Escolar Documentos
Profissional Documentos
Cultura Documentos
live cases
CHAPTER 5
LIVE CASES
Page 45
Chapter 5
live cases
In this chapter we will present few live cases of damaged concrete structures which require a serial of repair and strengthening procedures these structures includes residential building, hotels and bridges and it have different levels of damages varies between major and minor damages.
Page 46
Chapter 5
5.1.3. Project scope
live cases
In this building damages are detected after the removal of the wooden forms the damage was presented as (figure2, 3, and 4)
5.1.3.1Causes of repair
Chapter 5
live cases
5.1.4.Repair procedures
5.1.4.1. Repair of column by using (concrete jacket)
1. The slab is lifted up by wooden sections to remove the load from column
Figure5- 7 First step lifting up the slab with wood to be able to remove concrete cover
Page 48
Chapter 5
live cases
2. Cover is removed and steel bars have been inserted into old slab by epoxy to welded the new additional RFT to it (fig5-7)
3. Creating voids in the slab to insert new RFT of the column into the slab to increase the bond between the columns and to make the process of purring concrete into shutter easier.
Page 49
Chapter 5
live cases
4. After cleaning the surface insert new additional RFT and additional stirrups that preferred to be box stirrup to increase the bond then make the new shutter of the column from one or more sides according to repair design then pure the new concrete into column jacket.
Chapter 5
live cases
Figure5- 12 slab of first floor before and after adding additional top RFT
Page 51
Chapter 5
live cases
2. Remove base concrete and prepare the connection between slabs and columns
3. Make sure of Cleaning RFT from old concrete and ducts of electric wires.
Page 52
Chapter 5
live cases
4. Build up the new shutter of the slab in the same level of floor then insert electric ducts
5. Pour concrete into shutter then remove wooden forms after harden of reinforced concrete.
Chapter 5
live cases
5.2.1. Structure
Grande Shores Ocean Resort, Myrtle Beach, South Carolina this is a 7-story resort hotel on the Atlantic beachfront. It is constructed using standard concrete skeleton method.
Chapter 5
5.2.4. Solution
live cases
Pre-preg column wraps allowed for fast installation, completing project with minimal disruption and prior to hotels busy season. With this method they were still able to function with only a small area of rooms closed off to public Original design was to install 200 lb steel plates that would have added significant weight, would not have been aesthetically pleasing and would have closed a large area of the hotel losing them revenue.
Chapter 5
5.3. Highway-Bridge, Support Column Repair
live cases
Concrete bridge columns are an integral part of the integrity of highway bridges that may be damaged by various physical forces including earthquakes and vehicle accidents. Vertical effects on these bridge columns lead to significant variations in axial force demand which can result in fluctuations in moment demands at the face of the bent cap, amplification of moment demands at the girder mid-span, and changes to moment and shear capacity of the column. In this case, concrete columns were deemed to be fatigued due to deterioration of steel reinforcement.
5.3.3. Conclusion
Wrapping column with Fortec carbon fiber fabric allowed for minimal road closure as would have been needed with old method of teardown and replacement of column. The #4550 epoxy allowed contractor to cure out in field under difficult weather conditions. With highs in the 60's and lows dipping into the 40's a night curing was a challenge.
Page 56