that the Government of Assam use a phased approach over a three-year period to

implement the recommended strategy to remedy the main deficiencies of the present
procurement system. It can be estimated that a minimum period of three years will be
required to complete reforms and implement the process of change .

In this process, it is critical for the Government of Assam:

? To maintain a dialogue with the business community and the civil society in
order to achieve real improvement with the legal, institutional, and
organizational changes.

? To initiate, through the GOA, the necessary steps to establish an Advisory


Committee of professionals from major Line Departments, the private and
public sector, and international donors.

? To be advised that a new procurement regime with a legal and regulatory


framework should be based on principles and norms generally accepted by the
international community, such as the UNCITRAL Model on Procurement of
Goods, Works and Services.

? To conduct procurement workshops as part of the reengineering process.


Their main objectives would be to promote dialogue and discussions on the
main legal and regulatory procurement issues. The audience for the
workshops should be carefully selected and the number of attendees limited to
around 20-25 persons including Officials from the Government as well as
representatives from the business community and the civil society.

4. MEASURES TO BE TAKEN BY THE GOVERNMENT OF ASSAM

The following recommendations include a suggested timeline and identify the


entity(ies) responsible for each recommended action.

Major Issues Recommended Month after Responsible


Actions Start Date Agency
1) Outdated legal a) Preparation of a new 1-7 month GOA
and regulatory procurement Bill;
framework. b) Circulation of draft Bill for 7-9 month GOA
comments by public and
private sector, and donors;
c) Preparation of detailed 1-9 month GOA
regulations for the new
procurement Bill;
d) Submission of the Bill for 10-16 month GOA/
approval by the Assembly; Assembly
e) Approval of detailed 17-20 month GOA
regulations by GOA.

Drafted by Thomas Burola, Procurement Adviser -


2) Weak and f) Establishment of a 17-18 month GOA
inefficient procurement supervisory
organizational body, with composition and
procurement responsibilities to be
structure. defined under new
procurement Bill;
g) Preparation of 17-24 month GOA/Line
administrative tools to Departments
discharge responsibilities,
including: standard bidding
documents; pre-
qualification, evaluation,
and contract forms;
procurement manuals;
guidelines and procedures;
flow charts; and time
schedules for all
procurement methods.

3) Inefficient a) Definition of structure and 17 month GOA


organizational function of the regulatory
and regulatory authority and timetable for
framework. implementation;
b) Making a needs analysis for 17-19 month GOA/Line
Line Departments and other Departments/
Public bodies, and Public bodies
recommending the
appropriate structure to set
up a procurement function;
c) Implementing procurement 20-24 month GOA
training for key staff;
d) Establishment of a 24-26 month GOA/Line
management information Departments
system to improve present
record keeping system;
e) Preparation of a training 26-28 month GOA/Line
program to explain and Departments
apply new procurement
legislation, including
regulations.
4) Weak and a) Establishment of a Protest 29-34 month GOA
inefficient and Dispute system, with
Protest and the composition and
Dispute system. responsibilities to be
defined under the new
procurement Bill;
b) Establishment of a 34-36 month GOA
management information
system to improve record
keeping of options;

Drafted by Thomas Burola, Procurement Adviser -


c) Preparation of a training 34-36 month GOA
program to explain and
apply the Protest and
Dispute information in the
public and private sectors.
5) A lack of d) Establishment of skills, 10-14 month GOA
Procurement knowledge and experience-
professional based criteria to certify
capacity procurement staff and
building. include a new remuneration
structure in civil service for
procurement profession;
e) Implementation of a needs 20-26 month GOA
analysis, and establishment
in the University of Assam
of regular and customized
procurement training for
senior government officials,
project managers and
procurement practitioners.
6) Weak anti- f) Establish a civil society 34-36 month GOA
corruption anti-corruption watchdog
measures group with independent and
enforcement. credible members to advise
the GOA on public
procurement;
g) Establish a code of ethical 1- month GOA
conduct to professionalize
the procurement workforce.

Drafted by Thomas Burola, Procurement Adviser -