Você está na página 1de 52

CHE 425 Engineering Economics and Design Principles

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

CHAPTER 5

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

Definition

Capital cost pertains to the costs associated with construction of a new plant or modification to an existing chemical manufacturing plant.

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

Types of Capital Cost Estimate n Order of Magnitude Estimate (Feasibility) o Study Estimate / Major Equipment p Preliminary Design (Scope) Estimate q Definitive (Project Control) Estimate r Detailed (Firm or Contractors) Estimate

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

Types of Capital Cost Estimate (cont.)


Order of Magnitude Estimate (Feasibility)
Data: Cost information for a complete process Diagram: BFD

Study Estimate / Major Equipment


Data: List of major equipments Diagram: PFD

Preliminary Design (Scope) Estimate


Data: Accurate equipment sizes, layout of equipment, piping, instrumentation and electrical requirements Diagram: PFD and preliminary PI&D

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

Types of Capital Cost Estimate (cont.)


Definitive (Project Control) Estimate
Data: specification of all equipment, utilities, instrumentation, electrical and off-sites. Diagram: Final PFD and a preliminary PI&D

Detailed (Firm or Contractors) Estimate


Data: Complete engineering of the process and all related off-sies and utilities. Diagram: Final PFD and P&ID

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

Types of Capital Cost Estimate

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

Example 5.2

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

Estimating Purchased Equipment Costs


Vendor quote
Most accurate
based on specific information requires significant engineering

Use previous cost on similar equipment and scale for time and size
Less accurate
beware of large extrapolation beware of foreign currency

Use cost estimating charts and scale for time


Reasonably accurate Convenient
Prof. Adnan Alamer Chemical Engineering Dept., KFUPM 9

Effect of Size (Capacity)


Ca Aa = Cb Ab
n

(5.1)

Ca = KAa
where

(5.2)

K = Prof. Adnan Alamer n Chemical Engineering KFUPM AbDept.,

Cb

10

Effect of Size (Capacity)

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

11

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

12

Effect of Size (Capacity) (cont.)


n = 0.4 0.8 Typically Often n ~ 0.6 and we refer to Eq.(5.1) as the (6/10)s Rule
Assume all equipment have n = 0.6 in a process unit and scale-up using this method for whole processes Order-of-Magnitude estimate

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

13

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

14

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

15

Another way of looking at economy of scale

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

16

Economy of Scale
Prof. Adnan Alamer Chemical Engineering Dept., KFUPM 17

Effect of Time
Time increases cost increases (inflation) Inflation is measured by cost indexes - Figure 5.3
Chemical Engineering Plant Cost Index (CEPCI) Marshall and Swift Process Industry Index

Numbers based on basket of goods typical for construction of chemical plants - Table 5.5
Prof. Adnan Alamer Chemical Engineering Dept., KFUPM 18

Equation for Time Effect

I2 C 2 = C1 I 1

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

19

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

20

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

21

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

22

Example
Question Cost of vessel in 1993 was 25,000, what is estimated cost today (Sept 2003 CEPCI = 402)? Solution

I now 402 Cnow = C1993 = $27,990 I = 25,000 359 1993


Prof. Adnan Alamer Chemical Engineering Dept., KFUPM 23

Example - Accounting for Time and Size


2 heat exchangers, 1 bought in 1990 and the other in 1995 for the same service A 70 m2 1990 17 K 358 B 130 m2 1995 24 K 381

Area Time Cost I

= = = =

What is the Cost of a 80 m2 Heat Exchanger Today? (I = 402)


Prof. Adnan Alamer Chemical Engineering Dept., KFUPM 24

Example - Solution
Must First Bring Costs to a Common Time

A = 70
402 Ca (2003) = 17 = 19.089 358

A = 130
402 Cb (2003) = 24 = 25.323 381
Prof. Adnan Alamer Chemical Engineering Dept., KFUPM 25

Example Solution (cont.)

C = KA
n=

19.089 = K (70)
n

25.323 = K (130) n
= 0.4565

log ( 25.323 ) log(19.089) log (130 ) log(70)

19.089 C K = n = 0.4565 = $2.745 70 A

C = 2.745(80 )

0.4565

= $20.288 = $20,290
26

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

Total Cost of Plant


Purchased equipment cost equipment f.o.b. Installed cost Often 3 to 8 times larger than purchased equipment cost

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

27

Installed Cost of Equipment (Table 5.6)


1. Direct Project Expenses
Equipment Material for installation Labor for installation

2. Indirect Project Expenses


Freight, insurance, and taxes Construction overhead Contractor engineering expenses
Prof. Adnan Alamer Chemical Engineering Dept., KFUPM 28

Installed Cost of Equipment (Table 5.6) (cont.)


Contingency and Fee
Contingency Contractor fee

Auxiliary Facilities
Site development Auxiliary buildings Off-sites and utilities

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

29

Lang Factors
Table 5.7 Use multiplier depending on type of plant to escalate equipment costs to installed costs Flang = 4.74 = 3.63 = 3.10 Fluid processing plant Solid-Fluid processing plant Solid processing plant

This estimating technique is insensitive to changes in process configuration

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

30

Lang Factors (contd)

CTM = FLang C pi
i =1

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

31

Lang Factors (contd)

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

32

Module Factor Approach


Table 5.8 Direct, Indirect, Contingency and Fees are expressed as functions (multipliers) of purchased equipment
o cost (C p ) at base conditions (1 bar and CS)

Each equipment type has different multipliers Details given in Appendix A

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

33

Module Factor Approach

C BM = C
Bare Module Cost

o p F BM

Bare Module Factor (sum of all multipliers) Purchased Equipment Cost for CS and 1 atm pressure - Appendix A
o FBM = B1 + B2

FBM = B1 + B2FpFM
Fp = pressure factor (= 1 for 1 bar)

FM = material of construction factor (=1 for CS)

Cp = Co p F p FM
Prof. Adnan Alamer Chemical Engineering Dept., KFUPM 34

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

35

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

36

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

37

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

38

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

39

Pressure Factors

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

40

Pressure Factors

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

41

Pressure Factors

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

42

Pressure Factors

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

43

Illustrative Example
Compare Costs for
1. Shell-and-tube heat exchanger in 2001 with an area = 100 m2 for :
Carbon Steel at 1 bar Carbon Steel at 100 bar Stainless Steel at 1 bar Stainless Steel at 100 bar

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

44

Effect of Materials of Construction and Pressure on Bare Module Cost

P
1 bar 1 bar 100 bar 100 bar

MOC CS SS CS SS

Co p
25 K 25 K 25 K 25 K

o CBM

CBM 82.3 K 154 K 98.1 K 197.4 K


45

82.3 K 82.3 K 82.3 K 82.3 K

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

Bare-Module and Total-Module Costs


BM Previously Covered TM Includes Contingency and Fees at 15% and 3% of BM

CTM = 1.18

CBM

all equip

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

46

Materials of Construction

Very important Table 5.9 rough guide Perrys good source

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

47

Materials of Construction

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

48

Materials of Construction

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

49

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

50

Results of Example 5.14

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

51

Capcost
Calculates costs based on input CEPCI use current value of 401 or latest from Chemical Engineering Program automatically assigns equipment numbers

Prof. Adnan Alamer Chemical Engineering Dept., KFUPM

52

Você também pode gostar