Escolar Documentos
Profissional Documentos
Cultura Documentos
SHK-001 (PACKAGE I)
DESIGN, MANUFACTURE, SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF PLANT FOR UPGRADATION OF
THE EXISTING 220 KV SHIKARPUR SUBSTATION TO 500 KV LEVEL
ESTIMATED COST OF DISMANTLING & RECONCILATION OF BOUNDARY WALL OVER RETAINING OF STONE
MASONARY AROUND 500/220 SWITCHYARD AS PER DRAWING NO. BQB/NTDC/SHK/BW-107-13 AND SHK/NEIE/RW/1312
Detail Estimate:
Sr.No/ BOQ
Description
Item
1/
Dismantling work of Concrete /
K.1.5
Brick Work
2/
K 11 A -1
3/
K 6.4
Details
Old wall
Below DPC
Concrete Footing
Price
=
=
=
45.88
237.11
0.125
Total
@ 924 p Cu.mtr
1 x 370000 x 1950 x 550
=
283.115
261,598.26
396.82
Total
@ 364 pcum
1 x 313.5 x 1950 x 450
=
1 x 370000 x 1950 x 450
=
Total
@ 4047 pcum
396.82
144,442.48
0.274
324.675
324.949
Old Portion
Extension Portion
=
=
3rd
4th
5th
6th
7th
8th
6/
K 11 A 4i
7/
K 1.6
Damp proofing
Horizontal 1 thick (1:2:4)
210kg/cm2 concrete with damp
proofing compound
Wall
=
=
=
=
=
=
Total
@
=
=
=
Total
@
=
683500 x 343
Total
@ 675 pSq.m
229 x 343 x 343 x 2000 =
228 x 2657 x 230 x
=
2000
Total
@ 7885 p Cu.mtr
Plaster
Providing and laying minimum Below DPC
8/
1/2 thick cement plaster (1:4) Wall
K 11A B using ordinary Portland cement Top
whenever required as per
Drawing
&
Specification/
683500 x 2200
229 x 2657 x 2000
683500 x 230
=
=
=
9/
K 11 A 24
Edges
Wall
10
11
Analysis attached
Barbed Wire
12
Analysis attached
Fixing (20/09/83)
Analysis attached
13
Total
@ 260 p Sq.m
229 x 2 x 115 x 2000
=
229 x 3343 x 2000
=
Total
@ 219 P Sq.m
124 No.
=
Total
@ 1200
370 m
=
Total
@ 250/- PRm
105 No.
=
Total
@ 120/ 313.5 Rm
Cement
= 32.45/-
(ii)
Sand
= 8.00/-
Total = 40.46/-
B. Labour
(i)
Mason
0.108 @ 850/-
= 91.80/-
(ii)
Cooly
0.108 @ 425/-
= 45.90/-
(iii)
Water Man
0.027 @ 450/-
= 12.15/Total = 149.85/-
5.520 kg @ 172/-kg
= 949.44/-
(ii)
Cement
0.180 kg @ 12/-kg
= 2.16/-
(iii)
Sand
= 23.4/-
(iv)
Crush
= 63.57/-
Total = 1038.57/-
B. Labour
(i)
Mason
0.200 @ 850/-
= 170/-
(ii)
Cooly
0.200 @ 425/-
= 85/-
(iii)
Water Man
0.050 @ 450/-
= 22.5/Total = 277.5/-
ANALYSIS OF RATE FOR CEMENT PROVIDING & FIXING 4 rows barbed wire
fencing around bounding . 4! Wire - . 2 ply 4 points 100 apart complete
Unit : Meter
A. Material
(i)
Eye Hook
2.297 No @ 50/-
= 114.85/-
(ii)
Nat Bolts
2.297 No @ 16/-
= 36.75/-
(iii)
Barbed Wire
0.521 kg @ 150/-
= 78.15/-
(iv)
Binding Wire
0.022 kg @ 110/-
= 2.42/Total = 232.17/-
B. Labour
(i)
Black Smith
0.025 No @ 950/-
= 23.75/-
(ii)
Smithy Coolly
0.033 No @ 450/-
= 14.85/-
(iii)
Coolly
0.0980 No @ 450/-
= 44.1/-
ANALYSIS OF RATE FOR FIXING & .. ANGLE FROM POST WITH PEC 1:2:4
Unit : Each
A. Material
(i)
Cement
= 0.84/-
(ii)
Sand
= 5.94/-
(iii)
Crush
= 17.55/-
Total = 24.33/-
B. Labour
(i)
Mason
0.0623 @ 850/-
= 52.96/-
(ii)
Coolly
0.0636 @ 450/-
= 28.62/-
(iii)
Water Man
0.0002 @ 450/-
= 0.09/Total = 81.67/-
1 No @ 450/-
= 450/-
(ii)
0.050 @ 450/-
= 22.5/-