HYDROMATRIX An innovative way to hydropower generation


Conventional HYDROMATRIX

An array (Matrix) of small turbines instead of conventional sized turbines Best suited for low head sites with existing dam and weir structures Most economical in larger numbers -> not a typical small hydro application

ANDRITZ HYDRO 2011

www.andritz.com

HYDROMATRIX Advantages
Use of existing weir structures No major civil construction > less cost Little excavation & no coffer dams > less geological risk No additional land usage -> environmentally friendly Existing river flow pattern can be maintained HYDROMATRIX Modules removeable at flood conditions Standardized modular concept Compressed project schedule High availability & easy maintenance

ANDRITZ HYDRO 2011

www.andritz.com

HYDROMATRIX Application Range

Head Head 2--20 20m m 2


HWL

Submergence Submergence > >1.5 1.5m m

TWL

PlantFlow Flow> >60 60m/s m/s Plant


Unit flow 5-12 m3/s Unit Output 100 kW up to 1500 kW

Sill level

ANDRITZ HYDRO 2011

www.andritz.com

HYDROMATRIX Projects Locations

Agonitz Lower St. Anthony Falls Colebrook

Nussdorf Freudenau Chievo Ashta I&II

Jebel Aulia

ANDRITZ HYDRO 2011

www.andritz.com

HYDROMATRIX Design Features


Unregulated propeller turbine (CuAlNiFe or CrNi 13.4) Directly driven synchronous (Permanent Magnet Technology) or asynchronous generator Welded hydraulic steel structure Mechanical face seal Roller type bearings, oil sump lubrication Light weight (9 13 t) -> truckable Minimum maintenance -> annual oil change Flexible concept - Modular switchgear

ANDRITZ HYDRO 2011

www.andritz.com

HYDROMATRIX Innovation: From HYDROMATRIX to StrafloMatrixTM


HYDROMATRIX StrafloMatrixTM

Turbine

Turbine

Generator

Generator

ANDRITZ HYDRO 2011

www.andritz.com

HYDROMATRIX Differences HYDROMATRIX vs StrafloMatrixTM


HYDROMATRIX
Simple Bulb Design Synchronous or Asynchronous Operation Perm. Magnets or Conventional Rotor Winding Longer, Heavier than StrafloMatrix PF Compensation (for asynchronous version only)

StrafloMatrix
Generator outside of flow (straight flow) Synchronous Operation Permanent Magnet Technology Shorter, Less Weight No PF Compensation required

ANDRITZ HYDRO 2011

www.andritz.com

HYDROMATRIX Operation Aspects


Maintenance intervals
TG-Units: Annual Oil Inspection / Change BOP Equipment: According to maintenance schedule UW - Cables: Change every 10-12 years

Accessibility
Easy access to all maintenance-relevant components without disturbance of overall plant operation

Expected life time


Identical to conventional hydropower concepts

ANDRITZ HYDRO 2011

www.andritz.com

HYDROMATRIX Potential Applications

Navigation Dams

Irrigation Dams

Intake Towers

Canals and Abandoned Shiplocks

10

ANDRITZ HYDRO 2011

www.andritz.com

HYDROMATRIX

Application: Irrigation Dams

HYDROMATRIX Experience Irrigation Dams JEBEL AULIA /Sudan


Client: National Electricity Corp. D = 1,120 mm n = 375 rpm H = 5.5 m Ptu = 380 kW 80 units in 40 modules Ptotal = 30.4 MW Existing barrage on the White Nile Contract award: 2000

12

ANDRITZ HYDRO 2011

www.andritz.com

HYDROMATRIX Experience Irrigation Dams JEBEL AULIA /Sudan

Status November 2003

13

ANDRITZ HYDRO 2011

www.andritz.com

StrafloMatrixTM Experience Agonitz / Austria


Client: Energie AG D = 1,120 mm n = 428.6 rpm H = 8.5 m Ptu = 700 kW 1 unit, further development of HYDROMATRIX Contract award: 2002 Commissioning: 2003

14

ANDRITZ HYDRO 2011

www.andritz.com

StrafloMatrixTM Experience Agonitz / Austria


Installation of the first permanent StrafloMatrix unit in March 2004

15

ANDRITZ HYDRO 2011

www.andritz.com

HYDROMATRIX Experience NUSSDORF / Austria


Client: AHP / EVN / Wienstrom D = 1,320 mm n = 336.7 rpm H = 5.86 m Ptu = 545 kW 12 single units Ptotal = 4.5 MW Contract award: 2004 Commissioning: 2005

16

ANDRITZ HYDRO 2011

www.andritz.com

HYDROMATRIX Experience NUSSDORF / Austria

Construction Phase

17

ANDRITZ HYDRO 2011

www.andritz.com

HYDROMATRIX Experience NUSSDORF / Austria

Client: AHP / EVN / Wienstrom

After commissioning in June 2005

18

ANDRITZ HYDRO 2011

www.andritz.com

CHIEVO DAM - Italy Project Location

19

ANDRITZ HYDRO 2011

www.andritz.com

CHIEVO DAM - Italy Design Challenges


Use minimum river discharge for hydropower generation at existing lock & dam Maintain flood discharge capability through lock Use existing lock structure without major modifications Preserve architectural appearance of historic environment Establish possibilities for fish migration

20

ANDRITZ HYDRO 2011

www.andritz.com

CHIEVO DAM - Italy Plant Layout

21

ANDRITZ HYDRO 2011

www.andritz.com

StrafloMatrixTM Experience CHIEVO DAM / Italy


Client: Consorzio Canale Ind. le G.Camuzzoni D = 1,320 mm n = 250 rpm H = 3.8 m Ptu = 270 kW 5 units in 1 module Ptotal = 1.35 MW Annual Energy: 12 GWh Project Start: 2007 Commissioning: 2009
During StrafloMatrix plant construction

Prior to StrafloMatrix plant construction

22

ANDRITZ HYDRO 2011

www.andritz.com

CHIEVO DAM Project Data


Client: Consorzio Canale Ind. le G.Camuzzoni Consultant: Studio Frosio H = 3.8 m Ptu = 270 kW 5 StrafloMatrix units in 1 module Ptotal = 1.35 MW Annual Energy: 12 GWh Project Start: 2007 Commissioning: 2009

23

ANDRITZ HYDRO 2011

www.andritz.com

StrafloMatrixTM Experience CHIEVO DAM / Italy

The Winner of Austrian State Award for Environmental and Energy Technology 2010

24

ANDRITZ HYDRO 2011

www.andritz.com

LOWER ST ANTHONY FALLS - USA Project Location

(3)

25

ANDRITZ HYDRO 2011

www.andritz.com

LOWER ST ANTHONY FALLS - USA Design Challenges


Use existing lock structure without major modifications (no excavation) Maintain flood discharge capability through lock Model test at TU VIE Fulfill grid interconnection requirements No adverse effects on barge and rec. boat traffic Preserve architectural appearance of existing lock

26

ANDRITZ HYDRO 2011

www.andritz.com

LOWER ST ANTHONY FALLS - USA StrafloMatrixTM Plant in Auxiliary Shiplock


Technical Data: 16 TG-units (2 rows of 8) H GR max = 7.6 m P Gen = 625 kW Max. Plant Capacity: 10 MW Annual Energy: 62 GWh Project Start: 2007 Commissioning: 2011

27

ANDRITZ HYDRO 2011

www.andritz.com

HYDROMATRIX Experience ASHTA 1 & 2 / Albania


Client: Energji Ashta

2 HYDROMATRIX plants 45 Modules (1 row) per plant 1 TG-Unit per Module Ptotal = 24 + 45 MW Annual Energy: 242 GWh Project Start: Dec. 2008 Commissioning: 2012

28

ANDRITZ HYDRO 2011

www.andritz.com

HYDROMATRIX Experience ASHTA 1 & 2 / Albania


Plant Layout
2 Plants, 45 TG-Units each 6 km newly constructed discharge canal between Ashta 1 & 2 Turn-key supply of E & M Equipment

29

ANDRITZ HYDRO 2011

www.andritz.com

HYDROMATRIX Experience ASHTA 1 & 2 / Albania

TECHNICAL DATA: Ashta 1


OUTPUT: 45 x 534 kW = 24.03 MW / 24.64 MVA HEAD: 4.98 m SPEED: 300.0 rpm RUNNER DIAMETER: 1,320 mm RATED VOLTAGE: 3,300 V

TECHNICAL DATA: Ashta 2


NUMBER OF TG-UNITS: 45 OUTPUT: 45 x 1,003 kW = 45.14 MW / 46.29 MVA HEAD: 7.53 m SPEED: 375.0 rpm RUNNER DIAMETER: 1,320 mm RATED VOLTAGE: 3,300 V

Sectional View Ashta 1

30

ANDRITZ HYDRO 2011

www.andritz.com

HYDROMATRIX ASHTA 1 & 2 / Albania

31

ANDRITZ HYDRO 2011

www.andritz.com

HYDROMATRIX Contact Worldwide

For more information about HYDROMATRIX please contact:


Alexander BIHLMAYER HYDROMATRIX Product Management ANDRITZ HYDRO GmbH A - 4031 Linz, Austria Lunzerstrasse 78 Phone: Fax: E-mail: Web: +43 (732) 6986 74261 +43 (732) 6980 2554 alexander.bihlmayer@andritz.com http://www.andritz.com

32

ANDRITZ HYDRO 2011

www.andritz.com

Você também pode gostar