Escolar Documentos
Profissional Documentos
Cultura Documentos
19%
2%
66%
Thermal 1,37,386 MW
Hydro 39,291 MW
Nuclear 4,780 MW
Renewable 25,703 MW
2
13%
70%
Wind 17,875 MW
Solar 1041 MW
Biomass 3,366 MW
3
Climate Change
Access
Security
Industrial Sector
Renewable Energy
Transport
Power Generation
55
30 20 10 0
2002 2007
24.9
10.2 3.5
2012
2017
Achievements Up to IX Plan (3.5 GW) X Plan Achievements (6.7 GW) XI Plan Achievements (14.7 GW) XII Plan Targets (30 GW)
8
Grid solar power (large plants, roof top & distribution grid plants)
1,100 MW
200 MW
7 million sq meters
1,000 MW
15 million sq meters
2,000 MW
20 million sq meters
5 million
10 million
20 million
8 10
20000
20000 20
20
20
15000
15 10000 10 5000 1000 0 200 Phase 1 4000 1000 Phase 2 2000 5 Phase 3 7 5 10 10
Grid solar power (MW) Off-grid Applicationa (MW) 0 Phase 1 Phase 2 Phase 3
In addition, 100 MW capacity distributed small grid connected power plants during Phase -1
13
11
12
Phasing of Allocation
Solar PV: Selection of PV projects done in two batches of 150 MW and 350 MW over two financial years of Phase 1 i.e., 2010-2011 and 2011-2012. Solar Thermal: Given the longer gestation period of Solar Thermal Projects, entire capacity was selected in batch 1.
13
Domestic Content
Solar PV: Batch 1
Crystalline Technology: Use of modules manufactured in India was mandatory Thin film/ CPV : Was allowed to be sourced from other countries
Solar Thermal
30% of the Project Cost
14
Selection of projects
Projects were selected on the basis of discount offered by the Project Developers on CERC Approved Applicable Tariff
15
Solar PV : 30 projects for 150 MW selected in December, 2010. Average Tariff - Rs. 12.16 per unit (32% reduction on CERC Tariff)
26 Projects of 130 MW completed.
11.48
18
68
87.8
12 26 106
Other Programmes
Additionally, 21.5 MW capacity projects have been installed under other schemes of the Ministry.
14
Solar Water Heating Target: - Solar heating 70 lakh sq. meter of collector area by 2013. Achievement: - On cumulative basis, over 57 lakh sq. meter area of solar thermal collectors has been installed so far.
15
2.
3. 4.
Chhattisgarh
Delhi Gujarat
4.0
2.5 690
5.
6. 7.
Haryana
Jharkhand Karnataka
7.8
16.0 14.0
8.
Madhya Pradesh
7.35
Contd. 18
Others
TOTAL
500
3 0 2008-09
11
2009-10
36 2010-11 2011-12
1000 MW off grid solar applications by 2017 15 million square meters solar thermal collector area by 2017
25
26
Projected Growth
Projected Solar Generation Capacity (GW)
25
20
20
15
10
10
2012-13
2016-17
2021-22
R&D Activities
36 R&D projects under implementation 5 Centers of Excellence in research and education sanctioned Technology Validation 1 MW solar thermal power with storage; Field trials of thermal systems for industrial process heat Testing & Training 6 test labs for PV & 6 for solar thermal systems International collaborations Joint projects with USA, Japan, Germany, Spain 51 new Stations set up for Solar Radiation Data collection
28
Chhattisgarh
Ladakh
1
1
Maharashtra
Pudducherry Tamil Nadu
3
1 6
C-WET is implementing the project for setting up 51 ground monitoring stations Centralized data collection, analysis and calibration of measuring sensors
28
SEC is regularly conducting international training programmes in solar energy with MEA
SEC is designated to provide feedback on the project proposal to the financing institutions, if required, by them.
29
32
Institutional Arrangements
Solar Energy Corporation of India (SECI) has been set up as a Company Not for Profit under Section 25 of Company Act for implementation of activities under the Mission
Solar Energy Research Advisory Council, Chaired by Dr. Anil Kakodkar has been set up to advise on research policy with a view to achieve Mission targets.
Solar Energy Industry Advisory Council, Chaired by Shri Anand Mahindra set up.
35
21
23
23
40