GOVERNMENT OF JHARKHAND Drinking water & Sanitation Division ----------------------------Estimate for consultancy services Planning, Surveying, DATA collection,

Cost Estimation, Formulation / Preparation of PFR, Draft DPR & Final DPR of ................................. Rural Water Supply Scheme with/ without weir including / excluding PMC under Drinking Water& Sanitation Division ......................... during 2012-13.

Report
Preamble : This estimate has been framed by Executive Engineer, D.W. & S. Division ------------------ for consultancy services Planning, Surveying, DATA collection, Cost Estimation, Formulation / Preparation of PFR, Draft DPR & Final DPR of ................................. Rural Water Supply Scheme with/ without weir including / excluding PMC during 2012-13 as per direction of ----------------------------------. As per policy of the Government along with NRDWP guide lines the entire rural population has to be covered with sustainable piped water supply. In view of large volume of work for preparation of DPR within limited time frame will be possible only through obtaining consultancy services because of limited technical man power available. Accordingly this estimate has been framed. Necessary provision for Planning with community participation, surveying, Data collection, Cost estimation, Formulation/ Preparation of PFR, its approval, Preparation of Draft DPR & its approval and preparation of final DPR & its approval, preparation of Bid Document, Assistance in Bid Evaluation with Project Management Consultancy has been made in this estimate. Total estimated cost comes to Rs. .. including 1% contingency. Standard Specifications of CPHEEO and NRDWP guide lines shall be followed during the preparation of DPR and Project Management Consultancy.

Executive Engineer D. W & S. Division

Details of proposed scheme


Sl. No. Block Panchayat Village Thana No. Habitation Total Population SC ST Minority OBC Total House hold

10

11

12

Total approx. area to be surveyed (Populated area) : . Km2 Total approx. length of rising & distribution main : . Km Time of Completion of PFR, DPR, Weir(with or without) & PMC Work :

General abstract of cost Sl. No. Name of Activities 1 2 1 Cost for preparation of PFR, DPR 2 Cost for preparation of DPR of Weir 3 Cost of PMC for period .. Total Amount 4

Executive Engineer D. W & S. Division

Detailed Estimate
Cost estimation of item wise activity in breakup mode in respect of breakup of payment of consultancy fee for preparation & submission of PFR / DPR / Weir. PFR & DPR :
Sl. No. 1 1 2 3 Name of Activities 2 Cost for Field Surveying & Investigation Data collection & Observation report with various authorities & departments. Cost for Meeting & Discussion with local officers at all stages. Cost for orientation of PRO, VWSC, JALSAHIA and Meeting in all villages and Habitations with required IEC activity and obtaining proceeding of PRI / VWSC. Cost of collecting Present water supply status with details of source, per capita availability & its quality report. Cost for Meeting with villagers for Identification of sustainable source, Land required for the proposed scheme, its details & obtaining proposal/ declaration for acquiring of Land. Cost towards survey of Electricity or alternative option and obtaining estimate from electricity board if required for separate feeder line with voltage variation etc. complete job. Cost for preparation of Location Flow-Chart / Schematic Diagram with RL from source to end etc. complete job. Cost for detailed survey of surface water source for Intake well, Gangway, alignment All Rising Main, WTP, ESR-GSR, Distribution Network, Selection of economical Pipes with justification & Appurtenances Cost of design and drawing of Motor-Pump set (economical, Type/Make/Capacity), Transformer, Sub Station (If required), Cables/ wire, and other electrical and mechanical equipment required. Cost for obtaining & submission Certificate for Sustainability of Source in regard to 95% dependability & reliability. Cost of Submission of PFR in 5 sets Cost of preparation of G.A. Drawing Indicating location of all components with RL Civil + Electrical Mechanical items. Cost of Design & Drawing of Intake well -Gangway with Scour depth Cost of Design & Drawing of WTP

Rate 3

Amount 4

10 11 12 13 14

15 16 17 18 19

20 21 22

Cost of Design & Drawing of All Rising Main Cost of Design & Drawing of ESR-GSR Cost of Geo-Technical Investigation/ Soil bearing capacity testing & report related to Components Cost of Design & Drawing of Distribution network Cost for NOC / Consent certificate for Land, Electricity, Crossing road, Railway, Canal (as the case may be) & Utility sifting as well as alignment of laying of pipe lines. Cost for Submission of Draft DPR with O&M cost and approval thereof including community approval. Cost of Submission of Final DPR in 10 sets. Cost of Preparation of NIT, BOQ, Tender Document & Tender evaluation.

Weir :
Sl. No. 1 1 Name of Activities 2 Cost of Selection of appropriate site in consultation with community. Cost for Hydrological Investigation Collection & preparation of Details of Catchment area, Collection of Rain fall Data , HFL & River flow details Data in rainy season and also assessment of sub surface flow if any. Cost of Geo-Physical investigation Bore-Hole Chart (Strata of Sub-soil) Cost of preparation of River physical details Crosssection, L-section of U/S & D/S as per requirement Cost of Design , Drawing and estimate preparation Submission of Final DPR in 5 sets Total Rate 3 Amount 4

3 4 5 6

PMC Work :
Sl. No. 1 1 Name of Activities 2 Cost of checking of working design, drawing, layout, and get it approved Cost of proper supervision of construction activity including ensuring quality of the work as per specification of agreement and approved drawing including suggestion for alteration or modification in the drawing as per actual site condition if required. Cost of monitoring the time and cost overrun and reporting to department officials. Cost of proper supervision during commissioning and trial run including monitoring of water quality for a Rate 3 Amount 4

3 4

6 7

period of six month and also during handing over of the project to the VWSC. Cost of checking of completion plan of the project and get it approved Preparation of manual for proper operation & maintenance of the project with required reporting and accounting formats including capacity building of the VWSC/PRI members/ nominated person. Cost of performance evaluation of the scheme. TOTAL

Enclosed: i) ii) iii) iv) Analysis of rates of all the activity and its justification approved by SE. EOI Detailed list of R.W.S. S. Schedule of payment & Time framed. Executive Engineer D. W & S. Division