Escolar Documentos
Profissional Documentos
Cultura Documentos
D
riven by the emerging policy and key issues for designing, implementing
requirements of lenders, and operating an external monitoring
heightened public concern, and mechanism for complex projects. The
the scrutiny of civil society organizations, objectivity and technical expertise of the
Lessons of Experience
the market is increasingly demanding that external monitor can add value to a project
companies adopt responsible and by increasing trust and accountability
accountable environmental and social between the sponsor and key project
practices. To assist in managing these risks, stakeholders including lenders, project-
lenders and project sponsors pursuing affected communities, civil society
complex projects in emerging markets may organizations, and government regulators.
benefit from the use of an external monitor.
The role of the external monitor is to provide To highlight the practical challenges and
an independent, impartial, and transparent value of the external monitoring mechanism,
record of the sponsor's compliance with the the publication draws illustrative examples
project's environmental and social from the experiences of IFC during the
commitments. Chad-Cameroon pipeline project. In 2001,
IFC required an external monitoring role for
A number of challenging project investment the Chad-Cameroon project and appointed
conditions may signal the need to consider D'Appolonia S.p.A., a consulting firm from
use of an external monitor, including, but Italy, to form the External Compliance
1
not limited to, projects involving: Monitoring Group (ECMG). While the scale
» multiple public and private sector and complexity of the external monitoring
partners for the Chad-Cameroon project is not
» highly visible sectors such as natural necessarily indicative of the level of effort
resource extraction and resources that would be needed on all
» significant population resettlement complex projects, these lessons are a
» indigenous peoples valuable source of practical experience with
» biodiversity and sensitive habitats external monitoring. This publication has
» complex project benefit sharing, revenue
management, and governance systems
CONTENTS
» weak national regulatory regimes.
D'Appolonia, S.p.A.
Monitoring is the sponsor's primary means for
tracking and evaluating progress toward the
implementation of commitments designed to
avoid or mitigate the environmental and social
impacts of the project. These actions are Preparation for pipeline welding.
typically specified in the sponsor's
Environmental and Social Management
Program (ESMP). The ESMP details the
procedures and actions necessary to prevent What are the Benefits for
or manage the adverse impacts identified in
the project's social and environmental impact
Project Stakeholders?
assessment. This program is commonly
For lenders, the external monitor is an
implemented by an “Environment and Social
important tool to objectively verify and
Management Unit” (hereafter referred to as the
report on sponsor compliance with
“E & S Unit”) within a sponsor's management
environmental and social conditions of the
structure.
investment agreement during project
development. The financial sustainability of
The role of the external monitor is to provide
a project can be jeopardized if agreed
field-based verification of project activities
environmental and social measures are not
and ensure compliance by the sponsor with
demonstrated to have been credibly
the commitments established in the ESMP.
implemented by the sponsor. Lenders with
On projects with potentially significant
limited in-house environmental and social
environmental and social impacts that are
expertise may benefit from the external
diverse, irreversible, or unprecedented, IFC
monitor's ability to act in part as the “eyes
requires that sponsors retain qualified and
and ears” of the lender, fostering a proactive
experienced external experts to verify their
2 management approach to help the lender
monitoring information.
develop successful projects and avoid
reputational damage and related liabilities.
Funded and logistically supported by the
sponsor, the external monitor acts as an
For project sponsors, the external monitor
impartial layer of monitoring that
increases the sponsor's ability to document,
complements the sponsor’s internal monitoring
manage, and reduce their risk exposure to
systems. In addition, the project may be
environmental and social issues. By providing
subject to additional oversight conducted
additional technical expertise to supplement
directly by the staff of lenders, government
the sponsor's E & S Unit, the external monitor
regulators, and civil society groups.
increases the operational capacity of the
sponsor's management to take timely
actions to improve performance and comply
2
The IFC requirement for external monitoring by qualified experts is
contained in Performance Standard 1, paragraph 24. Full text of with environmental and social commitments.
Performance Standard 1 is available at www.ifc.org/envsocstandards.
The Equator Principles II defines a broadly similar requirement as part of
Principle 9: Independent Monitoring and Reporting. Full text of the Equator
Principles is available at: http://www.equator-principles.com/documents/
Page Two Equator_Principles.pdf
Lessons of Experience | September 2006 | Number 1
D'Appolonia S.p.A
supported by the Consortium, the ECMG serves transparent record
as the external monitoring team responsible for
auditing the implementation of the Consortium's
of the sponsor’s
environmental and social commitments for the compliance with
Chad-Cameroon Oil Pipeline project. Pipeline trenching in Cameroon.
the project’s
environmental
and social
The risk for sponsors whose projects are affected communities, are typically shared by commitments.
associated with poor environmental and the sponsor and various levels of government.
social performance extends beyond
damage to the corporate brand. With respect to project affected communities
Underperforming companies can lose their and civil society groups, the external monitor
license to operate along with the critical provides a team of qualified technical experts
support of project-affected communities. that can directly investigate and report on
Their products and services may incur specific issues of concern for the local
barriers to market entry from consumers and communities in the project area. It provides
regulators, and their ability to raise capital reporting that can be an independent source
from lenders may be constrained. The of information for local communities and
technical expertise of the external NGOs, which in turn serves to foster an
monitor allows sponsors to have atmosphere of trust required for effective
documented, independently verified, and working relationships.
publicly available reports of their actions—a
critical, unbiased record which can be used
to defend against potential allegations of How to Maintain the
poor environmental and social performance.
Independence of the
The benefit of external monitoring for host External Monitor
countries is the availability, at no cost, of an
expert team that provides regular, objective Maintaining impartiality, objectivity, and
monitoring of project compliance with transparency in the eyes of all project
applicable regulations and with other stakeholders is critical to the success of the
environmental and social requirements, as external monitor. However, the reliance of the
agreed with the sponsor at the outset of the external monitor on the financial and logistical
project. The external monitor may be support of the sponsor may create perceptions
particularly useful in helping to coordinate of bias. A number of steps should be taken to
joint technical solutions where responsibilities, proactively reassure project stakeholders as to
such as community health issues in project the independence of the monitor, including:
Page Three
External Monitoring of the Chad-Cameroon Pipeline Project
D'Appolonia S.p.A
operational protocols which define the
relationship of the external monitor to
other project stakeholders and allow the
external monitor to avoid conflicts of
ECMG Public Health Specialist consulting with community healers.
interest.
Page Four
Lessons of Experience | September 2006 | Number 1
D'Appolonia S.p.A
On the Chad-Cameroon project, this flexibility
impartiality,
allowed for the addition of a cultural heritage
expert to the ECMG who helped identify and objectivity, and
mitigate key gaps in the Consortium's
Revegetation of the pipeline right-of-way in the Atlantic Littoral transparency
management of impacts to cultural heritage Forest of Cameroon.
in the eyes of
sites during construction of the pipeline.
Incidents of inadequate management of all project
heritage sites along the pipeline route resulted stakeholders is
in a retroactive non-compliance citation by During construction, the ECMG also added
critical to the
the lenders against the Consortium. Further an ecologist who provided key input into the
incidents that may have resulted in costly management of invasive species and overall success of the
project delays were avoided due to the bio-restoration issues along the pipeline route. external monitor.
dialogue between the ECMG and the Additionally, the presence of a public health
Consortium's E & S Unit, which allowed for the expert on the team played an important role
identification and management of potential in facilitating joint approaches to managing
cultural heritage impacts. the occupational health issues of employees
and the larger community health issues faced
by communities and government authorities.
Page Five
External Monitoring of the Chad-Cameroon Pipeline Project
Page Six
Lessons of Experience | September 2006 | Number 1
D'Appolonia S.p.A
pertaining to the conditions of the ESMP. For
example, field visits by the ECMG highlighted
traffic safety and road dust as significant
impacts of increased project-related
transport activities, which were not fully ECMG close out meeting with officials in Cameroon.
identified in the project design phase and
relevant parts of the ESMP. Although the
Consortium was investigating corrective
actions, the increased focus on the issue acquisition (including resettlement,
provided by the ECMG ensured that the compensation, and livelihood restoration),
Consortium implemented a series of and community health and safety.
transportation safety measures such as
speed controls, community awareness Close out meetings were held at the
raising, convoy management, and road by- conclusion of site visits and involved the
passes, in addition to more effective dust ECMG, the Consortium's E & S Unit,
suppression. government representatives, and the
lenders. The meetings allowed field
Other technical issues that were monitored observations, findings, and preliminary
on site visits included protection of natural conclusions to be presented, and
resources, waste management and pollution information gaps, additional data needs,
prevention, project footprint reinstatement, and factual inaccuracies to be identified.
occupational health and safety, land Site visits by the ECMG were treated as a
“snapshot in time,” consistent with the
periodic frequency of the monitoring
schedule. Additional information received
Lesson 4 — “Direct field
after the site visits was set aside to be
monitoring is an essential task of the
investigated during the next project visit. This
external monitor.”
approach allowed sufficient time for the
Consortium's E & S Unit to react to technical
» The credibility of the external monitor is
dependent on the use of direct field
observations, and to evaluate the need for
verification and the collection of empirical and implement corrective actions in time for
observations. subsequent monitoring visits.
» Sole reliance on secondary sources, such as
reports provided by the sponsor's E & S Unit
and project contractors, should be avoided,
Frequency of Site Visits
and adequate time for field verification
should be planned.
» Close out meetings should be held at the
conclusion of site visits to allow field The frequency of visits by the external
observations and conclusions to be monitor to the project site is normally
presented, and factual inaccuracies to be determined by the likelihood of impacts
identified. predicted to occur at different phases of the
» Successful site visits require extensive logistical
Page Eight support from the sponsor.
Lessons of Experience | September 2006 | Number 1
D'Appolonia S.p.A
For the Chad-Cameroon project, the
monitor plays a
frequency of ECMG site visits was significantly
higher during the construction phase, key role during
because the potential for adverse project transition
environmental and social impacts was Pipeline stringing in the rainforest of Cameroon.
from construction
highest during the pipeline and permanent
facility construction. The ECMG undertook to operation
four project site visits per year during the phases.
construction phase of the project. Once the The transition from construction to operations
pipeline construction was completed in late needs to be carefully planned and
2003 and project completion was achieved implemented by both the sponsor's E & S Unit
in mid-2004, the ECMG schedule changed to and the external monitor. During the last
annual visits as part of the operations phase. semester of the construction phase for the
Additional visits during the operational phase Chad-Cameroon project, the ECMG played
are conducted only as necessary. This a key role in ensuring that transition plans and
reduction in the frequency of monitoring sufficient overlapping of staff and resources
reflects the relative decline in the potential within the Consortium's E & S Unit were in
significance of environmental and social place to maintain satisfactory performance in
issues due to end of the construction phase terms of ESMP compliance. The transition also
and the consequent reduction in the project entailed commensurate changes to the
workforce and related activities. structure of the ECMG including team
reduction, redefinition of key team
specializations, and modification of
monitoring protocols during site visits.
» The frequency of visits by the external During site visits, the external monitor may
monitor to the project site is normally identify a real or potential “non-compliance”
determined by the likelihood of impacts situation, which occurs when either the
predicted to occur at different phases of sponsor's E & S Unit or a project contractor
the project cycle. fails to implement a specific environmental or
» The attention and assistance of the external social commitment contained in the ESMP.
monitor is critical to ensuring a smooth
transition between project phases.
As shown in Figure 1 on the next page, the
» The shift from construction to operations
phases requires restructuring of both the definition of levels of non-compliance
sponsor’s E & S Unit and the external monitor developed for the Chad-Cameroon project
to account for different monitoring and ranged from level 1 (least important) to level 3
implementation requirements for the ESMP (most severe), and each required a set of
that are specific to the operations phase.
Page Nine
External Monitoring of the Chad-Cameroon Pipeline Project
Fig. 1 Example of
Non-Compliance
Classification System
Level 3:
for the Chad-Cameroon
Serious
Project
Impact to an
identified sensitive
resource
Level 2:
Expeditious Action
Required
Could give rise to a serious impact
to an identified sensitive resource
Level 1:
Source: D'Appolonia S.p.A
Early Warning
No significant impact, but not consistent with ESMP
Repeated Level 1-type incidents can escalate to a
Level 2 non-compliance situation
Page Ten
Lessons of Experience | September 2006 | Number 1
The External Monitor and Other Layers of responsible for implementing different
Project Monitoring aspects of the project's ESMP. These
contractors and sub-contractors each had a
monitoring system within their management
On complex projects, the monitoring of ESMP structure, and the Consortium's E & S Unit
commitments typically involves internal interacted with these groups during
monitoring systems of the sponsor and the monitoring activities. The Consortium's E & S
main project contractors, and external Unit assumed overall responsibility for Successful project
monitoring by the lender and government monitoring the social and environmental
monitoring
regulators. Successful project monitoring compliance of contractors and sub-
requires the development and integration of contractors associated with the project. requires the
these multi-layered monitoring systems. For development
the Chad-Cameroon project, the ECMG was Initial site visits by the ECMG, however,
and integration
positioned as an additional observer to demonstrated the limited capacity of sub-
oversee the sponsor’s internal monitoring contractors to implement environmental and of multi-layered
systems and complement the external social commitments, which posed a risk to monitoring
oversight conducted by other project overall ESMP compliance. On subsequent site
systems.
stakeholders. Figure 2 indicates the position of visits, the ECMG did not limit its field
the ECMG in the multi-layer monitoring system monitoring to the Consortium and its main
implemented for the Chad-Cameroon project contractor activities, but also
project. included field verification of sub-contractor
responsibilities in the ESMP.
The internal layers of the monitoring system for
the Chad-Cameroon project consisted of External monitoring on the Chad-Cameroon
environmental and social monitoring project involved both the lenders and
provided by the Consortium and their government regulators. Depending on their
contractor companies. As is typical of capacity, some lenders may use in-house or
complex projects, the Chad-Cameroon contracted environmental and social
pipeline involved numerous contractors and specialists to monitor the implementation of
sub-contractors, each of which was the ESMP. It is important to note that although
E
X Layer 5 Monitoring by IFC/World Bank Staff
T
E
R Layer 4 External Monitoring (ECMG) (Annual visits)
N (Quarterly visits)
A
L
Layer 3 Government Regulatory Monitoring
I
Source: D'Appolonia S.p.A
N
T
Layer 2 Monitoring by the Sponsor’s Environment and Social Management Unit
E
R
N Layer 1 Self-Monitoring by Contractors/Sub-Contractors
A
L
Page Eleven
Independent
External Monitoring
Monitoring
of theon
Chad-Cameroon
the Chad Cameroon
Pipeline
Pipeline
Project
Project
Page Thirteen
External Monitoring of the Chad-Cameroon Pipeline Project
Page Fourteen
Lessons of Experience | September 2006 | Number 1
Conclusion
Market forces are increasingly demanding
that companies take a proactive approach
towards managing the environmental and
social impacts of their projects. This IFC
Lessons of Experience publication has
demonstrated that external monitoring of
D'Appolonia S.p.A
environmental and social commitments can The external
be a powerful resource to help lenders and monitor can be
their project sponsors reduce the risks
an influential tool
inherent to complex projects.
Completed restoration along the pipeline route.
to ensure that
Throughout the publication, the experiences environmental
of the External Compliance Monitoring
and social
Group (ECMG) on the Chad-Cameroon
pipeline project have highlighted the For project affected communities and civil commitments
technical value of an external monitor. This society groups, the external monitor creates a are credibly
value is further enhanced by the external reporting mechanism that acts as an
implemented
monitor's ability to increase the transparency, independent source of information helping to
trust, and accountability between the key reinforce the credibility and trust in the project in the eyes of
project stakeholders. While the decision to sponsor required for successful projects. Host all project
employ an external monitor is related to countries, who often suffer from limited
stakeholders.
the particular scale and complexity of capacity to monitor the project themselves,
environmental and social issues associated receive objective, technical, and publicly
with a project, the business case for external disclosed assurance that the project is
monitoring is based on the monitor's ability to achieving agreed environmental and social
enhance the company's approach to outcomes.
addressing project risk.
Complex projects require companies, lenders,
All project stakeholders stand to benefit from project affected communities, civil society,
the involvement of an external monitoring and governments to work as part of a
mechanism. Project sponsors receive an partnership based on mutual responsibility
objective reporting record of their and trust. The external monitor can be an
performance on environmental and social influential tool to ensure that environmental
measures, which can reinforce the support of and social commitments are credibly
project affected communities and defuse implemented in the eyes of all project
the allegations of external critics. Lenders stakeholders, resulting in projects that are
benefit from an unbiased set of “eyes and economically, socially, and environmentally
ears” to assist them in ensuring project sustainable.
outcomes meet their environmental and
social requirements.
Page Fifteen
External Monitoring of the Chad-Cameroon Pipeline Project
Acknowledgements
“External Monitoring of the Chad-Cameroon Pipeline Project: Lessons of Experience” is the first
in a new publication series prepared by the Environment and Social Development Department
Lessons of Experience
of the IFC for the purposes of internal learning and knowledge sharing with clients and the
wider private sector. The publication was written by an IFC team comprising Christopher
Frankel (Task Manager), Patty Miller and Rosa Orellana, and carried out under the general
direction of Rachel Kyte (Director). Vanessa Manuel was responsible for design and layout.
The authors would also like to thank Mr. Ed Caldwell, Manager of Safety, Health and
Environment for Esso Exploration and Production Chad Inc., for his review and comment
on this publication.
Thanks are also due to the following IFC/World Bank colleagues who reviewed earlier
drafts: Rachel Kyte, Rashad Kaldany, Shahbaz Mavaddat, Richard Caines, Dennis Reyes,
Debra Sequeira, Richard Wyness, Carlos Arias, John Butler, Eric Brusberg, and Eluma Obibuaku.
Disclaimer
The views expressed in this publication are those of its authors and do not necessarily reflect the views of the wider institution.
Some of the information used in this document may come from publicly available sources such as company websites and
publications. The Lessons of Experience series does not represent a commitment by IFC to require projects it finances to take
certain or all of the actions specified in this publication. Instead, any issues arising in an IFC-financed project will be evaluated
and addressed in the context of the particular circumstances of the project.
Page Sixteen