Escolar Documentos
Profissional Documentos
Cultura Documentos
Complete Rating
Program Initiation 90
Program Planning 80
Functional 50
Requirement
Design and 40
Development
Implementation 40
Testing 30
Maintenance 20
Execution N/A
Program Program Planning Functional Design and Program Plan Testing Program
Initiation Requirements Development Implementation Maintenance
Management Buy Interim Temporary General General Risk Controls BC Plan Primary Site Change
In BC Plan Assessment Assessment Testing Monitoring
Program BC Program Detailed Risk Controls IT Recovery Test Recovery Site Change
Evaluation Management requirements Systems Evaluation Monitoring
Document related to
standards, rules,
and regulations
Program Program Structure Risk Management IT Systems Alternate IT BC Plan Contract Management
Commitment Recovery Recovery Site Approval
Strategy
Approval Process BIA Alternate IT A Tertiary BC Plan Risk Controls
Recovery Site Recovery Site Document
Has the program been Initiated 7 Program was initiated by the IT BC Program needs to be raised to top level and
formally department not just owned by IT
What is the extent of management's 8 CIO and other C-level officers are aware
awareness of the program but other than CIO they
don't consider it a top priority.
Is there a Project Sponsor 6 CIO is the project sponsor
What is the seniority and position of 7 CIO is the project sponsor
Project Sponsor
Plan exist to raise awareness of 4 Several presentations were presented Find out if there is a Utilize Steering Committee to raise top level
management to management. Some were made on steering committee. awareness.
their own requests. They were a high Steering committee will
level presentations. There is no formal help in raising top level
plan to raise awareness. awareness.
Business case prepared and 4 Yes. An informal business case was Was a budget prepared
evaluated prepared. (Yes. We presented our
initial budget and
provided an estimate of
yearly budget to CIO)
Clear Go/No Go decision made and at 8 Yes. CIO made the Go/No Go Board needs to have an active involvement in
what level of the management decision and presented the overall high level evaluation process.
this decision to senior
management. But the
board was not involved in
this process.
Full-time qualified program manager 2 No. We have a part-time (70%) Find out if the coordinator Assign full-time BC responsibility to BC
assigned business continuity coordinator has business continuity coordinator
assigned to this task. He is from the or DRP experience (No.)
corporate planning department and has
been involved with Emergency
Response Planning in the past.
Steering committee established 6 A committee structure has been This is a definitely a strength.
proposed and awaiting approval.
(company has the history of establishing
SC for high profile critical projects)
Steering committee members have 3 No. Define clear roles and responsibilities for
clear roles and responsibilities defined Steering Committee.
BC culture is well established 5 No. But, IT and Business units have a Develop a plan to improve corporate wide BC
better BC/DR culture compare to the culture.
rest of the company.
PP: Program Planning
Questions Ratin Response and Conclusion
g
Establishment of a
SC must become a
high priority. It will
help to resolve a
number of current
obstacles and issues
Assess team structure. Three
types of teams: Emergency
management, Emergency
response, and Business unit
teams.
Define responsibilities
for team members
Assign alternates to
team members
Find out what those part-time
staff are responsible for and
how critical those
responsibilities are. This is a
high risk factor.
FR: Functional Requirements
FR.1: General
Assessment
Functional requirements have Partially. Complete: FR.2
been assessed
Functional requirements have Not in a formal way.
been documented
Functional requirements have We will be presenting
been reviewed by senior general requirements to
management Steering Committee in the
near future.
Functional requirements have Not yet.
been approved
Requirements for alternate 8 Our canadian site may be They have work area
work area are analyzed and sufficient as a work area requirements in terms of
documented (space, until we get the more number of workstations
personnel, equipment, permanent work site with needed.
facilities, etc.) SunGard
Requirements are aligned with 8 Work station requirements
BIA findings in terms of critical are aligned with critical
business units and applications.
applications
Space requirements are 1 No Work out the detailed work area
known space requirements
Support personnel are known Yes. We know the key
staff from the business
areas needed in the
recovery.
Workstation requirements are 9 Yes
known
Network connectivity 9 Yes
requirements are known
Non-IT resource requirements 1 No. We will rely on Work out the Non-IT work area
are known (faxes, copiers, whatever is available at requirements for long term
etc.) the Canadian site recovery strategy.
FR.14: BC Tools 5
BC tools and software 5 Yes. We need a tool that Assess document/record
requirements are known is web based and allows management system tool
business unit plans and requirements.
integration of IT and ERP.
Easy to maintain and
learn. Security is also
important.
Recommend testing
compatability issues.
Recommend testing
compatability issues.
PI.11: Voice 8
Communication
VC infrastructure and Yes.
services are complete
Percentage completed 8 80
PI.13: BC Tools 2
BC tool is purchased 2 No. we are still Expedite tool
evaluating tools evaluation to
begin tool usage
and deployment
PI.15: Personnel 4
Are all required personnel 5 Most have been
hired hired but we are still
waiting to hire two
more staff reporting
to the Coordinator.
Responsibilities assigned to 5 Mostly assigned
personnel.
BC team insurance 0 No.
purchased
Percentage Complete 4 60
Assembly location
information
Crisis management center or
EOC information
Plan execution timeline and
schedule
Disaster scenarios and
recovery procedures
BC Plan change controls
BC plan distribution list
BC plan appendices
PT: Plan Testing
Questions Rating Response and Conclusion Further
Actions
Types of testing planned for future 7 Hot site testing of all systems
BC Plan is approved
BC Plan is approved by program
sponsor and BC steering
committee
BC plan is distributed to all staff
and personnel on distribution list
Recommend testing of
notification procedures;
EOC, and work areas.
PM.10: Management 5
Process
Steering committee is actively 4 Steering Committee
involved in the maintenance will be establish in
phase few months.
Program sponsor is actively 8 Yes.
involved in the maintenace
phase
BC Management meetings 8 Weekly with the
are held on weekly, monthly, sponsor and monthly
and quarterly periods with business unit
managers