and power was used to move the carcasses past the workers at a steady pace, they formed a true assembly. Stationary workers concentrated on one task, the pace was dictated by the machine. Unnecessary movement was minimized so production was done faster. On similar lines, Henry Ford, the American automobile manufacturer, designed an assembly line that began operation in 1913. The manufacturing time for magneto flywheels was reduced from 20 minutes to 5 minutes. After this success Ford applied the same technique to chassis assembly. Earlier, 12 1/2 man-hours were required for each chassis, however, Ford cut labor time to six man-hours using a rope to pull the chassis. Later, chains were used to drive to power assembly-line movement. So the assembly time fell to 93 man-minutes. With due credit to Ford's efforts, a private automobile could be afforded by a common man. The assembly line spread through a large part of U.S. industry and even low-cost unskilled labor could be employed. Sometimes, supervisors accelerated the pace of the machines and forced the workers to work faster. This led to conflict between the labor and supervisor. Furthermore, the assembly line jobs were monotonous and bored the workers. Quality was also not emphasized.

2. Concept

In todays world there is fierce competition and products are highly customized. The response times have reduced. This is especially true wrt machine tools, heavy construction equipment, heavy manufacturing in general and computer software and hardware. Even though the product is highly customized, yet it is required to be delivered with very short lead times, even shorter as compared to manufacturing lead time. So, the scheduling practice is to release the manufacturing order before the customer order is released and subsequently match incoming customer orders to units in progress. This is referred to as the build-to-forecast (BTF) approach. (Amitabh S. Raturia, Jack R. Mereditha, David M. McCutcheona and Jeffrey D. Camm) Assembly Line Balancing

Assembly lines are widely used for the mass production of consumer goods and components in large volume production systems. Design of these lines warrants taking into consideration not only cycle time and precedence constraints, but also other restrictions. Assembly Line Balancing would occur when for balance purposes workstation size or the no. used would have to be physically modified. The assembly line balancing problem is one of assigning all tasks to a series of workstations so that each workstation has no more than can be done in the workstation cycle time and so the unassigned (idle) time across all workstations is minimized.

Line Balancing is the process of assigning tasks to workstations in such a way that the workstations have approximately equal time requirements (Chase Richard B., Aquilano, Nicholas J, et al; Production & Operations Management- Manufacturing & Services; 8th edition; Tata McGraw Hill., New Delhi; 1999)

Workstation Cycle Time Time between successive units coming off at the end of the line

C = Production Time/ day Required output/ day (units)

Precedence Relationship It specifies the order in which tasks must be performed in the assembly process.

Evaluate the efficiency of the balance Efficiency = Sum of task times (T) Actual No. of WS (Na)* WS Cycle Time (C)

When Task Times are longer than workstation Cycle Times, the Solution is to 1. Split the task 2. Share the task 3. Use parallel workstations 4. Use a more skilled worker 5. Work overtime 6. Redesign Traditional and Dynamic Line Balancing The layout of production facilities also determines productivity potential of a manufacturing enterprise. It is particularly important in the design of assembly lines where the objective is to assign tasks to work stations in such a way as to minimize total variable production costs. A Balanced Layout would produce the desired output with the fewest number of work stations, minimizing idle time. Studies have shown that task times are random variables; therefore the cost of task incompletion must be considered a part of total production cost. Incompletion cost will be the cost of

repairing or completing tasks which cannot be completed within the cycle time after the item has reached the end of the assembly line. (John C. Carter* and Fred N. Silverman*) Dynamic line balancing, assigns operators to one or more operations, where each operation has a predetermined processing time. It is like a group of identical parallel stations. Operator costs and inventory costs are stochastic because they are functions of the assignment process employed in balancing the line, which may vary throughout the balancing period, and the required flow rate. Earlier studies focused on the calculation of the required number of stations and demonstrated why the initial and final inventories at the different operations are balanced. (K. Roscoe Davis* and Deena D. Kushner) Operator costs and inventory costs are the components of the cost function. The operator costs are based on the operations to which operators are assigned and are calculated for the entire work week regardless of whether an operator is given only a partial assignment which results in idle time. It is assumed that there is no variation in station speeds, no learning curve effect for operators' performance times, and no limit on the number of operators available for assignment. The costs associated with work-in-process inventories are computed on a value added basis. There is no charge for finished goods inventory after the last operation or raw material before the first operation. The conditions, which must be examined before using the cost evaluation method, are yield, input requirements, operator requirements, scheduling requirements and output requirements. Yield reflects the output of good units at any operation. The input requirement accounts for units discarded or in need of reworking. The operator requirements define the calculation of operator-hours per hour, set the minimum number of operators at an operation, and require that the work is completed. The scheduling requirements ensure that operators are either working or idle at all times, and that no operator is assigned to more than one operation at any time. The calculation of the output reflects the yield, station speed, and work assignments at the last operation on the line. 3. Challenges

An important obstacle is that some pairs of tasks cannot be assigned to the same station due to factors such as safety, physical demands 4. placed on workers, quality, and technological considerations. Analysis

One study shows that while most simple assembly line balancing problems can be solved optimally, presence of additional restrictions such as task assignments makes them inherently more difficult. Insights into this aspect. (Ram Rachamadugu) The cost evaluation method for dynamic balancing enables a manager to compare the costs of assigning operators to work stations. Using this method to calculate the operator and inventory costs, a number of different heuristics for assigning operators in dynamic balancing can be evaluated and compared for various configurations of the production line. The least cost solution procedure then can be applied to a real manufacturing situation with similar characteristics. (K. Roscoe Davis* and Deena D. Kushner) In order to evaluate candidate line layouts, a total cost model is developed. Total cost is the sum of normal operating costwhich is simply a function of the number of work stationsand the cost of repairing products containing incomplete tasks. Because this latter cost is a random variable for a given balance, the expected value is used to evaluate a candidate layout. The cost associated with one or more workers exceeding the cycle time is the product of the probability of this happening and the expected cost of off-line repair. The heuristic method for generating feasible balances builds workstations from continually updated lists of precedence satisfying tasks. Qualifying tasks are added to the station as long as the probability of the station exceeding the cycle time remains below a pre-specified threshold. The methodology requires systematically varying this threshold to permit a lowest total cost solution to emerge. The process of generating a large number of balances for a particular threshold is efficient. Evaluating the total costs of the resulting balances takes the majority of the computational time. Even for large-scale problems, the computational cost is infinitesimal in the context of assembly line balancing, where very small improvements in productivity can mean substantial increments to profitability. (John C. Carter* and Fred N. Silverman*) 5. Conclusion

With high levels of customization and shorter Lead Times, flexibility in manufacturing, Modular BOM, subcontracting and expediting are used.

In the age of Product Innovation, new technologies, the manufacturing system has to be flexible. So, several hybrid layouts have emerged. Set up times have reduced, so mixed model assembly lines are used. The newest manufacturing system (FMS) has worked wonders and can process any item. Manufacturing cells that resemble small assembly lines are designed to process families of items. Some companies are placing wheels on their machines for adjustment. Others are experimenting with modular conveyor system that allows assembly lines to be rearranged while workers are away.

Cost is an important element in layout design. reduced.

Inventory levels have Machines are

Instead of minimizing material flow, the number of loads has

been minimized and also the distance they are moved.

located closer together to allow the frequent movement of smaller loads. Planners are now concerned with the rapid movement of material to and from the facility itself. Preeti Nigam Sr. Lecturer, Production and Operations Management RBS Meadow

6.CASE STUDY
AT&T BUYS A PRINTER AT&T decided in 1991 to replace with state-of-the art technology the Troy brand of check printers that were being used in two of its operations sites. These sites printed checks for Payroll, Accounts Payable, Employee Reimbursements, and Billing Customer Refunds. Total annual print volume was estimated to be 13 million checks for 1992 and growing.

Treasury Operation's management thought that serving AT&T check printing needs in the future would require a major re-engineering of the check issuance process and that replacement of the printers was a first step. The current systems and equipment, for example, could not meet requirements for printing checks as part of AT&T marketing promotions.

The marketing team, therefore, was forced to use outside services to print these checks. While the outside services met most of the requirements, the accounting transactions that were associated with these checks were often incorrect, and check reconciliation for these checks was almost impossible. Treasury Operations believed that they could eliminate the use of outside services and improve the duality and costs of their current service if they purchased print equipment that was computer controlled. In addition, it was important that the magnetic ink character recognition (MICR) line that was printed at the bottom of the check be of high quality, because banks charge extra for processing checks with unreadable MICR lines. The team looking into new printers had identified Siemens, Delphax, Xerox, IBM, and NCR as the vendors that had printers that should be considered. Team members then decided on the following six criteria: 1. Features: Documented the technical features of each printer, maintenance availability, and requirements. 2. User rating: Documented results of a survey of users of each of the printers. 3. Pros/cons: Documented overall team observations. 4. Cost: Cost analysis included purchase of printers, maintenance, supplies, and software. 5. MICR quality: Conformance to MICR standards. 6. Print quality: Conformance to print quality standards. The team then assigned a point value (10 being the highest score), for each printer for each situation. Their final tabulation is shown on the next page. Criteria Features Siemens 9.9 6.6 8.0 Delphax 5.2 8.3 5.0 2.0 5.4 5.7 7.7 6.7 8.0 8.0 6.0 8.0 9.4 8.4 9.4 8.6 Xerox 8.2 8.6 8.0 8.6 IBM NCR

User Ratings Pros/Cons

10.0 1.0 4.0 9.7 9.7

Cost 10.0 6.0 MICR Quality Print Quality

TOTAL RANKING

57.3 33.0 34.9 44.1 50.8 1 5 4 3 2

DISCUSSION QUESTIONS 1. Is it appropriate taht in the final analysis MICR Quality was given the same weight as Cost? 2. Recompute the comparisons, using the following weight factors: Features 15%, User Ratings 15%, Pros/Cons 15%, Cost 30%, MICR Quality 12.5%, Print Quality 12.5%. Does this change the end result?

7. CONCLUSIONS/RECOMMENDATIONS
a NTPC Simhadri plant has created a benchmark in technology utilization, efficiency and effective utilization of resources. a It has been achieving records right from its synchronization. a It is the only Power plant in India where maximum Automation is done in its operations. a It is the first power plant which uses sea water as a coolant. a It has also achieved great environment standards through its infrastructure facilities like Tallest Chimneys in Asia (275m), Tallest cooling towers in Asia and maintaining an Ash pond which is eco-friendly. a It been maintaining excellent CSR(Corporate Social

Responsibility) by providing jobs to the land losers along with good compensation, providing employment for the locals on a contract basis, construction of roads, drainage systems, drinking water supply, hygienic conditions, hospitals, schools, etc all within 8 Kms of the NTPC plant. a NTPC Simhadri has followed the principles of production and operation management quite well and also maintained good relationship within its Micro as well as Macro environments.

a There should be more Involvement of management at all

levels with effective creation of policies, vision, Mission, values, goals and support, communicated and implemented throughout the Organization. a There should be training of senior executives in managing for quality. a It should evaluate plans for expansion in order to meet the Power needs of India as well as to create more employment.

8. BIBLIOGRAPHY

Production and Operations Management, Chary www.ntpc.in www.google.com Wikipedia Forbes India Business World

Você também pode gostar