Escolar Documentos
Profissional Documentos
Cultura Documentos
Gurjendra S. Bedi, P. E. Division of Component Integrity Office of Nuclear Reactor Regulation July 14-15, 2008
1
Introduction
Pump, valve, and snubber inservice testing (IST) issues have occurred since Ninth NRC/ASME Symposium on Pump and Valve Testing, July 2006: Smooth-running pump vibration issues Safety relief valve (SRV) testing frequency issues Check valve sample disassembly and inspection on-line Use of 10 CFR 50.59 processes to change the NRC authorized relief requests related to inservice inspection and testing
2
11
Use of 10 CFR 50.59 Process to Change the NRC Authorized IST Relief Request (RR)
Background In accordance with 10 CFR 50.55a, the NRC has approved alternatives and granted numerous reliefs from the ASME Code requirements related to inservice examination and testing of various components including pumps, valves & snubbers. The use of an alternative as authorized by the NRC becomes a regulatory requirement. NRC has learned that at least one licensee used the 10 CFR 50.59 process to revise an NRC approved alternative related to snubber inservice examination and testing.
14
Use of 10 CFR 50.59 Process to Change the NRC Authorized IST RR (continued)
Regulations 10 CFR 50.59 requires licensees To evaluate proposed changes to their facilities for their effects on the licensing basis of the plant, as described in the Final Safety Analysis Report (as updated), and To obtain prior NRC approval for changes that meet specified criteria (10 CFR 50.59) as having a potential impact upon the basis for issuance of the operating license. NEI-96-07, Revision 1, Guidelines for 10 CFR 50.59 Implementation, requires that the licensees activities controlled by regulation 10 CFR 50.55a, take precedence over 10 CFR 50.59. NEI-96-07 is endorsed by Regulatory Guide 1.187, Guidance for Implementation of 10 CFR 50.59, Changes, Tests, and Experiments.
15
Use of 10 CFR 50.59 Process to Change the NRC Authorized IST RR (continued)
Discussion The licensees are encouraged to be cautious when revising or changing programs or procedures referenced in an approved relief request. Any change or updates that supersedes or overwrites an alternative authorized in a relief request must be approved by the NRC.
16
Use of 10 CFR 50.59 Process to Change the NRC Authorized IST RR (continued)
Discussion (cont.) 10 CFR 50.59 process can not be used to revise an alternative as authorized by the NRC. Licensees are requested to resubmit their relief request with revised alternative to NRC for review. 10 CFR 50.59 process can not be used to revise portions of licensee controlled documents such as Technical Requirement Manual (TRM) for snubbers examination and testing, which were authorized by NRC as an alternative in lieu of the Code requirements.
17
Conclusions
The purpose of this paper is to make licensees aware of a number of pump, valve and snubber issues that staff has encountered since the Ninth NRC/ASME Symposium on Pump and Valve Testing in July 2006. Licensees who believe that some of the items discussed are applicable to their facilities may wish to review their current IST program and modify their program as appropriate.
18