Scope of Work of C5 Migration-MDF part


TABLE OF CONTENTS 1 Overview................................................................................................................. 3 2 General Requirements............................................................................................. 3 3 Scope of work for each part.................................................................................... 4 3.1 Vertical MDF Duplexing Scenario.........................................................................4 3.1.1 MDF port test..................................................................................................... 7 3.1.2 New subscriber cables routing and termination................................................9 3.1.3 Jumpering cable routing and termination..........................................................9 3.1.4 Migration and rollback..................................................................................... 10 3.1.5 Old subscriber cables dismantlement.............................................................11 3.1.6 Old jumpering cables dismantlement..............................................................12 3.1.7 Daily maintenance ......................................................................................... 12 3.2 Horizontal MDF duplexing+ jumpering cables migration gradually scenario.....12 3.2.1 MDF port test................................................................................................... 16 3.2.2 Voice service migration................................................................................... 18 3.2.2.1 New subscriber cables routing and termination...........................................18 3.2.2.2 Migration and rollback..................................................................................19 3.2.3 Broadband service migration..........................................................................20 3.2.3.1 New jumpering cables routing......................................................................20 3.2.3.2 Dismantle old exchange subscriber cables..................................................20 3.2.3.3 Migration and rollback..................................................................................21 3.2.4 Old subscriber cables dismantlement.............................................................22 3.2.5 Old jumpering cables dismantlement..............................................................22 3.2.6 Daily maintenance ......................................................................................... 23 3.3 Jumpering cable migration gradually scenario...................................................23 3.3.1 MDF port test................................................................................................... 25 3.3.2 New subscriber cables routing and termination..............................................26 3.3.3 New jumpering cables routing.........................................................................27 3.3.4 Migration and rollback..................................................................................... 27 3.3.5 Old subscriber cables dismantlement.............................................................28 3.3.6 Old jumpering cables dismantlement..............................................................28 3.3.7 Daily maintenance ......................................................................................... 29 3.4 MSAN cable and jumpering cable migration gradually scenario.........................29 3.4.1 MDF port test................................................................................................... 33 3.4.2 Voice service migration................................................................................... 35 3.4.2.1 New subscriber cables routing.....................................................................35 3.4.2.2 Migration and rollback..................................................................................35 3.4.3 Broadband service migration..........................................................................36 3.4.3.1 New jumpering cables routing......................................................................36 3.4.3.2 Migration and rollback..................................................................................36 3.4.4 Old subscriber cables dismantlement.............................................................38

Appendix 2 Scope of Work

PASOMNxxxxxxxxxxx

3.4.5 Old jumpering cables dismantlement..............................................................38 3.4.6 Daily maintenance ......................................................................................... 39 3.5 DDF migration.................................................................................................... 39 3.5.1 Migration and rollback..................................................................................... 39 3.5.2 Old E1 cables dismantlement..........................................................................40 4 Definitions............................................................................................................. 40

Appendix 2 Scope of Work

PASOMNxxxxxxxxxxx

1 Overview
Huawei has been awarded C5 migration project from Omantel, most of the jobs are between Omantel and Huawei. Now Huawei is kindly looking forward to cooperation with your company. This document out cables the requirement of C5 migration project, including new subscriber cable termination, MDF port test, old subscriber cable dismantlement, document update, daily activity during migration and other related job for this project. The subcontractor shall comply strictly with all the technical, design specifications, guide cables and procedures from Omantel and Huawei. The scope of work and responsibilities of the subcontractor are as follows, but not limited to.

2 General Requirements
2.1 All the work and materials shall be in accordance with approved generic drawings provided by Huawei, and to the satisfaction and approval from Omantel. The subcontractor shall fully cooperate with Huawei representative and follows given instructions related to work being implemented. The contract will be as a Back to Back contract, i.e., whatever change in order or directive comes from Omantel and is devoted to Huaweis scope of work, it will automatically be applied to the contract and will be obligated to subcontractor. Meantime, it will not affect the previously decided lump sum price by both parties. The subcontractor shall provide enough teams to keep good progress that always meets or exceeds the requirements from Omantel and Huawei. The subcontractor shall be solely responsible to the damage or loss of materials taking place by his own mistake or careless operation during the project. The subcontractor shall be solely responsible for all the Safety and Quality at site in accordance with the standards of Omantel and Huawei. The subcontractor shall submit regularly concerned management report to Huawei, and attend the project management meeting of Huawei or attend Omantel meeting on behalf of Huawei. After completion of work at the site, the subcontractor must clean up the site, and remove all debris resulting from his work; i.e. keep up the site status to its

2.2

2.3 2.4 2.5 2.6

2.7

Appendix 2 Scope of Work

PASOMNxxxxxxxxxxx

original one. Meanwhile, all unused materials have to be prepared a list and returned back to Huawei warehouse in Muscat. 2.8 The subcontractor shall be solely responsible to provide all transportation vehicles and installation tools, such as laptop, multimeter, wire stripper, wiring knife, etc. The subcontractor shall be solely responsible to provide relevant documentation to Huawei, such as check list, supplier certificate, quality selfinspection form, self-test results, including both hardcopy and softcopy etc., as per the standards from Omantel and Huawei.

2.9

2.10 The subcontractor shall be solely responsible to pass PAC successfully and correct all the mistakes, if any. 2.11 The price of the agreement is a lump sum price. The subcontractor shall be solely responsible to all the expenses, such as salary, accommodation, transportation, telecommunication and insurance for his employees, etc. 2.12 It is unacceptable to Huawei that the subcontractor re-subcontracts the project to other subcontractor. The detailed descriptions of different part as follows are as a guide and procedure, but the subcontractor can not just limit on them. The subcontractor should hand over the complete job to Huawei and Omantel.

3 Scope of work for each part


3.1 Vertical MDF Duplexing Scenario
If vertical MDF support duplexing and new horizontal MDF blocks space is available (or there are enough spare horizontal MDF blocks), this could be the best migration solution. Under this scenario, the broadband service and voice service will be migrated to the new MSAN together. The new jumbering cable need be routing and terminated between old vertical MDF and new horizontal MDF, the old jumpering cable between vertical MDF and old horizontal MDF will be cut down. Note: the spare or new horizontal MDF blocks should be in the same rack with the old horizontal blocks. As following example, the new build horizontal MDF should be in the same rack (or existing rack extended).

Appendix 2 Scope of Work

PASOMNxxxxxxxxxxx

Appendix 2 Scope of Work

PASOMNxxxxxxxxxxx

Under this scenario, the broadband service and voice service will be migrated to the new MSAN together. The new jumbering cable need be routing and terminated between old vertical MDF and new horizontal MDF, the old jumpering cable between vertical MDF and old horizontal MDF will be cut down.

Appendix 2 Scope of Work

PASOMNxxxxxxxxxxx

3.1.1 MDF port test


Definition: The MDF port test is divided into three stages. For each site the subcontractor should follow the procedure, provide the test report, update the MDF allocation list and correct the mistakes. before vertical MDF duplexing
No. Sub-items For the voice service, make manual test on vertical MDF(100% port) according to the MDF allocation list and make a record For the broadband service, make a sample test on vertical MDF(10% port) and make a record of modem activation rate Check the duplexing port status for each port when doing above test and make a record Feed back the test report to Omantel Check all issues with Omantel and update the MDF allocation list after all issue are solved Replace the old MDF module if the duplexing port is broken, or just move the subscriber to another spare MDF port, including the jumpering cable and subscriber cable Test report template should be confirmed by Omantel and Huawei

Prerequisite
Omantel already provide the MDF allocation list information, including telephone number, MDF port location, port attribute, etc.

Remark: For the ISDN BRA subscribers test, the NT1 and ISDN telephone should be prepared by subcontractor. For the broadband service test, the modem should be prepared by subcontractor.

After vertical MDF duplexing, before migration


No. Sub-items

Prerequisite

Appendix 2 Scope of Work

PASOMNxxxxxxxxxxx

Before test, plug out the isolator on new horizontal MDF port if the port is voice over ADSL 1. Huawei provide the dialing test tool and test data 2. The test telephone number has been provided by Omantel, which has CLIP function

Execute dialing test with dialing test tool(100% port)

3. The new jumperling cables between vertical MDF and new horizontal MDF have been finished by subcontractor 4. The software for dialing test tool has been installed in subcontractor laptop correctly

3 4 5

After test, plug in the isolator back to the new horizontal MDF port Provide the test report Correct the MDF issues according to test report The software of dialing test tool will generate report automatically

After migration
No. Sub-items For the voice service, make a sample test manually on vertical MDF port Compare the test result with latest MDF allocation list Correct the MDF issues Make broadband service test on vertical MDF after migration manually (10% port), make a record of modem activation rate Prepare the verification report

Prerequisite
1. The migration has been finished

2. The sample port list has been confirmed by Omantel and Huawei

2 3

Remark: the sample proportion usually is no more than 10%

Appendix 2 Scope of Work

PASOMNxxxxxxxxxxx

There are two scenarios of the test result. Scenario 1: No dial tone The reason could be: this port is for ISDN BRA; duplexing is not well; duplexing to a not working port. First of all, measure the voltage by the multimeter, if around -48V means that is a POTS port, if else means that is an ISDN port. If that is the POTS port, please try to duplex again or find out the correct port and make the duplexing. If that is the ISDN port, test with the NT1 and ISDN telephone again, if there is no dial tone yet, please try to duplex again or find out the correct port and make the duplexing. Scenario 2: Wrong number It means the new jumpering cable is connected to the wrong port (other working port). Please correct the new jumpering cable connection according to the latest MDF allocation list.

3.1.2 New subscriber cables routing and termination


Definition: The subcontractor should finish the new subscriber cables routing and termination in new MDF blocks of exchange side according to port mapping table.
No. Sub-items

Prerequisite
1. The new subscriber cables have already been laid on MDF rack and marker is correctly marked. 2. The port mapping table has already been provided by Huawei.

Route the new subscriber cables into the new horizontal MDF blocks

2 3

Strip the subscriber cable Wire the separated twisted pair cables to corresponding MDF port The new port mapping table has already been provided by Huawei.

3.1.3 Jumpering cable routing and termination


Definition: New jumpering cable between vertical MDF and new horizontal MDF should be routed and terminate on vertical MDF and horizontal MDF.

Appendix 2 Scope of Work

PASOMNxxxxxxxxxxx

It had been tested and proven that when the bridge tap is less than 30 meters, the degradation of speed is small and within acceptable range. In the MDF rack, the new jumpering cable usually is no more than 30 meter, but considering the subscriber cable from MSAN to new horizontal MDF, the bridge tap will exceed 30 meter, so the isolators will be used at the new horizontal MDF.
No. Sub-items Routing new jumpering cable between 1

Prerequisite
New horizontal MDF has been installed;

vertical MDF and new horizontal MDF


Punch the jumpering cable on vertical

MDF and new horizontal MDF


If the subscriber cable is voice over ADSL, plug in the isolator on the corresponding horizontal MDF port

The new port mapping table has already been provided by Huawei.

Remarks: before doing the duplexing, its necessary to check and make sure the new MSAN

cables are not connected to the boards. Pull it out from the board if found connected.

3.1.4 Migration and rollback


Definition: On the migration night, subcontractor should finish the migration as following procedure. If need, also finish the rollback procedure. Migration
No. Sub-items

Prerequisite
1. The new MSAN rack has been installed and data has been configured

Connect the new subscriber cable to the MSAN service board

2. The new subscriber cables have already been laid in MSAN rack and marked correct marker 3. The wiring has been finished and test

Plug out the isolator on the new horizontal MDF port if this is voice over ADSL port Plug in the isolator to the ADSL_out position

Remark: the old subscriber cable of exchange and DSLAM should also be unplugged from old

Appendix 2 Scope of Work

PASOMNxxxxxxxxxxx

equipment or just plug out the service board, but it is suggested to require Omantel to finish this job, since we do not know other vendors equipment. And they also should make a marker on the cable themselves before they disconnect the cable. After migration, the isolator also need be plugged into the ADSL_out port to avoid the ADSL speed reduction caused by bridge tap

rollback (if need)


No. 1 Sub-items Disconnect the new subscriber cable from the MSAN service board Plug in the isolator to the new horizontal MDF port if this port is voice over ADSL Plug out the isolator on the ADSL_out position

Prerequisite
If decide to rollback by Omantel and Huawei after sample test

Remark: the old subscriber cable should also be plugged into exchange and DSLAM or just plug into the service board, but it is suggested to require Omantel to finish this job.

3.1.5 Old subscriber cables dismantlement


Definition: This part describes the dismantlement of old subscriber cables after migration, including exchange cables and DSLAM cables.
No. 1 Sub-items Dismantle the exchange subscriber cables from MDF rack and lay them in the space of MDF room Dismantle the DSLAM subscriber cables from MDF rack and lay them in the space of MDF room Plug out the isolator on ADSL_out position

Prerequisite

Appendix 2 Scope of Work

PASOMNxxxxxxxxxxx

3.1.6 Old jumpering cables dismantlement


Definition: This part describes the dismantlement of old jumpering cables after migrations, including the jumpering cables between vertical MDF and old horizontal MDF and between old exchange and old DSLAM.
No. Sub-items Dismantle the old jumpering cables 1

Prerequisite

between vertical MDF and old horizontal MDF


Dismantle the old jumpering cables

between old exchange and old DSLAM

3.1.7 Daily maintenance


Definition: This part describes the daily maintenance work before Huawei gets PAC. There could be some issues related to MDF after migration, such as wrong connection, short of connection. Subcontractor should support Omantel to handle these issues when get request from Omantel or Huawei.
No. 1 2 3 Sub-items Support Omantel to solve MDF issues remotely or on-site Update the MDF allocation list Feed back the update information

Prerequisite

3.2

Horizontal MDF duplexing+ jumpering cables migration gradually scenario

If there is not space available for new horizontal MDF blocks or vertical MDF can support jumpering cable duplexing, but horizontal MDF can support the duplexing, then horizontal MDF duplexing solution can be used. Under this scenario, the broadband service and voice service will be migrated to the new MSAN separately. First, the new subscriber cables from new MSAN will be routed and duplex on the existing horizontal MDF port.

Appendix 2 Scope of Work

PASOMNxxxxxxxxxxx

Second, new jumbering cables need be routed and terminated between vertical MDF and horizontal MDF, but these new jumpering cables should be migrated one by one on migration night.

Appendix 2 Scope of Work

PASOMNxxxxxxxxxxx

Appendix 2 Scope of Work

PASOMNxxxxxxxxxxx

Appendix 2 Scope of Work

PASOMNxxxxxxxxxxx

3.2.1 MDF port test


Definition: The MDF port test is divided into four stages. For each site the subcontractor should follow the procedure, provide the test report, update the MDF allocation list and correct the mistakes. Before horizontal MDF duplexing
No. 1 Sub-items For the voice service, make manual test according to the MDF allocation list and make a record for pure voice service, on horizontal MDF(100% port) for voice over broadband service, on vertical and horizontal

Prerequisite
Omantel already provide the MDF allocation list(including vertical and horizontal MDF) information, including telephone number, MDF port location, port attribute, etc.

Appendix 2 Scope of Work MDF(100% port) For the broadband service, make a sample test on vertical MDF(10% port) and make a record of modem activation rate Check the duplexing port status for each port when doing above test and make a record Feed back the test report to Omantel Check all issues with Omantel and update the MDF allocation list if it is wrong Replace the old MDF module if the duplexing port is broken, or just move the subscriber to another spare MDF port, including the jumper cable and subscriber cable

PASOMNxxxxxxxxxxx

Test report template should be confirmed by Omantel and Huawei

Remark: for the ISDN BRA subscribers test, the NT1 and ISDN telephone should be prepared by subcontractor.

After horizontal MDF duplexing, before voice service migration


No. Sub-items

Prerequisite
1. Huawei provide the dialing test tool and test data 2. The test telephone number has been provided by Omantel, which has CLIP function 3. The wiring has been finished by subcontractor 4. The software for dialing test tool has been installed in subcontractor laptop correctly

Execute dialing test with dialing test tool(100% port)

2 3

Provide the test report Correct the MDF issues according to test report

The software of dialing test tool will generate report automatically

After voice service migration

Appendix 2 Scope of Work No. Sub-items Make a sample test manually on vertical MDF port Compare the test result with latest MDF allocation list Correct the MDF issues Prepare the verification report

PASOMNxxxxxxxxxxx

Prerequisite
1. The migration has been finished

2. The sample port list has been confirmed by Omantel and Huawei

2 3 4

Remark: the sample proportion usually is no more than 10%.

During broadband service migration During the broadband service migration, the voice service will also be influenced, so voice service also need be tested.
No. 1 Sub-items For the voice service, make a manually test on vertical MDF port (100% port) Compare the test result with latest MDF allocation list Correct the MDF issues For the broadband service, make a sample test on vertical MDF(10% port) and make a record of modem activation rate Prepare the verification report

Prerequisite

2 3

Remark:
The voice service test should be done during migration, not after migration, all issue should be corrected immediately.

3.2.2 Voice service migration 3.2.2.1


Definition:

New subscriber cables routing and termination

Appendix 2 Scope of Work

PASOMNxxxxxxxxxxx

The subcontractor should finish the new subscriber cables routing and termination in existing MDF blocks of exchange side according to new port mapping table.
No. Sub-items Route the new subscriber cables to the corresponding horizontal MDF blocks Strip the subscriber cable Wire the separated twisted pair cables to corresponding MDF port The port mapping table has already been provided by Huawei.

Prerequisite
1. The new subscriber cables have already been laid on MDF rack and marker is correctly marked. 2. The port mapping table has already been provided by Huawei

2 3

Remark: before doing the duplexing, its necessary to check and make sure the new MSAN

cables are not connected to the boards. Pull it out from the board if found connected.

3.2.2.2
Definition:

Migration and rollback

On the migration night, subcontractor should finish the migration as following procedure. If need, also finish the rollback procedure. Migration
No. Sub-items

Prerequisite
1. The new MSAN rack has been installed and data has been configured

Connect the new subscriber cable to the MSAN service board

2. The new subscriber cables have already been laid in MSAN rack and marked correct marker 3. The wiring has been finished and test

Remark: the old subscriber cable of exchange should also be unplugged from old equipment or just plug out the service board, but it is suggested to require Omantel to finish this job, since we do not know other vendors equipment. And they also should make a marker on the cable themselves before they disconnect the cable.

rollback (if need)


No. 1 Sub-items Disconnect the new subscriber cable

Prerequisite
If decide to rollback by Omantel and Huawei after

Appendix 2 Scope of Work from the MSAN service board sample test

PASOMNxxxxxxxxxxx

Remark: the old subscriber cable should also be plugged into exchange and DSLAM or just plug into the service board, but it is suggested to require Omantel to finish this job.

3.2.3 Broadband service migration 3.2.3.1


Definition: This part describes the new jumpering cable routing for broadband service migration preparation. If the horizontal MDF blocks support jumpering cable duplexing, the jumpering cables can be terminated on the migration point of horizontal MDF blocks before migration, but considering the bridge tap issue which will cause the reduction of speed, the jumpering cables termination on the migration point of vertical MDF blocks will be done during migration night.
No. Sub-items Routing new jumpering cables between the migration point of

New jumpering cables routing

Prerequisite

vertical MDF blocks and horizontal MDF blocks


Punch the new jumpering cables on horizontal MDF blocks if it supports jumpering cable duplexing Make a marker on both side of new jumpering cables

The port mapping table has been provide

3.2.3.2
Definition:

Dismantle old exchange subscriber cables

In order to avoid bridge tap issue during broadband service migration, the subscriber cables from old exchange should be dismantled from duplexing point. This step is necessary for the voice over ADSL subscribers. No. 1 2 Sub-items Dismantle the old exchange subscriber cables from duplex point of horizontal MDF block Make a marker on each cable

Prerequisite

Appendix 2 Scope of Work

PASOMNxxxxxxxxxxx

Remarks: there will be a monitoring stage after migration, only when the migration is confirmed successfully, the old cables will be dismantled completely.

3.2.3.3
Definition:

Migration and rollback

On the migration night, subcontractor should finish the migration as following procedure. If need, also finish the rollback procedure. Migration
No. Sub-items If MDF blocks can not support jmpering cable duplexing, please plug out the old jumpering cables on migration point and make a marker on each old cable if MDF blocks can support jumpering cable duplexing, please plug in the isolators at ADSL_in and ADSL_out point, this scenario could be much easier for rollback 1 In case of horizontal MDF block, please plug in the isolators at ADSL_in In case of vertical MDF block, please plug in the isolators at ADSL_out In case of horizontal MDF and vertical MDF, please plug in the isolators at ADSL_in and ADSL_out 1. The new MSAN rack has been installed Punch the new jumpering cables on vertical MDF migration point. 2. Broadband service data has been configured on MSAN and BRAS 3. The cables of voice over ADSL subscribers from old exchange have been dismantled from duplexing point

Prerequisite

Appendix 2 Scope of Work If horizontal MDF migration is not finished in step 3.2.3.1, please finish the new jumpering punching on horizontal MDF

PASOMNxxxxxxxxxxx

Remarks: the jumpering cable should be migrated one by one on migration point, only when the previous jumpering cable test is ok, subcontractor can start to migrate the next jumpering cable

rollback (if need)


No. 1 Sub-items Dismantle the new jumpering cables on the migration point of vertical MDF block and horizontal MDF block According to the migration step, repunch the old jumpering cables on migration point according to the marker on the cable. Or plug out the isolators at ADSL_in and ADSL_out point

Prerequisite

Remark: whether to rollback is decided by Omantel and Huawei after sample test

3.2.4 Old subscriber cables dismantlement


Definition: This part describes the dismantlement of old subscriber cables after migration, including exchange cables and DSLAM cables.
No. 1 Sub-items Dismantle the exchange subscriber cables from MDF rack and lay them in the space of MDF room Dismantle the DSLAM subscriber cables from MDF rack and lay them in the space of MDF room

Prerequisite

3.2.5 Old jumpering cables dismantlement


Definition:

Appendix 2 Scope of Work

PASOMNxxxxxxxxxxx

This part describes the dismantlement of old jumpering cables after migrations, including the jumpering cables between vertical MDF and horizontal MDF and the jumpering cables between old exchange and old DSLAM.
No. Sub-items Dismantle the old jumpering cables 1

Prerequisite

between vertical MDF and horizontal MDF


Dismantle the old jumpering cables

between old exchange and old DSLAM

3.2.6 Daily maintenance


Definition: This part describes the daily maintenance work before Huawei gets PAC. There could be some issues related to MDF after migration, such as wrong connection, short of connection. Subcontractor should support Omantel to handle these issues when get request from Omantel or Huawei.
No. 1 2 Sub-items Support Omantel to solve MDF issues remotely or on-site Update the MDF allocation list if necessary

Prerequisite

3.3

Jumpering cable migration gradually scenario

In case of both vertical MDF and horizontal MDF does not support duplexing, but new MDF block space is available (or there are enough spare horizontal MDF blocks), this method could be proposed, because the voice service and broadband service can be migrated together.

Appendix 2 Scope of Work

PASOMNxxxxxxxxxxx

Appendix 2 Scope of Work

PASOMNxxxxxxxxxxx

3.3.1 MDF port test


Definition: The MDF port test is divided into two stages under this scenario: before migration and during migration. For each site the subcontractor should follow the procedure, provide the test report, update the MDF allocation list and correct the mistakes. before migration
No. 1 Sub-items For the voice service, make manual test on vertical MDF(100% port) according to the MDF allocation list For the broadband service, make a sample test on vertical MDF(10% port) and make a record of modem activation rate Feed back the test report to Omantel Check all issues with Omantel and update the MDF allocation list if it is Test report template should be confirmed by Omantel and Huawei

Prerequisite
Omantel already provide the MDF allocation list information, including telephone number, MDF port location, port attribute, etc.

3 4

Appendix 2 Scope of Work wrong

PASOMNxxxxxxxxxxx

Remark: for the ISDN BRA subscribers test, the NT1 and ISDN telephone should be prepared by subcontractor.

During migration
No. Sub-items For the voice service, execute dialing test on vertical MDF manually(100% port) Compare the test result with latest MDF allocation list Correct the MDF issues For the broadband service, make a sample test on vertical MDF(10% port) and make a record of modem activation rate Prepare the verification report

Prerequisite
1. The subscriber data has been configured on MSAN and NGN by Huawei 2. The wiring has been finished by subcontractor

2 3

Remarks: the voice service test should be done during migration, not after migration, all issue should be corrected immediately.

3.3.2 New subscriber cables routing and termination


Definition: The subcontractor should finish the new subscriber cables routing and termination in new MDF blocks of exchange side according to port mapping table.
No. Sub-items

Prerequisite
1. The new subscriber cables have already been laid on MDF rack and marker is correctly marked. 2. The port mapping table has already been provided by Huawei.

Route the new subscriber cables into the new horizontal MDF blocks

2 3

Strip the subscriber cable Wire the separated twisted pair cables to corresponding MDF port The port mapping table has already been provided by Huawei.

Appendix 2 Scope of Work

PASOMNxxxxxxxxxxx

3.3.3 New jumpering cables routing


Definition: New jumpering cables between vertical MDF and new horizontal MDF should be routed before migration.
No. Sub-items Routing new jumpering cables between vertical MDF and new

Prerequisite
New horizontal MDF has been installed

horizontal MDF
2 3 Terminate the new jumpering cables on new horizontal MDF side Make a marker for each cable on vertical MDF side

3.3.4 Migration and rollback


Definition: On the migration night, subcontractor should finish the migration as following procedure. If need, also finish the rollback procedure. Migration
No. 1 Sub-items Dismantle the old jumpering cables at migration point on vertical MDF blocks Make a marker for dismantled jumpering cables on vertical MDF 1. The MSAN and NGN data has been configured 3 Punch the new jumpering cables on migration point on vertical MDF blocks 2. The new jumpering cables have already been laid at the side of migration point and with correct marker

Prerequisite

Remarks: the jumpering cable should be migrated one by one, only when the previous jumpering cable test is ok, subcontractor can start to migrate the next jumpering cable

Appendix 2 Scope of Work

PASOMNxxxxxxxxxxx

rollback (if need)


No. 1 Sub-items Dismantle new jumpering cables on the migration point Punch the old jumpering cable back to the migration point according to the marker

Prerequisite

3.3.5 Old subscriber cables dismantlement


Definition: This part describes the dismantlement of old subscriber cables after migration, including exchange cables and DSLAM cables.
No. 1 Sub-items Dismantle the exchange subscriber cables from MDF rack and lay them in the space of MDF room Dismantle the DSLAM subscriber cables from MDF rack and lay them in the space of MDF room

Prerequisite

3.3.6 Old jumpering cables dismantlement


Definition: This part describes the dismantlement of old jumpering cables after migrations, including the jumpering cables between vertical MDF and old horizontal MDF and between old exchange and old DSLAM.
No. Sub-items Dismantle the old jumpering cables 1

Prerequisite

between vertical MDF and old horizontal MDF


Dismantle the old jumpering cables

between old exchange and old DSLAM

Appendix 2 Scope of Work

PASOMNxxxxxxxxxxx

3.3.7 Daily maintenance


Definition: This part describes the daily maintenance work before Huawei gets PAC. There could be some issues related to MDF after migration, such as wrong connection, short of connection. Subcontractor should support Omantel to handle these issues when get request from Omantel or Huawei.
No. 1 2 3 Sub-items Support Omantel to solve MDF issues remotely or on-site Update the MDF allocation list Feed back the update information

Prerequisite

3.4

MSAN cable and jumpering cable migration gradually scenario

If horizontal MDF do not support duplexing and new MDF block space is not available, this solution could be the only choice.

Appendix 2 Scope of Work

PASOMNxxxxxxxxxxx

Appendix 2 Scope of Work

PASOMNxxxxxxxxxxx

Appendix 2 Scope of Work

PASOMNxxxxxxxxxxx

Appendix 2 Scope of Work

PASOMNxxxxxxxxxxx

3.4.1 MDF port test


Definition: The MDF port test is divided into three stages under this scenario. For each site the subcontractor should follow the procedure, provide the test report, update the MDF allocation list and correct the mistakes. Before migration
No. 1 Sub-items For the voice service, make manual test according to the MDF allocation list and make a record for pure voice service, on horizontal MDF(100% port) for voice over broadband service, on vertical and horizontal

Prerequisite
Omantel already provide the MDF allocation list(including vertical and horizontal MDF) information, including telephone number, MDF port location, port attribute, etc.

Appendix 2 Scope of Work MDF(100% port) For the broadband service, make a sample test on vertical MDF(10% port) and make a record of modem activation rate Feed back the test report to Omantel Check all issues with Omantel and update the MDF allocation list if it is wrong

PASOMNxxxxxxxxxxx

Test report template should be confirmed by Omantel and Huawei

Remark: for the ISDN BRA subscribers test, the NT1 and ISDN telephone should be prepared by subcontractor.

During voice migration


No. Sub-items Execute dialing test on vertical MDF manually(100% port) Correct the MDF issues Provide the test report Huawei provide test report template

Prerequisite
1. The subscriber data has been configured on MSAN and NGN by Huawei 2. The wiring has been finished by subcontractor

2 3

Remarks: the test should be done during migration, not after migration, all issue should be corrected immediately.

During broadband service migration During the broadband service migration, the voice service will also be influenced, so voice service also need be tested.
No. 1 Sub-items For the voice service, make a manually test on vertical MDF port (100% port) Compare the test result with latest MDF allocation list Correct the MDF issues

Prerequisite

2 3

Appendix 2 Scope of Work For the broadband service, make a sample test on vertical MDF(10% port) and make a record of modem activation rate Prepare the verification report

PASOMNxxxxxxxxxxx

Remark: the voice service test should be done during migration, not after migration, all issue should be
corrected immediately.

3.4.2 Voice service migration 3.4.2.1 New subscriber cables routing


Definition: The subcontractor should finish the new subscriber cables routing in horizontal MDF blocks according to port mapping table before voice migration.
No. Sub-items

Prerequisite
1. The new subscriber cables have already been laid on MDF rack and marker is correctly marked. 2. The port mapping table has already been provided by Huawei.

Route the new subscriber cables into the horizontal MDF blocks

2 3

Strip the subscriber cable Make a marker on each twist pairs

3.4.2.2 Migration and rollback


Definition: On the migration night, subcontractor should finish the migration as following procedure. If need, also finish the rollback procedure. Migration
No. 1 2 Sub-items Dismantle the old subscriber cable and make a marker on each twist pairs Punch new twist pairs on migration point according to the marker 1. The new MSAN has been installed and data has

Prerequisite

Appendix 2 Scope of Work

PASOMNxxxxxxxxxxx

been configured on MSAN and NGN 2. The MSAN cable has been connected to MSAN 3. The port test has been finished

rollback (if need)


No. 1 Sub-items Dismantle the new subscriber cables Punch the old subscriber cable back to the migration point according to the marker

Prerequisite
If decide to rollback by Omantel and Huawei after sample test

3.4.3 Broadband service migration 3.4.3.1 New jumpering cables routing


Definition: New jumpering cables between vertical MDF and horizontal MDF should be routed before broadband service migration. If the horizontal MDF blocks support jumpering cable duplexing, the jumpering cables can be terminated on the migration point of horizontal MDF blocks before migration.
No. 1 Sub-items Routing new jumpering cables between the migration point on

Prerequisite
The port mapping table has been provide

vertical MDF and horizontal MDF


2 Punch the new jumpering cables on horizontal MDF blocks if it supports jumpering cable duplexing Make a marker on both side of new jumpering cables

3.4.3.2 Migration and rollback


Definition:

Appendix 2 Scope of Work

PASOMNxxxxxxxxxxx

On the migration night, subcontractor should finish the migration as following procedure. If need, also finish the rollback procedure. Migration
No. Sub-items If MDF blocks can not support jmpering cable duplexing, please plug out the old jumpering cables on migration point and make a marker on each twist pairs if MDF blocks can support jumpering cable duplexing, please plug in the isolators at ADSL_in and ADSL_out point, this scenario could be much easier for rollback 1 In case of the horizontal MDF block, please plug in the isolators at ADSL_in In case of the vertical MDF block, please plug in the isolators at ADSL_out In case of horizontal MDF and vertical MDF, please plug in the isolators at ADSL_in and ADSL_out 1. The new MSAN rack has been installed 2 Punch the new jumpering cables on vertical MDF migration point If horizontal MDF migration is not finished in step 3.4.3.1, please finish the new jumpering punching on horizontal MDF 2. Broadband service data has been configured on MSAN and BRAS

Prerequisite

Remarks: the jumpering cable should be migrated one by one on migration point, only when the previous jumpering cable test is ok, subcontractor can start to migrate the next jumpering cable

rollback (if need)


No. Sub-items

Prerequisite

Appendix 2 Scope of Work Dismantle the new jumpering cables on the migration point of vertical MDF block and horizontal MDF block According to the migration step, repunch the old jumpering cables on migration point according to the marker on the cable. Or plug out the isolators at ADSL_in and ADSL_out point

PASOMNxxxxxxxxxxx

Remark: whether to rollback is decided by Omantel and Huawei after sample test

3.4.4 Old subscriber cables dismantlement


Definition: This part describes the dismantlement of old subscriber cables after migration, including exchange cables and DSLAM cables.
No. 1 Sub-items Dismantle the exchange subscriber cables from MDF rack and lay them in the space of MDF room Dismantle the DSLAM subscriber cables from MDF rack and lay them in the space of MDF room

Prerequisite

3.4.5 Old jumpering cables dismantlement


Definition: This part describes the dismantlement of old jumpering cables after migrations, including the jumpering cables between vertical MDF and horizontal MDF and the jumpering cables between old exchange and old DSLAM.
No. Sub-items Dismantle the old jumpering cables 1

Prerequisite

between vertical MDF and horizontal MDF


Dismantle the old jumpering cables

between old exchange and old

Appendix 2 Scope of Work

PASOMNxxxxxxxxxxx

DSLAM

3.4.6 Daily maintenance


Definition: This part describes the daily maintenance work before Huawei gets PAC. There could be some issues related to MDF after migration, such as wrong connection, short of connection. Subcontractor should support Omantel to handle these issues when get request from Omantel or Huawei.
No. 1 2 3 Sub-items Support Omantel to solve MDF issues remotely or on-site Update the MDF allocation list Feed back the update information

Prerequisite

3.5

DDF migration

This part describes the DDF migration scenario of PRA subscriber. If the PBX is connected to old device through E1 cable, then the migration should be finished on DDF. If the PBX is connected to old device through twisted pairs, the migration follow the normal PSTN migration procedure. The PRA service test after migration should be done by Huawei and Omantel.

3.5.1 Migration and rollback


Definition: This part describes the DDF migration.
No. 1 Sub-items Plug out the old E1 cables from DDF and make a marker for rollback 1. The new E1 cables have already been laid on DDF rack and marker is correctly marked. 2 Plug in the new E1 cables to DDF 2. The new E1 port mapping table has already been provided by Huawei.

Prerequisite

Appendix 2 Scope of Work

PASOMNxxxxxxxxxxx

3.5.2 Old E1 cables dismantlement


Definition: This part describes the dismantlement of old E1 cables after migration.
No. 1 Sub-items Dismantle the E1 cables from DDF rack and lay them in the space of DDF room

Prerequisite

4 Definitions
HUAWEI Subcontractor PAC MDF CLIP MSAN DDF PSTN DSLAM ISDN NGN ADSL BRAS BRA PRA HUAWEI Tech. Investments Oman Co., Ltd. Contractor assigned by HUAWEI Primary Acceptance Certification Main Distribution Frame Calling Cable Identification Presentation Multi-service Access Node Digital Distribution Frame Public Switched Telephone Network Digital Subscriber Line Access Multiplexer Integrated Services Digital Network Next Generation Network Asymmetric Digital Subscriber Line Broadband Remote Access Server Basic Rate Access Primary Rate Access