SQUARE ENGINEERING CONSTRUCTION L.L.

C
P.O. BOX: 47567, ABU DHABI, U.A.E. Tel. No. 02 681 9881, Fax: 02 681 9882 e-Mail: info@squareenc.com

PROJECT HEALTH, SAFETY AND ENVIRONMENT


132/22 KV Grid Station at Al Falah, Abu Dhabi

RISK ASSESMENT FOR LOAD TEST OF HOLLOW CORE SLAB


HAZARDS SNO ACTIVITIES POTENTIAL RISKS WHO MIGHT BE AFFECTED INITIAL RISK ASSESMENT RATING P R(1-5) S R (1-5) R R(PxS) PREVENTIVE CONTROL MEASURES FINAL RISK ASSESMENT RATING P R(1-5) S R (1-5) R R(PxS)

Lifting Activity

Collapse of mobile crane, Falling of materials

Workers and workers nearby

20

1. Proper tool box talk to operatives and operators. 2. Equipment used must be with warning signboards in place. 3. Equipment must have a valid third party certificate as well as operators and slings. 4. Outrigger must be placed in good foundation. 5. Certified riggers and slingers must be with the crane while lifting.

Use of crane in lifting

1.Collapse of mobile crane 2. Falling of materials 3. Crushing of materials

Workers and workers nearby

16

1.Proper tool box talk to operatives and operators 2. Equipment used must be with warning signboards in place 3. Equipment must have a valid third party certificate as well as operators and slings 4. Outrigger must be placed in good foundation 5. Certified riggers and slingers must be with the crane while lifting

SQUARE ENGINEERING CONSTRUCTION L.L.C


P.O. BOX: 47567, ABU DHABI, U.A.E. Tel. No. 02 681 9881, Fax: 02 681 9882 e-Mail: info@squareenc.com

PROJECT HEALTH, SAFETY AND ENVIRONMENT


132/22 KV Grid Station at Al Falah, Abu Dhabi

RISK ASSESMENT FOR LOAD TEST OF HOLLOW CORE SLAB


HAZARDS SNO ACTIVITIES POTENTIAL RISKS WHO MIGHT BE AFFECTED INITIAL RISK ASSESMENT RATING P R(1-5) S R (1-5) R R(PxS) PREVENTIVE CONTROL MEASURES FINAL RISK ASSESMENT RATING P R(1-5) S R (1-5) R R(PxS)

SQUARE ENGINEERING CONSTRUCTION L.L.C


P.O. BOX: 47567, ABU DHABI, U.A.E. Tel. No. 02 681 9881, Fax: 02 681 9882 e-Mail: info@squareenc.com

PROJECT HEALTH, SAFETY AND ENVIRONMENT


132/22 KV Grid Station at Al Falah, Abu Dhabi

RISK ASSESMENT FOR LOAD TEST FOR HOLLOW CORE SLAB

Risk Matrix
The intersection of Probability and of Severity (multiplication of their levels) shall be considered as Risk Rating:
Probability (P) Level 1 Level 1 Level 2 Level 3 Level 4 Level 5 Very Low 1 Low 2 Low 3 Low 4 Medium 5 Level 2 Low 2 Low 4 Medium 6 Medium 8 High 10 Severity (S) Level 3 Low 3 Medium 6 Medium 9 High 12 High 15 Level 4 Low 4 Medium 8 High 12 Very High Very High 20 Level 5 Medium 5 High 10 High 15 Very High 20 Extremely High 25

Risk Rating
1 Very Low Risk: Non-financial activities should be performed to control these risks. Low (Tolerable) Risk: May not require immediate action. Close follow-up should be ensured to control these risks. Likely improvement activities may be implemented after they are evaluated and approved from a financial point of view. Medium Risk: These risks should be dealt as soon as possible. Probability and relevant mitigation measures should be reviewed and programs should be developed and implemented as may be required. High Risk: Probability and relevant mitigation measures should be reviewed and improvement activities should be immediately initiated. Very High Risk: No work should be allowed unless relevant mitigation measures are in place. Programs should be developed and implemented in order to decrease or eliminate the risk level. Extremely High (Intolerable) Risk: Activities should be immediately stopped and improvement programs should be initiated.

2--3--4 5--6--8--9

10--12--15 16--20 25