Escolar Documentos
Profissional Documentos
Cultura Documentos
ir Maurice Bottiau
SEFE 7 - General Report Deep Foundations
Recent evolutions
Piling Ground improvement: probably more (marine works, reclaimed land...) Retaining walls
Evolution in the market Technological issues Recent research and practice
3
PILING
Technological improvements :
Hydraulics and increase in installed power : longer, larger, bigger Electronics and monitoring Miniaturisation
Driven piles
Type of hammer Diesel Hydraulic drop hammers Selfmonitored hydraulic Ram weight KN <200 <150 <1500 Rated energy KJ 0.4600 <200 <200 Efficiency transfer Ratio (ETR) 31 %(steel) 25%(concrete) 55-85 % 55-85 %
Hydraulic hammers:
Better energy transfer Reduced noise Driving sequence less soil-dependent
Diesel hammers:
Sturdy construction No external power unit Cheaper 9
Driving formulae:
Dutch, Engineering News formulae should be discarded Delmag, Danish, Gates formulae should be used with caution and never without calibration Pile Driving Analysis More attention should be given to set-up phenomenon
10
Vibratory driving
Key issues
Vibrodriveability Bearing capacity
After Holeyman (2002)
11
Vibratory driving
Vibro-driveability:
which vibro-hammer could drive the pile to the required depth? Premature refusal can often be encountered.
Bearing capacity:
Rausche(2002): usually still required to re-drive the pile with an impact hammer for acceptance. Viking (2002): too few case studies provide enough detailed information to increase the knowledge in this field. Borel & Guillaume (2002): no example could be found of accepted vibratory driven piles without field load tests.
12
Vibratory driving
13
Resonant vibro-driving
Resonant vibro-driving
HP 360-36 m Tight 4 piles cluster First trial with impact drop hammer and diesel densification, settlements, EOD > 25 blows/300 mm Driving time > 60 minutes 140 kW resonant vibrohammer was used: 12 minutes driving time, no settlements, vibration monitoring showed velocities < 3 mm/sec. Impact re-tap and PDA showed comparable results with impactdriven
Jacked piles
Key issues
Vibration-free installation Equipment capacity Relaxation
16
Jacked piles
Filip (2006): 4 Hoesch Larssen 43 sheet piles, clutched to a 750 mm square box. Pressed-in in sequence 12 m depth for the abutments 16 m depth for the piers.
17
Jacked piles
Lehane (2005): Relaxation Ru,static < Rinstallation
18
20
Sandouville
Sandouville
Enlarged base
Bored Piles
Strain incompatibility between side shear development (required movement 0.5 to 1% of pile diameter) and base resistance mobilisation (10 to 15 % of pile diameter-sometimes even more). Soil stress relaxation due to the process, especially in cohesionless soils. Correct cleaning and curing of the pile base
Post-grouting
24
25
CFA/ACIP piles
PCS piles diam 900 en 1200 mm in sands
Piling rig :
CFA piles
Monitoring is a relatively effective and reliable tool provided the presented records (e.g. Bustamante (2003): Come above all from rough data and give the adequate information (correct parameter) The sensor selected to measure each respective parameter has the capability to do it Is examined globally taking into account t he real soil conditions (and possible variations), the rig characteristics, the many possible incidents
30
Soil transport
Omega pile
Berkel pile
Fundamental issues of displacement auger piling Each system is characterized by : Its drilling process :
full displacement, some soil transport shape of the pile
The reproductibility of its installation process and the control during execution.
Reproductibility is a key issue Installation factor is globally 0.8, but differences exist between systems
A extensive and reliable soil investigation is much important The control during execution is therefore of major importance
CPT value
Help penetrate into dense sands and gravels Speed up the installation process Beneficial to final capacity
TOREN ERASMUSPAR K DEN HAAG september 2008 Omega piles founded in deep pleistocene sands 14 control CPT tests
50
PE-circuit BP
51
GROUND IMPROVEMENT
Deep Mixing
Key issues Reproductability Homogeneity of the mixed soil/cement column Strength scatter
Deep Mixing
Factors affecting strength (after Terashi, 2000)
I. Characteristics of hardening agent 1. Type of hardening agent 2. Quality 3. Mixing water and additives
II. Characteristics and conditions 1. Physical chemical and mineralogical properties of of soil soil 2. Organic content 3. pH of pore water 4. Water content III. Mixing conditions 1. Degree of mixing (Mixing energy) 2. Timing of mixing/remixing 3. Quantity of hardening agent IV. Curing conditions 1. Temperature 2. Curing time 3. Humidity 4. Wetting and drying/freezing and thawing, etc.
Deep Mixing
Lime-cement (Limix)
MIP (Bauer)
Deep Mixing
Deep Mixing
Depth (m)
8 10 12 14 16 18 20
Matthieu et al (2006)
Denies et al (2012)
Rigid inclusions
Typical applications
Rail/road embankments Tanks
Typical applications
Large industrial halls Logistical platforms
Rigid inclusions
Inclusions: piles, Compaction Grouting Omega, Controled Modulus Columns, Jet Grouting, Importance of the transfer layer: material : , characteristics, cohesion layers with internal cohesion (cement, limecement) Geotextile, geogrids Deformation highly dependent of the ratio Height/type of TL/distance between columns
No drainage function
Vibro-columns
B/2
Geotextile Embankment
1:
1.
PCC pile
Geotextile layer 25cm 25 cm thick gravel Geotextile layer 25cm 25 cm thick gravel
b/2 b/2
Ground surface
40 10
76 100
Pile Caps
Element which transfers the load from the transfer layer to the piles Increases the contact surface between the piles and the embankment Free, fixed to the pile, part of the pile itself
Horizontal loading
Transfer layer
Transfer layer
Specific points of attention:
Interaction between geogrid and fill material (granulometry) Limit of the treated area: return of grid on fill layer Placement and superposition of geogrids
RETAINING WALLS
40%
30%
20%
19%
10%
10%
8% 1%
8%
5%
0%
Soilmix
CUR Handboek diepwanden T114/ C174 Follows a serie of major problems during large infrastructure jobs in Europe Focused on controls during execution and interaction between design and execution Based on risk categorization
Bentonite
Attention to reaction with surrounding soil/cement treatment Low sand content (1%) before concreting: substitution should be preferred to cleaning
Excavation
Downward speed should be limited (0,5 1,0 m/s) in order to avoid cake destruction Upwards speed is even more critical, because bentonite slurry can only move along the grab. Tolerances of 0.5% are possible depending on soil conditions
Joints
Frame should be as vertical and in good shape as possible Guidance systems on frame are preferable Horizontal removal of joints is largely preferable Joints should be cleaned before concreting
Reinforcement/concrete
Relation with design: attention to excessive reinforcement. Attention to concrete and bentonite workability Distance between cages and joints Transversal reinforcement
Transversal reinforcement
Concreting
After each concrete delivery the level of the concrete inside the trench is controlled
Concrete
Much important is the continuity of the concreting process Content of binding agent to respect EN 1538. Up to 400-500 kg/m.
Conclusions
Technological advances have been enormous, in terms of systems or installed power, Need to improve the understanding of the installation effects of deep foundations techniques on the surrounding soil, and to convert them in installation factors. Need to anticipate and to use quality control systems properly: What do we do with the information? Do we reward the QA/QC? Know exactly what is behind safety factors