Escolar Documentos
Profissional Documentos
Cultura Documentos
INTEGRATED OIL & GAS DEVELOPMENT PROJECT Purchase Order Number: Purchase Order Title: Suppliers Name: Suppliers Reference Number and Revision: Supplier (Prepared By) Supplier (Checked By) Supplier (Approved By) Issue Date: PU270-6-1100-1 Package Substations and LV Switchgears Eaton Electric BV Rev. C C21379Y.10A Edwin van Zon Roy Otten Edwin van Zon / Roy Otten 19-05-08
Document Description: OTONET III (automatic change over) Equipment / Tag Number(s): Low Voltage switchboards SB101E1 Project No. GBU P.O.No. 6110001 SDR Code C12 Sequential No. 10102 Sheet No. 001 Issue No. 04
Also Covers SDRL codes Purchaser review and comments shall not be assumed to indicate either responsibility or liability for accuracy and completeness of this document or to alter any contractual terms and conditions.
Code 1
Code 2 Code 3 Code 4
Date:
Final Do not resubmit unless modified. Revise and Resubmit Incorporate Comments, Up-Rev and Resubmit. Work May Proceed Review Not Required Do not resubmit Rejected Incorporate Comments, Up-Rev and resubmit. Work may NOT Proceed Sign:
GEN-EPA-000-E12-000009-001-A02(Appendix-3)
Page 1 of 1
OTONET III
DESCRIPTION OF THE
SB101E1 (C21379A)
Gbaran Ubie
Document Ref.:
C21379Y.10A
SB101E1-C21379Y.10A revC.doc
Page 1 of 6
OTONET III
Index General................................................................................................................................. 3 Apparatus for control and operation ..................................................................................... 3 2.1 Located on the front of ATS-Panel ................................................................................ 3 2.2 . Located near the Air Circuit Breaker ........................................................................... 3 2.3 . Indication near the Air Circuit Breaker......................................................................... 4 3 Description ATS.................................................................................................................... 4 3.1 Normal operation........................................................................................................... 4 3.2 Automatic operation ...................................................................................................... 4 3.2.1 Loss of transformer voltage of incomer L1 (or R1)................................................. 4 3.2.2 Restoration of transformer voltage of incomer L1 (or R1) ...................................... 4 3.2.3 Loss of both transformer voltages .......................................................................... 4 3.2.4 Restoration of transformer voltages ....................................................................... 4 3.3 Manual operation........................................................................................................... 5 3.3.1 Local....................................................................................................................... 5 3.3.2 Remote................................................................................................................... 5 4 Communication signals ........................................................................................................ 6 4.1 Generator ...................................................................................................................... 6 4.2 General.......................................................................................................................... 6 1 2
SB101E1-C21379Y.10A revC.doc
Page 2 of 6
OTONET III
1 General
In many process industries, factories, hospitals and other buildings where great emphasis is laid on energy supply continuity, Eaton-Holec's automatic mains change-over system guaranties an automatic change-over between transformer supply and emergency supply. The ATS system can be applied in both emergency supply systems and combined heat and power systems, or a combination of both. The number of transformers and generator sets applied varies depending on the application. Partly due to this, a modular design PLC was chosen. This type of PLC has a powerful programmable packet and a bread selection of I/O modules, so that for each change-over operation, an optimum solution can be found.
SB101E1-C21379Y.10A revC.doc
Page 3 of 6
OTONET III
3 Description ATS
3.1 Normal operation
In normal operation both transformer incomers will supply the switchgear in non-parallel operation and the generator is stand by. The status of the ACBs will be as follow incomer L1, R1 & buscoupler R/N are closed incomer generator N1 & buscoupler L/R are open.
SB101E1-C21379Y.10A revC.doc
Page 4 of 6
OTONET III
SB101E1-C21379Y.10A revC.doc
Page 5 of 6
OTONET III
4 Communication signals
(via potential-free contacts)
4.1 Generator
Start command to Generator START COMMAND: closed contact, indicates the SB101E1 requires generator supply. This contact will remain close until the generator ACB is opened, no cool down time is includes. Return to normal supply (start active synchronisation) command to Generator This contact closed after the transformer supply is restored and the ACB control switch of the buscoupler R/N is turned in the CLOSE position. In this situation the transformer ACB is closed Generator ACB permissive to close contact (from Generator control panel): PERMISSIVE: closed contact, indicates the generator is ready to take the switchboard load. (generator ACB permissive to close) Opening this contact if the generator ACB is closed, will not open the ACB. Generator ACB Healthy: (from Generator control panel): HEALTHY: closed contact, indicates the generator is ready (in auto-position, also if the generator is not running) Opening of the contact, will open the generator ACB (if closed) and block the ACB to close Generator parallel operation contact: (from Generator control panel): This function will allow parallel operation between generator and transformer R1. This contact will start sync check for closing of buscoupler R/N. 3 phase 400Vac voltage derived from the busbar of bussection R This voltage is required for active synchronisation
4.2 General
ATS healthy: This relay is energized when PLC is healthy (in run mode), and no fault occurs. The following condition will de-energize the relay: loss of aux supply failure of the PLC incorrect status of the CBs failure of closing or opening command of the CB operation of the protection relay of the CB The generator does not start or permissive contact not available within 1 minute The generator stops during operation The sync mode not occur within 3 minutes
SB101E1-C21379Y.10A revC.doc