Você está na página 1de 14

International Project Estimating System

Bill of Quantities International Toll Road Project


Estimate: 134 - Preliminary Capital Cost Budget
Currency: AUD-Australia-Dollar
Item

Description

Unit

Quantity

Rate

Amount

Utility Relocations

10.10.2.1
10.10.2.2

10.10.2:Electrical Relocations
Relocation of Aerial lines
Relocation of Underground Cable

EA
EA

1.00
1.00

117,760.00
117,760.00

Section Total:

10.10.3.1
10.10.3.2

10.10.3: Cable TV Relocation


Relocation of Main Line
Relocation of Sub-lines

235,520.00

EA
EA

1.00
1.00

11,780.00
11,780.00

Section Total:

10.10.4.1
10.10.4.2
10.10.4.3
10.10.4.4
10.10.4.5
10.10.4.6

10.10.4: Waterline Relocation


Relocation of 14" Watermain
Relocation of 8 " Waterline
Relocation of 6 " Waterline
Relocation of 4 " Waterline
Relocation of 12" Waterline
Relocation of 10" Waterline

EA
EA
EA
EA
EA
EA

10.10.6: Irrigation Relocation


Relocation of Irrigation Pipe 10"
Relocation of Irrigation Pipe 10"
Relocation of Irrigation Pipe 10"
Relocation of Irrigation Pipe 10"

11,780.00
11,780.00
23,560.00

1.00
1.00
1.00
1.00
1.00
1.00

47,100.00
47,100.00
47,100.00
47,100.00
47,100.00
47,100.00

Section Total:

10.10.6.1
10.10.6.2
10.10.6.3
10.10.6.4

117,760.00
117,760.00

47,100.00
47,100.00
47,100.00
47,100.00
47,100.00
47,100.00
282,600.00

EA
EA
EA
EA

1.00
1.00
1.00
1.00

23,550.00
23,550.00
23,550.00
23,550.00

Section Total:

23,550.00
23,550.00
23,550.00
23,550.00
94,200.00

10.10.7: Protection National Water Conduit


10.10.7.1
10.10.7.2
10.10.7.3

Protection Water Conduit 1


Protection Water Conduit 2
Protection Water Conduit 3

LM
LM
LM

215.00
165.00
65.00

236.00
236.00
236.00

50,740.00
38,940.00
15,340.00

Section Total:

105,020.00

Sub Total:

740,900.00

Site Preparation

20.10.10.01
20.10.10.02
20.10.10.03
20.10.10.04

Site Preparation:
Milling Asphalt
Dismantling Barrier
Dismantaling of Existing Structures
Asphalt Spray Subgrade

9/1/03 4:30:26 PM

SM
LM
LS
SM

77,650.00
2,820.00
3.00
300,000.00

4.20
23.60
11,780.00
0.82

326,130.00
66,552.00
35,340.00
246,000.00

Page No 1 of 14

Item
20.10.10.07
20.10.10.08
20.10.10.09

Description
Strip Topsoil to an avg. depth of 30 cm in Cut
sections & 15 CM in Fill sections
GPS Points every 300 m
Additional Survey due to lack of ex. information

Unit
CM
EA
LS

Quantity
255,380.00
70.00
1.00

Rate
2.40

Amount
612,912.00

471.00
235,510.00

32,970.00
235,510.00

Section Total:

20.10.10.10
20.10.10.11

Landscaping Preparation:
Planting
Shrubs

1,555,414.00

SM
LS

50,000.00
1.00

4.70
29,440.00

Section Total:

20.10.10.12
20.10.10.13
20.10.10.14
20.10.10.15

Coordinate with Authorities


Environmental
Survey
Police
Traffic

264,440.00

LS
Month
LS
LS

1.00
20.00
1.00
1.00

23,550.00
4,710.00
117,760.00
235,510.00

Section Total:

10.10.9.1
10.10.9.2
10.10.9.3
10.10.9.4
10.10.9.5
10.10.9.6

Connection to Electrical Utility


Supply LDC-Light Distribution Cabinet - 80A
Supply LDC-Light Distribution Cabinet - 200A
Supply LDC-Light Distribution Cabinet - 250A
Supply LDC-Light Distribution Cabinet - 315A
Structure Light Connections
S & I Electrical Power to Irrigation Equipment

20.10.20.1
20.10.20.2
20.10.20.3
20.10.20.4

Transplantation of Trees
Trees to 15 cm DIA.
Trees 15 to 25 cm DIA.
Trees 25 to 40 cm DIA.
Trees 45 and larger cm DIA.

LS
LS
LS
EA
LS
LS

1.00
1.00
1.00
2.00
1.00
1.00

11,780.00
11,780.00
11,780.00
23,550.00
58,880.00
29,440.00

EA
EA
EA
EA

350.00
350.00
350.00
150.00

942.00
1,060.00
1,180.00
1,770.00

9/1/03 4:30:26 PM

329,700.00
371,000.00
413,000.00
265,500.00

Section Total:

1,379,200.00

Sub Total:

3,840,834.00

Detours
Pave Detours
Temp. Safety Measures -Phase 1
Temp. Safty Measures -Phase 2
Temp. Safety Measures Phase 3

Paving
Granular Subbase
Granular Base
Tack Coat
Prime Coat
Base Asphalt (13 cm depth)

11,780.00
11,780.00
11,780.00
47,100.00
58,880.00
29,440.00
170,760.00

LS
LS
LS
LS

1.00
1.00
1.00
1.00

117,760.00
23,550.00
23,550.00
23,550.00

Section Total:

20.40.1
20.40.2
20.40.3
20.40.4
20.40.5

23,550.00
94,200.00
117,760.00
235,510.00
471,020.00

Section Total:

20.60.10.1
20.60.10.2
20.60.10.3
20.60.10.4

235,000.00
29,440.00

117,760.00
23,550.00
23,550.00
23,550.00
188,410.00

CM
CM
SM
SM
SM

130,420.00
107,441.00
968,552.00
579,016.00
426,185.00

34.90
39.80
0.26
0.68
21.50

4,551,658.00
4,276,151.80
251,823.52
393,730.88
9,162,977.50

Page No 2 of 14

Item
20.40.6
20.40.7

Description
Wearing Asphalt (4 cm depth)
Binder Asphalt (5 cm depth)

Unit
SM
SM

Quantity
548,350.00
610,420.00

Rate
7.80
8.50

Section Total:

Amount
4,277,130.00
5,188,570.00
28,102,041.70

Landscaping

20.60.30.1
20.60.30.2
20.60.30.3

20.60.30: Landscaping Maintenance


Landscape Maintenance
Connecting to water system in addition to
connection in Iron I/C
Water supply system inside blue line including
busters water pipe system, valves

month X
Dunam
EA
EA

41,600.00

5.70

237,120.00

1.00

47,100.00

47,100.00

1.00

235,510.00

235,510.00

Section Total:

20.60.80.1
20.60.80.2
20.60.80.3
20.60.80.4
20.60.80.5

20.60.80: Wall Finishes


Simulated Stone Cladding (structural walls,
landscape walls)
Stone Facing on Agricultural Underpasses
Architectural Shotcrete
Terre Arme Integrated Stone Finish
Natural Coping Stone

519,730.00

SM

7,000.00

54.20

379,400.00

SM
SM
SM
LM

400.00
1,500.00
10,800.00
1,000.00

54.20
54.20
54.20
47.10

21,680.00
81,300.00
585,360.00
47,100.00

Section Total:

20.60.90.1

20.70.010
20.70.020
20.70.030
20.70.040
20.70.050
20.70.060
20.70.070
20.70.080
20.70.090
20.70.100
20.70.110
20.70.120

20.60.90: Landscape Walls


LA - Landscape Walls

1,114,840.00

ls

1.00

706,530.00

706,530.00

Section Total:

706,530.00

Sub Total:

2,341,100.00

Illumination
Lighting Poles Supply
Cabinets Supply
Fixture Supply
Generator Supply
Cables Supply
Infrastructure Installation
Footing Installation
Cable Installation
Pole Installation
Luminaire Installation
Cabinet Installation
Other Electrical Installations

LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS

1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00

1,010,180.00
78,780.00
310,010.00
58,340.00
272,830.00
164,680.00
313,470.00
39,730.00
47,970.00
13,850.00
124,020.00
737,500.00

Section Total:

1,010,180.00
78,780.00
310,010.00
58,340.00
272,830.00
164,680.00
313,470.00
39,730.00
47,970.00
13,850.00
124,020.00
737,500.00
3,171,360.00

Fencing & Signs

20.80.10

20.80.10: Barrier Wall


New Jersey Barrier

LM
Section Total:

9/1/03 4:30:26 PM

1,932.00

148.00

285,936.00
285,936.00

Page No 3 of 14

Item

20.80.20.1
20.80.20.2
20.80.20.3
20.80.20.4
20.80.20.5
20.80.20.6
20.80.20.7

Description

Unit

20.80.20: Safety Accessories


"W" Barrier Pole every 4m
"W" Barrier Pole every 2m
Double "W" Barrier
"ABC"
Quadguard
Turndown
Cats Eyes

LM
LM
LM
EA
EA
EA
EA

Quantity

Rate

Amount

35,939.00
1,112.00
14,650.00
83.00
3.00
2.00
220.00

37.70
63.60
73.00
5,300.00
31,790.00
2,120.00
31.80

Section Total:

20.80.201.1
20.80.201.2
20.80.201.3
20.80.201.4

20.80.201: Traffic Signs & Signage


Regulatory Signage
Curbstone 23/23/100 in Junction
Curbstone 17/25/100
Gr. Mounted Signs (varies sizes c/w fdns)

3,041,579.50

EA
LM
LM
EA

185.00
94.00
10,993.00
50.00

212.00
27.60
27.60
353.00

Section Total:

20.80.30.1
20.80.30.2
20.80.30.3
20.80.30.4
20.80.30.5
20.80.30.6
20.80.30.7

20.80.30: Marking & Painting


Yellow Line (?-7)
Rumble Strip Yellow Line
White Line (?-4)
Dashed Line (?-1)
Single Arrow Painted
Traffic Island Painted (Zebra)
Painted Curb Stone

LM
LM
LM
LM
EA
SM
LM

20.80.40.2

20.80.40.3

20.80.40: Fencing
Phase I: Installation of Posts, Gates & Tension
Wires (Start of Construction)
Phase II: Repair of Posts, Gates & Tension Wires
Damaged During Construction (Wear and Tear)
Phase III: Installation of Fencing Fabric & Animal
Protection Apron (Completion of Fence)

39,220.00
2,594.40
303,406.80
17,650.00
362,871.20

13,354.00
36,920.00
50,274.00
41,650.00
132.00
4,978.00
75.00

2.80
2.80
2.80
2.80
14.10
9.40
2.80

Section Total:

20.80.40.1

1,354,900.30
70,723.20
1,069,450.00
439,900.00
95,370.00
4,240.00
6,996.00

37,391.20
103,376.00
140,767.20
116,620.00
1,861.20
46,793.20
210.00
447,018.80

LM

32,000.00

35.30

1,129,600.00

LM

32,000.00

11.80

377,600.00

LM

32,000.00

70.70

2,262,400.00

Section Total:

3,769,600.00

Sub Total:

7,907,005.50

Bridges

30.10.1802.1
30.10.1802.2
30.10.1802.3
30.10.1802.4

30.10.18-02 Bridge 1: (Segmental)


1000 mm Caissons

VM

928.00

648.00

601,344.00

1200 mm Caissons

VM

634.00

890.00

564,260.00

Piers

VM

107.00

5,160.00

552,120.00

Bridge Structure

SM

9,500.00

1,380.00

13,110,000.00

9/1/03 4:30:26 PM

Page No 4 of 14

Item

Description

Unit

Quantity

Rate

Section Total:

Amount
14,827,724.00

30.10.18.04 Bridge 2: (Segmental)


30.10.18.04.1 1000 mm Caissons

VM

464.00

648.00

300,672.00

30.10.18.04.2 1200 mm Caissons

VM

1,092.00

890.00

971,880.00

30.10.18.04.3 Piers

VM

84.00

5,160.00

433,440.00

30.10.18.04.4 Bridge Structure

SM

6,536.00

1,380.00

9,019,680.00

Section Total:

30.10.1805.1
30.10.1805.2
30.10.1805.3
30.10.1805.4

10,725,672.00

30.10.18-05 Bridge 3. (Segmental)


1000 mm Caissons

VM

696.00

648.00

451,008.00

1200 mm Caissons

VM

512.00

890.00

455,680.00

Piers

VM

141.00

5,160.00

727,560.00

Bridge Structure

SM

8,213.00

1,380.00

11,333,940.00

Section Total:

30.10.1806.1
30.10.1806.2
30.10.1806.3
30.10.1806.4

12,968,188.00

30.10.18-06 Bridge 4: (Segment)


1000 mm Caissons

VM

804.00

648.00

520,992.00

1200 mm Caissons

VM

456.00

890.00

405,840.00

Piers

VM

61.00

5,160.00

314,760.00

Bridge Structure

SM

6,158.00

1,380.00

8,498,040.00

Section Total:

30.10.1807.1
30.10.1807.2
30.10.1807.3
30.10.1807.4

9,739,632.00

30.10.18-07 Bridge 5 Interchange (Girder)


1000 mm Caissons

VM

360.00

606.00

218,160.00

1200 mm Caissons

VM

400.00

890.00

356,000.00

Piers

VM

31.00

6,440.00

199,640.00

Bridge Structure

SM

1,533.00

1,470.00

2,253,510.00

Section Total:

30.10.1808.1

30.10.18-08 Bridge 6 Menashe Reservoir:


(Girder)
1000 mm Caissons

9/1/03 4:30:26 PM

3,027,310.00

VM

2,242.00

606.00

1,358,652.00

Page No 5 of 14

Item
30.10.1808.2
30.10.1808.3

Piers

Description

Unit
VM

Bridge Structure

SM

Quantity
24.00

Rate
6,440.00

Amount
154,560.00

2,750.00

1,470.00

4,042,500.00

Section Total:

30.10.1809.1
30.10.1809.2
30.10.1809.3
30.10.1809.4

5,555,712.00

30.10.18-09 Bridge 7 (Girder)


1000 mm Caissons

VM

650.00

606.00

393,900.00

1200 mm Caissons

VM

165.00

890.00

146,850.00

Piers

VM

12.00

6,440.00

77,280.00

Bridge Structure

SM

1,000.00

1,470.00

1,470,000.00

Section Total:

30.10.1810.1
30.10.1810.2

2,088,030.00

30.10.18-10 Bridge 8 (Girder)


1000 mm Caissons

VM

650.00

606.00

393,900.00

Bridge Structure

SM

790.00

1,470.00

1,161,300.00

Section Total:

30.10.1811.1
30.10.1811.2
30.10.1811.3
30.10.1811.4

1,555,200.00

30.10.18-11 Bridge 9 (Girder)


1000 mm Caissons

VM

334.00

606.00

202,404.00

1200 mm Caissons

VM

1,314.00

890.00

1,169,460.00

Piers

VM

31.00

6,440.00

199,640.00

Bridge Structure

SM

2,022.00

1,470.00

2,972,340.00

Section Total:

30.10.1812.1

30.10.18-12 Bridge 10 (Rigid)


Bridge Structure

4,543,844.00

SM

560.00

2,700.00

Section Total:

30.10.1814.1
30.10.1814.2
30.10.1814.3
30.10.1814.4

1,512,000.00

1,512,000.00

30.10.18-14 Bridge 11 (Girder)


1000 mm Caissons

VM

822.00

606.00

498,132.00

1200 mm Caissons

VM

209.00

890.00

186,010.00

Piers

VM

26.00

6,440.00

167,440.00

Bridge Structure

SM

1,265.00

1,470.00

1,859,550.00

Section Total:

9/1/03 4:30:26 PM

2,711,132.00

Page No 6 of 14

Item

30.10.1815.1
30.10.1815.2
30.10.1815.3
30.10.1815.4

Description

Unit

Quantity

Rate

Amount

30.10.18-15 Bridge 12 (Girder)


1000 mm Caissons

VM

852.00

606.00

516,312.00

1200 mm Caissons

VM

216.00

890.00

192,240.00

Piers

VM

48.00

6,440.00

309,120.00

Bridge Structure

SM

1,310.00

1,470.00

1,925,700.00

Section Total:

30.10.1831.1
30.10.1831.2
30.10.1831.3
30.10.1831.4

2,943,372.00

30.10.18-31 Bridge 13 (Girder)


1000 mm Caissons

VM

1,586.00

606.00

961,116.00

1200 mm Caissons

VM

402.00

890.00

357,780.00

Piers

VM

58.00

6,440.00

373,520.00

Bridge Structure

SM

2,440.00

1,470.00

3,586,800.00

Section Total:

30.10.1832.1

30.10.18-32 Bridge 14 (Rigid)


Bridge Structure

5,279,216.00

SM

1,050.00

2,700.00

Section Total:

30.10.1803.01
30.10.1803.02
30.10.1803.03
30.10.1803.04
30.10.1803.05
30.10.1803.06
30.10.1803.07
30.10.1803.08
30.10.1803.09
30.10.1803.10
30.10.1803.11
30.10.1803.12

2,835,000.00

2,835,000.00

30.10.18-03 Bridge 15
Temporary Erosion Protection

LS

1.00

5,890.00

5,890.00

Temporary Access Road/Crane Pads

LS

1.00

2,650.00

2,650.00

Unwatering Structures

LS

1.00

3,210.00

3,210.00

Earth Excavation for Structure

CM

6,510.00

22.50

146,475.00

Rock Excavation for Structure

CM

500.00

118.00

59,000.00

Structural Backfill

CM

15,640.00

27.70

433,228.00

Supply & Install Caissons

LM

1,456.00

744.00

1,083,264.00

Mass Concrete (Mudslab)

CM

76.00

146.00

11,096.00

Concrete in Footings

CM

1,185.00

241.00

285,585.00

Concrete in Substructure

CM

1,950.00

405.00

789,750.00

Concrete in Deck

CM

3,398.00

1,170.00

3,975,660.00

Concrete in Barrier Walls/Curb

LM

950.00

109.00

103,550.00

9/1/03 4:30:26 PM

Page No 7 of 14

Item
30.10.1803.13
30.10.1803.14
30.10.1803.15
30.10.1803.16
30.10.1803.17
30.10.1803.18
30.10.1803.19
30.10.1803.20
30.10.1803.21

Description
Concrete in Approach Slab

Unit
CM

Quantity
100.00

Rate
287.00

Amount
28,700.00

Concrete Reinforcing Rebar

Tonne

560.00

1,500.00

840,000.00

Post Tensioning

KG

360,000.00

4.70

1,692,000.00

Deck Joint Assemblies

LM

50.00

2,630.00

131,500.00

Bearings

EA

24.00

1,470.00

35,280.00

S & I Barrier Railing

LM

1,020.00

376.00

383,520.00

Embedded Work in Structure

LM

500.00

72.60

36,300.00

Bridge Deck Waterproofing

SM

5,885.00

27.20

160,072.00

Deck Drain System

EA

8.00

13,800.00

110,400.00

Section Total:

30.10.17-12

30.10.17-12 Bridge 16 (Girder)


A17-12W - Ramp 65E-N/S over Eron Stream
(Girder)

10,317,130.00

SM

87.00

4,510.00

Section Total:

30.10.1830.01
30.10.1830.02
30.10.1830.03
30.10.1830.04
30.10.1830.05
30.10.1830.06
30.10.1830.07
30.10.1830.08
30.10.1830.09
30.10.1830.10
30.10.1830.11
30.10.1830.12
30.10.1830.13
30.10.1830.14

392,370.00

392,370.00

30.10.18-30 Bridge 17 (Girder)


Temporary Erosion Protection

LS

1.00

5,890.00

5,890.00

Temporary Access Road/Crane Pads

LS

1.00

2,650.00

2,650.00

Unwatering Structures

LS

1.00

3,210.00

3,210.00

Earth Excavation for Structure

CM

4,865.00

22.50

109,462.50

Rock Excavation for Structure

CM

1,000.00

58.90

58,900.00

Structural Backfill

CM

6,435.00

20.50

131,917.50

Supply & Install Caissons

LM

3,536.00

615.00

2,174,640.00

Mass Concrete (Mudslab)

CM

98.00

146.00

14,308.00

Concrete in Footings

CM

1,145.00

248.00

283,960.00

Concrete in Substructure

CM

1,025.00

557.00

570,925.00

Concrete in Deck

CM

1,405.00

622.00

873,910.00

Concrete in Barrier Walls/Curb

LM

813.00

80.30

65,283.90

Concrete in Approach Slab

CM

315.00

246.00

77,490.00

Concrete Reinforcing Rebar

Tonne

1,050.00

1,500.00

1,575,000.00

9/1/03 4:30:26 PM

Page No 8 of 14

Item
30.10.1830.15
30.10.1830.16
30.10.1830.17
30.10.1830.18
30.10.1830.19
30.10.1830.20
30.10.1830.21
30.10.1830.22

Description
Fab,Del,Erect Precast Con. Box Girders

Unit
EA

Quantity
60.00

Rate
67,490.00

Amount
4,049,400.00

Deck Joint Assemblies

LM

47.00

2,630.00

123,610.00

Bearings

EA

30.00

1,450.00

43,500.00

S & I Barrier Railing

LM

866.00

376.00

325,616.00

Embedded Work in Structure

LM

205.00

72.60

14,883.00

Bridge Deck Waterproofing

SM

4,695.00

27.20

127,704.00

Deck Drain System

LS

1.00

5,890.00

5,890.00

Plexiglas Sound Stop Barriers

LM

431.00

707.00

304,717.00

Section Total:

30.10.1801.1
30.10.1801.2
30.10.1801.3
30.10.1801.4

10,942,866.90

30.10.18-01 Bridge 18
1000 mm Caissons

VM

505.00

648.00

327,240.00

1200 mm Caissons

VM

426.00

890.00

379,140.00

Piers

VM

72.00

5,160.00

371,520.00

Bridge Structure

SM

5,262.00

1,380.00

7,261,560.00

Section Total:

8,339,460.00

Sub Total:

110,303,858.90

Drainage

20.50.01
20.50.02
20.50.03
20.50.04

Drainage
S & I Pre-cast Concrete MH 100x120 cm.
S&P Grate,
S&P Con. Pipe, 80 cm.
S&P Con. Pipe, 100 cm. Dia class 5 grade 175

Unit
Unit
LM
LM

52.00
52.00
1,621.00
502.00

1,930.00
318.00
511.00
551.00

100,360.00
16,536.00
828,331.00
276,602.00

20.50.05
20.50.06
20.50.07

S&P Con. Pipe, 125 cm. Dia class 5


S&P Con. Pipe, 183 cm. Dia class 5
Construct Reinforced Concrete Outlets & Inlets,

LM
LM
CM

372.00
30.00
658.00

615.00
657.00
678.00

228,780.00
19,710.00
446,124.00

20.50.08
20.50.09
20.50.10
20.50.11

Spillways
Spillway for Draining Water from Cut Berm
Ancor Beam around Rip Rap (65*25 cm)
S&P Rip Rap B-20 concrete embedded (including
excavation)
S&P "Geoweb" Sheets 40/10 filled with B-20
concrete placed on Geotextile 200 gr./m2 at inlet
and/or outlet of culverts and drainage works

Unit
Unit
CM
SM

130.00
27.00
2,437.00
31,196.00

1,060.00
1,060.00
636.00
84.80

137,800.00
28,620.00
1,549,932.00
2,645,420.80

SM

17,135.00

75.40

1,291,979.00

S&P Boulders @ Streams, having a min. surface


0.6 sm & 0.4 m. thk.,
Stones (30 cm thickness)

SM

17,500.00

75.40

1,319,500.00

SM

17,500.00

75.40

1,319,500.00

20.50.12

20.50.13
20.50.14

9/1/03 4:30:26 PM

Page No 9 of 14

Item
20.50.15
20.50.16
20.50.17

Description
S & P Geotextile (cloth weight of 200 gr./sm)
Animal Passages
S & P "Geoweb" Sheets 40/10 filled with earth

Unit
SM
SM
SM

Quantity
17,500.00
2,070.00
17,790.00

Rate
3.20
254.00
42.40

Section Total:

20.60.20.1
20.60.20.2
20.60.20.3
20.60.20.4
20.60.20.5
20.60.20.6

30.20.18

Temp. Erosion Control Measures


Temporary Diversion Ditches (m)
Hay Bales (m)
Siltation Fences (m)
Inlet Protection (each)
Clover
Removal of Temporary Measures (l.s.)

Amount
56,000.00
525,780.00
754,296.00

11,545,270.80

LM
LM
LM
EA
ea
LS

5.00
17.00
7.00
100.00
200.00
60,000.00

424.00
42.40
21.20
424.00
212.00
1.10

2,120.00
720.80
148.40
42,400.00
42,400.00
66,000.00

Section Total:

153,789.20

Sub Total:

11,699,060.00

Culverts
Box Culverts

CM

2,339.00

777.00

Section Total:

1,817,403.00
1,817,403.00

Retaining Walls
30.30.18: Reinforced Earth Retaining Walls
30.30.18-01
30.30.18-06
30.30.18-10
30.30.18-18
30.30.18-24
30.30.18-28

Reinforced Earth Wall 1


Reinforced Earth Wall 2
Reinforced Earth Wall 3
Reinforced Earth Wall 4
Reinforced Earth Wall 5
Reinforced Earth Wall 6

SM
SM
SM
SM
SM
SM

766.00
1,126.00
1,336.00
3,932.00
680.00
2,852.00

738.00
911.00
902.00
934.00
958.00
907.00

Section Total:

565,308.00
1,025,786.00
1,205,072.00
3,672,488.00
651,440.00
2,586,764.00
9,706,858.00

30.30.181: Reinforced Concrete Retaining Walls


30.30.18-02
30.30.18-14
30.30.18-34
30.30.18-36

Reinforced Concrete Gravity Wall 1


Reinforced Concrete Gravity Wall 2
Reinforced Concrete Gravity Wall 3
Reinforced Concrete Gravity Wall 4

SM
SM
SM
SM

345.00
1,674.00
2,045.00
4,256.00

612.00
633.00
571.00
1,730.00

Section Total:

30.40.18

30.40.18: Concrete Drainage Channels


Concrete Channels

211,140.00
1,059,642.00
1,167,695.00
7,362,880.00
9,801,357.00

CM

2,185.00

788.00

1,721,780.00

Section Total:

1,721,780.00

Sub Total:

21,229,995.00

Earthworks
20.90: Earthworks

9/1/03 4:30:26 PM

Page No 10 of 14

Item

20.90.01a
20.90.01b

Description

Unit

Excavation Earth & Rock


Earth Excavation
Rock Excavation

CM
CM

Quantity

721,473.00
#########

Rate

Amount

10.40
13.90

Section Total:

20.90.03
20.90.04
20.90.05

20.90.06

Misc Road Items


Extra over for Excavation for Drainage Ditches.

7,503,319.20
30,085,396.30
37,588,715.50

CM

36,175.00

14.10

510,067.50

Agricultural Roads 5 m width 30 cm depth of


KM
subbase including earthworks.
Scarify & Compact Exist Ground where directed and SM
as specified (at bottom of sub excavation).

24.40

52,980.00

1,292,712.00

#########

0.97

1,238,593.00

CM

50,000.00

9.40

470,000.00

CM
SM

40,000.00
85,725.00

21.40
5.80

856,000.00
497,205.00

20.90.09
20.90.10

Excavate below Subgrade Level in Cut/Shallow Fill


Areas, & Replace with same material (
Supply, Spread & Compact Capping Mat'l
S & I HDPE / 1.0 mm/Bituminous Membrane as
specified.
Excavation for Box Culverts
Rock Stabilization c/w Shotcrete & Rock Bolts

CM
SM

10,542.00
12,000.00

23.60
294.00

248,791.20
3,528,000.00

20.90.11

Steel Wire Mesh (Maccaferri), Incl. Bolts & Cables

SM

5,500.00

23.60

129,800.00

20.90.07
20.90.08

Section Total:

20.90.02a
20.90.02b

20.60.40.1
20.60.40.2

Excavate Unsuitable/Excess Mat'l & Haul


Waste Earth
Waste Rock

8,771,168.70

CM
CM

267,892.00
803,674.00

6.80
12.50

Section Total:

11,867,590.60

Sub Total:

58,227,474.80

20.60.40: Topsoil for Landscaping


Soil Spread from Stockpile include haulage &
CM
spreading
Soil Spread from Offsite including material, haulage CM
& spreading

103,250.00

9.40

970,550.00

396,750.00

22.40

8,887,200.00

Section Total:

20.60.50.1
20.60.50.2
20.60.50.3
20.60.50.4
20.60.50.5

20.60.50: Preparation of Plant Pits


Planting in Boulders/Rip Rap (Class 1 to 3)
Planting in Boulders/Rip Rap (Class 4 & above)
Tree Pits-Digging in Rock/Removal of Debris
Tree Pits-Digging in Compacted Fill/Removal of
Debris
Tree Pits-Backfill with Suitable Material/Marking Pit

Section Total:

9/1/03 4:30:26 PM

1,821,665.60
10,045,925.00

9,857,750.00

EA
EA

25.00
48.00

471.00
471.00

11,775.00
22,608.00

EA
EA

75.00
75.00

471.00
471.00

35,325.00
35,325.00

EA

30.00

471.00

14,130.00

119,163.00

Page No 11 of 14

Item

Description

Unit

Quantity

Rate

Sub Total:

30.50.1
30.50.2

Overhead Structures
Gantry Overhead Support Structures
Cantilever Overhead Support Structures

LS
LS

6.00
6.00

35,330.00
29,440.00

Section Total:

40.10

Tolling
Electronic Tolling Cost

LS

Tunnels & Underpasses


Underground Tunnel & Portals

211,980.00
176,640.00
388,620.00

1.00

13,500,000.00

Section Total:

60.10.1

Amount
68,204,387.80

13,500,000.00
13,500,000.00

405.00

42,180.00

Section Total:

17,082,900.00
17,082,900.00

Overhead Costs
Assigned Subcontract Indirect Costs

91.10.00.1
91.10.00.2
91.10.00.3
91.20.00.1
91.20.00.2
91.30.00.1
91.30.00.2
91.30.00.3
91.30.00.4
91.30.00.5
91.30.00.6
91.40.00.1
91.50.00.1
91.60.00.1

Assigned Scope Overhead Earthworks


Salaries & Benefits
Employee Vehicles (7ea)
Employee Expenses & Meals
Tool & Supply Allowances
Travel & Subsistence
Buildings & Storage
Office Expenses
Telephone Expense
Services & Utilities
Hoisting & Handling
Service Equipment
Survey Layout
Traffic Control
Insurance

MO
V-MO
MO
MO
MO
MO
MO
MO
MO
MO
MO
month
sum
LS

36.00
252.00
36.00
30.00
36.00
36.00
36.00
36.00
36.00
30.00
30.00
30.00
1.00
1.00

50,610.00
830.00
2,330.00
1,060.00
2,710.00
4,470.00
1,520.00
1,360.00
1,280.00
13,580.00
23,720.00
8,210.00
317,940.00
264,950.00

Section Total:

91.10.00.1
91.10.00.2
91.10.00.3
91.20.00.1
91.20.00.2
91.30.00.1
91.30.00.2
91.30.00.3
91.30.00.4
91.30.00.5
91.30.00.6
91.40.00.1
91.50.00.1
91.60.00.1

Assigned Scope Overhead Structures


Salaries & Benefits
Employee Vehicles (7ea)
Employee Expenses & Meals
Tool & Supply Allowances
Travel & Subsistence
Buildings & Storage
Office Expenses
Telephone Expense
Services & Utilities
Hoisting & Handling
Service Equipment
Survey Layout
Traffic Control
Insurance

9/1/03 4:30:26 PM

1,821,960.00
209,160.00
83,880.00
31,800.00
97,560.00
160,920.00
54,720.00
48,960.00
46,080.00
407,400.00
711,600.00
246,300.00
317,940.00
264,950.00
4,503,230.00

MO
V-MO
MO
MO
MO
MO
MO
MO
MO
MO
MO
month
sum
LS

36.00
252.00
36.00
30.00
36.00
36.00
36.00
36.00
36.00
30.00
30.00
30.00
1.00
1.00

50,610.00
830.00
2,330.00
1,060.00
2,710.00
4,470.00
1,520.00
1,360.00
1,280.00
13,580.00
23,720.00
8,210.00
317,940.00
264,950.00

1,821,960.00
209,160.00
83,880.00
31,800.00
97,560.00
160,920.00
54,720.00
48,960.00
46,080.00
407,400.00
711,600.00
246,300.00
317,940.00
264,950.00

Page No 12 of 14

Item

Description

Unit

Quantity

Rate

Section Total:

91.10.00.1
91.10.00.2
91.10.00.3
91.20.00.1
91.20.00.2
91.30.00.1
91.30.00.2
91.30.00.3
91.30.00.4
91.30.00.5
91.30.00.6
91.40.00.1
91.50.00.1
91.60.00.1

Assigned Scope Overhead Paving


Salaries & Benefits
Employee Vehicles (7ea)
Employee Expenses & Meals
Tool & Supply Allowances
Travel & Subsistence
Buildings & Storage
Office Expenses
Telephone Expense
Services & Utilities
Hoisting & Handling
Service Equipment
Survey Layout
Traffic Control
Insurance

MO
V-MO
MO
MO
MO
MO
MO
MO
MO
MO
MO
month
sum
LS

36.00
252.00
36.00
30.00
36.00
36.00
36.00
36.00
36.00
30.00
30.00
30.00
1.00
1.00

50,610.00
830.00
2,330.00
1,060.00
2,710.00
4,470.00
1,520.00
1,360.00
1,280.00
13,580.00
23,720.00
8,210.00
317,940.00
264,950.00

Amount
4,503,230.00

1,821,960.00
209,160.00
83,880.00
31,800.00
97,560.00
160,920.00
54,720.00
48,960.00
46,080.00
407,400.00
711,600.00
246,300.00
317,940.00
264,950.00

Section Total:

4,503,230.00

Sub Total:

13,509,690.00

Consortium Indirect Cost

94.10.00.1
94.10.00.2
94.10.00.3

CJV Management & Supervision


Salaries
Employee Vehicles (32 ea)
Employee Expenses

MO
V-MO
MO

36.00
891.00
36.00

221,300.00
830.00
7,500.00

Section Total:

94.20.00.1
94.20.00.2

CJV Quality Control


Lab Testing Services
Quality Control Services

8,976,330.00

LS
LS

1.00
1.00

744,210.00
966,530.00

Section Total:

94.30.00.1

CJV Survey
Survey Control

CJV Expenses
Buildings
Office Expenses
Telephone Expense
Services & Utilities
Project Signs
Tool & Supply Allowances
Safety Expenses
Travel & Subsistence
Monitoring Services
Environmental Controls
Archeological Controls
Pay Duty Police for Traffic Control
Armed Security along Right of Way

9/1/03 4:30:26 PM

744,210.00
966,530.00
1,710,740.00

month

32.00

7,790.00

Section Total:

94.40.10.1
94.40.10.2
94.40.10.3
94.40.10.4
94.40.10.5
94.40.20.1
94.40.20.2
94.40.20.3
94.40.30.1
94.40.30.2
94.40.30.3
94.40.40.1
94.40.40.2

7,966,800.00
739,530.00
270,000.00

249,280.00
249,280.00

MO
MO
MO
MO
MO
MO
MO
MO
MO
MO
MO
month
months

36.00
36.00
36.00
36.00
36.00
36.00
1.00
36.00
1.00
36.00
1.00
6.00
36.00

7,330.00
23,110.00
8,690.00
10,800.00
540.00
32.70
4,710.00
16,750.00
254,350.00
2,940.00
211,960.00
19,430.00
10,010.00

263,880.00
831,960.00
312,840.00
388,800.00
19,440.00
1,177.20
4,710.00
603,000.00
254,350.00
105,840.00
211,960.00
116,580.00
360,360.00

Page No 13 of 14

Item
94.40.50.1
94.40.60.1
94.40.70.1
94.40.80.1
94.40.80.2
94.40.80.3
94.40.80.4
94.40.80.5

80.10.1

Description

Unit
LS
Yr
LS
LS
LS
LS
LS
LS

Public Relations
Municipal Taxes
Consulting Fees
Insurance
Bonding & Permits
Proposal Cost
Success Fee
Management Fee

Rate
34,030.00
5,300.00
180,170.00
11,775,520.00
11,543,540.00
3,569,160.00
3,212,360.00
4,640,730.00

Amount
34,030.00
15,900.00
180,170.00
11,775,520.00
11,543,540.00
3,569,160.00
3,212,360.00
4,640,730.00

Section Total:

38,446,307.20

Sub Total:

49,382,657.20

Sub Total:

62,892,347.20

Design
Design Cost

9/1/03 4:30:26 PM

Quantity
1.00
3.00
1.00
1.00
1.00
1.00
1.00
1.00

LS

1.00

17,898,790.00

17,898,790.00

Section Total:

17,898,790.00

Grand Total:

371,309,013.10

Page No 14 of 14

Você também pode gostar