Você está na página 1de 15

UNOPS

UNITED NATIONS OFFICE FOR PROJECT SERVICES

BILL OF QUANTITIES

ANDMA Building in Heart Herat, Afghanistan

2-Story Administration Building and a Guardhouse

NOTICE TO ALL BIDDERS - COMPLETE PROJECT PRICE: 1. All bidders MUST examine the complete project documents. These documents include the Drawings, BOQ, Schedules and Specifications. Any discrepancies between these documents are to be brought to the immediate attention of UNOPS Engineer. 2. Quotation given by the contractor on this BOQ are to cover any and all additional materials, labor or associated costs to complete the works as documented on the complete project documents. 3. Eventual claims for extra works are covered by project general documentation of contract.

Currency: Project No: Project Title: Location: Tender No: Tender Title: Original Issue:

US Dollars 1017 ANDMA Building in Heart Herat, Afghanistan 01 2-Story Administration Building and a Guardhouse November 07, 2010

UNOPS
Vertical Structures Unit

DETAILS OF COMPONENT
Currency: Project No: Project Title: Location: US Dollars 1017 ANDMA Building in Heart Herat, Afghanistan

Tender No: 01 Component: 2-Story Administration Building and a Guardhouse Original Issue: November 07, 2010

Pos. 1. General

Description of Work/Items

Project Schedules Ref.


1.1 Occupied Areas, 1.1 Existing Services Schedule and 1.1 Items to be supplied schedules

Unit

Quantity

Unit Cost

Total Cost

1.1 Preliminaries

1 2

Pre-construction work, mobilisation activities including paper/ documentation tasks. Post construction works and clean up. 1.2 Inspection notification schedule and 1.2 Warranty schedules

LS LS

1.00 1.00

1.2 General Requirements


1
Testing and Operation/Maintenance Manuals.

LS

1.00

Subtotal General

2. Site

2.0 Deal with Graves


1
Deal with human remains found in unmarked graves on the site. Excavate, remove remains, place in a suitable container, and re-bury remains in a place to be agreed by local authorities. All work to be carried out in a manner that does not offend religious and cultural rules and norms.

2.1 Identified hazardous materials and 2.3 Earthwork schedules

No. 2.1 Identified hazardous materials and 2.3 Earthwork schedules

5.00

2.3 Earthwork
1
Excavation (any soil type) for main building foundation and surrounding yard for grading purposes. This item includes disposal and temporary support or shoring if needed. See drawing and schedule for details. Excavation (any soil type) for guard room foundation. This item includes disposal and temporary support or shoring if needed. See drawing and schedule for details. Excavation (any soil type) for septic tank. This item includes disposal and temporary support or shoring if needed. See drawing and schedule for details. Ground improvement under foundations of main building. This includes supplying of filling materials and compacting the layers according to schedule and drawings. Soil backfilling on and around foundation of the main building up to ground level. This includes supplying of needed materials. See drawings and schedules for levels/dimensions and details.

CU.M

1,300.00

CU.M

25.00

CU.M

110.00

CU.M

15.00

CU.M 2/15

20.00

Currency: Project No: Project Title: Location:

US Dollars 1017 ANDMA Building in Heart Herat, Afghanistan

Tender No: 01 Component: 2-Story Administration Building and a Guardhouse Original Issue: November 07, 2010

Pos. 6

Description of Work/Items
Soil backfilling on and around foundation septic tank up to ground level. This includes supplying of needed materials. See drawings and schedules for levels/dimensions and details. Soil backfilling on and around foundation of guard room up to ground level. This includes supplying of needed materials. See drawings and schedules for levels/dimensions and details. Gravel compaction, Class 2, at any places shown for main building foundations, floors and its sidewalk/ramp. The cost includes leveling and compaction of ground surface, and supplying of needed materials and its compaction. See drawing and project schedules for dimensions and details. Gravel compaction, Class 2, for entire parking/walkway areas at the yard. The cost includes leveling and compaction of ground surface, and supplying of needed materials and its compaction. See drawing and project schedules for dimensions and details. Gravel compaction, Class 2, for septic tank. The cost includes leveling and compaction of ground surface, and supplying of needed materials and its compaction. See drawing and project schedules for dimensions and details. Gravel compaction, Class 2, for guard room. The cost includes leveling and compaction of ground surface, and supplying of needed materials and its compaction. See drawing and project schedules for dimensions and details.

Project Schedules Ref.

Unit

Quantity

Unit Cost

Total Cost

CU.M

45.00

CU.M

10.00

CU.M

43.00

CU.M

30.00

10

CU.M

15.00

11

CU.M

12.00

2.4 Service Trenching

2.1 Identified hazardous materials, 2.1 Salvaged Materials for Re-use and 2.3 Earthwork schedules

NOTE: Cost for trenching in this section includes all needed excavation, filling, compaction of different layers, warning tapes and any other thing shown on the drawing for the trenches.

1 2

All trenches for sewerage systems. All trenches for electrical systems.

Lin M Lin M

50.00 50.00

Subtotal Site

3. Structure

3.1 Concrete-General

3.1 Non reinforced concrete, 3.1 Reinforced concrete and 3.2 Concrete- Integral Finishes schedules

NOTE: Cost for concrete items in this section includes reinforcement, steel anchorage embedded in concrete, shuttering, concrete, concrete curing and all to the complete job. 3/15

Currency: Project No: Project Title: Location:

US Dollars 1017 ANDMA Building in Heart Herat, Afghanistan

Tender No: 01 Component: 2-Story Administration Building and a Guardhouse Original Issue: November 07, 2010

Pos. 1 2 3 4 5 6 7 8 9 10 11 12

Description of Work/Items
PCC lean concrete (10 Mpa) under the foundations and any other places shown as lean concrete for septic tank. RCC (20 Mpa) at the foundtions of 2-story main building. The quantity includes RCC at foundations and tie beams under the ground. RCC (20 Mpa) at the columns of first story of main building. RCC (20 Mpa) at the columns of second story of main building. RCC (20 Mpa) at the beams of first story of main building. RCC (20 Mpa) at the beams of second story of main building. RCC (20 Mpa) at the slabs of first story of main building. RCC (20 Mpa) at the slabs of second story of main building. RCC (20 Mpa) at the RCC stair case inside main building. RCC (20 Mpa) at the parapet of main building. RCC (20 Mpa) at the entire guard room. The quantity includes RCC at foundations, floors, columns, beams, ring beams, lintels, etc. RCC (20 Mpa) at entire septic tank and its manhole. The cost for RCCs here includes wall mounted fixed ladder inside the septic tank as well. PCC (20 Mpa) at the floors, roofs, side walks, ramps, window sills, kerbs, PCC pavements, flowerpots, septic tank, yard, and any other places shown as PCC in the drawings for main building, guard room and the septic tank.

Project Schedules Ref.

Unit

Quantity

Unit Cost

Total Cost

CU.M

2.00

CU.M CU.M CU.M CU.M CU.M CU.M CU.M CU.M CU.M

18.00 13.00 11.00 10.00 10.00 20.00 19.00 4.00 4.00

CU.M

6.00

CU.M

15.00

13

CU.M

63.00

3.5 Brickwork
1 2
Second Class Brick masonry with mortar for main building. This includes all brick walls/ brick masonry in the entire building. Second Class Brick masonry with mortar for guard room. This includes all brick walls/ brick masonry in the entire building. Stone masonry with mortar at the foundations and/or any places shown in the drawings for main building. See drawing and schedule for details. Stone masonry with mortar at the foundations and/or any places shown in the drawings for guard room. See drawing and schedule for details.

3.5 Brickwork construction schedule

CU.M

110.00

CU.M

18.00

3.6 Stonework
1

CU.M

50.00

CU.M 3.10 Concrete Unit Masonry

13.00

3.10 Concrete Unit Masonry


1
CMU masonry with mortar. This item covers CMU works on the roof and any other places shown on the drawings for main building. The cost includes all needed materials, steel bars, anchors etc and works.

CU.M

7.00

Subtotal Structure
4/15

Currency: Project No: Project Title: Location:

US Dollars 1017 ANDMA Building in Heart Herat, Afghanistan

Tender No: 01 Component: 2-Story Administration Building and a Guardhouse Original Issue: November 07, 2010

Pos. 4. Enclosure

Description of Work/Items

Project Schedules Ref.

Unit

Quantity

Unit Cost

Total Cost

4.1 Waterproofing
1
Single layer bitumen membrane (Isogam) at the floor and walls of toilets/kitchen and at the ground floors of main building and as well as guard room. This includes preparation of base layers shown on the drawings. Refer to schedule/drawing for details.

4.1 Waterproofing system schedule

SQ.M 4.2 Roofing materials, and 4.2 Gutter and Down pipe Schedules

255.00

4.2 Roofing
1
Flat roof for the main building. The cost for this item includes all roof layers shown such as rigid foam insulation layer, brick powder layer, PCC beneath Isogam layer, Isogam layer and the protective PCC layer on the Isogam. See drawings for details. The cost also includes Isogam and flashings needed for the parapet around the roof. GI corrugated roof for water tank enclosure on the roof of the building. The cost for this item includes all roof layers such as GI sheet, steel profiles for purlins, steel C-shape channels as the supporting members, mineral wool layer and the steel mesh supporting the mineral wool layer, and as well as all needed materials and accessories required for complete installation of a functioning roof. GI flat K-span roof for guard room. The cost for this item includes all roof layers such as GI sheet standing seam and mineral wool insulation layer and all needed materials, accessories, connections required for complete installation of a functioning roof. Down pipes, PVC pipe class-B. This includes all accessories such as over flow and stuffholder required for complete installation such as supplying, fixing and others as per drawing and schedules.

SQ.M

160.00

SQ.M

10.00

SQ.M

51.00

Lin M 4.3 Window, 4.3 Window Hardware, 4.5 Annealed Glasses, and 4.6 Glassblock work schedules

40.00

4.3 Windows and Window Hardware

NOTE: Prior to work, samples must be approved by UNOPS Engineer.

Wooden frame windows for main building. The work includes making, transportation, installation, hardware, glazing, glass-block work around window, insect screen, 3 coats of oil-based painting, and other accessories required for complete installation as per drawings and schedule.

SQ.M

102.00

5/15

Currency: Project No: Project Title: Location:

US Dollars 1017 ANDMA Building in Heart Herat, Afghanistan

Tender No: 01 Component: 2-Story Administration Building and a Guardhouse Original Issue: November 07, 2010

Pos. 2

Description of Work/Items
Wooden frame windows for guard room. The work includes making, transportation, installation, hardware, glazing, glass-block work around window, insect screen, 3 coats of oil-based painting, and other accessories required for complete installation as per drawings and schedule.

Project Schedules Ref.

Unit

Quantity

Unit Cost

Total Cost

SQ.M 4.4 Joinery doors 4.4 PVC doors, 4.4 Steel doors and 4.5 Annealed Glasses schedules

6.00

4.4 Doors and Door Hardware


NOTE: Prior to work, samples must be approved by UNOPS Engineer. NOTE: Cost for steel related items in this section includes supplying materials, accessories, connections, welding, any works, painting according to the schedules and specifications for steel member painting, which is at least on coat of anti-rust followed by 2 other coats of oil-based painting for all surfaces.

Wooden frame doors for main building. The work includes making, transportation, installation, hardware, glazing, and other accessories required for complete installation as per drawings and schedule. Wooden frame doors for guard room. The work includes making, transportation, installation, hardware, glazing, and other accessories required for complete installation as per drawings and schedule. Steel frame doors (for water tank enclosure on main building). The work includes making, transportation, installation, hardware, glazing, 1 coat of anti-rust followed by 2 other coats of oil-based painting, and other accessories required for complete installation as per drawings and schedule. Steel doors [the access way to the roof of main building] plus steel type fixed ladder at first floor hall. The work and the cost includes construction and complete installation of inner steel door to the ceiling of the first floor, and installation of outer steel plate pane at the roof, and as well as wall mounted steel ladder as shown. The cost also includes all hardware/accessories/works/materials needed to a complete and functioning job. The cost also includes one coat anti-rust followed by 2 other coats of oil-based painting to all nongalvanized steel surfaces as per given specs and full satisfaction of UNOPS engineer. 4.5 Mirrors schedules

SQ.M

58.00

SQ.M

9.00

SQ.M

0.80

LS

1.00

4.5 Glazing
1
Mirrors (40x60cm) at toilets of main building and the guard room. This includes complete installation.

No 4.6 Glass Block Schedule

7.00

4.6 Glass Blockwork

6/15

Currency: Project No: Project Title: Location:

US Dollars 1017 ANDMA Building in Heart Herat, Afghanistan

Tender No: 01 Component: 2-Story Administration Building and a Guardhouse Original Issue: November 07, 2010

Pos. 1

Description of Work/Items
Mortar jointed panels glass blockwork at window 'W6'. This includes reinforcement and all other accessories required for complete work. See drawing and schedule for details.

Project Schedules Ref.

Unit

Quantity

Unit Cost

Total Cost

SQ.M

12.00

Subtotal enclosure

5. Interior

5.4 Suspended Ceiling


1
Lasani wooden board, 6mm, fixed ceiling for soffits and ceilings of the water tank enclosure on main building. The cost includes fixings, accessories, materials, works, oil based painting etc for a complete job to the full satisfaction of Engineer. Aluminum frame with 60x60 gypsum board suspended ceiling for guard room. The cost includes fixings, accessories, materials, works, etc for a complete job to the full satisfaction of Engineer.

5.4 Suspended Ceiling Schedule

SQ M

10.00

SQ M 5.5 Joinery fixtures schedule

28.00

5.5 Joinery
1
Wooden frame, MDF finish, wall mounted cabinet at the kitchen for main building. See drawings for details. The cost includes making, installation, framing, hardware, finish, 3 coats oil-based painting and all to the complete job.

LS

1.00

Wooden frame, MDF finish, wall mounted cabinet at the kitchen for guard room. See drawings for details. The cost includes making, installation, framing, hardware, finish, 3 coats oil-based painting and all to the complete job. LS 1.00 Wooden frame, MDF finish, floor mounted cupboard at the kitchen for main building. See drawings for details. The cost includes making, installation, framing, finish, hardware, stone table top, splash back, 3 coats oil-based painting and all to the complete job. LS 1.00 Wooden frame, MDF finish, floor mounted cupboard at the kitchen for guard room. See drawings for details. The cost includes making, installation, framing, finish, hardware, stone table top, splash back, 3 coats oil-based painting and all to the complete job. LS 1.00 5.6 Metal Fixtures Schedule

5.6 Metalwork
1
Metallic plaster beads for outer corners at the corridors only, including edge of walls for main building and as well as for guard room. This includes any needed work for complete installation. See schedules and drawings for details.

Lin M

95.00

7/15

Currency: Project No: Project Title: Location:

US Dollars 1017 ANDMA Building in Heart Herat, Afghanistan

Tender No: 01 Component: 2-Story Administration Building and a Guardhouse Original Issue: November 07, 2010

Pos. 2

Description of Work/Items
Metal handrails, balustrades, infill and moldings to concrete stairs for main building. This includes any needed work for complete installation and also includes painting as per schedule and specification for metallic surface painting. See drawing for details. Metal guardrails at stair's landing for main building. This includes any needed work for complete installation and also includes painting as per schedule and specification for metallic surface painting. See drawing for details. Metal handrails, balustrades, infill and moldings to concrete for ramp. This includes any needed work for complete installation and also includes painting as per schedule and specification for metallic surface painting. See drawing for details. Toilet roll holders for main building and guard room. This also includes installation. Grab rail for handicap toilet. One complete set. This includes supplying and complete installation. Soap dishes for main building and guard room. This also includes installation.

Project Schedules Ref.

Unit

Quantity

Unit Cost

Total Cost

Lin M

8.00

Lin M

2.20

Lin M No

11.00 7.00

5 6 7

LS No 5.8 Fire Extinguishers Schedule No

1.00 7.00

5.8 Fire Extinguishers and Blankets


1
Extinguishers at main building and guard room, wall mounted, powder-type (9kg).

3.00

Subtotal Interior

6. Finish

6.1 Plastering
NOTE: Prior to work, samples must be approved by UNOPS Engineer. Internal and external surfaces

6.1 Plastering Schedule

Cement render medium CRM followed by cement render fine CRF on all internal and external surfaces of walls/ ceilings/ beams/ columns/ reveals/ parapets, porches etc for main building. See schedule for detail. Cement render medium CRM followed by cement render fine CRF on all internal and external surfaces of walls/ ceilings/ beams/ columns/ reveals/ etc for guard room. See schedule for detail. 6.3 Wall tiling and 6.3 Floor tiling schedules

SQ.M

1,940.00

SQ.M

200.00

6.3 Tiling
NOTE: Prior to work, samples must be approved by UNOPS Engineer.

1 2

For main building: Ceramic wall tiles for toilets, kitchen. The cost includes bed preparation, bedding and grout. SQ.M Ceramic floor tiles for toilets including bed preparation, bedding and grout. SQ.M 90.00 43.00 -

8/15

Currency: Project No: Project Title: Location:

US Dollars 1017 ANDMA Building in Heart Herat, Afghanistan

Tender No: 01 Component: 2-Story Administration Building and a Guardhouse Original Issue: November 07, 2010

Pos. 3 4

Description of Work/Items
Marble tiles for all rooms and halls where did not receive ceramic tiles. The cost includes bedding and grout. Marble skirting for all rooms and halls where did not receive ceramic tiles. The cost includes bedding and grout. Granite tiles (30mm) for stairs treads and landings including bedding and grout. Granite tiles (10mm) for stairs raise including bedding and grout. Granite skirting for stairs including bedding and grout. Granite tiles for internal window sill at window W6, including bedding and grout. For guard room: Ceramic wall tiles for toilets, kitchen. The cost includes bed preparation, bedding and grout. Ceramic floor tiles for toilets including bed preparation, bedding and grout. Marble skirting for all walls that did not receive ceramic tiles. The cost includes bedding and grout.

Project Schedules Ref.

Unit

Quantity

Unit Cost

Total Cost

SQ.M

202.00

Lin M SQ.M SQ.M Lin M No

210.00 15.00 4.00 14.00 1.00

5 6 7 8

9 10 11

SQ.M SQ.M

40.00 14.00

Lin M 6.6 Interior/Exterior painting schedule

13.00

6.6 Painting
NOTE: Prior to work, samples must be approved by UNOPS Engineer. Internal surfaces

Flat water based: Interior, on all surfaces that receive cement plaster for main building. The cost includes wall putty (gypsum filling) layer before painting and all needed preparation of the surfaces for painting. See schedule for detail on this paint system Flat water based: Interior, on all surfaces that receive cement plaster for guard room. The cost includes wall putty (gypsum filling) layer before painting and all needed preparation of the surfaces for painting. See schedule for detail on this paint system External surfaces Flat water based: Exterior, on all surfaces that receive cement plaster for main building. The cost includes wall putty (gypsum filling) layer before painting and all needed preparation of the surfaces for painting. See schedule for detail on this paint system Flat water based: Exterior, on all surfaces that receive cement plaster for guard room. The cost includes wall putty (gypsum filling) layer before painting and all needed preparation of the surfaces for painting. See schedule for detail on this paint system

SQ.M

1,450.00

SQ.M

105.00

SQ.M

490.00

SQ.M

95.00

Subtotal Finishes

8. Water Services
9/15

Currency: Project No: Project Title: Location:

US Dollars 1017 ANDMA Building in Heart Herat, Afghanistan

Tender No: 01 Component: 2-Story Administration Building and a Guardhouse Original Issue: November 07, 2010

Pos.

Description of Work/Items

Project Schedules Ref.


8.1 Water services samples, 8.1 Water system piping, 8.1 Sanitary fixtures, 8.1 Water heater schedules and 8.1 Water Services Testing schedules

Unit

Quantity

Unit Cost

Total Cost

8.1 Water Services

NOTE: The cost for all pipes exposed to weather includes glass wool thermal insulation cover. The cost given for all GI and PVC pipes with diameter less than 60mm includes all required fittings, accessories and work for complete system installation. To be mentioned that the following section cover water sanitation needs for main building, septic tank and the guard room. Water supply piping

1 2 3 4 5 6 7 8 9

GI water supply pipe D=32mm, including fittings and installation. GI water supply pipe D=25mm, including fittings and installation. GI water supply pipe D=20mm, including fittings and installation. GI water supply pipe D=15mm, including fittings and installation. Water supply bronze Valve D=32mm, including fittings and installation. Water supply bronze Valve D=25mm, including fittings and installation. Water supply bronze Valve D=20mm, including fittings and installation. Damp proof Insulation rubber tape for all GI Piping. Water supply inspection manhole less than 1200mm deep. This includes excavation and any needed work to make the manhole as per drawings and schedule. Sanitation Piping PVC pipe D=125mm, including supply and installation. This also includes supply and installation of PVC pipe from GI sheet downpipes to the open channel collector at the side walks. PVC pipe D=100mm, including supply and installation. This also includes supply and installation of PVC pipe from GI sheet downpipes to the open channel collector at the side walks. PVC pipe D=50mm, including fittings and installation. Ventilation PVC pipes D=100mm (from toilets to roof). This also includes supplying and installation of PVC screen at the pipe inlets inside the toilets. See drawing and schedule for details. Ventilation PVC pipes D=50mm (from toilets to roof). This also includes supplying and installation of PVC screen at the pipe inlets inside the toilets. See drawing and schedule for details.

Lin M Lin M Lin M Lin M No No No Lin M

80.00 110.00 100.00 148.00 2.00 3.00 4.00 200.00

No

1.00

10

Lin M

40.00

11

Lin M Lin M

95.00 110.00

12 13

Lin M

10.00

14

Lin M

35.00

10/15

Currency: Project No: Project Title: Location:

US Dollars 1017 ANDMA Building in Heart Herat, Afghanistan

Tender No: 01 Component: 2-Story Administration Building and a Guardhouse Original Issue: November 07, 2010

Pos. 15 16 17 18 19 20 21 22 23

Description of Work/Items
PVC Elbow D=50x50,45, including supply and installation. PVC Elbow D=50x50,90, including supply and installation. PVC Elbow D=100x100,45, including supply and installation. PVC Elbow D=100x100,135, including supply and installation. PVC Tee D=100x50x100,45, including supply and installation. PVC Tee D=50x100x50,45, including supply and installation. PVC Tee D=50x50,45, including supply and installation. PVC Tee D=100x100, 45, including supply and installation. Sewer Manhole. This includes excavation and any needed work to make the manhole according to the drawings and schedules. Sanitary and other fixtures Western toilet, including supply, installation and accessories. Ceramic sink at toilets and labs, including mixer and all accessories, supplying and installation. Shower, including supply, installation and accessories. Floor trap D=50mm, including supply and installation. kitchen steel sink, Including supply and installation. Ventilation cap D=100mm, including supply and installation. Ventilation cap D=50mm, including supply and installation. Service Sink, including supply and installation. Electrical water boiler with capacity of 50 Liter, including supply and installation. Electrical water boiler with capacity of 30 Liter, including supply and installation. PVC Reservoir capacity of 2000 Liter, including supply and installation. Grease Trap less than 1200mm deep. This includes excavation and any needed work to make the manhole according to the drawings and schedules. Borehole Drilling well (8") diameter in soil, any type. Actual well depth will depend the site water level. Gravel river type 8-12mm in size. PCC and clay seal to borehole.

Project Schedules Ref.

Unit
No No No No No No No No

Quantity
2.00 8.00 1.00 4.00 4.00 7.00 5.00 2.00

Unit Cost

Total Cost
-

No

7.00

24 25 26 27 28 29 30 31 32 33 34 35

No

7.00

No No No No No No No No No No

7.00 1.00 7.00 2.00 1.00 3.00 2.00 3.00 2.00 1.00

No

2.00

Tube well:

Lin M LS LS

80.00 2.00 2.00

36 37

11/15

Currency: Project No: Project Title: Location:

US Dollars 1017 ANDMA Building in Heart Herat, Afghanistan

Tender No: 01 Component: 2-Story Administration Building and a Guardhouse Original Issue: November 07, 2010

Pos. 38

Description of Work/Items
(6") diameter PVC pipe 7-10mm in thickness. The actual pipe length will be adjusted according to the actual well depth in the site.

Project Schedules Ref.

Unit

Quantity

Unit Cost

Total Cost

Lin M

50.00

39

(6") diameter PVC filter 7-10mm thickness. See schedule for slot sizes and other specs. The actual pipe length will be adjusted according to the actual well depth in the site. Lin M 8.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 Insulation of casing and filter. Gravel pack around casing, filters up to 10m from surface of ground. Clay and cement pack from 10m to surface level. Water wash and Compression test of well. Preparation of hydro geological section, yield of well, water level, in report Chemical and bacteriological analysis tests of water samples. Draw down test for well Manhole on top of the well More than 1200mm deep. This includes excavation and any needed work to make the manhole according to the drawings and schedules. Installation of Italian 'Pedrollo' brand or equivalent submersible D=40mm water pump with 40 L\min discharge capacity capable of 153m total head, power capacity=4kw,three phase. This item includes complete and functioning pump installation and reinstating of the place to the satisfaction of UNOPS engineer if required. This also includes all mechanical works needed for successful installation. For electrical accessories required for the pump installation refer to section 9. Electrical Services down this document. LS LS LS LS LS No LS

40 41 42 43 44 45 46 47

No

1.00

48

No

1.00

Subtotal Water Services

9. Electrical Services

9.1 Electrical Services

9.1 Electrical systems, 9.1 Electrical supply mains, 9.1 Electrical switchboard design, 9.1 Main 380VAC Distribution System, 9.1 Panel Construction, 9.1 Power accessories, 9.1 Lighting control and fittings, 9.1 Fire Detection Equipment Schedule Schedules and the Attachments

Note: for all items below the cost includes complete/installations with all needed accessories and works. To be mentioned that the following section cover water sanitation needs for main building and the guard room.

12/15

Currency: Project No: Project Title: Location:

US Dollars 1017 ANDMA Building in Heart Herat, Afghanistan

Tender No: 01 Component: 2-Story Administration Building and a Guardhouse Original Issue: November 07, 2010

Pos. 1

Description of Work/Items
Power Distribution Main and Sub Boards 30KA ISC /0.5Sec, 380Y/220 Volt. 3 Phase, 4 Wire , 50Hz, having grounding bus and surge arrestors with all accessories. Out door NEMA enclosure type, Main Power Distribution Panel Board (MDP) . 30KA ISC /0.5Sec, 380Y/220 Volt. 3 Phase, 4 Wire , 50Hz, having grounding bus and surge arrestors with all accessories. In door NEMA enclosure type, Main Power Distribution Panel Board (DP1) . 30KA ISC /0.5Sec, 380Y/220 Volt. 3 Phase, 4 Wire , 50Hz, having grounding bus and surge arrestors with all accessories. In door NEMA enclosure type, Main Power Distribution Panel Board (DP2) . 30KA ISC /0.5Sec, 380Y/220 Volt. 3 Phase, 4 Wire , 50Hz, having grounding bus and surge arrestors with all accessories. Out door NEMA enclosure type, Main Power Distribution Panel Board (DP3) . Main circuit breaker, MCCB, 3x80Amps. Main circuit breaker, MCCB, 3x63Amps. Main circuit breaker, MCCB, 3x40Amps. Main circuit breaker, MCCB, 3x20Amps. Circuit breaker, MCB, 1x32Amps. Circuit breaker, MCB, 1x20Amps. Circuit breaker, MCB, 1x16Amps. Distribution cabling and wiring

Project Schedules Ref.

Unit

Quantity

Unit Cost

Total Cost

No.

1.00

No.

1.00

No.

1.00

No. No. No. No. No. No. No. No.

1.00 1.00 3.00 1.00 2.00 3.00 33.00 6.00

5 6 7 8 9 10 11

12

13 14 15

1(4Cx16mm) PVC/PVC Insulated Cable, in 50mm PVC electrical conduit. Note: (conduit is only from hand hole to the DP1) 1(4Cx10mm + 1x10mm ) PVC/PVC Insulated Cable, in 50mm PVC electrical conduit. 1(4Cx6mm ) PVC/PVC Insulated Cable. 2(1C x 4mm) + 4mm GND wires pulled in PVC conduit, assorted colors as per phase requirement RST/UVW, white color is for neutral and green color for grounding, the duct should not be filled more than 50%. 2(1C x 2.5mm) + 2.5mm GND wires pulled in PVC conduit, assorted colors as per phase requirement RST/UVW, white color is for neutral and green color for grounding, the duct should not be filled more than 50%. Fittings/Fixtures 10Amp Single Pole/Double Pole light switch. 4x18W recessed mounted fluorescent light fixture. Water proof and normal 2x36W surface mounted fluorescent light fixture. 13/15

Lin M

65.00

Lin M Lin M

6.00 25.00

Lin M

560.00

16

Lin M

260.00

17 18 19

No No No

30.00 4.00 25.00

Currency: Project No: Project Title: Location:

US Dollars 1017 ANDMA Building in Heart Herat, Afghanistan

Tender No: 01 Component: 2-Story Administration Building and a Guardhouse Original Issue: November 07, 2010

Pos. 20 21 22 23 24 25 26 27 28 29

Description of Work/Items
1x36W surface mounted fluorescent light fixture. 1x32W ceiling mounted circular fluorescent light fixture, Water Proof 1x18W ceiling mounted circular fluorescent light fixture, Water Proof 1x18W wall mounted mirror light fixture, Water Proof 1x20W wall mounted rechargeable emergency light fixture. 1x20W surface mounted rechargeable exit light fixture. 13Amp Duplex power receptacle. 16 Amp water proof power receptacle. 20 Amp water proof power receptacle. Note: according to the drawings for AC & oven.

Project Schedules Ref.

Unit
No No No No No No No No

Quantity
22.00 9.00 4.00 2.00 3.00 3.00 55.00 10.00

Unit Cost

Total Cost
-

No 20 Amp non fuse disconnect switch. AC/Split Units and Exhaust fans No

6.00 3.00

30

18000 BTU AC/ Split outdoor, indoor and remote control units with all accessories,220 V, 50HZ Samsung or equaling No 1.00 12000 BTU AC/ Split outdoor, indoor and remote control units with all accessories,220 V, 50HZ Samsung or equaling No 2.00 9000 BTU AC/ Split outdoor, indoor and remote control units with all accessories,220 V, 50HZ Samsung or equaling No 7.00 4.00 50W ,220V, 50Hz exhaust fans . Electrical Grounding. No

31

32

33

34

Grounding system according to the grounding drawing with electrodes, ground ring and grounding cables. Labeling Proper and correct all circuits numbering, cable circuit drawings, cable and switchboard labeling to the full satisfaction of UNOPS engineer.

Sets

2.00

35

LS

1.00

Subtotal Electrical Services

14/15

UNOPS
Vertical Structures Unit

SUMMARY ESTIMATE
Currency: Project No: Project Title: Location: Tender No: Component: Original Issue: US Dollars 1017 ANDMA Building in Heart Herat, Afghanistan 01 2-Story Administration Building and a Guardhouse November 07, 2010

Work Type
Total for General Total for Site Total for Structure Total for Enclosure Total for Interior Total for Finish Total for Water Supply Services Total for Electrical Services 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total for 2-Story Administration Building and a Guardhouse

0.00

Estimate Value for whole tender in words: Zero

Agreed on behalf of Contractor Name Position Signature

UNOPS Name Position Signature

Address and Mobile Number

Você também pode gostar