JAYPEE NIGRIE SUPER THERMAL POWER PROJECT, (2 X 660 MW) STEAM TURBINE GENERATORS & AUXILIARIES PACKAGE OWNER : OWNER'S CONSULTANT: J AIPRAKASH LIMITED POWER VENTURES
____ 3
DEVELOPMENT LIMITED
CONSULTANTS
PRIVATE
PS Prepared
SP/VP Checked
VL Approved
25/09/2010 Date
Document No: LT-P000003 Progress Report No-11 Page No- 2 of 103
LARSEN & TOUBRO LIMITED Power Project Management Services, Vadodara JOB NO: T209001
INDEX
SECTION 1 1.1 1.2 1.3 1.4 1.4.1 1.4.2 1.4.3 1.4.4 1.5 1.6 2 2.1 2.1.1 2.1.2 2.1.3 2.1.4 2.1.5 2.1.6 2.2 2.2.1 2.2.2 2.2.3 2.4 2.4.1 2.4.2 Executive Summary Project Details Progress Statistic Major Achievements During The Month S Curves Overall S Curve Engineering S Curve Procurement S Curve S Curve Trend Analysis Areas of Support Required Calendar of Major Events Detail Project Status Engineering Status Engineering Progress Statistics Engineering Progress for The Month Cumulative Major Engineering Completed Till Sep'10 ( Action 2) Summary of Document Approval Status Detail Figures of Engineering Drawings/Documents List of Documents On Which Comments Awaited Procurement Status Procurement Progress Statistics Procurement Progress for The Month Vendor Progress for Major Packages Milestone Status L&T's Plan # Unit 1 L&T's Plan # Unit 2 JAIPRAKASH POWER VENTURES LIMITED CONTENTS PAGE NO. 4 5 6 6-7 8 9 10 11 12 13-14 15 16 17 17 17-21 21-25 26 27 28-31 32 32 32 33-36 37 37 38 Document No: LT-P000003 Progress Report No-11 Page No- 3 of 103
LARSEN & TOUBRO LIMITED Power Project Management Services, Vadodara JOB NO: T209001
2.4.3
39
2.4.4 3 3.2 3.3 4 4.1 4.2 4.2.1 4.2.2 4.3 4.4 4.5
Client Obligation - Commissioning Phase # Unit 1 & 2 Activities Planned For Next Month Engineering Plan Procurement Plan Annexure Document Control Index Procurement Status Ordering Status Manufacturing Status Project WBS Structure, Weightage Principle and Basis of Progress Measurement Primavera Schedule -Level 2 Project Photographs JAIPRAKASH POWER VENTURES LIMITED
40 41 42-44 44 45 46-58 59 60-64 65-68 69-70 71-99 100-103 Document No: LT-P000003 Progress Report No-11 Page No- 4 of 103
LARSEN & TOUBRO LIMITED Power Project Management Services, Vadodara JOB NO: T209001
Project
: 2 x 660 MW Steam Turbine Generators & Auxiliaries Package for Jaypee Nigrie Super Thermal Power Project
Owner
Owner's Consultant: Development Consultants Private Limited, Kolkata EPC Contractor Scope of Work : Larsen & Toubro Limited, : Design, Engineering, Manufacture, Supply, Transportation, Insurance, Erection, Testing, Commissioning, Performance Guarantee Tests for 2x660 MW Steam Turbine Generators & Auxiliaries Project Key Dates : LOI/NTP: - July 23, 2009
Project Completion : Unit 1:- 45 months from NTP (April 22, 2013) Unit 2:- 51 months from NTP (Oct 22, 2013)
LARSEN & TOUBRO LIMITED Power JAIPRAKASH POWER VENTURES LIMITED Project Management Services, Vadodara JOB NO: T209001 2x660 MW Steam Turbine Generators and Auxiliaries Document No: LT-P000003 Progress Report No-11 Page No- 6 of 103
1.2 Progress
S.No
Description
1 2 3
During the Month (%) Sch Sch Actual (Early) (Late) 0.33 0.27 0.39 2.69 0.21 3.23 2.56 0.09 2.92 1.92 0.06 2.37
Cumulative Till Sep (%) Sch Sch Actual (Early) (Late) 5.03 4.01 4.90 20.79 0.51 26.33 19.74 0.29 24.04 18.49 0.06 23.45
1) Kickoff Meeting for Condensate Extraction Pump held with M/s KSB, India at Pune
1.3.2
Engineering:
A) Documents Approved:
1) Calculation for LP Bypass Steam System Sizing (Rev C) - Action 2 2) Crab drawing for 40/10T BFP Bay EOT Crane (Rev A) - Action 2 3) DCD for Piping Stress Analysis (Rev E) - Action 2
- With this Approval, All DCDs have been approved in Action 2
B) Documents Submitted:
1) Single Line Diagram for Generator Circuit (Rev C) 2) Schematic Diagram of Generator Circuit (Rev B) 3) Schematic Diagram of Generator Auxiliaries (Rev B) 4) Condenser Datasheet (Rev D)
LARSEN & TOUBRO LIMITED Power JAIPRAKASH POWER VENTURES LIMITED Project Management Services, Vadodara JOB NO: T209001 2x660 MW Steam Turbine Generators and Auxiliaries Document No: LT-P000003 Progress Report No-11 Page No- 7 of 103
5) Technical Datasheet for HP Closed Feed Water Heater (Rev D), LP Closed Feed Water Heaters (Rev C) and Duplex LP Closed Feed Water Heaters (Rev C)
8) 9)
GA Drawing for 115/15T x 31.20M Span TG Hall D/G EOT Crane (1&2) (Rev D) Crab Sub Assembly for 115/15T x 31.20M Span TG Hall D/G EOT Crane
(1&2) (Rev D)
1.3.3 Procurement:
1) Order Finalized on M/s Siemens , India for Condenser Polishing Unit 2) RFQ for Erection Services released
1) Service bay readiness for EOT crane erection 2) Clearance for insitu condenser 3) Turbine building readiness for STG erection
Note:- Requested date are given with reference to the JPVL's suggestion for adopting insitu erection of condenser (Ref :- LTH-JPVLO-JNSTPP-T209001-10-L-0005, 18th August 2010) Document No: LT-P0LARSEN & TOUBRO LIMITED Power JAIPRAKASH POWER VENTURES LIMITED 00003 Progress Report Project Management Services, Vadodara No-11 JOB NO: T209001 Page No- 8 of 103 2x660 MW Steam Turbine Generators and Auxiliaries
1.4 S - CURVES
LARSEN & TOUBRO LIMITED Power Project Management Services, Vadodara JOB NO: T209001
Ordering of BFP and Drive Turbine for BFP had been delayed which is hampering downstream Engineering There were delay in final issue of Deaerator datasheet because of 'Deaerator sizing criteria' finalization There were delay in sending comments from client side on 1st submission of Datasheets & GAs of Condenser and Heaters which hampered downstream progress of drawing review There is delay in receipt of data regarding TG Building by DCPL/JPVL (Refer Section 1.5) which is causing delay in 3D Modeling and LMTG Engineering There were delay in sending comments from client side on various LMTG documents which caused delay in progress of drawing review
Procurement
As far as cumulative progress is concerned the actual progress is below late curve The cumulative actual progress is 24.66% against scheduled early (27.7%) and late basis (26.3%) of procurement progress respectively Delay reasons are as follows
Ordering of BFP and Drive Turbine for BFP had been delayed which in turn hampering downstream manufacturing progress There were delay in final issue of Datasheets & GAs of Deaerator, Condenser and Heaters which is hampering their downstream product engineering ,sub ordering and other manufacturing activities
Overall
During the reporting period curve is below early curve. The cumulative actual progress is 23.45% against scheduled early (26.3%) & late basis (24%) of overall progress respectively
S.No
1
JAIPRAKASH POWER VENTURES LIMITED LARSEN & TOUBRO LIMITED Power Project Management Services, Vadodara JOB NO: T209001 2x660 MW Steam Turbine Generators and Auxiliaries
Target Date
Remarks
JAIPRAKASH POWER VENTURES LIMITED LARSEN & TOUBRO LIMITED Power Project Management Services, Vadodara JOB NO: T209001 2x660 MW Steam Turbine Generators and
Auxiliaries
DCPL
Immediate
11 nos (I -11 ) of HED documents are pending for approval for more than 30 days
section 2.1.6 for detail list) 6 Approval on LTSL documents (Refer section 2.1.6 for detail list)
DCPL
Immediate
08 nos (I -8)of LTSL documents are pending for approval for more than 30
Approval on KSB (CEP) &,Flowserve (MD & TD BFP) & AIL (EOT) documents
DCPL
Immediate
days -01 no (A-1) of KSB(CEP) -05 nos ( A-3, I-2) Flowserve(MD&TD BFP) -13 nos (A-2 , AIL (EOT)
LARSEN & TOUBRO LIMITED Power Project Management Services, Vadodara JOB NO: T209001
e r
o f
I n t e n t /
N o t i
c e
P r
o c e e d
a t
hi Post LOI meeting with JPVL Initial site visit Contract finalization meeting at JPVL , Delhi Invoice submitted
D e l
for first 5% advance payment Official contract signing & press meet at JPVL, Delhi First 5% Advance payment received Invoice submitted for second 5% advance payment L1 schedule approved Kick off meeting held at L&T Faridabad Layout finalization meeting held at DCPL, Kolkata Contract review meeting at L&T, Vadodara Contract Coordination Procedure finalized @ JPVL,Noida Meeting regarding Project Insurance at JPVL, Noida Technical review meeting with JPVL, DCPL at L&T
d a t e
L O I
Faridabad L2 schedule finalized on Technical review meeting with : JPVL/DCPL at DCPL, Kolkata Technical Co-ordination meeting with JPVL/DCPL at L&T Baroda 0 5 / 0 8 / 2 0 0 9
f i n a l i z a t i o n
Jaypee Nigrie Site Visit by L&T personnel PAC issued from client TCM held with JPVL/DCPL at L&T Faridabad Kick off Meeting for EOT crane with M/s Anupam Cranes, India Kick off Meeting for MDBFP & TDBFP with M/s Flowserve TCM held & 3D Model Review Completed with JPVL / DCPL at L&T, Vadodara Hazira Manufacturing Location Visit by JPVL senior official Kick off Meeting for Condensate Extraction Pump with M/s
1 2
m e e t i n g
/ 0 8 / 2 0 0 9
2 : 0 0 2 6 / 0 8 / 0 3 : 9
: 07/01/10-08/01/10 : 21/01/10
LARSEN & TOUBRO LIMITED Power Project Management Services, Vadodara JOB NO: T209001
PROGRESS WEIGHTAGE
Engineering -75%
-10%
LARSEN & TOUBRO LIMITED Power Project Management Services, Vadodara JOB NO: T209001
Engineering (100%)
During The Month (%) Early Sch (%) Late Sch. (%) Actual (%) 3.3 2.6 3.9 Cumulative Till Sep'10 (%) Early Sch (%) Late Sch. (%) Actual (%) 50.4 40.1 49
2.1.2 Engineering Progress for the Month:A) Documents Approved: Sl No. Document No. Description Rev No Action Cat.
2.0
LTSL-M0-00305
Calculation
Calculation for LP Bypass Steam System Pipe Sizing
3.0
LTSL-M1-00701 LTSL-M1-00702 LTSL-M1-00703
List
List -Pipeline List-Valve Specialty Item List
LARSEN & TOUBRO LIMITED Power Project Management Services, Vadodara JOB NO: T209001
2.0
LMTG-E0-02005 LMTG-E0-02315 LMTG-E0-02102
Generator
Electrical Load List Turbine Generator Terminal & CT Assembly Specification & Schematic Diagram of AVR Cubicle C C A 6 6 6 I I A
Turbine Generator H2 Gas Dryer Outline Turbine Generator Vapour Extractor Outline Turbine Generator Loop Seal Tank Outline
A A A
6 6 6
I I I
1) 2)
D A F A D C
A A A A A A A A
2.0
1) 2)
Deaerator
Data Sheet for Deaerator Painting Scheme for Deaerator
3.0
1) 2) 3) 4)
Heaters
Technical Datasheet for HP closed Feed Water Heaters Technical Datasheet for LP closed Feed Water Heaters
Technical Datasheet for Duplex LP closed Feed Water Heaters C Painting Scheme for Feed Water Heaters A
1) 2) 3)
LMTG-I0-01302 LMTG-M0-01013 LMTG-M0-01014 LMTG-E0-02333 LMTG-E0-02005 LMTG-E0-02011 LMTG-E0-02315 LMTG-E0-02323-02325 LMTG-E0-02326 LMTG-E0-02330-02331 LMTG-E0-02361 LMTG-E0-02362
Drive List for TCS and TPS Utility List for Steam Turbine Electrical Load List for Steam turbine
2.0
1) 2) 3) 4) 5) 6) 7) 8) 9)
Generator
Turbine Generator Foundation Embedded Materials layout (1/4) Electrical Load List Painting Color List (MELCO Portion) Turbine Generator terminal and CT assembly Turbine Generator Auxiliary Equipment Wiring Diagram (3 sheets) Turbine Generator Foundation Conduit arrangement Turbine Generator Method of Mounting ( 2 sheets) Turbine Generator grout retainer arrangement Embedded plate arrangement for neutral cover support JAIPRAKASH POWER VENTURES LIMITED
LARSEN & TOUBRO LIMITED Power Project Management Services, Vadodara JOB NO: T209001
10) 11) 12) 13) 14) 15) 16) 17) 18) 19) 20) 21) 22) 23) 24) 25) 26) 27) 28) 29)
LMTG-E0-02007 LMTG-E0-02016 LMTG-E0-02017 LMTG-E0-02023 LMTG-E0-02031 LMTG-E0-02036 LMTG-E0-02034 LMTG-E0-02302 LMTG-E0-02601 LMTG-E0-02024 LMTG-E0-02025 LMTG-E0-02602 LMTG-E0-02035 LMTG-E0-02807 LMTG-E0-02808 LMTG-E0-02809 LMTG-E0-02810 LMTG-E0-02605 LMTG-E0-02801 LMTG-E0-02802
Single Line diagram Generator Circuit Outline drawing of generator control & synchronization panel Outline drawing of generator Auxiliary panel Assembly drawing of Generator bushing CT terminal box Specification for Motor Local control panel Outline drawing of Direct Current Motor for ST Jacking oil pump (B) Outline drawing of Direct Current Motor for ST Emergency oil pump Turbine Generator H2 & CO2 gas diagram Outline dimensions and unit datasheet of Unit 1 & 2 DC Motor starter Schematic diagram of generator circuit Schematic diagram of generator auxiliaries
C C C C A B B B B B B
A A A I I I I A A A A
Outline dimensions and unit datasheet of Unit 1 & 2 distribution B board B Outline dimension of three phase induction motor for ST turning oil pump Outline dimension of AC Motor for main oil tank vapor extractor C fan(A) Outline dimension of AC Motor for main oil tank vapor extractor C fan(B) Outline dimension of AC Motor for EH oil pump(A) B Outline dimension of AC Motor for EH oil pump(B) General specification for unit 1& 2 distribution board Outline dimension of AC Motor for Turning gear Outline dimension of AC Motor for Auxiliary oil pump B B D D
Outline dimension of AC Motor for Jacking oil pump(A) Outline dimension of AC Motor for Main oil tank oil transfer pump Outline dimension of AC Motor for storage tank oil transfer pump Outline dimension of AC Motor for polishing pump
Outline dimension of AC Motor for main oil tank vapor extractor fan(A) 35) LMTG-E0-02808 Outline dimension of AC Motor for main oil tank vapor extractor fan(B) LARSEN & TOUBRO LIMITED Power JAIPRAKASH POWER VENTURES LIMITED Project Management Services, Vadodara JOB NO: T209001 2x660 MW Steam Turbine Generators and Auxiliaries
Outline dimension of AC Motor for EH oil pump(A) Outline dimension of AC Motor for EH oil pump(B) General specification for unit 1& 2 distribution board
B B B
I I I
2.1.3 Cumulative Major Engineering Completed Till Sep'10 (Action-2) SL No. Drawing/Document No LTSL Drawings/Documents 1.0 Design Criteria Documents
1) 2) LTSL-M0-00102 LTSL-M0-00101
Description
DCD - Feed Water System DCD - Condensate System JAIPRAKASH POWER VENTURES LIMITED Document No: LT-P000003 Progress Report
3) LTSL-M0-00105 4) LTSL-M0-00103 5) LTSL-M0-00104 6) LTSL-M0-00107 7) LTSL-M0-00109 8) LTSL-M0-00113 9) LTSL-E0-00100 10) LTSL-I0-00100 11) LTSL-M0-00108 12) LTSL-M0-00110 13) LTSL-M0-00111 14) LTSL-M0-00112 15) LTSL-I0-00100 16) LTSL-M0-00115
DCD - LP Bypass Steam System DCD - Extraction Steam System DCD - Heaters, Vents, & Drains System DCD - Auxiliary Steam System DCD - Circulating Water System DCD - Service Water Distribution System DCD - Electrical System DCD - C&I System DCD - Condenser Air Removal System DCD - Closed Cooling Water System DCD - DM Water Distribution System DCD - Instrument Air / Service Air Distribution System DCD-Condensate Polishing Unit DCD-Piping Stress Analysis Calc - Feed Water Pump Sizing Calc - Condensate Extraction Pump Sizing Calc - Feed Water System Pipe Sizing Calc - Heater Drain & Vent Pipe Sizing Calc - Condenser Air Removal System Calc - Circulating Water System Pipe Sizing Calc - DM Water distribution system Pipe Sizing Calc - Condensate System Pipe Sizing Calc - LP Bypass Steam System Pipe Sizing P&ID - Index, Legends & Symbols JAIPRAKASH POWER VENTURES LIMITED Document No: LT-P000003 Progress Report No-11 Page No- 23 of 103
2.0
Calculations
1) LTSL-M0-00333 2) LTSL-M0-00332 3) LTSL-M0-00302 4) LTSL-M0-00304 5) LTSL-M0-00308 6) LTSL-M0-00309 7) LTSL-M0-00311 8) LTSL-M0-00301 9) LTSL-M0-00305
3.0
P&IDs
1) LTSL-M1-00200
LARSEN & TOUBRO LIMITED Power Project Management Services, Vadodara JOB NO: T209001
2) LTSL-M1-00208 3) LTSL-M1-00205 4) LTSL-M1-00207 5) LTSL-M1-00201 6) LTSL-M1-00202 7) LTSL-M1-00203 8) LTSL-M1-00204 9) LTSL-M1-00209 10) LTSL-M1-00211
P&ID - Condenser Air Removal System P&ID - LP Bypass steam System P&ID - Auxiliary Steam System P&ID-Condensate System P&ID - Feed Water System P&ID - Extraction Steam System P&ID - Heaters, Vents, & Drains System P&ID - Circulating Water System P&ID - DM Water Distribution System
P&ID - Service Water Distribution System P&ID - Closed Cooling Water System P&ID - Instrument Air / Service Air Distribution System
2.0
1) 2)
Generator
LMTG-E0-02016 LMTG-E0-02017
2.0
Condenser
LARSEN & TOUBRO LIMITED Power Project Management Services, Vadodara JOB NO: T209001
1) LT-M0-03000-DS 2) LT-QO-03000
3.0
Deareator
1) LT-QO-03003
12) LT-QO-00014 13) LT-Q0-00010 14) LT-Q0-00020 15) LT-Q0-00019 16) LT-Q0-00021 17) LT-Q0-00015 LARSEN & TOUBRO LIMITED Power Project Management Services, Vadodara JOB NO: T209001
QAP - Plate Heat Exchanger QAP - EOT Crane QAP - Online tube Cleaning System QAP - Vibration Monitoring System QAP - Control Valve QAP - LP Bypass Valve JAIPRAKASH POWER VENTURES LIMITED Document No: LT-P000003 Progress Report No-11 Page No- 25 of 103
QAP - HP Heater three way Bypass Valve QAP - Butterfly Valve QAP - Rubber Expansion Joint QAP - Metallic Expansion Joint QAP - Steam Turbine QAP-Control Valves
SR. NO. 1 2
PAGE: - 26 of 103
MELCO (Generator)
GRAND TOTAL =
8 QAP APP. INFO. TOTAL
557
24 0 24
295
24 0 24
133
23 0 23
72
1 0 1
90
0 0 0
LARSEN & TOUBRO LIMITED Power Project Mangement Services, Vadodara 3.1.3 SU MMARY STATUS OF ENGINEERING
S.NO DOCUMENT NAME
JAIPRAKASH POWER VENTURES LIMITED 2 X 660 MW Steam Turbine Generator & Auxiliaries JCUMENTS TOTAL NO OF DOCUMENTS 13 3 16 2 18 20 7 6 13 0 15 15 5 56 61 27 98 125 14 71 85 68 116 184 15 61 76 2 85 87 5 149 154 2 46 48 106
DRAWINGS /DO
DOCUMENT CATEGORY (A/I) A I Total
DRAWINGS RELEASED DURING THE MONTH CUMULATIVE 1st SUB >1st SUB FINAL SUB 1st SUB >1st SUB 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 0 1 1 0 4 4 0 8 8 3 1 4 1 20 0 4 2 0 0 0 0 8 0 1 1 0 4 4 2 0 2 0 2 2 0 0 0 2 7 9 0 4 4 6 29 35 6 4 10 1 19 20 0 0 0 0 0 0 13 0 0 0 0 0 0 0 1 1 0 0 0 0 0 0 0 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 13 3 16 2 17 19 7 6 13 0 10 10 1 2 3 23 38 61 8 22 30 42 60 102 13 27 40 2 60 62 5 2 7 2 1 3 72 13 3 16 2 11 13 7 6 13 0 5 5 1 0 1 23 25 48 7 11 18 27 27 54 9 8 17 0 0 0 0 0 0 0 0 0 43
REMARKS CODE6
A 1.1
0 0 0 0 1 1 0 1 1 0 0 0 1 0 1 1 2 3 2 5 7 1 5 6 2 0 2 0 2 2 0 0 0 0 0 0 5
0 0 0 0 6 6 0 1 1 0 2 2 0 0 0 0 9 9 5 0 5 18 10 28 1 22 23 2 5 7 0 0 0 0 0 0 26
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 2 0 0 0 0 20 20 2 0 2 0 0 0 3
0 0 0 0 2 2 0 0 0 0 7 7 0 0 0 0 9 9 0 13 13 14 21 35 0 2 2 0 9 9 0 0 0 0 0 0 14
1.2
Calculation
A I Total
1.3
P&IDs
A I Total
1.4
Lists
A I Total
1.5
A I Total
Subtotal LTSL
A I Total
C 1
A I Total
MELCO (Generator)
A I Total
A I Total
A I Total
A I Total
A I Total
35 43 8 36 44
56 69 15 63 78
0 0 0 1 1
46 89 66 71 137
0 0 10 4 14
0 11 33 12 45
12 17 6 14
37 63 26 46
21 24 3 21
45 59 14 54 68
B 1
A I Total
24 0 24
0 0 0
0 0 0
0 0 0
24 0 24
24 0 24
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
Note
For Detail Enginerring list refer annexure 5.1 'Overall Engineering Status'
LARSEN & TOUBRO LIMITED Power Project Management Services, Vadodara. JOB NO: - T209001
Document No:- LT-P000003 Progress Report No: - 11 Annexure No: Page No:- 28 of 103
2.1.6 List of Documents On Which Comments Awaited From Client For More Than 30 Days
Approval Category Sr No. Drawing No 1 LMTG-P1-01003 2 LMTG-M0-01020 3 4 5 6 LMTG-E0-02018 LMTG-E0-02019 LMTG-E0-02021 LMTG-E0-02022 Description Heat Balance Diagram Control and Lubricating oil System Diagram Outline Drawing of generator Seal Oil Control Panel Outline Drawing of Generator Stator Coil Cooling Water Control Panel Arrengement Drawing of Generator Seal Oil Control Panel Arrengement Drawing of Generator Stator Coil Cooling Water Control Panel LOGIC DIAGRAM OF GENERATOR AUXILIARIES Data sheet of 115/15 T TG Hall EOT Crane (Double Girder) Data sheet of 40/10 T BFP Bay EOT Crane (Double Girder) Complete Grout Pump Datasheet Motor Sizing Calculation Complete Grout Pump Datasheet CEP GA drawing common for pump & motor access Description Calculation for Closed Cooling Water System Pipe Sizing 24 V DC Battery & Battery Charger Sizing calculation List - Equipment List - Instrument Calculation for Service Water Distribution System Pipe Sizing Interface/terminal point list Calculation for Extraction Steam System Pipe Sizing Calculation for Closed Cooling Water Pump Sizing Complete Mechanical Design Calculation for HPH-8A/8B Complete Mechanical Design Calculation for HPH-7A/7B Complete Mechanical Design Calculation for HPH-6A/6B Complete Mechanical Design Calculation for LP4 Complete Mechanical Design Calculation for LP3 Complete Mechanical Design Calculation for Duple Heater Rev No D B B B B B Category A A A A A A L&T DTN No. DT0153 DT0153 DT0156 DT0155 DT0155 DT0155 DTN Date 1-Jun-10 1-Jun-10 4-Jun-10 4-Jun-10 4-Jun-10 4-Jun-10
7 8 9 10 11 12 13
A C A B B B A
A A A A A A A
Information Category Sr No. Drawing No 1 LTSL-M0-00310 2 3 4 5 6 7 8 9 10 11 12 13 14 LTSL-E0-00301 LTSL-M1-00700 LTSL-I1-00700 LTSL-M0-00313 LTSL-M1-00704 LTSL-M0-00303 LTSL-M0-00335 LT-M0-03059 LT-M0-03063 LT-M0-03067 LT-M0-03072 LT-M0-03076 LT-M0-03081
Rev No A A 0 A C B B B C B B B B B
Category
L&T DTN No. DT0136 DT0128 DT0206 DT0208 DT0232 DT0236 DT0219 DT0219 DT0180 DT0180 DT0181 DT0181 DT0179 DT0179
DTN Date 23-Apr-10 23-Apr-10 23-Jul-10 23-Jul-10 13-Aug-10 23-Apr-10 11-Aug-10 11-Aug-10 14-Jul-10 14-Jul-10 14-Jul-10 14-Jul-10 14-Jul-10 14-Jul-10
LARSEN & TOUBRO LIMITED Power Project Management Services, Vadodara. JOB NO: - T209001
Document No:- LT-P000003 Progress Report No: - 11 Annexure No: Page No:- 29 of 103
2.1.6 List of Documents On Which Comments Awaited From Client For More Than 30 Days
15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46
LT-M0-03003 LT-M0-03016 LT-M0-03018 LT-M0-03022 LT-M0-03015 LMTG-P0-01025 LMTG-M0-01016 LMTG-E0-02316 LMTG-E0-02338 LMTG-E0-02339 LMTG-E0-02340 LMTG-E0-02341 LMTG-E0-02342 LMTG-E0-02343 LMTG-E0-02344 LMTG-E0-02345 LMTG-E0-02346 LMTG-E0-02347 LMTG-E0-02348 LMTG-E0-02349 LMTG-E0-02350 LMTG-E0-02351 LMTG-E0-02352 LMTG-E0-02353 LMTG-E0-02354 LMTG-E0-02355 LMTG-E0-02356 LMTG-P0-01026 LMTG-E0-02004 LMTG-E0-02012 LMTG-E0-02327 LMTG-M0-01022
Loading Data for Condenser Procedure for Surface preparation & Painting Hydrostatic Test Procedure Post Weld Heat Treatment Procedure WPS & PQR Steam Purity Recommendation Valve List Turbine Generator CT Terminal Box & Coduits Arrengement Turbine Generator Exhaust Piping (1 / 2) Turbine Generator Exhaust Piping (2 / 2) Turbine Generator Cooling Water Piping (1 / 5) Turbine Generator Cooling Water Piping (2 / 5) Turbine Generator Cooling Water Piping (3 / 5) Turbine Generator Cooling Water Piping (4 / 5) Turbine Generator Cooling Water Piping (5 / 5) Turbine Generator Gas & Seal Oil Piping (1 / 10) Turbine Generator Gas & Seal Oil Piping (2 / 10) Turbine Generator Gas & Seal Oil Piping (3 / 10) Turbine Generator Gas & Seal Oil Piping (4 / 10) Turbine Generator Gas & Seal Oil Piping (5 / 10) Turbine Generator Gas & Seal Oil Piping (6 / 10) Turbine Generator Gas & Seal Oil Piping (7 / 10) Turbine Generator Gas & Seal Oil Piping (8 / 10) Turbine Generator Gas & Seal Oil Piping (9 / 10) Turbine Generator Gas & Seal Oil Piping (10 / 10) Turbine Generator Gas Feed Piping (1 / 2) Turbine Generator Gas Feed Piping (2 / 2) Performance Curves of STG Utility List Painting Procedure (MELCO PORTION) Turbine Generator Foundation Bolt Arrengement Plan for Arrangement of Foundation Bolt C B B A A A A A A A A A A A A A A A A A A A A A A A B B B
0 DT-0237 DT-0237 DT-0237 DT-0237 DT0090 DT0121 DT0201 DT0201 DT0201 DT0201 DT0201 DT0201 DT0201 DT0201 DT0201 DT0201 DT0201 DT0201 DT0201 DT0201 DT0201 DT0201 DT0201 DT0201 DT0201 DT0201 DT0195 DT0154 DT0159 DT0096 C JAIPRAKASH POWER VENTURES LIMITED DT0166
DT0143
4-Jan10 20-Aug-10 20-Aug-10 20-Aug-10 20-Aug-10 22-Feb-10 16-Apr-10 20-Jul-10 20-Jul-10 20-Jul-10 20-Jul-10 20-Jul-10 20-Jul-10 20-Jul-10 20-Jul-10 20-Jul-10 20-Jul-10 20-Jul-10 20-Jul-10 20-Jul-10 20-Jul-10 20-Jul-10 20-Jul-10 20-Jul-10 20-Jul-10 20-Jul-10 20-Jul-10 19-Jul-10 1-Jun-10 8-Jun-10 16-Mar-10 21-Jun-10
LARSEN & TOUBRO LIMITED Power Project Management Services, Vadodara. JOB NO: - T209001
Document No:- LT-P000003 Progress Report No: - 11 Annexure No: Page No:- 30 of 103
2.1.6 List of Documents On Which Comments Awaited From Client For More Than 30 Days
47 48 49 LMTG-M0-01023 LMTG-M0-01019 LMTG-M0-01008 Plan for Arrangement of Anchor Bolt Turbine Generator Outline TG foundation design criteria C E D DT0166 DT0167 DT0167 21-Jun-10 24-Jun-10 24-Jun-10
50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69
LMTG-P0-01036 LMTG-I0-01308 LMTG-M0-01210 LMTG-M0-01209 LMTG-M0-01206 LMTG-M0-01201 LMTG-M0-01202 LMTG-M0-01205 LMTG-M0-01207 LMTG-E0-02326 LMTG-E0-02038 LMTG-E0-02039 LMTG-E0-02040 LMTG-E0-02357 LMTG-E0-02332 LMTG-E0-02302 LMTG-Q0-02202 LMTG-Q0-02203 LMTG-E0-02309 LMTG-E0-02310
System description for steam turbine Instrument List For Steam Turbine Embedded Metal Plan Around Storage Tank Foundation Of Lube Oil Storage Tank Details Of Embedded Materials Oil Piping And Equipment Arrangement Foundation Of Lubricating Oil Equipment Foundation Embedded Material For Piping Embedded Metal Plan Around Lube Oil Purifier Turbine Generator Foundation Embedded Conduit Layout Electrical Equipment General Arrangment (El.+0.00M) Electrical Equipment General Arrangment (El.+9.00M) Lectrical Equipment General Arrangment (El.+17.00M) Plan Of Scaffolding For Turbine Generator Maintenance Turbine Generator Hydrogen Gas Temperature Control Valve Outline Turbine Generator H2&Co2 Gas Diagram Shop Test And Inspection Procedure For Control Panels Shop Test And Inspection Procedure For Control Panels Turbine Generator Co2 Gas Vaporizer Outline Turbine Generator H2 Gas Pressure/Purity Monitoring Unit Outline Turbine Generator Water Detector Outline Structural calculations for 115/15 T TG Hall crane Mechanism Sizing Calculation for 40/10 T BFP Bay EOT cranes Gantry Rail installation for 40/10 T BFP Bay EOT cranes 40T main hook block assembly 10 T Aux Hook Block Assembly LT Drive wheel assembly LT idle wheel assembly CT Drive wheel assembly CT idle wheel assembly
A A R0 R0 3 4 R2 2 R2 A C C C A A A A A B B
DT0171 DT0213 DT0215 DT0215 DT0215 DT0217 DT0217 DT0217 DT0217 DT0124 DT0177 DT0177 DT0177 DT0201 DT0201 DT0216 DT0218 DT0218 DT0224 DT0224
2-Jul-10 30-Jul-10 2-Aug-10 2-Aug-10 2-Aug-10 7-Aug-10 7-Aug-10 7-Aug-10 7-Aug-10 20-Apr-10 13-Jul-10 13-Jul-10 13-Jul-10 20-Jul-10 26-Jul-10 7-Aug-10 9-Aug-10 9-Aug-10 12-Aug-10 12-Aug-10
70 71 72 73 74 75 76 77 78 79
LMTG-E0-02312 AIL-M0-03231 AIL-M0-03253 AIL-M0-03256 AIL-M0-03258 AIL-M0-03259 AIL-M0-03260 AIL-M0-03261 AIL-M0-03262 AIL-M0-03263
B A A A A A A A A A
DT0224 DT0231 DT0228 DT0241 DT0241 DT0241 DT0241 DT0241 DT0241 DT0241
12-Aug-10 17-Aug-10 13-Aug-10 23-Aug-10 23-Aug-10 23-Aug-10 23-Aug-10 23-Aug-10 23-Aug-10 23-Aug-10 Document No:- LT-P000003 Progress Report No: - 11 Annexure No: Page No:- 31 of 103
2.1.6 List of Documents On Which Comments Awaited From Client For More Than 30 Days
80 81 82 83 AIL-M0-03264 AIL-M0-03280 FPD-C0-03305 FMD-M0-03372 Long travel Machinery Assembly for 40/10 T TGHall EOT crane Crane lubrication Complete Grout General Arrangement Complete Grout General Arrangement A A A A I I I I DT0241 DT0241 235 235 23-Aug-10 23-Aug-10 23-Aug-10 23-Aug-10
Project Management Services, Vadodara JOB NO: T209001 2x660 MW Steam Turbine Generators and Auxiliaries
Order Finalized for CPU on M/s Siemens,India Enquires Floated for the following items a) Erection Services b) LP Valves
Offers Received for the following items:
a) Butterfly Valve
a) Elevators b) OLTCS c) VMS d) DCS e) HP Valve Bid Evaluation completed for Vacuum Pump
LARSEN & TOUBRO LIMITED Power Project Management Services, Vadodara JOB NO: T209001
2)
Condenser
L&T HED
3)
4)
L&T HED
LARSEN & TOUBRO LIMITED Power Project Management Services, Vadodara JOB NO: T209001
Auxiliaries
Sl No 4)
5)
6)
Sl No
Under Finalization Nozzle Flanges Turbine LMTG HIP & LP Ordered Received -> LP-1,LP-2 &HP Rotor Rotor Forging machining in progress HIP Outer Ordered Received ->Stationary & Rotating Casing Casting Blades machining in Ordered Received progress ->HIP casing Stationary and machining started ordinary blade material Ordered In Progress LP inner casing Generators LMTG Ordered In Progress ->Generator Stator Rotor manufacturing in Forging progress Retaining Ordered In Progress Ring Material ->Generator Rotor machining in progress Ordered In Progress Through Bolt Material & Core Bolt Material Ordered In Progress Steel Plate for Generator Stator LARSEN & TOUBRO LIMITED Power JAIPRAKASH POWER VENTURES LIMITED Document No: LT-P0Project Management Services, Vadodara 00003 Progress Report No-11 JOB NO: T209001 Page No- 35 of 103 2x660 MW Steam Turbine Generators and Auxiliaries
->LP-1 ,LP-2 &HP Rotor machining in progress ->Stationary & Rotating blades machining in progress
Equipment
Vendor
Items
Motor Brake Forgings 7) EOT Crane for TG Hall Bay AIL Bearing Wire Rope Spring Buffer Hook Rope Drum Pipe Motor Brake Forgings 8) EOT Crane for BFP AIL Bearing Wire Rope Hook
Ordered Ordered Ordered Ordered Ordered Ordered Ordered Ordered Ordered Ordered Ordered Ordered Ordered Ordered In Progress In Progress In Progress In Progress In Progress In Progress In Progress In Progress In Progress In Progress In Progress In Progress In Progress
Sl No 9)
Ordered In Progress Rope Drum Pipe LARSEN & TOUBRO LIMITED Power JAIPRAKASH POWER VENTURES LIMITED Document No: LT-P0Project Management Services, Vadodara 00003 Progress Report No-11 JOB NO: T209001 Page No- 36 of 103 2x660 MW Steam Turbine Generators and Auxiliaries
Equipment MDBFP
Vendor Flowserve
10)
TDBFP
Flowserve
Seal Booster Pump Gear Box Shaft Material Mechanical Seal Motor
11)
CEP
KSB
LARSEN & TOUBRO LIMITED Power Project Management Services, Vadodara JOB NO: T209001
LARSEN & TOUBRO LIMITED Power Project Management Services, Vadodara JOB NO: T209001
Sr No
MILESTONE DESCRIPTION
MONTH
SCHEDULED DATE
EXPECTED DATE
ACTUAL DATE
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Supply of embedded parts for TG Start of EOT crane erection Receipt of MDBFP at site Commencement of insitu Condenser Erection Receipt of Deaerator at Site Receipt of LP turbine at Site Commencement of TG Erection Receipt of Generator at Site Readiness of TG/C&I system Commissioning MDBFP TG Boxing-up TG oil Flushing Completion Steam blowing completion Completion of Governing System TG on Barring Gear TG Rolling & Synchronization ( On Oil ) TG Rolling & Synchronization ( On Coal ) Completion of Trial Operation of Unit
23 28 32 32 33 35 35 38 44 45 45 45 47 47 47 49 49 51
22-Jun-11 23-Nov-11 22-Mar-12 23-Mar-12 22-Apr-12 22-Jun-12 23-Jun-12 22-Sep-12 22-Mar-13 22-Apr-13 22-Apr-13 22-Apr-13 22-Jun-13 22-Jun-13 22-Jun-13 16-Aug-13 22-Aug-13 22-Oct-13 Document No: LT-P000003 Progress Report No-11 Page No- 39 of 103
LARSEN & TOUBRO LIMITED Power Project Management Services, Vadodara JOB NO: T209001
Sr No.
1
Customer Input
Month Availability of leveled & graded land, water & electricity for site infrastructure (Office, Stores, Workshop & Colony) Readiness of site access road for transportation of heavy eqpt Service bay readiness for EOT crane erection Readiness of foundation/floor @ 9 mtrs Clearance for insitu condenser erection Turbine building readiness for STG erection Readiness of 0 mtr foundations 14
Unit # 1
Sch 22-Sep-10 Actual Month 14
Unit # 2
Sch 22-Sep-10 Actual
2 3 4 5 6 7
16 22 25 26 26 26
22 28 31 32 32 32
(BFPs, CPU ,PHE, etc) Readiness of foundation/floor @ 17 mtrs 9 Readiness of strand jack foundation for generator lifting 10 Readiness of floor @ 31 mtrs ( Deaerator foundation) 11 Main & Service building readiness for Elevator erection 12 Readiness of electrical & instrumentation earth grids 13 Readiness of AC/DC/UPS panel & Battery bank floor 14 Readiness of Control room for DCS & Marshalling panel erection LARSEN & TOUBRO LIMITED Power Project Management Services, Vadodara 8 JOB NO: T209001
28 28 30 32 32 32 33
22-Nov-11 22-Nov-11 21-Jan-12 22- Mar-12 22- Mar-12 22- Mar-12 21-Apr-12
34 34 36 38 38 38 39
22-May-12 22-May-12 22-July-12 22-Sep-12 22-Sep-12 22-Sep-12 21-Oct-12 Document No: LT-P000003 Progress Report No-11 Page No- 40 of 103
Sr No.
1 2 3 4 5 6 7 8 9
Customer Input
Month Readiness of 415V supply for EOT & Elevator Availability of DM water Availability of trained O&M manpower for commissioning etc. Readiness of HVAC system for DCS commissioning Readiness of 415V,3.3 kV,11kV & emergency power supply Readiness of 220V & 24 DC power supply Readiness of fire protection, detection, & alarm system Availability instru & service air 25 34 34 36 36 36 36 36 36 38 41
Unit # 1
Sch 22-Aug-11 22-May-12 22-May-12 21-July-12 21-July-12 21-July-12 21-July-12 21-July-12 21-July-12 22-Sept-12 22-Dec-12 Actual Month 31 40 40 42 42 42 42 42 42 44 47
Unit # 2
Sch 22-Feb-12 22-Nov-12 21-Nov-12 21-Jan-13 21-Jan-13 21-Jan-13 21-Jan-13 21-Jan-13 21-Jan-13 22-Mar-13 22-Jun-13 Document No: LT-P000003 Progress Report No-11 Page No- 41 of 103 Actual
Availability of auxiliary cooling water 10 Availability of condenser cooling water 11 Readiness of GT , UAT, GCB & switchyards LARSEN & TOUBRO LIMITED Power Project Management Services, Vadodara JOB NO: T209001
Auxiliaries
Layout of Terminal Box Steam Purity Recommendation Painting Schedule Dimensions & Weight of Turbine Major Part Arrangement of Embedded Conduit (Turbine Internal) Instrument List for Steam Turbine TCS/TPS I/O List
1) LMTG-E0-02008 Instrument List 2) LMTG-E0-02360 Generator Design Datasheet 3) LMTG-E0-02015 Signal interface list with DCS 4) LMTG-E0-02103 External terminal of AVR Cubicle 5) LMTG-E0-02359 Erection Procedure for Reference Plant (Generator & its Auxiliaries) Document No: LT-P0LARSEN & TOUBRO LIMITED Power JAIPRAKASH POWER VENTURES LIMITED 00003 Progress Report Project Management Services, Vadodara No-11 JOB NO: T209001 Page No- 43 of 103 2x660 MW Steam Turbine Generators and Auxiliaries
TG Hall EOT Crane Data sheet of 115/15 T TG Hall EOT Crane (Double Girder) Mechanism Sizing Calculation for 115/15 T TG Hall EOT cranes Electrical equipment layout in cabin for 115/15 T TG Hall EOT crane Gantry Rail installation for 115/15 T TG Hall EOT cranes General arrangement for PVC shrouded conductor type DSL for 115/15T TG Hall EOT crane 115T main hook block assembly 15 T Aux Hook Block Assembly Long travel Machinery Assembly for 115/15 T TG Hall EOT crane Structural calculations for 115/15 T TG Hall crane Painting procedure Crane lubrication LT Drive wheel assembly LT idle wheel assembly CT Drive wheel assembly CT idle wheel assembly BFP EOT Crane Make of Bought Out Item List Mechanism Sizing Calculation for 40/10 T TG Hall EOT cranes Data sheet of 40/10 T TG Hall EOT Crane (Double Girder) General arrangement for 40/10 T TG Hall EOT crane Crab sub assembly for 40/10T TG Hall EOT crane Gantry Rail installation for 40/10 T TG Hall EOT cranes General arrangement for PVC shrouded conductor type DSL for 40/10T TG Hall EOT crane 115T main hook block assembly
AIL-M0-03208 AIL-M0-03209 AIL-M0-03214 AIL-M0-03231 AIL-M0-03233 AIL-M0-03230 AIL-M0-03210 AIL-M0-03211 AIL-M0-03212 AIL-M0-03213 AIL-M0-03284 AIL-M0-03253 AIL-M0-03251 AIL-M0-03254 AIL-M0-03255 AIL-M0-03256 AIL-M0-03257
8) AIL-M0-03258
9) AIL-M0-03259 15 T Aux Hook Block Assembly 10) AIL-M0-03264 Long travel Machinery Assembly for 40/10 T TG Hall EOT crane 11) AIL-M0-03283 Painting procedure 12) AIL-M0-03260 LT Drive wheel assembly Document No: LT-P0LARSEN & TOUBRO LIMITED Power JAIPRAKASH POWER VENTURES LIMITED 00003 Progress Report Project Management Services, Vadodara No-11 JOB NO: T209001 Page No- 44 of 103 2x660 MW Steam Turbine Generators and Auxiliaries
13) AIL-M0-03261 14) AIL-M0-03262 15) AIL-M0-03263 16) AIL-M0-03280 17) AIL-M0-03281 BFP Drawings /Documents 1.0 1) FPD-M0-03311 2) FPD-Q0-03332 3) FPD-M0-03466 2.0 1) FMD-M0-03311 2) FQD-Q0-03332
LT idle wheel assembly CT Drive wheel assembly CT idle wheel assembly Crane lubrication Structural calculations for 40/10 T TG Hall crane MDBFP Complete Group Pump Performance Performance test procedure for Booster Pump Motor Sizing Calculation TDBFP Complete Group Pump Performance Performance test procedure for Booster Pump
3.2 Procurement Plan Enquires shall be floated for the following items
a) Control Valves
a) b) a) b)
LP Valves Erection Services Vacuum Pump JAIPRAKASH POWER VENTURES LIMITED Document No: LT-P000003 Progress Report No-11 Page No- 45 of 103
SECTION-4 ANNEXURES
LARSEN & TOUBRO LIMITED Power Project Management Services, Vadodara JOB NO: T209001 JAIPRAKASH POWER VENTURES LIMITED 2x660 MW Steam Turbine Generators and Auxiliaries Document No: LT-P000003 Progress Report No-11 Page No- 46 of 103
DOCUMENT NO.: -
LT-P0-00003
PAGES :- 12
DISTRIBUTION OF WTG. POINTS WITHIN ENGINEERING STATUS ANNEXURES BASED ON WBS STRUCTURE ENGINEERING (100%)
% of Overall Project = 10% Total Weightage Points (Per Unit Basis) =100000
BASIC ENGINEERING
35% DESCRIPTION DESIGN CRITERIA DOCUMENTS CALCULATIONS P&IDS PROCUREMENT ASSISTANCE % of Overall Project = Total Weightage Points (Per Unit Basis) = % OF WEIGHTAGE 20% 10% 30% 40% WTG POINTS 7000 3500 10500 14000 3.50% 35000 ANNEXURE NO. ANNEXURE - 4.1 ANNEXURE - 4.1 ANNEXURE - 4.1 ANNEXURE - 4.1
DETAIL ENGINEERING
65% DESCRIPTION TG BUILDING GA & PIPING COMPOSITE DRGs VENDOR DRAWING & DOCUMENTS REVIEW PIPING STRESS ANALYSIS, ISOMETRICS & LIST PIPE SUPPORT DRAWINGS O&M MANUALS & PG TEST PROCEDURE ELECTRICAL DOCUMENTS C&I DOCUMENTS 3% % of Overall Project = Total Weightage Points (Per Unit Basis) = % OF WEIGHTAGE WTG POINTS 20% 20% 30% 15% 1625 3% 10% 1625 6500 13000 13000 19500 9750 6.50% 65000 ANNEXURE NO. ANNEXURE - 4.1 ANNEXURE - 4.2 ANNEXURE - 4.1 ANNEXURE - 4.1 ANNEXURE - 4.1 ANNEXURE - 4.1 ANNEXURE - 4.1
:A
:LT-P000003 :4.1
Last Wk Recd
Last Wk Recd
Last Wk Recd
To Wk Rcvd Next
To Wk Rcvd Next
To Wk Rcvd Next
Last Wk Recd
Submited Last Wk
Submited Last Wk
Submited Last Wk
Next WkSubm.
Next WkSubm.
Submission Date
Next WkSubm.
Submited Last Wk
Schedule First
Sr. No.
Description
Category (A/I)
FLAG
FLAG
FLAG
FLAG
FLAG
FLAG
FLAG
To Wk Rcvd Next
Unit No.
ZX&DO
Subm. Wk Next
FLAG
Release
Receive
Release
Receive
Release
L&T
Date
DTN No.
Date
I/W No.
JNSTPP
L&T
Date
DTN No.
Date
I/W No.
JNSTPP
L&T
Date
DTN No.
Date
I/W No.
JNSTPP
L&T
Date
DTN No.
Date
I/W No.
JNSTPP
Date
DTN No.
Date
I/W No.
BASIC Engineering
Design Criteria Document
Power System LTSL-M0-00102 1-Oct-09 I 2 Sch. 1-Oct-09 JPVLODT0004 31-Oct-09 DCPL -0010 10-Nov-09 DCPLODT0059 10-Dec-09 DCPL -0040 20-Dec-09 DCPLODT0117 19-Jan-10 DCPL -0092 29-Jan-10 28-Feb-10 13-May-10 12-Jun-10 DCD - Feed Water System
DCPl 0173
Act.
21-Sep-09
8-Dec-09
19-Jan-10
9-Feb-10
9-Apr-10
23-Apr-10
LTSL-M0-00101
7-Oct-09
A2
Sch.
7-Oct-09
DCPLODT0012
6-Nov-09
DCPL 0010
16-Nov-09
DCPLODT0049
16-Dec-09
DCPl 0038
26-Dec-09
DCPLODT0117
25-Jan-10
DCPL 0092
4-Feb-10
6-Mar-10
13-May-10
12-Jun-10
Act.
16-Nov-09
8-Dec-09
18-Jan-10
6-Feb-10
9-Apr-10
23-Apr-10
1.1.3
LTSL-M0-00105
5-Nov-09
A2
Sch.
5-Nov-09
DCPLODT0018
5-Dec-09
DCPL 0012
15-Dec-09
DCPLODT0026
14-Jan-10
DCPL 0031
24-Jan-10
DCPLODT0054
23-Feb-10
DCPL 0049
5-Mar-10
DCPLODT0080
4-Apr-10
DCPL 0092
4-Mar-10
DCPLODT0221
3-Apr-10
Act.
27-Nov-09
24-Dec-09
18-Dec-09
11-Jan-10
19-Jan-10
12-Feb-10
10-Feb-10
23-Apr-10
11-Aug-10
30-Aug-10
1.1.4
LTSL-M0-00103
13-Oct-09
A2
Sch.
13-Oct-09
DCPLODT0016
12-Nov-09
DCPL -0014
22-Nov-09
DCPLODT0049
22-Dec-09
DCPL 0049
1-Jan-10
DCPLODT0080
31-Jan-10
DCPL 0057
10-Feb-10
DCPLODT0117
12-Mar-10
22-Mar-10
21-Apr-10
Act.
20-Nov-09
29-Dec-09
18-Jan-10
17-Feb-10
10-Feb-10
2-Mar-10
9-Apr-10
1.1.5
LTSL-M0-00104
19-Oct-09
A2
Sch.
19-Oct-09
DCPLODT0016
18-Nov-09
DCPL -0014
28-Nov-09
DCPLODT0059
28-Dec-09
DCPL -0042
7-Jan-10
DCPLODT0117
6-Feb-10
DCPL -0092
16-Feb-10
18-Mar-10
13-May-10
12-Jun-10
DCPl 0158
Act.
20-Nov-09
29-Dec-09
19-Jan-10
12-Feb-10
9-Apr-10
23-Apr-10
1.1.6
LTSL-M0-00106
24-Oct-09
A2
Sch.
24-Oct-09
DCPLODT0018
23-Nov-09
DCPL -0030
3-Dec-09
DCPLODT0082
2-Jan-10
DCPL 0061
12-Jan-10
DCPLODT0117-0
11-Feb-10
21-Feb-10
DCPLODT0120-1
23-Mar-10
DCPL 0123
1-Jul-10
DCPLODT0170
31-Jul-10
2-Aug-10
Act.
27-Nov-09
11-Jan-10
10-Feb-10
5-Mar-10
9-Apr-10
16-Apr-10
1-Jun-10
1-Jul-10
2-Aug-10
1.1.7
LTSL-M0-00107
30-Oct-09
A2
Sch.
30-Oct-09
DCPLODT0020
29-Nov-09
DCPL -0016
9-Dec-09
DCPLODT0050
8-Jan-10
DCPL 0049
18-Jan-10
17-Feb-10
27-Feb-10
29-Mar-10
6-Apr-10
Act.
5-Dec-09
29-Dec-09
18-Jan-10
12-Feb-10
1.2
BOP System
1.2.1
LTSL-M0-00109
28-Dec-09
Sch.
28-Dec-09
DCPLODT0018
27-Jan-10
DCPL 0031
6-Feb-10
DCPLODT0082
8-Mar-10
DCPL 0074
18-Mar-10
DCPLODT0117-0
17-Apr-10
DCPL 0092
27-Apr-10
27-May-10
13-May-10
12-Jun-10
6-Apr-10
Act.
27-Nov-09
11-Jan-10
10-Feb-10
29-Mar-10
9-Apr-10
23-Apr-10
1.2.2
LTSL-M0-00113
11-Nov-09
Sch.
11-Nov-09
DCPLODT0082
11-Dec-09
DCPL -0078
21-Dec-09
DCPLODT0117
20-Jan-10
DCPL 0078
30-Jan-10
1-Mar-10
11-Mar-10
10-Apr-10
6-Apr-10
Act.
10-Feb-10
3-Apr-10
9-Apr-10
3-Apr-10
1.2.3
LTSL-E0-00100
16-Dec-09
A2
Sch.
16-Dec-09
DCPLODT0011
15-Jan-10
DCPL 0011
25-Jan-10
DCPLODT0082-0
24-Feb-10
DCPL 0064
6-Mar-10
DCPLODT0118-1
5-Apr-10
DCPL 0096
15-Apr-10
15-May-10
14-May-10
13-Jun-10
6-Apr-10
Act.
7-Nov-09
9-Dec-09
10-Feb-10
8-Mar-10
9-Apr-10
24-Apr-10
1.2.4
LTSL-I0-00100
22-Dec-09
A2
Sch.
22-Dec-09
DCPLODT0012
21-Jan-10
DCPl 0022
31-Jan-10
DCPLODT0118
2-Mar-10
DCPLO0102
12-Mar-10
11-Apr-10
21-Apr-10
21-May-10
13-May-10 12-Jun-10
30-Apr-10
Act.
16-Nov-09
5-Jan-10
9-Apr-10
30-Apr-10
1.2.5
LTSL-M0-00108
17-Nov-09
A2
Sch.
17-Nov-09
DCPLODT0018
17-Dec-09
DCPl 0031
27-Dec-09
DCPLODT0080
26-Jan-10
DCPL 0057
5-Feb-10
DCPLODT0117-0
7-Mar-10
DCPL 0092
17-Mar-10
16-Apr-10
DCPL 0181
6-Apr-10
Act.
27-Nov-09
11-Jan-10
10-Feb-10
2-Mar-10
9-Apr-10
23-Apr-10
1.2.6
LTSL-M0-00110
23-Nov-09
A2
Sch.
23-Nov-09
DCPLODT0019
23-Dec-09
Nt Come
2-Jan-10
DCPLODT0082
1-Feb-10
DCPl 0078
11-Feb-10
DCPLODT0117-0
13-Mar-10
DCPL 0092
23-Mar-10
22-Apr-10
13-May-10
12-Jun-10
6-Apr-10
Act.
30-Nov-09
10-Feb-10
3-Apr-10
9-Apr-10
23-Apr-10
1.2.7
LTSL-M0-00111
28-Nov-09
Sch.
28-Nov-09
DCPLODT0018
28-Dec-09
DCPl 0031
7-Jan-10
DCPLODT0082
6-Feb-10
DCPL 0074
16-Feb-10
DCPLODT0117
18-Mar-10
DCPL 0092
28-Mar-10
27-Apr-10
13-May-10
12-Jun-10
6-Apr-10
Act.
27-Nov-09
11-Jan-10
10-Feb-10
29-Mar-10
9-Apr-10
23-Apr-10
1.2.8
LTSL-M0-00112
4-Dec-09
A2
Sch.
4-Dec-09
DCPLODT0019
3-Jan-10
DCPL 0028
13-Jan-10
DCPLODT0082
12-Feb-10
DCPl 0078
22-Feb-10
DCPLODT0117-0
24-Mar-10
DCPl 0092
3-Apr-10
3-May-10
13-May-10
12-Jun-10
6-Apr-10
Act.
30-Nov-09
11-Jan-10
10-Feb-10
3-Apr-10
9-Apr-10
23-Apr-10
1.2.9
LTSL-M0-00115
10-Dec-09
A2
Sch.
10-Dec-09
DCPLODT0028
9-Jan-10
DCPL 0039
19-Jan-10
DCPLODT0087
18-Feb-10
DCPL 0075
28-Feb-10
DCPLODT0125
30-Mar-10
9-Apr-10
DCPLODT0191
9-May-10
15-Sep-10
Act.
19-Dec-09
9-Feb-10
19-Feb-10
31-Mar-10
21-Apr-10
19-Jul-10
2 2.1 C 2.1.1
Calculations
Power System Calc - Turbine Building Piping Load Data LTSL-M0-00551 14-Jan-10 I 3 Sch. 14-Jan-10 DCPLODT0051 13-Feb-10 DCPl -0070 23-Feb-10 25-Mar-10 4-Apr-10 4-May-10 14-May-10 13-Jun-10
13-May-10 12-Jun-10
Act.
18-Jan-10
15-Mar-10
2.1.2
LTSL-M0-00333
24-Oct-09
A2
Sch.
24-Oct-09
DCPLODT0014
23-Nov-09
DCPL 0010
3-Dec-09
DCPLODT0040
2-Jan-10
Nt Come
12-Jan-10
DCPLODT0108
11-Feb-10
DCPL 0093
21-Feb-10
23-Mar-10
23-Apr-10
Page 47 of 12
:A
19-Oct-10
:LT-P000003 :4.1
15-Mar-10 23-Apr-10
2.1.3
LTSL-M0-00302
24-Oct-09
Sch.
24-Oct-09
DCPLODT0014
23-Nov-09
DCPL 0033
3-Dec-09
DCPLODT0092
2-Jan-10
DCPL 0080
12-Jan-10
DCPLODT0184
11-Feb-10
Act.
18-Nov-09
11-Jan-10
26-Feb-10
5-Apr-10
16-Jul-10
30-Aug-10
2.1.4
LTSL-M0-00332
30-Oct-09
A2
Sch.
30-Oct-09
DCPLODT0021
29-Nov-09
DCPL 0012
9-Dec-09
DCPLODT0041
8-Jan-10
Nt Come
18-Jan-10
DCPLODT0108
17-Feb-10
DCPL 0093
27-Feb-10
29-Mar-10
13-May-10
12-Jun-10
Act.
9-Dec-09
24-Dec-09
31-Dec-09
30-Mar-10
23-Apr-10
2.1.5
LTSL-M0-00301
30-Oct-09
Sch.
30-Oct-09
DCPLODT0025
29-Nov-09
DCPL 0032
9-Dec-09
DCPLODT0091
8-Jan-10
DCPL 0107
18-Jan-10
DCPLODT0200
17-Feb-10
DCPL 0173
27-Feb-10
29-Mar-10
19-Sep-10
19-Oct-10
Act.
17-Dec-09
11-Jan-10
25-Feb-10
5-May-10
20-Jul-10
30-Aug-10
2.1.6
LTSL-M0-00304
16-Dec-09
Sch.
16-Dec-09
DCPLODT0029
15-Jan-10
DCPL -0045
25-Jan-10
DCPLODT0184
24-Feb-10
DCPL 0173
6-Mar-10
5-Apr-10
15-Apr-10
15-May-10
Act.
21-Dec-09
12-Feb-10
16-Jul-10
30-Aug-10
2.1.7
LTSL-M0-00303
10-Dec-09
Sch.
10-Dec-09
DCPLODT0022
9-Jan-10
DCPL 0047
19-Jan-10
DCPLODT0219
18-Feb-10
28-Feb-10
30-Mar-10
9-Apr-10
9-May-10
Act.
9-Dec-09
15-Feb-10
11-Aug-10
2.1.8
LTSL-M0-00305
2-Jan-10
Sch.
2-Jan-10
DCPLODT0028
1-Feb-10
DCPL 0047
11-Feb-10
DCPLODT0200
13-Mar-10
23-Mar-10
DCPLODT0230
22-Apr-10
DCPL 0174
2-May-10
1-Jun-10
26-Sep-10
26-Oct-10
15-Mar-10
Act.
19-Dec-09
15-Feb-10
20-Jul-10
13-Aug-10
6-Sep-10
2.1.9
LTSL-M0-00340
11-Nov-09
Sch.
11-Nov-09
DCPLODT0079
11-Dec-09
Nt Come
21-Dec-09
20-Jan-10
30-Jan-10
1-Mar-10
11-Mar-10
10-Apr-10
Not Rqrd
Act.
10-Feb-10
2.1.10
LTSL-M0-00307
28-Dec-09
Sch.
28-Dec-09
DCPLODT0149
27-Jan-10
DCPL 0147
6-Feb-10
8-Mar-10
18-Mar-10
17-Apr-10
27-Apr-10
27-May-10
Act.
24-May-10
17-Jul-10
2.1.11
LTSL-M0-00550
14-Jan-10
Sch.
14-Jan-10
DCPLODT0085
13-Feb-10
DCPL 0070
23-Feb-10
DCPLODT0163
25-Mar-10
4-Apr-10
4-May-10
14-May-10
13-Jun-10
15-Mar-10
Act.
12-Feb-10
15-Mar-10
10-Jun-10
2.2
2.2.1
LTSL-M0-00308
10-Dec-09
Sch.
10-Dec-09
DCPLODT0026
9-Jan-10
DCPL 0094
19-Jan-10
DCPLODT0149
18-Feb-10
DCPL 0134
28-Feb-10
DCPLODT0200
30-Mar-10
DCPL 0173
9-Apr-10
9-May-10
19-Sep-10
19-Oct-10
Act.
18-Dec-09
24-Apr-10
24-May-10
18-Jun-10
20-Jul-10
30-Aug-10
2.2.2
LTSL-M0-00309
20-Jan-10
Sch.
20-Jan-10
DCPLODT0026
19-Feb-10
DCPL 0079
1-Mar-10
DCPLODT0149
31-Mar-10
DCPL 0134
10-Apr-10
DCPLODT0191
10-May-10
DCPL 0173
20-May-10
19-Jun-10
19-Sep-10
19-Oct-10
Act.
18-Dec-09
3-Apr-10
24-May-10
18-Jun-10
19-Jul-10
30-Aug-10
2.2.3
LTSL-M0-00335
16-Dec-09
Sch.
16-Dec-09
DCPLODT0136
15-Jan-10
DCPL 0153
25-Jan-10
DCPLODT0219
24-Feb-10
6-Mar-10
5-Apr-10
15-Apr-10
15-May-10
Act.
23-Apr-10
26-Jul-10
11-Aug-10
2.2.4
LTSL-M0-00310
16-Dec-09
Sch.
16-Dec-09
DCPLODT0136
15-Jan-10
25-Jan-10
24-Feb-10
6-Mar-10
5-Apr-10
15-Apr-10
15-May-10
Act.
23-Apr-10
2.2.5
LTSL-M0-00311
22-Dec-09
Sch.
22-Dec-09
DCPLODT0033
21-Jan-10
DCPL -0103
31-Jan-10
DCPLODT0149
2-Mar-10
12-Mar-10
DCPLODT0191
11-Apr-10
DCPL -0173
21-Apr-10
21-May-10
19-Sep-10
19-Oct-10
Act.
25-Dec-09
3-May-10
24-May-10
19-Jul-10
30-Aug-10
2.2.6
LTSL-M0-00313
4-Dec-09
Sch.
4-Dec-09
DCPLODT0082
3-Jan-10
DCPL 0104
13-Jan-10
DCPLODT0191
12-Feb-10
22-Feb-10
DCPLODT0232
24-Mar-10
3-Apr-10
3-May-10
Act.
10-Feb-10
3-May-10
19-Jul-10
18-Aug-10
2.2.7
LTSL-M0-00312
28-Dec-09
Sch.
28-Dec-09
DCPLODT0091
27-Jan-10
DCPL 0097
6-Feb-10
8-Mar-10
18-Mar-10
17-Apr-10
27-Apr-10
27-May-10
Act.
25-Feb-10
24-Apr-10
2.2.8
LTSL-E0-00301
8-Mar-10
Sch.
8-Mar-10
DCPLODT0128
7-Apr-10
17-Apr-10
17-May-10
27-May-10
26-Jun-10
6-Jul-10
5-Aug-10
Act.
23-Apr-10
2.2.9
Calc - LV Cable
LTSL-E0-00300
5-May-10
Sch.
5-May-10
4-Jun-10
14-Jun-10
14-Jul-10
24-Jul-10
23-Aug-10
2-Sep-10
2-Oct-10
Act.
3 3.1 3.1.1
P&IDs
Up to Release for Construction P&ID - Index, Legends & Symbols LTSL-M0-00200 1-Oct-09 I 3 Sch. 1-Oct-09 JPVLODT0002 31-Oct-09 DCPL -0008 10-Nov-09 DCPLODT0036-0 10-Dec-09 Nt Come 20-Dec-09 19-Jan-10 29-Jan-10 28-Feb-10
30-Nov-09
Act.
1-Oct-09
30-Nov-09
29-Dec-09
3.1.2
LTSL-M1-00202
10-Dec-09
A2
Sch.
10-Dec-09
DCPLODT0041
9-Jan-10
DCPL 0057
19-Jan-10
DCPLODT0081
18-Feb-10
DCPL 0057
28-Feb-10
DCPLODT0128
30-Mar-10
DCPL 0120
9-Apr-10
DCPLODT0147
9-May-10
18Jun-10
Act.
31-Dec-09
2-Mar-10
10-Feb-10
2-Mar-10
23-Apr-10
27-May-10
24-May-10
24-Jun-10
9-Jul-10
3.1.3
LTSL-M1-00201
23-Nov-09
A2
Sch.
23-Nov-09
DCPLODT0041
23-Dec-09
DCPL 0057
2-Jan-10
DCPLODT0081
1-Feb-10
DCPL 0057
11-Feb-10
DCPLODT0129
13-Mar-10
DCPL 0120
23-Mar-10
DCPLODT0147
22-Apr-10
16-Jun-10
DCPLODT0169
16-Jul-10
DCPL 0145
18Jun-10
Act.
31-Dec-09
2-Mar-10
10-Feb-10
2-Mar-10
23-Apr-10
27-May-10
24-May-10
24-Jun-10
9-Jul-10
3.1.4
LTSL-M1-00204
8-Jan-10
A2
Sch.
8-Jan-10
DCPLODT0059
7-Feb-10
DCPL 0062
17-Feb-10
DCPLODT0081
19-Mar-10
DCPL 0062
29-Mar-10
DCPLODT0128
28-Apr-10
DCPL 0116
8-May-10
DCPLODT0148-0
7-Jun-10
1-Jun-10
1-Jul-10
12-May-10
Act.
19-Jan-10
5-Mar-10
10-Feb-10
5-Mar-10
23-Apr-10
12-May-10
24-May-10
3.1.5
LTSL-M1-00210
16-Dec-09
Sch.
16-Dec-09
DCPLODT0082
15-Jan-10
DCPL 0108
25-Jan-10
DCPLODT0136
24-Feb-10
6-Mar-10
DCPLODT0173
5-Apr-10
DCPL 0151
15-Apr-10
DCPLODT0222
15-May-10
12-Aug-10
11-Sep-10
Act.
10-Feb-10
10-May-10
23-Apr-10
3-Jul-10
23-Jul-10
11-Aug-10
2-Jan-10
DCPLODT0049
1-Feb-10
DCPL 0059
11-Feb-10
DCPLODT0081
13-Mar-10
DCPL 0059
23-Mar-10
DCPLODT0125
22-Apr-10
DCPL 0120
2-May-10
DCPLODT0169
1-Jun-10
DCPL 0145
16-Jun-10
16-Jul-10
18Jun-10
Act.
18-Jan-10
2-Mar-10
10-Feb-10
2-Mar-10
21-Apr-10
27-May-10
24-Jun-10
9-Jul-10
3.1.7
LTSL-M1-00209
28-Dec-09
Sch.
28-Dec-09
DCPLODT0082
27-Jan-10
Nt Come
6-Feb-10
DCPLODT0123
8-Mar-10
DCPL 0095
18-Mar-10
DCPLODT0148-0
17-Apr-10
DCPl 0145
27-Apr-10
DCPLODT0253
27-May-10
29-Jul-10
28-Aug-10
24-Apr-10
Page 48 of 12
:A
13-Jun-10
:LT-P000003 :4.1
24-Apr-10
3.1.8
LTSL-M1-00208
10-Dec-09
A2
Sch.
10-Dec-09
DCPLODT0048
9-Jan-10
DCPl 0067
19-Jan-10
DCPLODT0081
18-Feb-10
DCPL 0067
28-Feb-10
DCPLDT0123
30-Mar-10
DCPL 0095
9-Apr-10
Act.
16-Jan-10
8-Mar-10
10-Feb-10
8-Mar-10
17-Apr-10
24-Apr-10
3.1.9
LTSL-M1-00213
4-Dec-09
Sch.
4-Dec-09
DCPLODT0083
3-Jan-10
Nt Come
13-Jan-10
DCPLODT0129
12-Feb-10
DCPL -0116
22-Feb-10
DCPLODT0148-0
24-Mar-10
DCPl -0145
3-Apr-10
3-May-10
29-Jul-10
28-Aug-10
12-May-10
Act.
10-Feb-10
23-Apr-10
12-May-10
24-May-10
9-Jul-10
3.1.10
LTSL-M1-00205
2-Jan-10
A2
Sch.
2-Jan-10
DCPLODT0054
1-Feb-10
DCPL 0067
11-Feb-10
DCPLODT0081
13-Mar-10
DCPL 0067
23-Mar-10
DCPLDT0123
22-Apr-10
DCPL 0095
2-May-10
1-Jun-10
14-May-10
13-Jun-10
24-Apr-10
Act.
19-Jan-10
8-Mar-10
10-Feb-10
8-Mar-10
17-Apr-10
24-Apr-10
3.1.11
LTSL-M1-00207
28-Dec-09
A2
Sch.
28-Dec-09
DCPLODT0050
27-Jan-10
DCPL -0067
6-Feb-10
DCPLODT0081
8-Mar-10
DCPL -0067
18-Mar-10
17-Apr-10
27-Apr-10
27-May-10
Send to LMB
Act.
18-Jan-10
8-Mar-10
10-Feb-10
8-Mar-10
3.1.12
LTSL-M1-00212
22-Dec-09
Sch.
22-Dec-09
DCPLODT0082
21-Jan-10
Nt Come
31-Jan-10
DCPLODT0125
2-Mar-10
DCPL 0124
12-Mar-10
11-Apr-10
21-Apr-10
DCPLODT0222
21-May-10
DCPl 0173
29-Jul-10 28-Aug-10
5-Aug-10
Act.
10-Feb-10
21-Apr-10
4-Jun-10
11-Aug-10
30-Aug-10
3.1.13
LTSL-M1-00211
22-Dec-09
Sch.
22-Dec-09
DCPLODT0082
21-Jan-10
DCPL 0115
31-Jan-10
DCPLODT0125
2-Mar-10
12-Mar-10
DCPLODT0148
11-Apr-10
DCPl 0145
21-Apr-10
21-May-10
22Jun-10
Act.
10-Feb-10
17-May-10
21-Apr-10
24-May-10
9-Jul-10
Sr. No.
Description
Category (A/I)
Unit No.
L&T
Date
DTN No.
Date
I/W No.
JNSTPP
L&T
Date
DTN No.
Date
I/W No.
JNSTPP
L&T
Date
DTN No.
Date
I/W No.
JNSTPP
L&T
Date
DTN No.
Date
I/W No.
JNSTPP
Date
DTN No.
Date
I/W No.
4 4.1 4.1.1
4.1.1.1
LTSL-M0-00601-SP
23-Jul-09
Sch.
23-Jul-09
15-Oct-09
Act.
15-Oct-09
4.1.1.2
Deaerator
LTSL-M0-00606-SP
23-Jul-09
Sch.
23-Jul-09
15-Oct-09
Act.
15-Oct-09
4.1.1.3
LTSL-M0-00607-SP
23-Jul-09
Sch.
23-Jul-09
15-Oct-09
Act.
15-Oct-09
4.1.1.4
LTSL-M0-00603-SP
24-Oct-09
Sch.
24-Oct-09
13-Nov-09
Act.
13-Nov-09
4.1.1.5
LTSL-M0-00604-SP
4-Dec-09
Sch.
4-Dec-09
27-Nov-09
Act.
27-Nov-09
4.1.1.6
EOT Crane
LTSL-M0-00624-SP
2-Jan-10
Sch.
2-Jan-10
24-Dec-09
Act.
24-Dec-09
4.1.1.7
LTSL-M0-00602-SP
28-Nov-09
Sch.
28-Nov-09
19-Feb-10
Act.
19-Feb-10
4.1.1.8
Vacuum Pump
LTSL-M0-00605-SP
10-Dec-09
Sch.
10-Dec-09
8-Feb-10
Act.
8-Feb-10
4.1.1.9
LTSL-M0-00610-SP
26-Jan-10
Sch.
26-Jan-10
11-Feb-10
Act.
11-Feb-10
4.1.1.10
DMCW Pump
LTSL-M0-00608-SP
16-Dec-09
Sch.
16-Dec-09
16-Feb-10
Act.
16-Feb-10
4.1.1.11
LTSL-M0-00712 - SP
17-Apr-10
Sch.
17-Apr-10
13-Jan-10
Act.
13-Jan-10
4.1.1.12
LTSL-M0-00609-SP
16-Dec-09
Sch.
16-Dec-09
12-Feb-10
Act.
12-Feb-10
4.1.1.13
LTSL-M0-00612-SP
20-Jan-10
Sch.
20-Jan-10
25-Mar-10
Act.
25-Mar-10
4.1.1.14
LTSL-M0-00618-SP
29-Apr-10
Sch.
29-Apr-10
25-Mar-10
Act.
25-Mar-10
4.1.1.15
LTSL-M0-00628-SP
29-Apr-10
Sch.
29-Apr-10
19-Jul-10
Act.
19-Jul-10
4.1.1.16
LTSL-M0-00613-SP
28-Dec-09
Sch.
28-Dec-09
24-Feb-10
Page 49 of 12
:A
:LT-P000003 :4.1
21-May-10
4.1.1.17
Butterfly Valves
LTSL-M0-00620-SP
17-May-10
Sch.
17-May-10
Act.
21-May-10
4.1.1.18
LP Bypass Valve
LTSL-M0-00614-SP
18-Feb-10
Sch.
18-Feb-10
14-Mar-10
Act.
14-Mar-10
4.1.1.19
Piping Specialities
LTSL-M0-00617-SP
3-Jun-10
Sch.
3-Jun-10
24-May-10
Act.
24-May-10
4.1.1.20
LTSL-M0-00619-SP
21-Jun-10
Sch.
21-Jun-10
29-Apr-10
Act.
29-Apr-10
4.1.1.21
LTSL-M0-00621-SP
3-Jun-10
Sch.
3-Jun-10
25-Mar-10
Act.
25-Mar-10
4.1.1.22
Elevators
LTSL-M0-00626-SP
2-Jan-10
Sch.
2-Jan-10
2-Jan-10
Act.
2-Jan-10
4.1.1.23
LTSL-M0-00611-SP
26-Jul-10
Sch.
26-Jul-10
25-Mar-10
Act.
25-Mar-10
4.1.1.24
30-Aug-10
Sch.
30-Aug-10
19-Jul-10
Act.
19-Jul-10
4.1.1.25
LTSL-M0-00616-SP
26-Jul-10
Sch.
26-Jul-10
24-May-10
Act.
24-May-10
4.1.1.27
LTSL-M0-00622-SP
12-Aug-10
Sch.
12-Aug-10
10-May-10
Act.
10-May-10
4.1.1.28
LTSL-M0-00623-SP
30-Aug-10
Sch.
30-Aug-10
23-Aug-10
Act.
23-Aug-10
4.1.1.30
Strainers
LTSL-M0-00615-SP
16-Sep-10
Sch.
16-Sep-10
21-May-10
Act.
21-May-10
4.1.1.32
LTSL-M0-00625-SP
13-Nov-10
Sch.
13-Nov-10
23-Aug-10
Act.
23-Aug-10
4.1.2
4.1.2.1
LTSL-M0-00601-BR
24-Aug-09
Sch.
24-Aug-09
4-Dec-09
Act.
4-Dec-09
4.1.2.2
Deaerator
LTSL-M0-00606-BR
24-Aug-09
Sch.
24-Aug-09
4-Dec-09
Act.
4-Dec-09
4.1.2.3
LTSL-M0-00607-BR
24-Aug-09
Sch.
24-Aug-09
28-Nov-09
Act.
28-Nov-09
4.1.2.4
LTSL-M0-00603-BR
30-Jan-10
Sch.
30-Jan-10
15-Mar-10
Act.
15-Mar-10
4.1.2.5
LTSL-M0-00602-BR
24-Mar-10
Sch.
24-Mar-10
15-Jun-10
Act.
15-Jun-10
4.1.2.6
LTSL-M0-00604-BR
5-Apr-10
Sch.
5-Apr-10
15-Mar-10
Act.
15-Mar-10
4.1.2.7
EOT Crane
LTSL-M0-00624-BR
9-Apr-10
Sch.
9-Apr-10
8-Apr-10
Act.
8-Apr-10
4.1.2.8
Vacuum Pump
LTSL-M0-00605-BR
27-May-10
Sch.
27-May-10
17-Aug-10
Act.
17-Aug-10
4.1.2.9
LTSL-M0-00610-BR
14-Jun-10
Sch.
14-Jun-10
21-Aug-10
Act.
21-Aug-10
4.1.3
PERCHASE SPECIFICATION
4.1.3.1
LTSL-M0-00601-PS
10-Sep-09
Sch.
10-Sep-09
4-Dec-09
Act.
4-Dec-09
4.1.3.2
Deaerator
LTSL-M0-00606-PS
10-Sep-09
Sch.
10-Sep-09
4-Dec-09
Act.
4-Dec-09
4.1.3.3
LTSL-M0-00607-PS
10-Sep-09
Sch.
10-Sep-09
4-Dec-09
Page 50 of 12
:A
:LT-P000003 :4.1
24-May-10
4.1.3.4
LTSL-M0-00603-PS
11-Feb-10
Sch.
11-Feb-10
Act.
24-May-10
4.1.3.5
LTSL-M0-00602-PS
10-Apr-10
Sch.
10-Apr-10
15-Jun-10
Act.
15-Jun-10
4.1.3.6
EOT Crane
LTSL-M0-00624-PS
20-May-10
Sch.
20-May-10
24-May-10
Act.
24-May-10
4.1.3.7
LTSL-M0-00604-PS
27-May-10
Sch.
27-May-10
24-May-10
Act.
24-May-10
4.2
4.2.1
SPECIFICATION
4.2.1.1
LTSL-E0-00600-SP
10-Aug-10
Sch.
10-Aug-10
15-Jun-10
Act.
15-Jun-10
4.2.1.2
24 V DC System
LTSL-E0-00602-SP
1-Oct-10
Sch.
1-Oct-10
20-Jul-10
Act.
20-Jul-10
4.2.1.3
LTSL-E0-00603-SP
10-Dec-10
Sch.
10-Dec-10
19-Jul-10
Act.
19-Jul-10
4.2.1.4
LTSL-E0-00604-SP
1-Feb-11
Sch.
1-Feb-11
21-Aug-10
Act.
21-Aug-10
4.2.2
4.2.3
PERCHASE SPECIFICATION
Sr. No.
Description
Category (A/I)
Unit No.
L&T
Date
DTN No.
Date
I/W No.
JNSTPP
L&T
Date
DTN No.
Date
I/W No.
JNSTPP
L&T
Date
DTN No.
Date
I/W No.
JNSTPP
L&T
Date
DTN No.
Date
I/W No.
JNSTPP
Date
DTN No.
Date
I/W No.
4.3
4.3.1
SPECIFICATION
4.3.1.1
LTSL-I0-00601-SP
6-Apr-10
Sch.
6-Apr-10
21-Jul-10
Act.
21-Jul-10
4.3.1.2
Flow Elements
LTSL-I0-00602-SP
28-Jun-10
Sch.
28-Jun-10
30-Jun-10
Act.
30-Jun-10
4.3.1.3
LTSL-I0-00606-SP
20-Oct-10
Sch.
20-Oct-10
21-Apr-10
Act.
21-Apr-10
4.3.1.4
DCS
LTSL-I0-00600-SP
24-Nov-10
Sch.
24-Nov-10
14-Mar-10
Act.
14-Mar-10
4.3.2
4.3.3
PERCHASE SPECIFICATION
5 5.1
Detail Engineering
Turbine Building Layout - GA / Piping Composite Drawings Up to Release for
Construction GA - Turbine Building Plan & Sections LTSL-M0-0001 19-Sep-09 A A3 Sch. 19-Sep-09 DCPLODT0005 19-Oct-09 DCPL 0001 29-Oct-09 DCPLODT0013 28-Nov-09 DCPL 0020 8-Dec-09 DCPLODT0057 7-Jan-10 DCPL 0055 17-Jan-10 DCPLODT0135 16-Feb-10 DCPL 0126 18-Mar-10 DCPLODT0175 17-Apr-10
Act. 16-Oct-09 23-Oct-09 18-Nov-09 5-Jan-10 19-Jan-10 26-Feb-10 23-Apr-10 8-Jun-10 9-Jul-10 LTSL-M0-00920 1-Oct-10 I Sch. 1-Oct-10 DCPLODT0258 31-Oct-10 10-Nov-10 10-Dec-10 20-Dec-10 19-Jan-11 29-Jan-11 28-Feb-11
5.1.1
6 6.1 1 6.1.1
6.2
6.2.1
1069.4
7.13%
6.2.1.1
LATER
7-Jul-10
Sch.
7-Jul-10
6-Aug-10
16-Aug-10
15-Sep-10
25-Sep-10
25-Oct-10
4-Nov-10
4-Dec-10
Act.
26-May-10
6.2.2
Page 51 of 12
:A
:LT-P000003 :4.1
3-Jul-10
6.4.1
List - Equipments
LTSL-M1-00700
6-Feb-10
6.4.2
List - Pipelines
LTSL-M1-00701
12-Feb-10
Sch.
12-Feb-10
DCPLODT0136
14-Mar-10
DCPL 0141
24-Mar-10
DCPLODT0221
23-Apr-10
DCPL 0173
3-May-10
2-Jun-10
12-Jun-10
12-Jul-10
5-Aug-10
Act.
23-Apr-10
30-Jun-10
11-Aug-10
30-Aug-10
6.4.3
List - Valves
LTSL-M1-00702
12-Feb-10
Sch.
12-Feb-10
DCPLODT0136
14-Mar-10
DCPL 0141
24-Mar-10
DCPLODT0206
23-Apr-10
DCPL 0173
3-May-10
2-Jun-10
12-Jun-10
12-Jul-10
5-Aug-10
Act.
23-Apr-10
30-Jun-10
23-Jul-10
30-Aug-10
6.4.4
List - Specialities
LTSL-M1-00703
1-Mar-10
Sch.
1-Mar-10
DCPLODT0136
31-Mar-10
DCPL -0141
10-Apr-10
DCPLODT0210
10-May-10
DCPL -0173
20-May-10
19-Jun-10
29-Jun-10
29-Jul-10
5-Aug-10
Act.
23-Apr-10
30-Jun-10
26-Jul-10
30-Aug-10
6.4.5
LTSL-M1-00704
18-Feb-10
Sch.
18-Feb-10
DCPLODT0125
20-Mar-10
DCPL -0157
30-Mar-10
DCPLODT0236
29-Apr-10
9-May-10
8-Jun-10
18-Jun-10
18-Jul-10
Act.
21-Apr-10
2-Aug-10
23-Aug-10
6.4.6
LTSL-M1-00711
10-May-10
Sch.
10-May-10
DCPLODT0128
9-Jun-10
DCPL 0117
19-Jun-10
19-Jul-10
29-Jul-10
28-Aug-10
7-Sep-10
7-Oct-10
18-May-10
Act.
23-Apr-10
18-May-10
6.5
6.5.1
LTSL-E0-00702
1-Feb-10
Sch.
1-Feb-10
DCPLODT0123
3-Mar-10
DCPLO DT0101
13-Mar-10
12-Apr-10
22-Apr-10
22-May-10
1-Jun-10
1-Jul-10
30-Apr-10
Act.
17-Apr-10
30-Apr-10
6.5.2
LTSL-E0-00703
23-Feb-10
Sch.
23-Feb-10
DCPLODT0125
25-Mar-10
DCPL 0099
4-Apr-10
4-May-10
14-May-10
13-Jun-10
23-Jun-10
23-Jul-10
Act.
21-Apr-10
30-Apr-10
6.5.3
LTSL-E0-00704
26-May-10
Sch.
26-May-10
DCPLODT0128
25-Jun-10
DCPL 0117
5-Jul-10
4-Aug-10
14-Aug-10
13-Sep-10
23-Sep-10
23-Oct-10
18-May-10
Act.
23-Apr-10
18-May-10
6.6
Lists / C&I
6.6.1
List - Instruments
LTSL-I1-00700
10-May-10
Sch.
10-May-10
DCPLODT0208
9-Jun-10
19-Jun-10
19-Jul-10
29-Jul-10
28-Aug-10
7-Sep-10
7-Oct-10
Act.
23-Jul-10
78 9 9.1 1 9.1.1
Pipe Support Drawings O&M Manual & PG Test Procedure ELE SCHEM & Cable Sched etc....
Release for Construction 24 V DC System SLD Up to
1584.4
97.50%
LTSL-E0-00200
12-Feb-10
Sch.
12-Feb-10
DCPLODT0128
14-Mar-10
24-Mar-10
23-Apr-10
3-May-10
2-Jun-10
12-Jun-10
12-Jul-10
Act.
23-Apr-10
10 13 C 13.1
Act.
1-Oct-10
1-Oct-09
30-Nov-09
13.2
LTSL-JPN:E-0019
4-Nov-09
Sch.
4-Nov-09
DCPLODT0009
4-Dec-09
DCPL 0021
14-Dec-09
13-Jan-10
23-Jan-10
22-Feb-10
4-Mar-10
3-Apr-10
Act.
4-Nov-09
5-Jan-10
13.3
LT-P0-00001
21-Sep-09
Sch.
21-Sep-09
JPVLODT0004
21-Oct-09
31-Oct-09
DCPLODT0010
30-Nov-09
10-Dec-09
JPVLODT0011
9-Jan-10
19-Jan-10
18-Feb-10
Act.
21-Sep-09
5-Nov-09
6-Jan-10
13.4
LTSL-P0-00201
1-Oct-09
Sch.
1-Oct-09
JPVLODT0004
31-Oct-09
10-Nov-09
DCPLODT0010
10-Dec-09
20-Dec-09
19-Jan-10
29-Jan-10
28-Feb-10
Act.
21-Sep-09
5-Nov-09
13.5
592201-LOAD
12-Feb-10
Sch.
12-Feb-10
DCPLODT0085
14-Mar-10
24-Mar-10
23-Apr-10
3-May-10
2-Jun-10
12-Jun-10
12-Jul-10
Act.
12-Feb-10
13.6
592201.0
12-Feb-10
Sch.
12-Feb-10
DCPLODT0085
14-Mar-10
DCPL 0115
24-Mar-10
23-Apr-10
3-May-10
2-Jun-10
12-Jun-10
12-Jul-10
Act.
12-Feb-10
17-May-10
13.7
592301.0
12-Feb-10
Sch.
12-Feb-10
DCPLODT0085
14-Mar-10
DCPL 0115
24-Mar-10
23-Apr-10
3-May-10
2-Jun-10
12-Jun-10
12-Jul-10
Act.
12-Feb-10
17-May-10
13.8
LT-JPN-EN-PPM-006
1-Feb-10
Sch.
1-Feb-10
DCPLoDT0073
3-Mar-10
DCPL-0071
13-Mar-10
12-Apr-10
22-Apr-10
22-May-10
1-Jun-10
1-Jul-10
Act.
1-Feb-10
15-Mar-10
13.9
LT-JPN-EN-PPM-007
1-Feb-10
Sch.
1-Feb-10
DCPLODT0073
3-Mar-10
DCPl 0071
13-Mar-10
12-Apr-10
22-Apr-10
22-May-10
1-Jun-10
1-Jul-10
Act.
1-Feb-10
15-Mar-10
13.10
LTSL-M0-00908
18-Mar-10
Sch.
18-Mar-10
DCPLODT0098
17-Apr-10
27-Apr-10
27-May-10
6-Jun-10
6-Jul-10
16-Jul-10
15-Aug-10
Act.
18-Mar-10
13.11
JPN-SK-M-007
19-Jan-10
Sch.
19-Jan-10
DCPLODT0056
18-Feb-10
DCPL 0041
28-Feb-10
30-Mar-10
9-Apr-10
9-May-10
19-May-10
18-Jun-10
Act.
19-Jan-10
9-Feb-10
13.12
16-Sep-09
Sch.
16-Sep-09
JPVLO0001
16-Oct-09
26-Oct-09
25-Nov-09
5-Dec-09
4-Jan-10
14-Jan-10
13-Feb-10
Page 52 of 12
:A
:LT-P000003 :4.1
13.13
22-Dec-09
Sch.
22-Dec-09
Act.
22-Dec-09
13.14
97000-2381-8
6-Jan-10
Sch.
6-Jan-10
DCPLODT0045
5-Feb-10
15-Feb-10
DCPLODT0158
17-Mar-10
27-Mar-10
26-Apr-10
6-May-10
5-Jun-10
Act.
6-Jan-10
5-Jun-10
13.15
Information for Boiler feed pump design (LMB Document for Information purpose)
97000-2311-1
6-Jan-10
Sch.
6-Jan-10
DCPLODT0045
5-Feb-10
15-Feb-10
DCPLODT0158
17-Mar-10
27-Mar-10
26-Apr-10
6-May-10
5-Jun-10
Act.
6-Jan-10
5-Jun-10
13.16
LTSL-M0-00635
10-Jun-10
Sch.
10-Jun-10
DPCLODT0161
10-Jul-10
DCPL 0139
20-Jul-10
19-Aug-10
29-Aug-10
28-Sep-10
8-Oct-10
7-Nov-10
Act.
10-Jun-10
18-Jun-10
13.17
JPN-SK-M-021
10-Jun-10
Sch.
10-Jun-10
DPCLODT0162
10-Jul-10
20-Jul-10
DPCLODT0164
19-Aug-10
29-Aug-10
28-Sep-10
8-Oct-10
7-Nov-10
Act.
10-Jun-10
14-Jun-10
13.18
10-Jun-10
Sch.
10-Jun-10
DCPLoDT0162
10-Jul-10
20-Jul-10
19-Aug-10
29-Aug-10
28-Sep-10
8-Oct-10
7-Nov-10
Act.
10-Jun-10
13.19
LTSL-M0-00637
14-Jul-10
Sch.
14-Jul-10
DCPLODT0178
13-Aug-10
23-Aug-10
DCPLODT0207
22-Sep-10
2-Oct-10
1-Nov-10
11-Nov-10
11-Dec-10
Act.
14-Jul-10
23-Jul-10
Sr. No.
Description
Category (A/I)
Unit No.
L&T
Date
DTN No.
Date
I/W No.
JNSTPP
L&T
Date
DTN No.
Date
I/W No.
JNSTPP
L&T
Date
DTN No.
Date
I/W No.
JNSTPP
L&T
Date
DTN No.
Date
I/W No.
JNSTPP
Date
DTN No.
Date
I/W No.
13.20 Sketch Interface of Auxiliary Columns (Along row a1, a2& a3) with Equipment /
JPN-SK-M-023
14-Jul-10
Sch.
14-Jul-10
DCPLODT0178
13-Aug-10
23-Aug-10
22-Sep-10
2-Oct-10
1-Nov-10
11-Nov-10
11-Dec-10
Act.
14-Jul-10
LTSL-M0-00638
16-Jul-10
Sch.
16-Jul-10
DCPLODT0187
15-Aug-10
25-Aug-10
24-Sep-10
4-Oct-10
3-Nov-10
13-Nov-10
13-Dec-10
Act.
16-Jul-10
16-Jul-10
Sch.
16-Jul-10
DCPLODT0187
15-Aug-10
25-Aug-10
24-Sep-10
4-Oct-10
3-Nov-10
13-Nov-10
13-Dec-10
Act.
16-Jul-10
JPN-SK-M-024
23-Jul-10
Sch.
23-Jul-10
DCPLODT0207
22-Aug-10
1-Sep-10
1-Oct-10
11-Oct-10
10-Nov-10
20-Nov-10
20-Dec-10
Act.
23-Jul-10
13.24
23-Jul-10
Sch.
23-Jul-10
DCPLODT0207
22-Aug-10
1-Sep-10
1-Oct-10
11-Oct-10
10-Nov-10
20-Nov-10
20-Dec-10
Act.
23-Jul-10
13.25 TG Building Floor Opening for Unit # 1 Along with the Row B & C
JPN-SK-M-026
12-Aug-10
Sch.
12-Aug-10
DCPLODT0223
11-Sep-10
21-Sep-10
21-Oct-10
31-Oct-10
30-Nov-10
10-Dec-10
9-Jan-11
Act.
12-Aug-10
13.26 Sketch Showing RC Slab & Grating Floor Requirement for Mazzanine Floor Elevation
JPN-SK-M-027
23-Aug-10
Sch.
23-Aug-10
DCPLODT0238
22-Sep-10
2-Oct-10
1-Nov-10
11-Nov-10
11-Dec-10
21-Dec-10
20-Jan-11
Act.
23-Aug-10
LTSL-M0-00641
30-Aug-10
Sch.
30-Aug-10
DCPLODT0246
29-Sep-10
9-Oct-10
8-Nov-10
18-Nov-10
18-Dec-10
28-Dec-10
27-Jan-11
Act.
30-Aug-10
13.28 Steam Turbine & Generator Componant layout plan at operating Floor EL. (+) 17M
LTSL-M0-00552
27-Aug-10
Sch.
27-Aug-10
DCPLODT0244.
26-Sep-10
6-Oct-10
5-Nov-10
15-Nov-10
15-Dec-10
25-Dec-10
24-Jan-11
Act.
27-Aug-10
LMTG-P0-01037
10-Sep-10
Sch.
10-Sep-10
DCPLODT0261
10-Oct-10
20-Oct-10
19-Nov-10
29-Nov-10
29-Dec-10
8-Jan-11
7-Feb-11
Act.
10-Sep-10
13.30
Piping Load Data for Stress Analysis System for CIVIL Design (Feed Water
LTSL-M0-00920
Sch.
DCPLODT0261 10-Sep-10
Act.
Page 53 of 12
Abbreviation: A - Approval I - Information N - Not for Submission x x x x I/W No. - Inward No. DTN No. - Document Transmittal No. | x Weightage Point not considered ____x x _____x ________x x x x x x x x x x x x x x x x x x x x x x x x x x x x
Unit type: C - Common for both Units - For Unit No. 1 only - For Unit No. 2 only x x x x
1 2
________x
_____________x
13.1.7
#
13 13.1 13.1
13.2.4
Gland Steam and Drain Plan Piping for Turbine Diagram Enclosure
C&I Documents
Utility List
14.14
Logic Diagram of Generator Auxiliaries Arrengement Drawing of Generator Stator Coil Cooling Water Control Panel
VDR - Steam Turbine Generator & its Auxiliaries Documents for Steam Turbine Up To Release for Construction
General Documents C 13.1.11
13.1.10
13.3.1
13.2.5
Oil Purifier Oil PipingPlan Diagram for Arrangement of T/G Foundation Deck
14.16
13.1.1
Equipment Numbering Procedure for Steam Turbine & Generator 13.2.7 Turbine Sectional Assembly Plan for Arrangement of Foundation Bolt
13.3.2
14.17
13.1.2
13.1.24
13.3.3
Plan for Arrangement of Anchor Bolt 13.2.8 Utility List for Steam Turbine
14.18
13.1.4
Equipment List C
13.2
Mechanical Documents
13.3.4
13.2.1
Valve List
14.19
13.1.5
Control and Lubricating oil System Diagram 13.2.10 T/G Foundation Loading Motor Diagram List for Steam Turbine
13.1.6
13.2.11
14.21
:LT-P0-00003
Submited Last Wk
Submited Last Wk
L&T A Sch.
14.23
LMTG-E0-02023 JEU51963
Date 15-Apr-10
Date 15-May-10
JNSTPP
L&T
Date 14-Jun-10
DTN No.
Date 14-Jul-10
I/W No.
JNSTPP
L&T
Submited Last Wk
Schedule
Sr. No.
Description
Unit No.
Date 13-Aug-10
Date
I/W No.
JNSTPP
L&T
Date
DTN No.
Date
I/W No.
JNSTPP
Date-Unit 1
DTN No 17-Jul-10
Act.
4-Jun-10
17-Jul-10
10-Sep-10
14.24
LMTG-E0-02024 JEZ2V684
15-Apr-10
Sch.
15-Apr-10
DCPLODT0119
15-May-10
DCPL -0106
14-Jun-10
DCPLODT0264
14-Jul-10
Act.
13-Apr-10
5-May-10
17-Sep-10
14.25
LMTG-E0-02025 JEZ2V685
15-Apr-10
Sch.
15-Apr-10
DCPLODT0119
15-May-10
DCPL -0109
14-Jun-10
DCPLODT0265
14-Jul-10
Act.
13-Apr-10
10-May-10
17-Sep-10
14.30
LMTG-E0-02030 GAE-KN-E157
15-Feb-11
Sch.
15-Feb-11
DCPLODT0096
17-Mar-11
DCPL -0084
16-Apr-11
DCPLODT0155
16-May-11
DCPL -0148
17-Jul-10
Act.
16-Mar-10
7-Apr-10
4-Jun-10
17-Jul-10
14.31
LMTG-E0-02031 GAE-KN-E401
15-Jul-10
Sch.
15-Jul-10
DCPLODT0260
14-Aug-10
13-Sep-10
13-Oct-10
Act.
10-Sep-10
14.34
LMTG-E0-02034 GAE-KN-E801
20-Mar-10
Sch.
20-Mar-10
DCPLODT0189
19-Apr-10
DCPL -0156
19-May-10
DCPLODT0260
18-Jun-10
28-Jul-10
Act.
17-Jul-10
28-Jul-10
10-Sep-10
14.35
Outline Drawing of Three Phase Induction Motor for ST Turning Oil Pump
LMTG-E0-02035 GAE-KN-E802
20-Mar-10
Sch.
20-Mar-10
DCPLODT0189
19-Apr-10
DCPL -0156
19-May-10
DCPLODT0266
18-Jun-10
28-Jul-10
Act.
17-Jul-10
28-Jul-10
17-Sep-10
14.36
LMTG-E0-02036 GAE-KN-E803
20-Mar-10
Sch.
20-Mar-10
DCPLODT0189
19-Apr-10
DCPL -0156
19-May-10
DCPLODT0260
18-Jun-10
28-Jul-10
Act.
17-Jul-10
28-Jul-10
10-Sep-10
14.37
5-Jan-10
Sch.
5-Jan-10
JPVLODT0002
4-Feb-10
DCPL -0002
6-Mar-10
DCPLODT0030
5-Apr-10
DCPL 0024
Act.
2-Oct-09
23-Oct-09
22-Dec-09
5-Jan-10
14.38
LMTG-E0-02038 JEK79173
3-Feb-10
Sch.
3-Feb-10
DCPLODT0063
5-Mar-10
DCPL -0044
4-Apr-10
DCPLODT0154
4-May-10
DCPl 0136
18-Jun-10
Act.
1-Feb-10
12-Feb-10
1-Jun-10
18-Jun-10
14.39
LMTG-E0-02039 JEK79174
3-Feb-10
Sch.
3-Feb-10
DCPLODT0063
5-Mar-10
DCPL -0044
4-Apr-10
DCPLODT0154
4-May-10
DCPl 0136
18-Jun-10
Act.
1-Feb-10
12-Feb-10
1-Jun-10
18-Jun-10
14.40
LMTG-E0-02040 JEK79175
3-Feb-10
Sch.
3-Feb-10
DCPLODT0063
5-Mar-10
DCPL -0044
4-Apr-10
DCPLODT0154
4-May-10
DCPl 0136
18-Jun-10
Act.
1-Feb-10
12-Feb-10
1-Jun-10
18-Jun-10
Sch.
3-Feb-10
DCPLODT0063
5-Mar-10
DCPL -0044
4-Apr-10
DCPLO -0105
4-May-10
3-Jun-10
DCPLODT0154
12-Feb-10
Act.
1-Feb-10
12-Feb-10
24-Mar-10
1-Jun-10
14.42
LMTG-E0-02042 JEU51974
11-Feb-10
Sch.
11-Feb-10
DCPLODT0063
13-Mar-10
DCPL -0044
12-Apr-10
12-May-10
12-Feb-10
Act.
1-Feb-10
12-Feb-10
14.43
LMTG-E0-02101 JEJ63766
15-Apr-10
Sch.
15-Apr-10
DCPLODT0030
15-May-10
DCPL -0024
14-Jun-10
DCPLODT0096
14-Jul-10
DCPL -0085
13-Aug-10
DCPLODT0189
12-Sep-10
DCPl -0156
28-Jul-10
Act.
22-Dec-09
5-Jan-10
16-Mar-10
7-Apr-10
17-Jul-10
28-Jul-10
14.44
LMTG-E0-02102 JEZ2Z308
15-Jul-10
Sch.
15-Jul-10
DCPLODT0224
14-Aug-10
DCPL -0175
13-Sep-10
13-Oct-10
Act.
12-Aug-10
6-Sep-10
14.46
QAP - Generator
LMTG-Q0-02201 JEVM-8F38-02
15-Apr-10
Sch.
15-Apr-10
DCPLODT0007
15-May-10
DCPL -0023
14-Jun-10
DCPLODT0088
14-Jul-10
DCPL 0066
Act.
31-Oct-09
5-Jan-10
22-Feb-10
8-Mar-10
14.47
LMTG-Q0-02202 JEVM-8F38-11
15-Aug-10
Sch.
15-Aug-10
DCPLODT0218
14-Sep-10
14-Oct-10
13-Nov-10
Act.
9-Aug-10
14.48
LMTG-Q0-02203 JEVM-8F38-12
15-Aug-10
Sch.
15-Aug-10
DCPLODT0218
14-Sep-10
14-Oct-10
13-Nov-10
Act.
9-Aug-10
14.77
LMTG-E0-02301 A11K933
13-Mar-10
Sch.
13-Mar-10
DCPLODT0102
12-Apr-10
DCPL -0095
12-May-10
11-Jun-10
Act.
22-Mar-10
24-Apr-10
14.78
LMTG-E0-02302 A11K934
13-Mar-10
Sch.
13-Mar-10
DCPLODT0102
12-Apr-10
DCPL -0127
12-May-10
DCPLODT0264
11-Jun-10
Act.
22-Mar-10
11-Jun-10
17-Sep-10
Page 56 of 12
:LT-P0-00003
C 14.79 Turbine Generator Seal Oil Diagram LMTG-E0-02303 A11K935 13-Mar-10 A Sch. 13-Mar-10 DCPLODT0155 12-Apr-10 12-May-10 11-Jun-10 Act. 4-Jun-10
14.80
LMTG-E0-02304 A11K936
13-Mar-10
Sch.
13-Mar-10
DCPLODT0155
12-Apr-10
DCPL -0166
12-May-10
11-Jun-10
Act.
4-Jun-10
25-Aug-10
14.81
LMTG-E0-02305 A11K768
15-Dec-09
Sch.
15-Dec-09
DCPLODT0030-0
14-Jan-10
DCPL -0021
13-Feb-10
DCPLODT0096-A
15-Mar-10
DCPL 0085-A
14-Apr-10
DCPLODT0140-B
14-May-10
DCPL -0119
24-May-10
Act.
22-Dec-09
5-Jan-10
16-Mar-10
7-Apr-10
11-May-10
24-May-10
14.82
LMTG-E0-02306 A11K937
1-May-10
Sch.
1-May-10
DCPLODT0138
31-May-10
DCPl -0167
30-Jun-10
30-Jul-10
Act.
29-Apr-10
25-Aug-10
14.83
LMTG-E0-02307 A11K938
1-May-10
Sch.
1-May-10
DCPLODT0138
31-May-10
DCPl -0167
30-Jun-10
30-Jul-10
Act.
29-Apr-10
25-Aug-10
14.84
LMTG-E0-02308 ASO2382
1-May-10
Sch.
1-May-10
DCPLODT0138
31-May-10
DCPl -0167
30-Jun-10
30-Jul-10
Act.
29-Apr-10
25-Aug-10
14.85
LMTG-E0-02309 ASO2383
1-May-10
Sch.
1-May-10
DCPLODT0126
31-May-10
DCPL -0125
30-Jun-10
DCPLODT0224
30-Jul-10
8-Jun-10
Act.
23-Apr-10
8-Jun-10
12-Aug-10
14.86
LMTG-E0-02310 ASO2384
1-May-10
Sch.
1-May-10
DCPLODT0126
31-May-10
DCPL -0125
30-Jun-10
DCPLODT0224
30-Jul-10
8-Jun-10
Act.
23-Apr-10
8-Jun-10
12-Aug-10
14.87
LMTG-E0-02311 ASO2385
1-May-10
Sch.
1-May-10
DCPLODT0126
31-May-10
DCPL -0172
30-Jun-10
30-Jul-10
Act.
23-Apr-10
30-Aug-10
14.88
LMTG-E0-02312 ASO2386
1-May-10
Sch.
1-May-10
DCPLODT0126
31-May-10
DCPL -0125
30-Jun-10
DCPLODT0224
30-Jul-10
8-Jun-10
Act.
23-Apr-10
8-Jun-10
12-Aug-10
14.89
LMTG-E0-02313 ASO2387
1-May-10
Sch.
1-May-10
DCPLODT0126
31-May-10
DCPL -0172
30-Jun-10
30-Jul-10
Act.
23-Apr-10
30-Aug-10
14.90
LMTG-E0-02314 ASO2388
1-May-10
Sch.
1-May-10
DCPLODT0126
31-May-10
DCPL -0172
30-Jun-10
30-Jul-10
Act.
23-Apr-10
30-Aug-10
14.91
LMTG-E0-02315 A11K775
27-Mar-10
Sch.
27-Mar-10
DCPLODT0100
26-Apr-10
DCPl -0090
26-May-10
DCPLODT0189
25-Jun-10
DCPl 0156
25-Jul-10
DCPLODT0252
Act.
18-Mar-10
20-Apr-10
17-Jul-10
28-Jul-10
7-Sep-10
14.92
LMTG-E0-02316 A11K967
15-Jul-10
Sch.
15-Jul-10
DCPLODT0201
14-Aug-10
13-Sep-10
13-Oct-10
Act.
20-Jul-10
14.93
LMTG-E0-02317 A11K769
27-Mar-10
Sch.
27-Mar-10
DCPLODT0113
26-Apr-10
DCPL -0105
26-May-10
25-Jun-10
Act.
5-Apr-10
3-May-10
14.94
LMTG-E0-02318 A11K770
27-Mar-10
Sch.
27-Mar-10
DCPLODT0113
26-Apr-10
DCPL -0105
26-May-10
25-Jun-10
Act.
5-Apr-10
3-May-10
14.95
LMTG-E0-02319 A11K771
27-Mar-10
Sch.
27-Mar-10
DCPLODT0113
26-Apr-10
DCPL -0105
26-May-10
25-Jun-10
Act.
5-Apr-10
3-May-10
14.96
LMTG-E0-02320 A11K772
27-Mar-10
Sch.
27-Mar-10
DCPLODT0113
26-Apr-10
DCPL -0105
26-May-10
25-Jun-10
Act.
5-Apr-10
3-May-10
14.97
LMTG-E0-02321 A11K773
27-Mar-10
Sch.
27-Mar-10
DCPLODT0113
26-Apr-10
DCPL -0105
26-May-10
25-Jun-10
Act.
5-Apr-10
3-May-10
14.98
LMTG-E0-02322 A11K774
27-Mar-10
Sch.
27-Mar-10
DCPLODT0113
26-Apr-10
DCPL -0105
26-May-10
25-Jun-10
Act.
5-Apr-10
3-May-10
14.99
LMTG-E0-02323 A11K939
1-May-10
Sch.
1-May-10
31-May-10
30-Jun-10
DCPLODT0252
30-Jul-10
Act.
7-Sep-10
14.100
LMTG-E0-02324 A11K940
1-May-10
Sch.
1-May-10
31-May-10
30-Jun-10
DCPLODT0252
30-Jul-10
Act.
7-Sep-10
14.101
LMTG-E0-02325 A11K941
1-May-10
Sch.
1-May-10
31-May-10
30-Jun-10
DCPLODT0252
30-Jul-10
Act.
7-Sep-10
14.102
LMTG-E0-02326 AS02549
9-Jan-10
Sch.
9-Jan-10
DCPLODT0044-0
8-Feb-10
DCPL -0150
10-Mar-10
DCPLODT0252
9-Apr-10
Act.
6-Jan-10
17-Jul-10
7-Sep-10
14.103
LMTG-E0-02327 A11K776
9-Jan-10
Sch.
9-Jan-10
DCPLODT0034-0
8-Feb-10
DCPL -0018
10-Mar-10
DCPLODT0096
9-Apr-10
Act.
29-Dec-09
2-Jan-10
16-Mar-10
Page 57 of 12
:LT-P0-00003
C 14.104 Turbine Generator Ground Connection Terminal Arrengement LMTG-E0-02328 AS02551 9-Jan-10 Sch. 9-Jan-10 DCPLODT0044 8-Feb-10 DCPL -0076 10-Mar-10 9-Apr-10 Act. 6-Jan-10 31-Mar-10
14.105
LMTG-E0-02329 AS02550
9-Jan-10
Sch.
9-Jan-10
DCPLODT0044
8-Feb-10
10-Mar-10
DCPLODT0085-0
9-Apr-10
DCPL 0132
15-Jun-10
Act.
6-Jan-10
12-Feb-10
15-Jun-10
14.106
LMTG-E0-02330 A11K777
1-May-10
Sch.
1-May-10
DCPLODT0127
31-May-10
DCPL -0150
30-Jun-10
DCPLODT0252
30-Jul-10
Act.
23-Apr-10
17-Jul-10
7-Sep-10
14.107
LMTG-E0-02331 A11K778
1-May-10
Sch.
1-May-10
DCPLODT0127
31-May-10
DCPL -0159
30-Jun-10
DCPLODT0252
30-Jul-10
Act.
23-Apr-10
3-Aug-10
7-Sep-10
14.108
LMTG-E0-02332 AS02389
1-May-10
Sch.
1-May-10
DCPLODT0209
31-May-10
30-Jun-10
30-Jul-10
Act.
26-Jul-10
14.109
LMTG-E0-02333 A11K942
31-Mar-10
Sch.
31-Mar-10
DCPLODT0124
30-Apr-10
DCPL -0150
30-May-10
DCPLODT0248
29-Jun-10
15-Jun-10
Act.
20-Apr-10
17-Jul-10
1-Sep-10
14.110
LMTG-E0-02334 A11K943
31-Mar-10
Sch.
31-Mar-10
DCPLODT0124
30-Apr-10
DCPL -0150
30-May-10
29-Jun-10
15-Jun-10
Act.
20-Apr-10
17-Jul-10
14.111
LMTG-E0-02335 A11K944
31-Mar-10
Sch.
31-Mar-10
DCPLODT0124
30-Apr-10
DCPL -0150
30-May-10
29-Jun-10
15-Jun-10
Act.
20-Apr-10
17-Jul-10
Page 58 of 12
:LT-P0-00003
Last Wk Rcvd
Submited Last Wk
Sr. No.
Description
FLAG
To Wk Rcvd Next
As Built Release
Unit No.
14.112
LMTG-E0-02336 A11K945
Date 31-Mar-10
Date 30-Apr-10
JNSTPP
L&T
Date 30-May-10
DTN No.
Date 29-Jun-10
I/W No.
JNSTPP
L&T
Date
DTN No.
Date
I/W No.
JNSTPP
L&T
Date
DTN No.
Date
I/W No.
JNSTPP
Date-Unit 1
DTN No 15-Jun-10
Act.
20-Apr-10
17-Jul-10
14.113
LMTG-E0-02337 A11K946
31-Mar-10
Sch.
31-Mar-10
DCPLODT0124
30-Apr-10
30-May-10
29-Jun-10
Act.
20-Apr-10
14.114
LMTG-E0-02338 A11K947
15-Jul-10
Sch.
15-Jul-10
DCPLODT0201
14-Aug-10
13-Sep-10
13-Oct-10
Act.
20-Jul-10
14.115
LMTG-E0-02339 A11K948
15-Jul-10
Sch.
15-Jul-10
DCPLODT0201
14-Aug-10
13-Sep-10
13-Oct-10
Act.
20-Jul-10
14.116
LMTG-E0-02340 A11K949
15-Jul-10
Sch.
15-Jul-10
DCPLODT0201
14-Aug-10
13-Sep-10
13-Oct-10
Act.
20-Jul-10
14.117
LMTG-E0-02341 A11K950
15-Jul-10
Sch.
15-Jul-10
DCPLODT0201
14-Aug-10
13-Sep-10
13-Oct-10
Act.
20-Jul-10
14.118
LMTG-E0-02342 A11K951
15-Jul-10
Sch.
15-Jul-10
DCPLODT0201
14-Aug-10
13-Sep-10
13-Oct-10
Act.
20-Jul-10
14.119
LMTG-E0-02343 A11K952
15-Jul-10
Sch.
15-Jul-10
DCPLODT0201
14-Aug-10
13-Sep-10
13-Oct-10
Act.
20-Jul-10
14.120
LMTG-E0-02344 A11K953
15-Jul-10
Sch.
15-Jul-10
DCPLODT0201
14-Aug-10
13-Sep-10
13-Oct-10
Act.
20-Jul-10
14.121
LMTG-E0-02345 A11K954
15-Jul-10
Sch.
15-Jul-10
DCPLODT0201
14-Aug-10
13-Sep-10
13-Oct-10
Act.
20-Jul-10
14.122
LMTG-E0-02346 A11K955
15-Jul-10
Sch.
15-Jul-10
DCPLODT0201
14-Aug-10
13-Sep-10
13-Oct-10
Act.
20-Jul-10
14.123
LMTG-E0-02347 A11K956
15-Jul-10
Sch.
15-Jul-10
DCPLODT0201
14-Aug-10
13-Sep-10
13-Oct-10
Act.
20-Jul-10
14.124
LMTG-E0-02348 A11K957
15-Jul-10
Sch.
15-Jul-10
DCPLODT0201
14-Aug-10
13-Sep-10
13-Oct-10
Act.
20-Jul-10
14.125
LMTG-E0-02349 A11K958
15-Jul-10
Sch.
15-Jul-10
DCPLODT0201
14-Aug-10
13-Sep-10
13-Oct-10
Act.
20-Jul-10
14.126
LMTG-E0-02350 A11K959
15-Jul-10
Sch.
15-Jul-10
DCPLODT0201
14-Aug-10
13-Sep-10
13-Oct-10
Act.
20-Jul-10
14.127
LMTG-E0-02351 A11K960
15-Jul-10
Sch.
15-Jul-10
DCPLODT0201
14-Aug-10
13-Sep-10
13-Oct-10
Act.
20-Jul-10
14.128
LMTG-E0-02352 A11K961
15-Jul-10
Sch.
15-Jul-10
DCPLODT0201
14-Aug-10
13-Sep-10
13-Oct-10
Act.
20-Jul-10
14.129
LMTG-E0-02353 A11K962
15-Jul-10
Sch.
15-Jul-10
DCPLODT0201
14-Aug-10
13-Sep-10
13-Oct-10
Page 59 of 12
:LT-P0-00003
Act. 20-Jul-10 C 14.130 Turbine Generator Gas & Seal Oil Piping (10 / 10) LMTG-E0-02354 A11K963 15-Jul-10 Sch. 15-Jul-10 DCPLODT0201 14-Aug-10 13-Sep-10 13-Oct-10
Act.
20-Jul-10
14.131
LMTG-E0-02355 A11K964
15-Jul-10
Sch.
15-Jul-10
DCPLODT0201
14-Aug-10
13-Sep-10
13-Oct-10
Act.
20-Jul-10
14.132
LMTG-E0-02356 A11K965
15-Jul-10
Sch.
15-Jul-10
DCPLODT0201
14-Aug-10
13-Sep-10
13-Oct-10
Act.
20-Jul-10
14.133
LMTG-E0-02357 A11K966
31-Mar-10
Sch.
31-Mar-10
DCPLODT0201
30-Apr-10
30-May-10
29-Jun-10
Act.
20-Jul-10
14.137
LMTG-E0-02361 AS02552
9-Jan-10
Sch.
9-Jan-10
DCPLODT0044-0
8-Feb-10
DCPL -0132
10-Mar-10
DCPLODT02852
9-Apr-10
15-Jun-10
Act.
6-Jan-10
16-May-10
7-Sep-10
14.138
LMTG-E0-02362 AS02553
9-Jan-10
Sch.
9-Jan-10
DCPLODT0044-0
8-Feb-10
DCPL 0132
10-Mar-10
DCPLODT0252
9-Apr-10
15-Jun-10
Act.
6-Jan-10
16-May-10
7-Sep-10
14.139
LMTG-E0-02363 A35E036
9-Jan-10
Sch.
9-Jan-10
DCPLODT0044-0
8-Feb-10
DCPL 0132
10-Mar-10
9-Apr-10
15-Jun-10
Act.
6-Jan-10
16-May-10
14.160
Outline Dimensions and unit Data sheet of Unit 1 & 2 DC motor Starter
LMTG-E0-02601 09JNG723A0B00
16-Mar-10
Sch.
16-Mar-10
15-Apr-10
15-May-10
DCPLODT0264
14-Jun-10
Act.
17-Sep-10
14.161
LMTG-E0-02602 09JNG723F0B00
16-Mar-10
Sch.
16-Mar-10
15-Apr-10
15-May-10
DCPLODT0266
14-Jun-10
Act.
17-Sep-10
14.164
LMTG-E0-02605 JNM005C682P31
16-Mar-10
Sch.
16-Mar-10
DCPLODT0104
15-Apr-10
DCPL -0086
15-May-10
DCPLODT0267
14-Jun-10
Act.
23-Mar-10
7-Apr-10
17-Sep-10
14.179
LMTG-E0-02801 BC22689
20-Mar-10
Sch.
20-Mar-10
DCPLODT0157-B
19-Apr-10
DCPL 0138
19-May-10
DCPLODT0192
18-Jun-10
DCPL 0155
16-Sep-10
DCPLODT0268
28-Jul-10
Act.
5-Jun-10
18-Jun-10
19-Jul-10
28-Jul-10
17-Sep-10
14.180
LMTG-E0-02802 BC22690
20-Mar-10
Sch.
20-Mar-10
DCPLODT0157-B
19-Apr-10
DCPL 0138
19-May-10
DCPLODT0192
18-Jun-10
DCPL 0155
16-Sep-10
DCPLODT0268
28-Jul-10
Act.
5-Jun-10
18-Jun-10
19-Jul-10
28-Jul-10
17-Sep-10
14.181
LMTG-E0-02803 BC22691
20-Mar-10
Sch.
20-Mar-10
DCPLODT0157-B
19-Apr-10
DCPL 0138
19-May-10
DCPLODT0192
18-Jun-10
DCPL 0155
16-Sep-10
DCPLODT0268
28-Jul-10
Act.
5-Jun-10
18-Jun-10
19-Jul-10
28-Jul-10
17-Sep-10
14.182
Outline Dimensions of AC Motor for Main Oil Tank Oil Transfer Pump
LMTG-E0-02804 BC22692
20-Mar-10
Sch.
20-Mar-10
DCPLODT0145
19-Apr-10
DCPL 0138
19-May-10
DCPLODT0192
18-Jun-10
DCPL 0155
18-Jul-10
DCPLODT0268
28-Jul-10
Act.
18-May-10
18-Jun-10
19-Jul-10
28-Jul-10
17-Sep-10
14.183
LMTG-E0-02805 BC22693
20-Mar-10
Sch.
20-Mar-10
DCPLODT0145
19-Apr-10
DCPL 0138
19-May-10
DCPLODT0192
18-Jun-10
DCPL 0155
18-Jul-10
DCPLODT0268
28-Jul-10
Act.
18-May-10
18-Jun-10
19-Jul-10
28-Jul-10
17-Sep-10
14.184
LMTG-E0-02806 BC22694
20-Mar-10
Sch.
20-Mar-10
DCPLODT0145
19-Apr-10
DCPL 0138
19-May-10
DCPLODT0192
18-Jun-10
DCPL 0155
18-Jul-10
DCPLODT0268
28-Jul-10
Act.
18-May-10
18-Jun-10
19-Jul-10
28-Jul-10
17-Sep-10
14.185
Outline Dimensions of AC Motor for Main Oil Tank Vapour Extractor Fan (A)
LMTG-E0-02807 BC22695
20-Mar-10
Sch.
20-Mar-10
DCPLODT0145
19-Apr-10
DCPL 0138
19-May-10
DCPLODT0192
18-Jun-10
DCPL 0155
18-Jul-10
DCPLODT0267
28-Jul-10
Act.
18-May-10
18-Jun-10
19-Jul-10
28-Jul-10
17-Sep-10
14.186
Outline Dimensions of AC Motor for Main Oil Tank Vapour Extractor Fan (B)
LMTG-E0-02808
20-Mar-10
Sch.
20-Mar-10
DCPLODT0145
19-Apr-10
DCPL 0138
19-May-10
DCPLODT0192
18-Jun-10
DCPL 0155
18-Jul-10
DCPLODT0267
28-Jul-10
BC22696
Act.
18-May-10
18-Jun-10
19-Jul-10
28-Jul-10
17-Sep-10
15
_
C C
15.1
15.2
97000-2381-8
6-Jan-10
Sch.
6-Jan-10
DCPLODT0045
5-Feb-10
13-May-10
Act.
6-Jan-10
15.3
97000-2281
6-Jan-10
Sch.
6-Jan-10
DCPLODT0045
5-Feb-10
13-May-10
Act.
6-Jan-10
Page 60 of 12
:LT-P0-00003
C 15.4 Legend for P&I Diagram 97000-2110 28-Jun-10 Sch. 28-Jun-10 LMB-531 Rev - 1 28-Jun-10
28-Jun-10
Act.
15.4
97000-2111-1
28-Jun-10
Sch.
28-Jun-10
28-Jun-10
Act.
15.4
97000-2135-1
28-Jun-10
Sch.
28-Jun-10
28-Jun-10
Act.
15.4
97000-2135-1-2
28-Jun-10
Sch.
28-Jun-10
28-Jun-10
Act.
15.4
97000-2112-1
28-Jun-10
Sch.
28-Jun-10
28-Jun-10
Act.
15.4
97000-2111-2
28-Jun-10
Sch.
28-Jun-10
28-Jun-10
Act.
15.4
97000-2112-2
28-Jun-10
Sch.
28-Jun-10
28-Jun-10
Act.
Page 61 of 12
:LT-P0-00003
Last Wk Rcvd
Submited Last Wk
Sr. No.
Description
FLAG
To Wk Rcvd Next
As Built Release
Unit No.
Date
DTN No.
Date
I/W No.
JNSTPP
L&T
Date
DTN No.
Date
I/W No.
JNSTPP
L&T
Date
DTN No.
Date
I/W No.
JNSTPP
L&T
Date
DTN No.
Date
I/W No.
JNSTPP
Date-Unit 1
DTN No
5-Dec-10
Act.
15-Oct-09
6-Nov-09
23-Nov-09
5-Dec-09
16.1.1.4
QAP - LP Heater
LT-QO-03002
15-Oct-09
Sch.
15-Oct-09
DCPLODT0004
14-Nov-09
DCPL -0003
14-Dec-09
DCPLODT0017
13-Jan-10
DCPL -0009
5-Dec-10
Act.
15-Oct-09
6-Nov-09
23-Nov-09
5-Dec-09
16.1.2
HP Heater 8A / 8B
16.1.2.1
LT-M0-03057
12-Jan-10
Sch.
12-Jan-10
DCPLODT0043
11-Feb-10
DCPL 0073
13-Mar-10
DCPLODT0114
12-Apr-10
DCPL 0091
11-Jul-10
DCPLODT0273
23-Apr-10
Act.
4-Jan-10
24-Mar-10
9-Apr-10
23-Apr-10
18-Sep-10
16.1.2.2
LT-M0-03058
30-Jan-10
Sch.
30-Jan-10
DCPLODT0071
1-Mar-10
DCPL -0114
31-Mar-10
30-Apr-10
Act.
22-Jan-10
14-May-10
16.1.2.3
LT-M0-03059
14-Apr-10
Sch.
14-Apr-10
14-May-10
13-Jun-10
13-Jul-10
12-Aug-10
DCPLODT0180
Act.
14-Jul-10
16.1.2.4
LT-M0-03060
14-Feb-10
Sch.
14-Feb-10
DCPLODT0122
16-Mar-10
DCPL 0121
15-Apr-10
15-May-10
Act.
15-Apr-10
1-Jun-10
16.1.3
16.1.3.1
LT-M0-03062
30-Jan-10
Sch.
30-Jan-10
DCPLODT0071
1-Mar-10
DCPL 0114
31-Mar-10
30-Apr-10
Act.
22-Jan-10
14-May-10
16.1.3.2
LT-M0-03063
14-Apr-10
Sch.
14-Apr-10
14-May-10
13-Jun-10
DCPLODT0180
13-Jul-10
Act.
14-Jul-10
16.1.3.3
LT-M0-03064
14-Feb-10
Sch.
14-Feb-10
DCPLODT0122
16-Mar-10
DCPL 0121
15-Apr-10
15-May-10
Act.
15-Apr-10
1-Jun-10
16.1.4
Hp Heater 6A / 6B
~C ~ C
16.1.4.1
LT-M0-03066
30-Jan-10
Sch.
30-Jan-10
DCPLODT0071
1-Mar-10
DCPL 0114
31-Mar-10
30-Apr-10
Act.
22-Jan-10
14-May-10
CC
16.1.4.2
LT-M0-03067
14-Apr-10
Sch.
14-Apr-10
14-May-10
13-Jun-10
DCPLODT0181
13-Jul-10
Act.
14-Jul-10
CC
16.1.4.3
LT-M0-03068
14-Feb-10
Sch.
14-Feb-10
DCPLODT0122
16-Mar-10
DCPL 0121
15-Apr-10
15-May-10
Act.
15-Apr-10
1-Jun-10
16.1.5
16.1.5.1
LT-M0-03070
12-Jan-10
Sch.
12-Jan-10
DCPLODT0043
11-Feb-10
DCPL -0068
13-Mar-10
DCPLODT0114
12-Apr-10
DCPL 0091
11-Jul-10
DCPLODT0273
23-Apr-10
Act.
4-Jan-10
15-Mar-10
9-Apr-10
18-Sep-10
16.1.5.2
LT-M0-03071
30-Jan-10
Sch.
30-Jan-10
DCPLODT0071-0
1-Mar-10
DCPL 0118
31-Mar-10
30-Apr-10
Act.
22-Jan-10
24-May-10
16.1.5.3
LT-M0-03072
14-Apr-10
Sch.
14-Apr-10
14-May-10
13-Jun-10
DCPLODT0181
13-Jul-10
Page 62 of 12
:LT-P0-00003
Act. 14-Jul-10
15-May-10
16.1.5.4
LT-M0-03073
14-Feb-10
Sch.
14-Feb-10
DCPLODT0122
16-Mar-10
DCPL 0121
15-Apr-10
Act.
15-Apr-10
1-Jun-10
16.1.6
LP Heater 3
16.1.6.1
LT-M0-03075
30-Jan-10
Sch.
30-Jan-10
DCPLODT0071+0
1-Mar-10
DCPL 0118
31-Mar-10
30-Apr-10
Act.
22-Jan-10
24-May-10
16.1.6.2
LT-M0-03076
14-Apr-10
Sch.
14-Apr-10
14-May-10
13-Jun-10
DCPLODT0179
13-Jul-10
Act.
14-Jul-10
16.1.6.3
LT-M0-03077
14-Feb-10
Sch.
14-Feb-10
DCPLODT0122
16-Mar-10
DCPL 0121
15-Apr-10
15-May-10
Act.
15-Apr-10
1-Jun-10
16.1.7
16.1.7.1
LT-M0-03079
12-Jan-10
Sch.
12-Jan-10
DCPLODT0043
11-Feb-10
DCPL 0073
13-Mar-10
DCPLODT0114
12-Apr-10
DCPL 0091
11-Jul-10
DCPLODT0273
23-Apr-10
Act.
4-Jan-10
24-Mar-10
9-Apr-10
18-Sep-10
16.1.7.2
GA Drawing for Duplex LP Heater (Including Sectional View & Internal Details)
LT-M0-03080
30-Jan-10
Sch.
30-Jan-10
DCPLODT0071-0
1-Mar-10
DCPL 0118
31-Mar-10
30-Apr-10
Act.
22-Jan-10
24-May-10
16.1.7.3
LT-M0-03081
14-Apr-10
Sch.
14-Apr-10
14-May-10
13-Jun-10
DCPLODT0179
13-Jul-10
Act.
14-Jul-10
VDR - Condenser
Engg. Drawing & Documents Filled - in - Datasheet LT-M0-03000-DS 12-Jan-10 A Sch. 12-Jan-10 DCPLODT0043 11-Feb-10 DCPL 0060 13-Mar-10 DCPLODT0086 12-Apr-10
Act.
4-Jan-10
4-Mar-10
18-Feb-10
9-Apr-10
23-Apr-10
18-Sep-10
16.2.1.2
LT-M0-03002
25-Dec-09
Sch.
25-Dec-09
DCPLODT0043
24-Jan-10
DCPl 0166
23-Feb-10
25-Mar-10
Act.
4-Jan-10
25-Aug-10
16.2.1.3
QAP - Condenser
LT-QO-03000
15-Oct-09
Sch.
15-Oct-09
DCPLODT0004
14-Nov-09
DCPL 0003
14-Dec-09
DCPLODT0017
13-Jan-10
DCPL 0009
12-Feb-10
DCPLODT0273
5-Dec-10
Act.
15-Oct-09
6-Nov-09
23-Nov-09
5-Dec-09
18-Sep-10
16.2.1.4
LT-M0-03000
30-Jan-10
Sch.
30-Jan-10
DCPLODT0071
1-Mar-10
DCPL 0115
31-Mar-10
30-Apr-10
Act.
22-Jan-10
17-May-10
16.2.1.5
LT-M0-03001
30-Jan-10
Sch.
30-Jan-10
DCPLODT0071
1-Mar-10
DCPL 0115
31-Mar-10
30-Apr-10
Act.
22-Jan-10
17-May-10
16.2.1.6
LT-M0-03003
12-Jan-10
Sch.
12-Jan-10
DCPLODT0043-0
11-Feb-10
13-Mar-10
12-Apr-10
Act.
4-Jan-10
16.2.1.7
LT-M0-03004
15-Apr-10
Sch.
15-Apr-10
DCPLODT0122-0
15-May-10
DCPL 0130
14-Jun-10
14-Jul-10
Act.
15-Apr-10
15-Jun-10
16.2.1.8
LT-M0-03005
15-Apr-10
Sch.
15-Apr-10
DCPLODT0122-0
15-May-10
DCPL 0130
14-Jun-10
14-Jul-10
Act.
15-Apr-10
15-Jun-10
16.2.1.9
LT-M0-03006
15-Apr-10
Sch.
15-Apr-10
DCPLODT0122-0
15-May-10
DCPL -0128
14-Jun-10
14-Jul-10
11-Jun-10
Act.
15-Apr-10
11-Jun-10
16.2.1.10
LT-M0-03007
15-Apr-10
Sch.
15-Apr-10
DCPLODT0122-0
15-May-10
DCPL 0128
14-Jun-10
14-Jul-10
11-Jun-10
Act.
15-Apr-10
11-Jun-10
16.2.2
Manufacturing Documents
16.2.2.4
LT-M0-03015
15-May-10
Sch.
15-May-10
DCPLODT0237
14-Jun-10
14-Jul-10
13-Aug-10
Act.
20-Aug-10
16.2.2.5
LT-M0-03016
15-Apr-10
Sch.
15-Apr-10
DCPLODT0150
15-May-10
DCPL 0144
14-Jun-10
14-Jul-10
13-Aug-10
DCPLODT0237
Act.
25-May-10
6-Jul-10
20-Aug-10
16.2.2.7
LT-M0-03018
15-Apr-10
Sch.
15-Apr-10
DCPLODT0150
15-May-10
DCPL 0144
14-Jun-10
DCPLODT0237
14-Jul-10
Act.
25-May-10
6-Jul-10
20-Aug-10
16.2.2.8
LT-M0-03019
15-Apr-10
Sch.
15-Apr-10
DCPLODT0150
15-May-10
DCPL 0144
14-Jun-10
14-Jul-10
Act.
25-May-10
6-Jul-10
16.2.2.9
LT-M0-03020
15-Apr-10
Sch.
15-Apr-10
DCPLODT0150
15-May-10
DCPL 0144
14-Jun-10
14-Jul-10
6-Jul-10
Act.
25-May-10
6-Jul-10
16.2.2.10
LT-M0-03021
15-Apr-10
Sch.
15-Apr-10
DCPLODT0150
15-May-10
DCPL -0144
14-Jun-10
14-Jul-10
6-Jul-10
Page 63 of 12
:LT-P0-00003
Act. 25-May-10 6-Jul-10 C 16.2.2.11 Post weld Heat Treatment Procedure LT-M0-03022 15-Apr-10 Sch. 15-Apr-10 DCPLODT0150 15-May-10 DCPL 0144 14-Jun-10 DCPLODT0237 14-Jul-10
Act.
25-May-10
6-Jul-10
20-Aug-10
16.2.2.12
LT-M0-03023
15-Apr-10
Sch.
15-Apr-10
DCPLODT0150
15-May-10
DCPL 0144
14-Jun-10
DCPLODT0273
14-Jul-10
Act.
25-May-10
6-Jul-10
18-Sep-10
16.2.2.13
LT-M0-03025
20-Sep-10
20-Sep-10
DCPLODT0272
20-Oct-10
Extra
20-Sep-10
16.2.2.14
LT-M0-03117
20-Sep-10
20-Sep-10
DCPLODT0272
20-Oct-10
Extra
20-Sep-10
16.2.2.15
LT-M0-03094
20-Sep-10
20-Sep-10
DCPLODT0272
20-Oct-10
13-Mar-10 12-Apr-10 DCPL 0078 12-May-10 11-Jun-10 DCPL 0131 11-Jul-10 DCPLODT0245
Extra
20-Sep-10
VDR - Deaerator
Engg. Drawing & Documents Filled-in-Datasheet with Technical schedule LT-M0-03100-DS 12-Jan-10 A Sch. 12-Jan-10 DCPLODT0072 11-Feb-10 DCPL -0078 DCPLODT0074 DCPLODT0139
Act.
1-Feb-10
3-Apr-10
2-Feb-10
3-Apr-10
10-May-10
15-Jun-10
30-Aug-10
16.3.1.2
GA drawing of Deaerator
LT-M0-03100
30-Jan-10
Sch.
30-Jan-10
DCPLODT0139-1
1-Mar-10
DCPL 0146
31-Mar-10
30-Apr-10
Act.
10-May-10
9-Jul-10
Page 64 of 12
:LT-P000003 :4.2 :A
Submited Last Wk
Submited Last Wk
L&T I Sch.
16.3.1.3
LT-M0-03101
Date 12-Jan-10
Date 11-Feb-10
JNSTPP
L&T
Date 13-Mar-10
DTN No.
Date 12-Apr-10
I/W No.
JNSTPP
L&T
Submited Last Wk
Sr. No.
Description
Schedule
Unit No.
Date
DTN No.
Date
I/W No.
JNSTPP
L&T
Date
DTN No.
Date
I/W No.
JNSTPP
Date-Unit 1
DTN No
Act.
2-Feb-10
3-Apr-10
16.3.1.6
QAP - Deaerator
LT-QO-03003
15-Oct-09
Sch.
15-Oct-09
DCPLODT0004
14-Nov-09
DCPL 0003
14-Dec-09
DCPLODT0017
13-Jan-10
DCPL 0009
5-Dec-10
Act.
15-Oct-09
6-Nov-09
23-Nov-09
5-Dec-09
17 17.1 C 17.1.3
VDR - Boiler Feed Pump (TD & MD) Motor Driven Boiler Feed Pump
Complete Group General Arrnagment drawing FPD-C0-03305 1-Sep-10 I Sch. 1-Sep-10 DCPLODT0235 1-Oct-10 31-Oct-10 30-Nov-10
23-Aug-10
17.1.9
Sch.
1-Sep-10
DCPLODT0240
1-Oct-10
31-Oct-10
30-Nov-10
23-Aug-10
17.1.15
Sch.
1-Sep-10
DCPLODT0235
1-Oct-10
DCPL -0180
31-Oct-10
30-Nov-10
23-Aug-10
15-Sep-10
17.1.76
Sch.
5-Sep-10
DCPLODT0240
5-Oct-10
4-Nov-10
4-Dec-10
Act.
23-Aug-10
17.2
17.2.3
Act.
23-Aug-10
17.2.14
FPD-M0-03384
1-Sep-10
Sch.
1-Sep-10
DCPLODT0235
1-Oct-10
DCPL 0180
31-Oct-10
30-Nov-10
Act.
23-Aug-10
15-Sep-10
17.2.69
FPD-M0-03311
1-Sep-10
Sch.
1-Sep-10
DCPLODT0240
1-Oct-10
31-Oct-10
30-Nov-10
Act.
23-Aug-10
18 19 C 19.1
VDR - Steam Turbine Drive VDR - EOT Cranes VDR - EOT Crane for TG Building
Data sheet of 115/15 T TG Hall EOT Crane (Double Girder) AIL-M0-03201 25-Jun-10 A Sch. 25-Jun-10 25-Jul-10 24-Aug-10 DCPLODT0185 23-Sep-10 DCPL -0164 23-Oct-10 DCPLODT0231 22-Nov-10 DCPL -0179
19.3
AIL-M0-03203
25-Jun-10
Sch.
25-Jun-10
25-Jul-10
24-Aug-10
DCPLODT0186
23-Sep-10
DCPL 0182
Act.
16-Jul-10
15-Sep-10
19.4
AIL-M0-03204
27-Jun-10
Sch.
27-Jun-10
27-Jul-10
26-Aug-10
25-Sep-10
25-Oct-10
DCPLODT0190
24-Nov-10
DCPL 0164
24-Dec-10
DCPLODT0251
Act.
17-Jul-10
10-Aug-10
7-Sep-10
19.5
AIL-M0-03205
27-Jun-10
Sch.
27-Jun-10
27-Jul-10
26-Aug-10
25-Sep-10
25-Oct-10
DCPLODT0190
24-Nov-10
DCPL 0164
24-Dec-10
DCPLODT0251
Act.
17-Jul-10
10-Aug-10
7-Sep-10
19.6
AIL-M0-03206
15-Jul-10
Sch.
15-Jul-10
14-Aug-10
13-Sep-10
DCPLODT0247
13-Oct-10
Act.
30-Aug-10
19.7
General arrangement for PVC shrouded conductor type DSL for 115/15T TG Hall EOT crane
AIL-M0-03207
15-Jul-10
Sch.
15-Jul-10
14-Aug-10
13-Sep-10
DCPLO -DT0234
13-Oct-10
DCPl 0177
Act.
18-Aug-10
15-Sep-10
19.8
AIL-M0-03208
15-Jul-10
Sch.
15-Jul-10
14-Aug-10
13-Sep-10
DCPLODT0247
13-Oct-10
Act.
30-Aug-10
19.9
AIL-M0-03209
15-Jul-10
Sch.
15-Jul-10
14-Aug-10
13-Sep-10
DCPLODT0247
13-Oct-10
Act.
30-Aug-10
19.10
AIL-M0-03210
15-Jul-10
Sch.
15-Jul-10
14-Aug-10
13-Sep-10
DCPLODT0247
13-Oct-10
Page 65 of 12
:LT-P0-00003
Act. 30-Aug-10 C 19.11 LT idle wheel assembly AIL-M0-03211 15-Ju l -10 Sch. 15-Jul-10 14-Aug-10 13-Sep-10 DCPLODT0247 13-Oct-10
Act.
30-Aug-10
19.12
AIL-M0-03212
15-Jul-10
Sch.
15-Jul-10
14-Aug-10
13-Sep-10
DCPLODT0247
13-Oct-10
Act.
30-Aug-10
19.13
AIL-M0-03213
15-Jul-10
Sch.
15-Jul-10
14-Aug-10
13-Sep-10
DCPLODT0247
13-Oct-10
Act.
30-Aug-10
19.14
AIL-M0-03214
15-Jul-10
Sch.
15-Jul-10
14-Aug-10
13-Sep-10
DCPLODT0247
13-Oct-10
Act.
30-Aug-10
19.15 CC
AIL-M0-03215
27-Jun-10
Sch.
27-Jun-10
27-Jul-10
26-Aug-10
DCPLODT0234
25-Sep-10
DCPL 0177
15-Sep-10
Act.
18-Aug-10
15-Sep-10
Schematic circuit diagram of protective panel and lighting circuit for 115/15 19.16 T TGHall crane AIL-E0-03216 27-Jun-10
Sch.
27-Jun-10
27-Jul-10
26-Aug-10
DCPLODT0185
25-Sep-10
DCPL 0160
25-Oct-10
DCPLODT0225
24-Nov-10
DCPl 0165
Act.
16-Jul-10
3-Aug-10
12-Aug-10
25-Aug-10
19.17
Schematic circuit diagram of Main hoist panel for 115/15 T TGHall crane
AIL-E0-03217
27-Jun-10
Sch.
27-Jun-10
27-Jul-10
26-Aug-10
DCPLODT0185
25-Sep-10
DCPL -0160
25-Oct-10
DCPLODT0225
24-Nov-10
DCPl -0165
Act.
16-Jul-10
3-Aug-10
12-Aug-10
25-Aug-10
19.18
Schematic circuit diagram of Aux. hoist panel for 115/15 T TGHall crane
AIL-E0-03218
27-Jun-10
Sch.
27-Jun-10
27-Jul-10
26-Aug-10
DCPLODT0185
25-Sep-10
DCPL 0160
25-Oct-10
DCPLODT0225
24-Nov-10
DCPl 0165
Act.
16-Jul-10
3-Aug-10
12-Aug-10
25-Aug-10
19.19
Schematic circuit diagram of Cross Traverse and Micro Cross Traverse panel & BOM for 115/15 T TGHall crane
AIL-E0-03219
27-Jun-10
Sch.
27-Jun-10
27-Jul-10
26-Aug-10
DCPLODT0185
25-Sep-10
DCPL 0160
25-Oct-10
DCPLODT0225
24-Nov-10
DCPl 0165
Act.
16-Jul-10
3-Aug-10
12-Aug-10
25-Aug-10
19.20
Schematic circuit diagram of Long Traverse panel for for 115/15 T TGHall crane
AIL-E0-03220
27-Jun-10
Sch.
27-Jun-10
27-Jul-10
26-Aug-10
DCPLODT0185
25-Sep-10
DCPL 0160
25-Oct-10
DCPLODT0226
24-Nov-10
DCPl 0165
Act.
16-Jul-10
3-Aug-10
12-Aug-10
25-Aug-10
19.21
Bill of material for Main, Aux. Hoist, CT circuit, LT circuit and main (Pro ) circuit for 115/15 T TGHall
AIL-E0-03221
27-Jun-10
Sch.
27-Jun-10
27-Jul-10
26-Aug-10
DCPLODT0185
25-Sep-10
DCPL 0160
25-Oct-10
DCPLODT0226
24-Nov-10
DCPL 0165
Act.
16-Jul-10
3-Aug-10
12-Aug-10
25-Aug-10
19.22
G.A. drawing of Protective panel & transformer enclosure for 115/15 T TGHall crane
AIL-E0-03222
27-Jun-10
Sch.
27-Jun-10
27-Jul-10
26-Aug-10
DCPLODT0185
25-Sep-10
DCPL 0160
25-Oct-10
DCPLODT0226
24-Nov-10
DCPl 0165
Act.
16-Jul-10
3-Aug-10
12-Aug-10
25-Aug-10
19.23
AIL-E0-03223
27-Jun-10
Sch.
27-Jun-10
27-Jul-10
26-Aug-10
DCPLODT0185
25-Sep-10
DCPL 0160
25-Oct-10
DCPLODT0226
24-Nov-10
DCPl 0165
Act.
16-Jul-10
3-Aug-10
12-Aug-10
25-Aug-10
19.24
AIL-E0-03224
27-Jun-10
Sch.
27-Jun-10
27-Jul-10
26-Aug-10
DCPLODT0185
25-Sep-10
DCPL 0160
25-Oct-10
DCPLODT0226
24-Nov-10
DCPl 0165
Act.
16-Jul-10
3-Aug-10
12-Aug-10
25-Aug-10
19.25
AIL-E0-03225
27-Jun-10
Sch.
27-Jun-10
27-Jul-10
26-Aug-10
DCPLODT0185
25-Sep-10
DCPL -0160
25-Oct-10
DCPLODT0226
24-Nov-10
DCPl -0165
Act.
16-Jul-10
3-Aug-10
12-Aug-10
25-Aug-10
19.26
AIL-E0-03226
27-Jun-10
Sch.
27-Jun-10
27-Jul-10
26-Aug-10
DCPLODT0185
25-Sep-10
DCPL 0160
25-Oct-10
DCPLODT0226
24-Nov-10
DCPl 0165
3-Aug-10
Act.
16-Jul-10
3-Aug-10
12-Aug-10
25-Aug-10
19.27
AIL-E0-03227
15-Ju -10
Sch.
15-Jul-10
14-Aug-10
13-Sep-10
DCPLODT0203
13-Oct-10
DCPL 0162
12-Nov-10
DCPLODT0226
12-Dec-10
DCPl 0165
3-Aug-10
Act.
20-Jul-10
3-Aug-10
12-Aug-10
25-Aug-10
19.28
AIL-E0-03228
27-Jun-10
Sch.
27-Jun-10
27-Jul-10
26-Aug-10
DCPLODT0203
25-Sep-10
DCPL 0160
25-Oct-10
DCPLODT0226
24-Nov-10
DCPl 0165
Act.
20-Jul-10
3-Aug-10
12-Aug-10
25-Aug-10
19.29
AIL-E0-03229
27-Jun-10
Sch.
27-Jun-10
27-Jul-10
26-Aug-10
DCPLODT0186
25-Sep-10
DCPL 0161
25-Oct-10
DCPLODT0226
24-Nov-10
DCPl 0165
Act.
16-Jul-10
3-Aug-10
12-Aug-10
25-Aug-10
19.30
Crane lubrication
AIL-M0-03230
15-Ju -10
Sch.
15-Jul-10
14-Aug-10
13-Sep-10
DCPLODT0247
13-Oct-10
Act.
30-Aug-10
19.31
AIL-M0-03231
15-Ju -10
Sch.
15-Jul-10
DCPLODT0231
14-Aug-10
13-Sep-10
13-Oct-10
Act.
17-Aug-10
19.34
AIL-M0-03234
15-Ju -10
Sch.
15-Jul-10
14-Aug-10
13-Sep-10
13-Oct-10
Act.
12-Aug-10
25-Aug-10
19.35
AIL-M0-03235
27-Jun-10
Sch.
27-Jun-10
27-Jul-10
26-Aug-10
DCPLODT0186
25-Sep-10
DCPL 0161
25-Oct-10
DCPLODT0227
24-Nov-10
DCPL 0165
Act.
16-Jul-10
3-Aug-10
12-Aug-10
25-Aug-10
19.36
Earthing details
AIL-M0-03236
15-Ju -10
Sch.
15-Jul-10
14-Aug-10
13-Sep-10
DCPLODT0203
13-Oct-10
DCPL 0162
12-Nov-10
DCPLODT0227
12-Dec-10
DCPl 0165
3-Aug-10
Act.
20-Jul-10
3-Aug-10
12-Aug-10
26-Aug-10
Page 66 of 12
:LT-P000003 :4.2 :A
C 19.44 DSL Sizing Calculation for 115/15 T TG Hall EOT Crane AIL-M0-03243 13-Aug-10 Sch. 13-Aug-10 12-Sep-10 12-Oct-10 DCPLODT0227 11-Nov-10 Act. 12-Aug-10
Act.
17-Aug-10
15-Sep-10
19.3
AIL-M0-03253
28-Jul-10
Sch.
28-Jul-10
DCPLODT0228
27-Aug-10
26-Sep-10
26-Oct-10
Act.
13-Aug-10
19.4
AIL-M0-03254
26-Jul-10
Sch.
26-Jul-10
DCPLODT0234
25-Aug-10
24-Sep-10
24-Oct-10
Act.
23-Aug-10
19.5
AIL-M0-03255
26-Jul-10
Sch.
26-Jul-10
DCPLODT0234
25-Aug-10
24-Sep-10
24-Oct-10
Act.
23-Aug-10
19.7
General arrangement for PVC shrouded conductor type DSL for 40/10T TG Hall EOT crane
AIL-M0-03257
9-Aug-10
Sch.
9-Aug-10
DCPLODT0242
8-Sep-10
DCPL -0176
8-Oct-10
7-Nov-10
Act.
27-Aug-10
6-Sep-10
Page 67 of 12
:LT-P0-00003
Schedule First Sr. No. Description Drawing / Doc. No. Submission Date Early Start
FLAG
FLAG
d
3rd Submission (Rev. C) Release I/W No. JNSTPP L&T Date DTN No.
E
N
|1
dv
Receive
SuNexLasub L S Date
ttL
Release I/W No. JNSTPP Receive L&T Date
c R oT
Release
L&T
Date
Date
I/W No.
JNSTPP
DTN No.
Date
I/W No.
JNSTPP
C 19.8 C 19.9 C 19.10 C 19.11 C 19.12 C 19.13 C 19.14 C C C C C C C C C C C C C C C LT Drive wheel assembly LT idle wheel assembly CT Drive wheel assembly CT idle wheel assembly Long travel Machinery Assembly for 40/10 T TGHall EOT crane AIL-M0-03260 AIL-M0-03261 AIL-M0-03262 AIL-M0-03263 AIL-M0-03264 9-Aug-10 9-Aug-10 9-Aug-10 9-Aug-10 9-Aug-10 15 T Aux Hook Block Assembly AIL-M0-03259 9-Aug-10 115T main hook block assembly AIL-M0-03258 9-Aug-10
Sch. Act. Sch. Act. Sch. Act. Sch. Act. Sch. Act. Sch. Act. Sch. Act.
9-Aug-10 23-Aug-10 9-Aug-10 23-Aug-10 9-Aug-10 23-Aug-10 9-Aug-10 23-Aug-10 9-Aug-10 23-Aug-10 9-Aug-10 23-Aug-10 9-Aug-10 23-Aug-10
7 N 7 7 7 7 7 7
19.16 19.17 19.18 19.19 19.20 19.21 19.22 19.26 19.27 19.28 19.29 19.30 19.31 19.34 19.35
Schematic
circuit
diagram
of
protective
panel
and
lighting
circui
for 40/10 T TGHall crane_________________________________________ Schematic circuit diagram of Main hoist panel for 40/10 T TGHall crane_________________________________________________________ Schematic circuit diagram of Aux. hoist panel for 40/10 T TGHall crane_________________________________________________________ Schematic circuit diagram of Cross Traverse and Micro Cross
AIL-E0-03266 AIL-E0-03267 AIL-E0-03268 AIL-E0-03269 AIL-E0-03270 AIL-E0-03271 AIL-E0-03272 AIL-E0-03276 AIL-E0-03277 AIL-E0-03278 AIL-E0-03279 AIL-M0-03280 AIL-M0-03281 AIL-M0-03284 AIL-E0-03285
30-Jul-10 30-Jul-10 30-Jul-10 30-Jul-10 30-Jul-10 30-Jul-10 1-Aug-10 1-Aug-10 1-Aug-10 1-Aug-10 1-Aug-10 9-Aug-10 30-Jul-10 30-Jul-10 1-Aug-10 Sch. Act. Sch. Act. Sch. Act. Sch. Act. Sch. Act. Sch. Act. Sch. Act. Sch. Act. Sch. Act. Sch. Act. Sch. Act. Sch. Act. Sch. Act. Sch. Act.
DCPLO-DT0229 13-Aug-10 30-Jul-10 13-Aug-10 30-Jul-10 13-Aug-10 30-Jul-10 13-Aug-10 30-Jul-10 13-Aug-10 30-Jul-10 13-Aug-10 1-Aug-10 13-Aug-10 1-Aug-10 16-Aug-10 1-Aug-10 13-Aug-10 1-Aug-10 13-Aug-10 1-Aug-10 13-Aug-10 9-Aug-10 23-Aug-10 30-Jul-10 30-Aug-10 30-Jul-10 1-Aug-10 13-Aug-10 31-Aug-10 15-Sep-10 31-Aug-10 26-Aug-10 31-Aug-10 26-Aug-10 31-Aug-10 26-Aug-10 8-Sep-10 29-Aug-10 29-Aug-10 31-Aug-10 26-Aug-10 DCPLO-DT0228 29-Aug-10 26-Aug-10 29-Aug-10 26-Aug-10 29-Aug-10 26-Aug-10 29-Aug-10 26-Aug-10 29-Aug-10 26-Aug-10 29-Aug-10 26-Aug-10 DCPLO-DT0229 DCPLO-DT0229 DCPLO-DT0229 DCPLO-DT0229 DCPLO-DT0229 DCPLO-DT0229 DCPLO-DT0229 DCPLO-DT0228 DCPLO-DT0228 DCPLO-DT0228 DCPLO-DT0241 DCPLO-DT0247
DCPL -0171 DCPL -0171 DCPL -0171 DCPL -0171 DCPL -0171 DCPL -0171
[Traverse panel & BOM for 40/10 T TGHall crane____________________ Schematic circuit diagram of Long Traverse panel for for 40/10 T TGHall crane Bill of material G.A. drawing for Main, Aux. Hoist, CT circuit, LT circuit and of Protective panel & transformer enclosure for main (Pro ) circuit for 40/10 T TGHall_____________________________ 40/10 T TGHall crane__________________________________________ G.A. of Long Traverse panel for 40/10 T TGHall crane Cable Schedule for 40/10 T TGHall crane Crane contrlol write up Cable size calculation for 40/10 T TGHall crane Crane lubrication Structural calculations for 40/10 T TGHall crane Make of Bought Out Item List Electrical feeder diagram
15-Sep-10
DCPl -0171 28-Sep-10 28-Sep-10 28-Sep-10 28-Sep-10 28-Sep-10 28-Sep-10 30-Sep-10 30-Sep-10 30-Sep-10 30-Sep-10 30-Sep-10 8-Oct-10 28-Sep-10 28-Sep-10 12-Aug-10 30-Sep-10 28-Oct-10 28-Oct-10 28-Oct-10 28-Oct-10 28-Oct-10 30-Oct-10 30-Oct-10 30-Oct-10 30-Oct-10 30-Oct-10 7-Nov-10 28-Oct-10 28-Oct-10 26-Aug-10 30-Oct-10
DCPLO-DT0227
DCPL -0171
31-Aug-10
Page 68 of 12
:LT-P000003 :4.2 :A
Earthing details C 19.44 DSL Selection & Voltage drop Calculation for 40/10 T BFP EOT Crane_______________________________________________________ AIL-E0-03286 AIL-M0-03294 25-Aug-10 Sch. Act. Sch. Act. 1-Aug-10 13-Aug-10 25-Aug-10 13-Aug-10 DCPLO-DT0228 DCPLO-DT0228 31-Aug-10 26-Aug-10 24-Sep-10 26-Aug-10 DCPl -0171 DCPl -0171 24-Oct-10 30-Sep-10 3 0 2
20 C 20.1
Page 69 of 12
:LT-P0-00003
C 20.5 CEP GA Drawing common for pump & motor & acces. (INSTA KSB-M0-03503 11-Aug-10 Sch. Act. 11-Aug-10 23-Jul-10 DCPLO-DT0205 10-Sep-10 A Sch. Act. 11-Aug-10 23-Jul-10 DCPLO-DT0205 10-Sep-10 10-Oct-10 10-Oct-10 9 N 9 N C KSB-M0-03504
20.6
11-Aug-10
VDR - Vacuum Pump VDR - Condensate Polishing Units VDR - DMCW Pumps VDR - Plate Heat Exchangers VDR - Butter Fly Valves VDR - LP Bypass Valves VDR Shop Fabricated Tanks - Steel VDR - AC & DC Distribution Board VDR - Elevators VDR - OLTCs & Debris Filter VDR - HP Heaters 2/3 Way Bypass Valves VDR - Misc. VDR - Power Cycle Valves VDR - Control Valves & Pneumetic ON / OFF Valves VDR - Shop Fabricated Piping
21 22 23 24 25 26 27 28 29 30 31 32 33
34
35
Page 70 of 12
:LT-P000003 :4.2 :A
Last Wk Rcvd
Submited Last Wk
Sr. No.
Description
FLAG
FLAG
To Wk Rcvd Next
As Built Release
Unit No.
L&T
Date
DTN No.
Date
I/W No.
JNSTPP
L&T
Date
DTN No.
Date
I/W No.
JNSTPP
L&T
Date
DTN No.
Date
I/W No.
JNSTPP
L&T
Date
DTN No.
Date
I/W No.
JNSTPP
Date-Unit 1
DTN No
38
39
40
41
42 43 44
VDR - Expansion Joints (Metallic & Rubber) VDR Vibration Monitoring System
45 46 47 48
VDR - LP Valves VDR - Extraction Steam Check Valves VDR - LV power & Control Cables
49 50
*
TXH1A-090XX1 K6A24-009-DWG-M-002
E
29-Dec-09 Sch. 29-Dec-09 DCPLODT0037 28-Jan-10 Act. 29-Dec-09 29-Dec-09 Sch. 29-Dec-09 DCPLODT0038 28-Jan-10 Act. 29-Dec-09 29-Dec-09 Sch. 29-Dec-09 DCPLODT0038 28-Jan-10 Act. 29-Dec-09 4-Jan-10 Sch. 4-Jan-10 DCPLODT0043 3-Feb-10 DCPl -0071 Act. 4-Jan-10 15-Mar-10 18-Jan-10 Sch. 18-Jan-10 DCPLODT0053 17-Feb-10 DCPl 0046
51
GENERAL DOCUMENTS
Heat & Mass Balance Diagram for HP-LP Baypass
Extra
17.2
17.3
Plant Lay-Out
Extra
17.4
JPN-SK-M-006
Extra
17.5
LT-M0-03092
Extra
17.6
JPN-SK-E-003
Extra
Act.
19-Jan-10
15-Feb-10
Page 71 of 12
:LT-P0-00003
C 17.7 Sketch Showing Cable Tray Exit Along Grid 12 & Electrical Equipment Erection Act. 19-Jan-10 JPN-SK-E-001 19-Jan-10 Sch. 19-Jan-10 DCPLODT0058 18-Feb-10 Extra
17.8
Sketch Showing Cable Tray Exit Along Grid C & Electrical Equipment Erection
JPN-SK-E-002
19-Jan-10
Sch.
19-Jan-10
DCPLODT0058
18-Feb-10
Extra
Act.
19-Jan-10
17.9
DS-ESP
97140-08-DS-0001
Sch.
By Mail
DCPL 0058
Extra
Act.
10-Oct-09
2-Mar-10
17.10
97140-01-DS-0001
Sch.
By Mail
DCPL 0058
Extra
Act.
10-Oct-09
2-Mar-10
17.11
97140-01-DS-0002
Sch.
By Mail
DCPL 0058
Extra
Act.
10-Oct-09
2-Mar-10
17.12
GAE-KN-T001
13-Apr-10
Sch.
13-Apr-10
DCPLODT0119
13-Apr-10
DCPL 0106
Extra
Act.
13-Apr-10
5-May-10
17.13
LMTG-M0-01207 LMTG-M0-01207
12-May-10
Sch.
12-May-10
DCPLODT0141
12-May-10
DCPLODT0202
Extra
Act.
12-May-10
15-Jun-10
17.14
LMTG-M0-01206 LMTG-M0-01206
12-May-10
Sch.
12-May-10
DCPLODT0141
12-May-10
DCPL 0132
Extra
Act.
12-May-10
15-Jun-10
17.15
LMTG-M0-01205 LMTG-M0-01205
12-May-10
Sch.
12-May-10
DCPLODT0141
11-Jun-10
DCPL 0132
Extra
Act.
12-May-10
15-Jun-10
17.16
T3101PLPA101 LMTG-M0-01201
1-Feb-10
Sch.
1-Feb-10
DCPLO D T0069
1-Feb-10
DCPL 0150
Extra
Act.
1-Feb-10
17-Jul-10
17.17
LMTG-P0-01036
2-Jul-10
Sch.
2-Jul-10
DCPLODT0171
2-Jul-10
Extra
Act.
2-Jul-10
17.18
LMTG-M0-01202
29-Apr-10
Sch.
29-Apr-10
DCPLODT0137
29-Apr-10
DCPLODT0202
Extra
Act.
29-Apr-10
15-Jun-10
17.17
17-Jul-10
Sch.
17-Jul-10
DCPLODT0188
17-Jul-10
Extra
Act.
17-Jul-10
17.18
LMTG-M0-02809
23-Jul-10
Sch.
23-Jul-10
DCPLODT0204
23-Jul-10
DCPLODT0267
Extra
Act.
23-Jul-10
6-Aug-10
17.17
LMTG-M0-02810
23-Jul-10
Sch.
23-Jul-10
DCPLODT0204
23-Jul-10
DCPLODT0267
Extra
Act.
23-Jul-10
6-Aug-10
17.18
11-Aug-10
Sch.
11-Aug-10
DCPLODT0220
11-Aug-10
Extra
Act.
11-Aug-10
Abbreviation: A - Approval I - Information N - Not For Submission I/W No. - Inward No. DTN No. - Document Transmittal No. Unit type:C - Common for both Units 1 - For Unit No. 1 only Sch. - Schedule Date for Submission Act. - Actual Date of Submission
Total:
Page 72 of 12
A 1 2 3 4 5 6 B 1 2 3 4 C 1 2 3 4 5 6 7 8 9 10
LARSEN & TOUBRO LIMITED Power Project Management Services, Baroda. JOB NO: - T209001
JAIPRAKASH POWER VENTURES LIMITED 2 X 660 MW STEAM TURBINE GENERATOR & AUXILIARIES
DOCUMENT NO.: - LT:JNSTPP:CON:PPM:003 PROGRESS REPORT NO.: - 11 ANNEXURE NO.: PAGE NO. 60 of 103
JAIPRAKASH POWER VENTURES LIMITED 2 X 660 MW STEAM TURBINE GENERATOR & AUXILIARIES
DOCUMENT NO.: - LT:JNSTPP:CON:PPM:003 PROGRESS REPORT NO.: - 11 ANNEXURE NO.: PAGE NO. :- 61 of 103
Enq. Float 11 12 12 13 D 1 2 3 4 5 6 7 8 9 E 1 2 3 4 5 F 1 2 Hp piping & Fittings of Feedwater System Expansion Joints of Feed Water System Butterfly Valve for Feed Water System 2/3 Way Valve for Feed Water System CONDENSATE SYSTEM Condenser Condensate Extraction Pump Condensate Polishing Unit LPH Gland Steam Condenser LP Valve of Condensate System Hangers & Support of Condesate System Miscellaneous Items of Condensate System LP piping & Fittings of Condensate System VACUUM SYSTEM Vacuum Pump LP Valves of Vacuum System Hangers & Supports of Vacuum Ssytem Miscellaneous Items of Vacuum System LP Piping & Fittings of Vacuum System CLOSED COOLING WATER SYSTEM DMCW Pump Plate Heat Exchanger LARSEN & TOUBRO LIMITED Power Project Management Services, Baroda. JOB NO: - T209001 100.00% 100.00% 100.00% 100.00% 0.00% 0.00% 0.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00%
100.00% 100.00%
0.00% 0.00%
4-Nov-10 4-Nov-10
0.00% 0.00%
30.00% 30.00%
3 4
JAIPRAKASH POWER VENTURES LIMITED 2 X 660 MW STEAM TURBINE GENERATOR & AUXILIARIES
DOCUMENT NO.: - LT:JNSTPP:CON:PPM:003 PROGRESS REPORT NO.: - 11 ANNEXURE NO.: PAGE NO. 62 of 103
5 6 7 G 1 2 3 4 5 6 7 H 1 2 3 4 5 6 7 I 1
Hangers & Supports of Closed Cooling Water Sys Miscellaneous Items of Closed Cooling Water Sys LP Piping & Fittings of Closed Cooling Water Syst DRAIN SYSTEM HP & LP Flash Tanks HP valves of Drain System LP Piping & Fittings of Drain System LP Valves of Drain System Hangers & Supports of Drain System Miscellaneous Items of Drain System HP Piping & Fittings of Drain System EXTRACTION STEAM SYSTEM FCNRV HP valves of Extraction System LP Piping & Fittings of Extraction System LP Valves of Extraction System Hangers & Supports of Extraction System Miscellaneous Items of Extraction System HP Piping & Fittings of Extraction System LP BYPASS STEAM SYSTEM LP Bypass Valve LARSEN & TOUBRO LIMITED Power Project Management Services, Baroda. JOB NO: - T209001
L&T-HED
21-Sep-09 -
21-Sep-09 -
L&T-MHI
25-Aug-09 -
25-Aug-09 -
0.00%
0.00%
0.00%
28-Jan-11
0.00%
0.00%
2 3 4 5 6 J
JAIPRAKASH POWER VENTURES LIMITED 2 X 660 MW STEAM TURBINE GENERATOR & AUXILIARIES
DOCUMENT NO.: - LT:JNSTPP:CON:PPM:003 PROGRESS REPORT NO.: - 11 ANNEXURE NO.: PAGE NO. :- 63 of 103
1 2 3 4 5 6 7 K 1 2 3 4 L 1 2 3 4
Rubber Expansion Joints Butterfly Valve for Circulating Water System OLTCs LP Valves of Circulating Water System Hangers & Supports of Circulating Water System Miscellaneous Items of Circulating Water System LP Piping & Fittings of Circulating Water System ELECTRICAL SYSTEM AC, DC, UPS Distribution Board Battery Bank & Chargers Power Cables Miscellaneous Items of Electrical System C&I SYSTEM Vibration Monitoring System DCS System & Panel C&I Cables Field Instruments LARSEN & TOUBRO LIMITED Power Project Management Services, Baroda. JOB NO: - T209001
JAIPRAKASH POWER VENTURES LIMITED 2 X 660 MW STEAM TURBINE GENERATOR & AUXILIARIES
DOCUMENT NO.: - LT:JNSTPP:CON:PPM:003 PROGRESS REPORT NO.: - 11 ANNEXURE NO.: PAGE NO. :- 64 of 103
Miscellaneous Items of C&I System LARSEN & TOUBRO LIMITED Power Project Management Services, Baroda JOB NO: - T209001
SR. NO. A 1
JAIPRAKASH POWER VENTURES LIMITED 2 X 660 MW STEAM TURBINE GENERATOR & AUXILIARIES
DOCUMENT NO.: - LT:JNSTPP:CON:PPM:003 PROGRESS REPORT NO.: - 11 ANNEXURE NO.: PAGE NO 65 of 103
COMMON SYSTEM EOT Crane for Tg Building Anupam Cranes,India 12-May-10 27-May-10 0.00% 18.00%
2 3 4 5 6 B 1 2 3 4 C 1 2 3 4 5 6 7 8 9 10 11
EOT Crane for BFP Elevator for Main & Service Building Insulation Paints Misccellaneous Items for Commom System STG SYSTEM Steam Turbine Generator Turbine Preservation System Miscellaneous Items for STG System FEED WATER SYSTEM Deaerator MDBFP TDBFP Drive Turbine for BFP HPH HP valve of Feed Water System LP Piping & Fitting of Feed Water System LP Valve of Feed Water System Hangers & Support of Feed Water System Miscellaneous Items for Feed Water System Hp piping & Fittings of Feedwater System LARSEN & TOUBRO LIMITED Power Project Management Services, Baroda JOB NO: - T209001
Anupam Cranes,India
17-May-10 -
L&T-MHI L&T-MHI
25-Aug-09 25-Aug-09 -
19-Jan-10 19-Jan-10 -
19-Jan-10 19-Jan-10 -
0.50% 4.00% 4.00% 0.00% 2.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
9.00% 18.00% 18.00% 0.00% 19.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% DOCUMENT NO.: - LT:JNSTPP:CON:PPM:003 PROGRESS REPORT NO.: - 11 ANNEXURE NO.: PAGE NO :- 66 of 103
SR. NO. 12 12
JAIPRAKASH POWER VENTURES LIMITED 2 X 660 MW STEAM TURBINE GENERATOR & AUXILIARIES
Expansion Joints of Feed Water System Butterfly Valve for Feed Water System
13 D 1 2 3 4 5 6 7 8 9 E 1 2 3 4 5 F 1 2 3 4
2/3 Way Valve for Feed Water System CONDENSATE SYSTEM Condenser Condensate Extraction Pump Condensate Polishing Unit LPH Gland Steam Condenser LP Valve of Condensate System Hangers & Support of Condesate System Miscellaneous Items of Condensate System LP piping & Fittings of Condensate System VACUUM SYSTEM Vacuum Pump LP Valves of Vacuum System Hangers & Supports of Vacuum Ssytem Miscellaneous Items of Vacuum System LP Piping & Fittings of Vacuum System CLOSED COOLING WATER SYSTEM DMCW Pump Plate Heat Exchanger DMCW Expansion Tanks LP Valves of Closed Cooling Water System LARSEN & TOUBRO LIMITED Power Project Management Services, Baroda JOB NO: - T209001 L&T-HED KSB,India Siemens, India L&T-HED L&T-MHI
0.00%
0.00%
0.00% 0.00% 0.00% 0.00% DOCUMENT NO.: - LT:JNSTPP:CON:PPM:003 PROGRESS REPORT NO.: - 11 ANNEXURE NO.: PAGE NO :- 67 of 103
SR. NO. 5 6 7
JAIPRAKASH POWER VENTURES LIMITED 2 X 660 MW STEAM TURBINE GENERATOR & AUXILIARIES
Hangers & Supports of Closed Cooling Water Syste Miscellaneous Items of Closed Cooling Water Syste LP Piping & Fittings of Closed Cooling Water System
G 1 2 3 4 5 6 7 H 1 2 3 4 5 6 7 I 1 2 3 4
DRAIN SYSTEM HP & LP Flash Tanks HP valves of Drain System LP Piping & Fittings of Drain System LP Valves of Drain System Hangers & Supports of Drain System Miscellaneous Items of Drain System HP Piping & Fittings of Drain System EXTRACTION STEAM SYSTEM FCNRV HP valves of Extraction System LP Piping & Fittings of Extraction System LP Valves of Extraction System Hangers & Supports of Extraction System Miscellaneous Items of Extraction System HP Piping & Fittings of Extraction System LP BYPASS STEAM SYSTEM LP Bypass Valve HP valves of LP Bypass Steam System LP Piping & Fittings of LP Bypass Steam System Hangers & Supports of LP Bypass Steam System LARSEN & TOUBRO LIMITED Power Project Management Services, Baroda JOB NO: - T209001 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% DOCUMENT NO.: - LT:JNSTPP:CON:PPM:003 PROGRESS REPORT NO.: - 11 ANNEXURE NO.: PAGE NO :- 68 of 103 L&T-MHI 25-Aug-09 19-Jan-10 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% L&T-HED 21-Sep-09 -
SR. NO. 5 6 J 1
JAIPRAKASH POWER VENTURES LIMITED 2 X 660 MW STEAM TURBINE GENERATOR & AUXILIARIES
Miscellaneous Items of LP Bypass Steam System HP Piping & Fittings of LP Bypass Steam System CIRCULATING WATER SYSTEM Rubber Expansion Joints
0.00%
0.00%
2 3 4 5 6 7 K 1 2 3 4 L 1 2 3 4 5
Butterfly Valve for Circulating Water System OLTCs LP Valves of Circulating Water System Hangers & Suuports of Circulating Water System Miscellaneous Items of Circulating Water System LP Piping & Fittings of Circulating Water System ELECTRICAL SYSTEM AC, DC, UPS Distribution Board Battery Bank & Chargers Power Cables Miscellaneous Items of Electrical System C&I SYSTEM Vibration Monitoring System DCS System & Panel C&I Cables Field Instruments Miscellaneous Items of C&I System
LARSEN & TOUBRO LIMITED Power Project Management Services, Vadodara JOB NO: T209001
4.3 PROJECT WBS STURCTURE, WEIGHTAGE PRINCIPLE AND BASIS OF PROGRESS MEASUREMENT
LEVEL : I
WTG PT
1000000
LEVEL :II
ENGINEERING WTG PT
10%
75%
15%
100000
PROCUREMENT
WTG PT
750000
CONSTRUCTION
WTG PT
150000
LEVEL : III
BASIC ENGINEERING WTG PT
65% ORDERING
90%
2%
3%
80%
15%
"T"65000
WTG PT
T75000
WTG PT
~675000 WTG PT
TENDERING
ENABLING WORKS
COMMISSIONING
3000
WTG PT
4500
WTG PT
120000
WTG PT
22500
LEVEL : IV
DESIGN CRITERIA DOCUMENTS 20% TG BUILDING GA, PIPING LAYOUT & ELECTRICAL - 5% ROTATING EQUIPMENTS STATIC EQUIPMENTS BOP / MISCELLANEOUS ITEMS C & I - 5% PIPES VALVES ELECTRICAL ITEMS TOTAL INSTRUMENTATION ITEMS TOTAL ROTATING EQUIPMENTS STATIC EQUIPMENTS BOP / MISCELLANEOUS ITEMS PIPES VALVES ELECTRICAL ITEMS INSTRUMENTATION ITEMS TOTAL 25% 20% 17% 10% 10% 100% 8% 10% 100% 35% 20% 15% 10% 10% 5% 5% 100% ORDER ON ERECTION 100% OPENING OF SITE OFFICE 100% CONTRACTOR STG SYSTEM FEED WATER SYSTEM CONDENSATE SYSTEM VACUUM SYSTEM CLOSED CW SYSTEM DRAIN SYSTEM EXTRACTION SYSTEM LP BYPASS SYSTEM CONDENSER CW SYSTEM C & I SYSTEM ELECTRICAL SYSTEM COMMON SYSTEM INSULATION PAINTING TOTAL 45% 13% 21% 1.00% 3.00% 2.00% 2.00% 1.00% 2.00% 3.00% 3.00% 1.00% 2.00% 1.00% 100.00% PRE COMM. UNIT COMM. TOTAL 90% 10% 100%
COMPOSITE DRGS
20%
20%
CALCULATION
10%
30%
15%
2.5%
P & IDs
30%
2.5%
AS BUILT - 2.5%
NOTE : 10% Rotating Equipment Includes :- Turbine & Auxillieries, Generator & Auxillieries, GSC, BFP, Drive Turbine, Motor for MDBFP, CEP, Vacuum pump, DMCW pump. Static Equipment lncludes :- Deaerator, HPH, LPH, Condenser, PHE, DMCW Expansion Tank, HP Flash Tank, LP Flash Tank BOP/Miscellaneous items :- Turbine Preservation System, CPU, OLTC & Debris filter, EOT cranes, Elevators, Expansion Joints, Insulation,Paints etc
PROCUREMENT ASSISTANCE
40%
MECHANICAL - 90%
TOTAL
100%
LEVEL : V
BASIS OF WEIGHTAGE :
ORDERING- EFFORTS
: L"
PROCUREMENT
MANUFACTURING / DELIVERY
BASIC & DETAIL ENGINEERING BASIC ENGINEERING 2nd Submission Incorporating Comments 15% 1st Submission to Jaypee / DCPL
CONSTRUCTION 2.5% Bid Evaluation 45% 2nd Submission Incorporating Comments Released for Construction As built DRGS/DOCS to be submitted for Information 1st Submission to Jaypee / DCPL Released for Construction As built 70%
70% As built
DCD
Approval
5%
Purchase Specification
10%
80%
P & IDs
Approval
12.5% Specification
45%
DETAIL ENGINEERING DRGS/DOCS to be submitted for Approval 1st Submission to Jaypee / DCPL
CHKDBY:
ORDERING / TENDERING
10% 70%
MANUFACTURING / DELIVERY Standard Milestones for Progress measurement of ITEMs / MRs 20%
Prorata RCPT of Major Material Prorata Manufacturing Inspection Despatch Receipt at site Bulk Material MFG / Testing Despatch Receipt at site PROGRESS WILL BE MEASURED PRORATA BY WORK ACHIEVED 10% 10%
20% AGAINST TOTAL WORK VOLUME. THE PROGRESS SHALL BE 40% 5% CALCULATED AT SITE AS THE WORK COMMENCES ON SITE 5% 10% 90% 5% 5%
VL
APPROVED BY :
Enquiry
DATE :
VP PG PREP BY :
DOC NO :
LARSEN & TOUBRO LIMITED Power Project Management Services, Vadodara JOB NO: T209001
Activity ID
Original Start Duration Finish 2009 Q2 Q3 Q4
2010
Q1 Q2 Q3 Q4
2011
Q1 Q2 Q3 Q4
2012
Q1 Q2 Q3 Q4
2013
Q1 Q2
2014
Q 3
2010
1475 23-Jul-09 A 0 23-Jul-09 A 0 0 0 23-May-11* 0 12-Oct-11* 0 0 26-Dec-11 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Page 1 of 28 24-Jan-12* 22-Mar-12* 27-Mar-12* 06-Nov-12* 24-Jan-13* 09-Feb-13* 09-Feb-13* 26-Mar-13* 26-Mar-13* 12-Apr-13* 25-Apr-13* 24-Jun-13* 24-Jun-13* 05-Aug-13* Date 28-SEP-10 20-Dec-11*
2011
2012
2013
2014
JTONE
Date of "Notice To Proceed" Opening of Site office & Mobilization Unit-1 Supply of Embedded parts for TG Unit-1 Commencement of EOT erection Unit-1 Commencement of insitu Condenser erection Unit-1 MDBFP receipt at site ***Unit-1 Commencement of TG erection Unit-1 Receipt of LP Turbine at site Unit-1 Receipt of Generator at site Unit-1 Receipt of Deaerator at site Unit-1 TG oil flushing completion Unit-1 Readiness of TG/C&I system Unit-1 Completion of Governing system Unit-1 TG boxing up Unit-1 Boiler Light up readiness Unit-1 Commissioning of MDBFP Unit-1 TG on Barring Gear Unit-1 Steam Blowing completion Unit-1 TG Synchronization on Coal Unit-1 TG Synchronization on Oil Unit-1 Completion of Trial operation
CLIENT INPUTS
CONSTRUCTION PHASE ML200
Project Baseline Bar Actual Work Remaining Work Critical Remaining Work Milestone
Project Baseline Bar Actual Work Remaining Work Critical Remaining Work Milestone
ML300 ML301 ML302 ML308 ML304 ML303 ML305 ML306 ML307 ML309 ML310
Unit-1 Readiness of 415V supply for EOT & Elevator Unit-1 Availability of trained O&M manpower for co... Unit-1 Availability of DM water at terminal points at... Unit-1 Availibility of Auxillary cooling water at termi... Unit-1 Readiness Emergen... of 415V,3.3KV,11KV & 0 0 0 0 0 0 0 0 0
22-Aug11* 22-May12* 22-May12* 21-Jul12* 21-Jul12* 21-Jul12* 21-Jul12* 21-Jul12* 21-Jul12* 22-Sep12* 22-Dec12*
Unit-1 Readiness of HVAC system for DCS commi... Unit-1 Readiness of 220V & 24V DC power supply ... Unit-1 Readiness of Fire protection, detection & al... Unit-1 Availability of Instru & Service air at terminal... Unit-1 Availability of Condenser cooling water at te... Unit-1 Readiness Switchyards of GT, UAT, GCB &
487 23-Sep-09 A 22-Jan-10 A 105 236 104 23-Sep-09 A Jan-10 A 23-Dec-09 A Jan-10 A 23-Dec-09 A 222219Jan10 A
Other equipments, Floors & Control room TG Foundation deck Condenser Pit including
EN202
EN203
BFP CEP
&
130 23-Dec-09 A 19-Jan-10 A 1389 23-Jul-09 A 815 23-Jul-09 A 324 23-Jul-09 A 11-May-13 02-Jan-12 26-Nov-10
COMMON SYSTEM
ENGINEERING
EN100 EN101 Major Engineering Balance Engineering
Supply of Main Girder for Crane-2 Supply of Trolley for CraneCMN90 2 Supply of Balance & Misc CMN60 items for Crane-2 Supply of Balance & Misc items for Crane-1 Project Baseline Bar Actual Work Remaining Work Critical Remaining Work
Milestone
2010
2011
2012
2013
2014
Q2 Q3 Q1 Q4 Q2
Date 28-SEP-10
Installation of Counterweight guard, Cocounterwei... Installation of Elevator car alongwith doors and oth... Installation of Electrical and Control equipments Commissioning of Main & Service Building Elevators Ordering Manufacturing Supply
TURBINE
CMN430 CMN440 CMN450 CMN460 CMN470 CMN480 CMN490 CMN500 Ordering Manufacturing Supply Application Ordering Product Engineering Manufacturing Supply for Unit-1 & 2 90 29-Feb-12 60 13-Jun-12 100 22-Aug-12 92 25-Jan-13 500 10-May-11 90 10-May-11 60 23-Aug-11 189 01-Nov-11 180 24-Feb-12 1398 23-Jul-09 A 06-Jun-12 25-Nov-11 20-May-13 13-Jun-12 22-Aug-12 17-Dec-12 11-May-13 21-Sep-12 23-Aug-11 01-Nov-11 08-Jun-12 21-Sep-12
STG SYSTEM
MANUFACTURING & SUPPLY MANUFACTURING 1050 23-Jul-09 A 856 23-Jul-09 A
1 H H H
STG( Machining of Castings STG! HIPT Pedestal STG7 Balance & Misc items including Electrical & C&I ite... STG! Assembly & Testing of Turbine
Original Start Duration 287 26-Jul-10 A 217 24-Sep-10 237 24-Sep-10 130 28-Jun-11 535 26 59 33 55 53 57 95 85 122 106 590 52 30 60 60 60 80 105 70 60 92 39 30 48 33 20-Dec-10 20-Dec-10 17-Nov-11 17-Nov-11 22-Nov-11 24-Nov-11 24-Nov-11 26-Nov-11 26-Nov-11 26-Nov-11 04-Feb-12 23-Sep-11 23-Sep-11 26-Dec-11 30-Jan-12 10-Feb-12 22-Feb-12 09-Apr-12 16-Apr-12 20-Apr-12 02-May-12 14-May-12 11-Jul-12 25-Aug-12 29-Sep-12 09-Feb-13
Finish 24-Mar-11 03-Jun-11 27-Jun-11 25-Nov-11 06-Jun-12 18-Jan-11 24-Jan-12 24-Dec-11 24-Jan-12 24-Jan-12 28-Jan-12 15-Mar-12 03-Mar-12 16-Apr-12 06-Jun-12 04-May-13 22-Nov-11 28-Jan-12 07-Apr-12 19-Apr-12 01-May-12 10-Jul-12 15-Aug-12 10-Jul-12 10-Jul-12 28-Aug-12 24-Aug-12 28-Sep-12 23-Nov-12 20-Mar-13
Embedded parts for HIPT, LPT-1 and LPT-2 LPT-1 & 2 Casings Bearing Pedestal for HIPT LPT-1 & 2 Rotors HIPT Rotor HIPT Casings LPT-1 & 2 other miscellaneous items HIPT other miscellaneous items Other auxiliaries & systems like Lube oil system, Pi... STG1 Balance & Misc items including Electrical & C&I ite... ERECTION STG200 HIPT Brg Pedestal and LPT 1&2- Chipping of fdn ... STG210 HIPT Brg Pedestal and LPT 1&2- Fixing of Seatin... STG220 HIPT- Placement of bottom half, internals and leve... STG230 LPT 1- Placement of bottom half, internals and lev... STG240 LPT 2- Placement of bottom half, internals and lev... STG250 HIPT- Placement of Rotor in Position and its cente... STG280 Erection of Lube, Jacking, EH Oil System STG260 LPT 1- Placement of Rotor in Position and its cent... STG270 LPT 2- Placement of Rotor in Position and its cent... STG290 Erection of MSV/GVs & RSV/ICVs STG300 Alignment of HIPT, LPT-1 & LPT-2 Rotors STG310 Coupling of Turbine Rotors STG320 Setting of Steam path clearances and boxing up STG330 Erection of Turning gear motor
SUPPLY STG' STG' STG1 STG1 STG1 STG1 STG1 STG1 STG1
Page 6 of 28
29 23-Jul-09 A 25-Aug-09 A 500 26-Aug-09 A 12-May-11 260 13-Jan-10 A 03-Nov-10 200 20-Feb-10 A 18-Nov-10 185 20-Feb-10 A 20-Nov-10 140 01-Sep-10 A 09-Feb-11 217 09-Feb-11 20-Oct-11 456 20-Dec-10 19-Mar-12 26 20-Dec-10 18-Jan-11 129 20-Oct-11 114 20-Oct-11 99 20-Oct-11 84 24-Nov-11 84 24-Nov-11 84 24-Nov-11 367 23-Nov-11 50 23-Nov-11 10 23-Mar-12 30 04-Apr-12 10 09-May-12 15 21-May-12 10 07-Jun-12 Page 7 of 28 19-Mar-12 01-Mar-12 13-Feb-12 01-Mar-12 01-Mar-12 01-Mar-12 23-Nov-12 19-Jan-12 03-Apr-12 08-May-12 19-May-12 06-Jun-12 18-Jun-12
B B B B B
STG4 Rotor STG< Bearing Pedestal STG4 Exciter STG4 Control panels Balance & Misc items including Electrical & C&I ite... Erection of Strand Jack lifting arrangement Lifting of Stator and its placement in position Preparation for Rotor threading and electrical testi... Rotor threading Lowering of Generator Rotor on Bearings Mounting of Fan blades on Rotor
Project Baseline Bar Actual Work Remaining Work Critical Remaining Work Milestone
Duratio t at both ... STG800 Runout of Coupling half of Generator rotor STG560 Erection of Generator Gas (H2, CO2) system
11-Aug-12 13-Jul-12 25
COMMISSIONING
10-Sep-12 11-Aug-12 25 STG540 Erection of Stator Cooling Alignment of Generator Rotor 24-Sep-12 25-Aug-12 with 26 Turbine Rotor water System STG570 10-OctCoupling of Gen. Rotor 25-Sep-12 with 14Turbine Rotor 12 27Oct-12 STG580 Erection 11-Oct-12 of 15 Exciter STG590 Boxing up of Bearing 23-Nov-12 Pedestal 29-Oct-12 23 of Generator STG600 05-Aug-13 10-Sep-12 329 STG610 STG620 STG650 STG630 STG640 STG660 Trial run Flushing of 10-Sep-12 Stator water21-Sep-12 cooling 10 system Tightness test of Generator 06-May-13 12-Apr-13 20 (Air & H2) STG full loading 07-Jun-13 19-Jul-13 & 36 Stabilisation Synchronization 07-Jun-13* 0 on Oil 07-Jun-13* Synchronization 0 on Coal 1405-Aug-13 19-Jul-13
90 60 189 150 75 10 500 90 60 189 180 31-May-11 13-Sep-11 22-Nov-11 25-May-12 22-Sep-12 19-Dec-12 10-May-11 10-May-11 23-Aug-11 01-Nov-11 24-Feb-12 12-Sep-11 21-Nov-11 28-Jun-12 15-Nov-12 19-Dec-12 31-Dec-12 21-Sep-12 23-Aug-11 01-Nov-11 08-Jun-12 21-Sep-12
1400 23-Jul-09 A
Page 8 of 28
22-May-13
EN103 EN102
FW100 FW10 FW20 FW40 FW30 FW50 FW1050 FW70 FW60 FW80 FW90 FW110 FW120
339 23-Jul-09 A
Finish
28-SEP-10
MDBFP
FW130 FW140 FW150 FW160 FW170 FW180 FW200 FW210 FW220 FW230 FW240
45 29-Dec-09 A 120 26-Jul-10 A 338 09-Aug-10 A 90 06-Sep-11 90 06-Sep-11 80 20-Dec-11 80 22-Mar-12 30 23-Jun-12 30 28-Jul-12 15 01-Sep-12 15 24-Sep-12 Page 9 of 28
FW250
Commissioning of MDBFPs
FW260 FW270 FW280 FW300 FW290 Ordering Product Engineering Manufacturing Supply of TDBFP-1 & Accessories Supply of TDBFP-2 & Accessories 45 120 338 90 90 29-Dec-09 A 26-Jul-10 A 09-Aug-10 A 06-Sep-11 06-Sep-11
45 02-Feb-13 26-Mar-13
24-May-10 A 07-Oct-10 06-Sep-11 20-Dec-11 20-Dec-11 22-Mar-12 23-Jun-12 11-Oct-12 29-Oct-12 22-May-13 22-May-13 23-Aug-10 A 10-Feb-11 07-Mar-12 20-Aug-12 20-Aug-12 13-Jul-12 08-Aug-12 06-Sep-12 11-Oct-12 29-Oct-12 09-Nov-12 22-May-13 24-Jan-13 09-Jun-12 21-Sep-09 A 16-Oct-10
FW310 Erection of TDBFP-1 including all its accessories FW330 FW340 FW350 FW360 FW370 FW380 FW390 FW400 FW410 Erection of TDBFP-2 including all its accessories Erection of Oil System Cleaning of Oil pipes & Normalization Commissioning of TDBFP Ordering Product Engineering Manufacturing Supply of Drive Turbine-1 & Accessories Supply of Drive Turbine-2 & Accessories
50 14-Apr-10 A 120 24-Sep-10 395 03-Dec-10 142 08-Mar-12 142 08-Mar-12 20 21-Jun-12 22 14-Jul-12 25 30 15 10 49 1282 1053 09-Aug-12 07-Sep-12 12-Oct-12 30-Oct-12 27-Mar-13 23-Jul-09 A 23-Jul-09 A
FW420 Chipping of Foundation and fixing of packers and ... FW430 Placement, levelling and centering of Turbine module FW440 Alignment of Turbine with BFP & Gear box FW450 Erection of Oil System FW1080 Cleaning of Oil pipes & Normalization FW460 Turning Gear operation of Drive turbines FW470 Commissioning of Drive Turbines
HPH
MANUFACTURING & SUPPLY FW1090 FW480 Ordering Product Engineering
Project Baseline Bar Actual Work Remaining Work Critical Remaining Work Milestone Date Particulars 28-SEP-10 UNIT 1 STG PACKAGE - L2 SCHEDULE
Finish
Activity ID
Activity Name
2x660 MW JPVL NIGRIE STPP - UNIT#1 L2 SCHEDULE
Original Star Duratio t n 140 17-Feb11 Finis h 29-Jul11 01-Nov-11 02-Jan-12 13-Jun-12 26-Sep-12 26-Sep-12 01-Nov-11 02-Jan-12 13-Jun-12 26-Sep-12 01-Feb-13 23-Aug-11 01-Nov-11 13-Jun-12 26-Sep-12 14-Dec-12 01-Feb-13 11-Oct-12 22-Sep-11 01-Dec-11 21-Jun-12 04-Oct-12 11-Oct-12 30-Oct-12 06-Dec-10 14-Feb-11 21-Mar-12
FW78 0 FW800 SYSTEM FW810 FW820 FW830 FW1010 FW1020 FW1030 FW1040 FW620 FW630 FW640 FW650 FW660 FW670
Manufacturin g
H&S
OF
Ordering Product Engineering Manufacturing Supply for Unit-1 & 2 Ordering Product Engineering Manufacturing Supply for Unit-1 & 2
FEED
WATER
435 19-Jul-11 90 19-Jul-11 53 01-Nov-11 140 02-Jan-12 180 29-Feb-12 435 19-Jul-11 90 19-Jul-11 53 01-Nov-11 140 02-Jan-12 180 29-Feb-12 633 10-May-11 90 10-May-11 60 23-Aug-11 193 01-Nov-11 210 25-Jan-12 85 07-Sep-12 42 15-Dec-12 490 09-Jun-11 90 09-Jun-11 60 22-Sep-11 174 01-Dec-11 150 12-Apr-12 30 07-Sep-12 742 25-Jun-10 A 90 25-Jun-10 A 60 07-Dec-10 344 15-Feb-11 Page 12 of 28
Project Baseline Bar Actual Work Remaining Work Critical Remaining Work Milestone
Activity ID
Activity Name
2x660 MW JPVL NIGRIE STPP - UNIT#1 L2 SCHEDULE
Original Start Duration Finish
2010
2011
2012
2013
CND' Tube sheets & Tube Support plates 67 CNDl Lower exhaust parts Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2neck Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 86 CND1 Expansion bellows 86 CND1 Balance & Miscellaneous items 190
180 12-Jan-12 08-Aug-12 20 26-Sep-12 18-Oct-12 10 30-Oct-12 19-Oct-12 592 07-Dec-12 25-Apr-11
90 60 225 180 34 10 25-Apr-11 08-Aug-11 17-Oct-11 17-Apr-12 18-Oct-12 27-Nov-12 08-Aug-11 17-Oct-11 05-Jul-12 13-Nov-12 26-Nov-12 07-Dec-12
FW940 Commissioning
FW950 FW960 FW970 FW980 FW990 FW1000
CONDENSATE SYSTEM
ENGINEERING
02-Jan-12 26-Nov-10
1319 23-Jul-09 A
02-Mar-13
MANUFACTURING CND1 Ordering CND1 Product Engineering CND2 Procurement of Raw Material,Tubes etc CND3 Machining & Drilling Tube Sheets & Tube Support ... CND> Fabrication & Machining of Water Boxes at Shop SUPPLY CNDI Hotwell parts & Shell panels CND! Tubes
Activity ID
2009
Activity Name
Page 13 of 28
2010
Date 28-SEP-10
2011
2012
2013
2014
Project Baseline Bar Actual Work Remaining Work Critical Remaining Work Milestone
Activity ID
Activity Name
2010
2011
2012
2013
2014
152
22-Oct-11
541
90
97
110
06-Jun11
CND830 Preassembly of Lower exhaust necks & Expansion... CND145 Condenser insitu erection start
30 09-Aug-11 0 12 O ct11
Condesnser
neck
&
Expansion
10
12-Oct-11
Hotwell
&
Tubebundles
106
24-Oct-11
66
29-Feb12
Activity ID
Activity Name
20 60 15 10-Apr-12 03-May12 12-Jul-12 03-May12 12-Jul-12 30Jul12 10Au g12
2010
2011
2012
I.I.
2013
2014
16-May-12 CND170 Erection of LPH 1A/2A & 1B/2B CND180 Expansion bellows & Lower Exhaust neck erection... CND200 Water box assembly
10
30-Jul-12
CND220 CND230 CND240 CND250 CND270 CND260 CND280 CND790 CND290 CND300 CND310
Ordering Product Engineering Manufacturing Supply of CEP-1and its accessories Supply of CEP-3 and its accessories Supply of CEP-2 and its accessories Erection CEP-1and its accessories Erection CEP-2 and its accessories Erection CEP-3 and its accessories Trial run of Motors Commissioning of CEPs Ordering Product Engineering
CPU (3 X 50%)
CND320 CND330
90 13-Jan-10 A 120 26-Jul-10 A 308 16-Aug-10 A 60 28-Jun-11 60 28-Jun-11 60 28-Jun-11 45 23-Sep-11 45 15-Nov-11 45 06-Jan-12 15 23-Aug-12 17 15-Jan-13 1034 15-Apr-10 A 90 15-Apr-10 A 120 24-Sep-10
24-May-10 A 24-Sep-10 A 02-Aug-11 06-Sep-11 06-Sep-11 06-Sep-11 14-Nov-11 05-Jan-12 27-Feb-12 10-Sep-12 04-Feb-13 02-Mar-13 24-Sep-10 A 10-Feb-11
iii
i-----r
Project Baseline Bar Actual Work Remaining Work Critical Remaining Work Milestone Page 14 of 28 Date 28-SEP-10 Particulars UNIT 1 STG PACKAGE - L2 SCHEDULE
Activity ID
2x660 MW JPVL NIGRIE STPP - UNIT#1 L2 SCHEDULE
ID CND340 CND350 CND360 CND370 CND380 CND800 CND810 CND390 Activity Name Manufacturing Supply of Skid with Pumps & its accessories Supply of Vessels & Tanks with its accessories Supply of Balance & Miscellaneous items Erection of CPU-1 & its accessories including Elec... Erection of CPU-2 & its accessories including Elec... Erection of CPU-3 & its accessories including Elec... Commissioning Original Start Finish Duration 218 07-Jan-11 17-Sep-11 90 15-Aug-11 26-Nov-11 90 15-Aug-11 26-Nov-11 120 19-Sep-11 04-Feb-12 45 24-Oct-11 14-Dec-11 45 15-Dec-11 04-Feb-12 45 06-Feb-12 28-Mar-12 23 04-Feb-13 02-Mar-13 1273 23-Jul-09 A 15-Jan-13 993 23-Jul-09 A 10-Apr-12 52 23-Jul-09 A 21-Sep-09 A 200 22-Sep-09 A 16-Oct-10 186 03-Feb-10 A 15-Feb-11 199 16-Dec-10 05-Aug-11 147 15-Feb-11 05-Aug-11 120 15-Feb-11 05-Jul-11 50 05-Jul-11 01-Sep-11 100 01-Sep-11 27-Dec-11 90 27-Dec-11 10-Apr-12 90 27-Dec-11 10-Apr-12 90 27-Dec-11 10-Apr-12 90 27-Dec-11 10-Apr-12 280 10-Apr-12 15-Jan-13 110 10-Apr-12 16-Aug-12 60 16-Aug-12 25-Oct-12 30 11-Dec-12 15-Jan-13 1319 23-Jul-09 A 02-Mar-13 27 23-Jul-09 A 22-Aug-09 A 90 22-Dec-10 05-Apr-11 Page 15 of 28
2010
2009
2011
2012
2013
2014
Q2 Q3 Q1 Q2 Q3 Q4 Q4
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
LPH
MANUFACTURING & SUPPLY CND840 Ordering CND400 Product Engineering CND410 Procurement of Raw Material,Tubes,Forgings etc CND420 Fabrication of Shells CND440 Forming of Dish ends CND430 Machining and Drilling of Tube sheets CND450 Tubing CND460 Assembly CND480 Supply of LPH-4 and its accessories CND490 Supply of LPH-1A/2A and its accessories CND500 Supply of LPH-1B/2B and its accessories CND470 Supply of LPH-3 and its accessories ERECTION & COMMISSIOING CND510 Erection of LPH-3 & 4 CND520 Erection of Drains, Vents and safety Valves CND530 Commissioning of LPHs
Project Baseline Bar Actual Work Remaining Work Critical Remaining Work Milestone
Date 28-SEP-10
2010 Q2 Q3 Q4 Q 1
2011 Q2 Q3 Q4
CND550
Manufacturing
10-Nov-11
Supply of Exhauster and its accessories Supply of Gland Steam Cooler and its accessories Erection of Gland Steam Cooler & Exhausters Erection of seal steam regulating valve & Piping Commissioning of GSC
3
B
P n
l:
17-Feb-11
n :: . T! : n
1
iiii
CND700
150 24-May-11
14-Nov-11
:1
i
1
437 19-Jul-11
28-Sep-12
01-Nov-11
CND760 CND770
02-Jan-12 15-Jun-12 i
CND780
150 06-Apr-12
28-Sep-12
i; ; ;
[
i
jjL
r1
CND640
180 02-Mar-12
28-Sep-12
" 1
i i
i
CND650 CND660
Erection of Condensate System piping (along with ... Commissioning of Condensate Sys piping (Hydro t...
11-Dec-12 15-Jan-13
: :i
1
Project Baseline Bar Actual Work Remaining Work Critical Remaining Work Milestone Date 28-SEP-10
2010
2011
2012
2013
2014
Original Duration
Start
VACUUM SYSTEM
ENGINEERING
815 23-Jul-09 A EN106 EN107 Major Engineering Balance Engineering 1287 23-Jul-09 A 29-Jan-13
Finish 2009 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
03-Jan-12 332 23-Jul-09 A 27-Nov-10 576 14-Dec-09 A 03-Jan-12 1020 25-Feb-10 A 29-Jan-13 VACUUM VAC10 PUMP Ordering 90 25-Feb-10 A 06-Dec-10 VAC20 Product Engineering 120 07-Dec-10 25-Apr-11 VAC30 Manufacturing 203 15-Feb-11 08-Oct-11 VAC70 Supply of Vacuum pump-4 & its accessories 90 10-Oct-11 21-Jan-12 VAC60 Supply of Vacuum pump-3 & its accessories 90 10-Oct-11 21-Jan-12 VAC50 Supply of Vacuum pump-2 & its accessories 90 10-Oct-11 21-Jan-12 VAC40 Supply of Vacuum pump-1 & its accessories 90 10-Oct-11 21-Jan-12 VAC80 Erection of Vacuum pump-1 45 23-Jan-12 14-Mar-12 VAC90 Erection of Vacuum pump-2 45 22-Feb-12 13-Apr-12 VAC100 Erection of Vacuum pump-3 45 22-Mar-12 12-May-12 VAC110 Erection of Vacuum pump-4 45 14-May-12 04-Jul-12 VAC120 Trial run of Motors 19 23-Aug-12 14-Sep-12 VAC130 Commissioning of Vacuum pumps 60 21-Nov-12 29-Jan-13 378 21-Sep-10 A 29-Dec-11 LP VALVE OF VACUUM SYSTEM VAC190 Ordering 90 21-Sep-10 A 16-Dec-10 VAC200 Product engineering 53 17-Dec-10 16-Feb-11 VAC210 Manufacturing 151 17-Feb-11 11-Aug-11 VAC220 Supply for Unit-1 & 2 180 03-Jun-11 29-Dec-11 483 20-Jul-11 14-Nov-12 H&S OF VACUUM SYSTEM VAC230 Ordering 90 20-Jul-11 02-Nov-11 VAC240 Product engineering 53 02-Nov-11 03-Jan-12 Project Baseline Bar Actual Work Remaining Work Critical Remaining Work Milestone Page 17 of 28 Date 28-SEP-10 Particulars UNIT 1 STG PACKAGE - L2 SCHEDULE
20-Jul-11
14-Nov-12
PHE
Project Baseline Bar Actual Work Remaining Work Critical Remaining Work Milestone Date Particulars 28-SEP-10 UNIT 1 STG PACKAGE - L2 SCHEDULE
Page 18 of 28
Finish
75 15-Dec-10 11-Mar-11 141 12-Mar-11 23-Aug-11 60 24-Aug-11 01-Nov-11 60 24-Aug-11 01-Nov-11 60 24-Aug-11 01-Nov-11 30 02-Nov-11 06-Dec-11 30 07-Dec-11 10-Jan-12 30 11-Jan-12 14-Feb-12 18 09-Oct-12 30-Oct-12 90 10-May-10 A 06-Dec-10 75 07-Dec-10 03-Mar-11 761 10-May-10 A 170 04-Mar-11 17-Sep-11 60 19-Sep-11 26-Nov-11 30 23-Jan-12 25-Feb-12 18 09-Oct-12 30-Oct-12 337 21-Sep-10 A 18-Nov-11 90 21-Sep-10 A 16-Dec-10 52 17-Dec-10 15-Feb-11 147 16-Feb-11 05-Aug-11 180 23-Apr-11 18-Nov-11 442 19-Jul-11 03-Oct-12 90 19-Jul-11 01-Nov-11 52 01-Nov-11 31-Dec-11 147 31-Dec-11 20-Jun-12 180 07-Mar-12 03-Oct-12 337 10-May-10 A 18-Nov-11 90 10-May-10 A 16-Dec-10 Page 19 of 28
30-Oct-12
LP VALVE
CCW340 CCW350 CCW360 CCW370
S OF CLOSE CW SYSTEM
Ordering Product engineering Manufacturing Supply for Unit-1 & 2
H&S OF C
CCW380 CCW390 CCW400 CCW410 CCW420
LOSE CW SYSTEM
Ordering Product engineering Manufacturing Supply for Unit-1 & 2 Ordering of Chemical Pot Feeder Tank
Project Baseline Bar Actual Work Remaining Work Critical Remaining Work Milestone
DRAIN SYSTEM
EN110
ENGINEERING
1241 23-Jul-09 A 14-Dec-12 324 23-Jul-09 A 575 15-Dec-09 A 1241 23-Jul-09 A 52 23-Jul-09 A 120 28-Jan-10 A 15-Oct-11 180 07-Apr-12 60 16-Jun-12 60 23-Nov-12 19
Ordering Product Engineering Fabrication Supply HP & LP Flash tanks & its accessories Erection of HP & LP Flash tanks & its accessories
2010
2011
2012
2013
2014
DRN180
18023-Oct-12 27-Mar-12
90 52 149 180 21-Sep-10 A 17-Dec-10 16-Feb-11 13-May-11 90 52 149 180 462 90 52 149 180 549 90 60 171 180 77 19 16-Dec-10 15-Feb-11 08-Aug-11 08-Dec-11 01-Nov-11 462 23-Oct-12 19-Jul-11 31-Dec-11 22-Jun-12 23-Oct-12 23-Oct-12 01-Nov-11 31-Dec-11 22-Jun-12 23-Oct-12 14-Dec-12 27-Sep-11 06-Dec-11 22-Jun-12 23-Oct-12 22-Nov-12 14-Dec-12 02-Jan-12
EXTRACTION SYSTEM
815 23-Jul-09 A
324 23-Jul-09 A
1298 23-Jul-09 A
26-Nov-10
Page 21 of 28 P r o
09-Feb-13
Activity ID Activity Name ject Baseline Bar Actual Work Remaining Work Critical
Remaining Work Milestone Date Particulars 28-SEP-10 UNIT 1 STG PACKAGE - L2 SCHEDULE
EN113
Balance Engineering
Q2 Q3
Q4 Q1
Q2 Q4
Q3 Q1 Q2
I *
' '
'
, I
Product Engineering Manufacturing Supply Erection of all FCNRVs in Extraction lines Commissioning
90 24-Sep-10 06-Jan-11 200 01-Jul-11 18-Feb-12 90 16-Jan-12 28-Apr-12 30 01-Dec-12 05-Jan-13 27 05-Jan-13 06-Feb-13
EXT110 EXT120 EXT130 EXT140 EXT150 EXT160 EXT170 EXT180 EXT190 EXT200 EXT210 EXT220 EXT230 EXT240 EXT250 EXT260
Ordering Product Engineering Manufacturing Supply for Unit-1 & 2 Ordering Product Engineering Manufacturing Supply for Unit-1 & 2 Ordering Product Engineering Manufacturing Supply for Unit-1 & 2 90 53 159 180
90 17-May-10 A 60 07-Dec-10 182 15-Feb-11 180 28-Jun-11 90 53 159 180 90 53 159 180 19-Jul-11 01-Nov-11 02-Jan-12 17-Apr-12
_l__________________________________________________________
Project Baseline Bar Actual Work Remaining Work Critical Remaining Work Milestone
Page 22 of 28
EXT270 Ordering EXT280 Product Engineering EXT290 Manufacturing EXT300 Supply for Unit-1 & 2 HP PIPING & FITTING OF EXTRACTION SYST... EXT60 Ordering EXT70 Product Engineering EXT80 Manufacturing EXT90 Supply for Unit-1 & 2 EXT100 Erection of Extraction piping (along with LP Piping ...
90 53 159 180
LP BYPASS SYSTEM
825 23-Jul-09 A
90 14-Jun-11 60 27-Sep-11 182 06-Dec-11 180 17-Apr-12 120 22-Sep-12 1200 23-Jul-09 A 02-Jan-12 90 02-Dec-10 60 17-Mar-11 238 21-Apr-11 90 24-Jan-12 60 08-May-12 4 17-Jul-12 413 17-May-10 A 90 17-May-10 A 60 07-Dec-10 182 15-Feb-11 180 28-Jun-11 483 09-Jul-11 Page 23 of 28
EN114 Major EXT310 Ordering ENGINEERING Engineerin EXT320 Product Engineering EXT330 Manufacturing g
EXT340 EXT350 EXT360 EXT420 EXT430 EXT440 EXT450 Supply Erection Commissioning Ordering Product Engineering Manufacturing Supply for Unit-1 & 2
332 23-Jul-09 A
17-Mar-11 26-May-11 24-Jan-12 08-May-12 17-Jul-12 21-Jul-12 23-Jan-12 06-Dec-10 14-Feb-11 14-Sep-11 23-Jan-12 03-Nov-12
27-Nov-10
Remaining Work Milestone Date Particulars 28-SEP-10 UNIT 1 STG PACKAGE - L2 SCHEDULE
Activity ID Activity Name EXT460 EXT470 EXT480 Ordering Product Engineering Manufacturing
2x660 MW JPVL NIGRIE STPP - UNIT#1 L2 SCHEDULE
Original Start Duration 28-SEP-10 UNIT 1 STG PACKAGE - L2 SCHEDULE
815 23-Jul-09 A 324 23-Jul-09 A 575 15-Dec-09 A 571 06-Jun-11 90 06-Jun-11 60 19-Sep-11 180 28-Nov-11 Page 24 of 28
60 10-Aug-12 19-Oct-12 CWS50_ Erection of Rubber expansion bellows for Condnse... 6028-Dec-12 19-Oct-12 CWS360 Erection of Rubber expansion 807 25-Jun-10 A 20-Feb-13 bellows for Condnse...
Ordering Product Engineering Manufacturing Supply for Unit-1 & 2 Erection of Butterfly valves for Condenser-1 Erection of Butterfly valves for Condenser-2 Commissioning Ordering Product Engineering Manufacturing Supply OLTC & its accessories Erection of OLTC-1 Erection of OLTC-2 Commissioning Ordering Product Engineering Manufacturing Supply for Unit-1 & 2 Ordering Product Engineering Manufacturing Supply for Unit-1 & 2 90 25-Jun-10 A 90 07-Dec-10 198 22-Mar-11 180 30-Aug-11 60 10-Aug-12 60 19-Oct-12 16 01-Feb-13 90 26-Apr-10 A 90 07-Dec-10 159 22-Mar-11 90 19-Aug-11 75 10-Aug-12 75 06-Nov-12 16 01-Feb-13 377 21-Sep-10 A 90 21-Sep-10 A 53 17-Dec-10 159 17-Feb-11 180 02-Jun-11 482 19-Jul-11 90 19-Jul-11 53 01-Nov-11 159 02-Jan-12 180 16-Apr-12 Page 25 of 28 06-Dec-10 21-Mar-11 07-Nov-11 26-Mar-12 19-Oct-12 28-Dec-12 20-Feb-13 06-Dec-10 21-Mar-11 22-Sep-11 01-Dec-11 06-Nov-12 01-Feb-13 20-Feb-13 28-Dec-11 16-Dec-10 16-Feb-11 20-Aug-11 28-Dec-11 12-Nov-12 01-Nov-11 02-Jan-12 05-Jul-12 12-Nov-12
Project Baseline Bar Actual Work Remaining Work Critical Remaining Work Milestone
Finish 482
19-Jul-11
12-Nov-12
90 19-Jul-11 53 01-Nov-11 159 02-Jan-12 180 16-Apr-12 582 19-Jul-11 90 19-Jul-11 53 01-Nov-11 159 02-Jan-12 180 16-Apr-12 105 10-Aug-12 16 01-Feb-13 1245 23-Jul-09 A 815 23-Jul-09 A 324 23-Jul-09 A 575 15-Dec-09 A 560 22-Feb-11 90 22-Feb-11 90 07-Jun-11 180 20-Sep-11 180 07-Feb-12 53 22-May-12 4 23-Jul-12 482 28-May-11 90 28-May-11 90 10-Sep-11 128 24-Dec-11 01-Nov-11 02-Jan-12 05-Jul-12 12-Nov-12 20-Feb-13 01-Nov-11 02-Jan-12 05-Jul-12 12-Nov-12 11-Dec-12 20-Feb-13 18-Dec-12 02-Jan-12 26-Nov-10 02-Jan-12 04-Sep-12 07-Jun-11 20-Sep-11 17-Apr-12 04-Sep-12 23-Jul-12 27-Jul-12 21-Sep-12 10-Sep-11 24-Dec-11 22-May-12
H H H H H H H H H
CWS320 CWS330 CWS340 CWS350 CWS180 CWS190 CWS200 CWS210 CWS220 CWS230
Ordering Product Engineering Manufacturing Supply for Unit-1 & 2 Ordering Product Engineering Manufacturing Supply for Unit-1 & 2 Erection of Condenser CW piping (along with LP V... Water circulation in Condenser CW line
ELECTRICAL SYSTEM
ENGINEERING
H H H H H H H H H H
EN118 EN119 ELE10 ELE20 ELE30 ELE40 ELE50 ELE60 ELE70 ELE80 ELE90
Major Engineering Balance Engineering Ordering Product Engineering Manufacturing Supply of AC,DC,UPS Dist Panels & its accessorie... Erection Panels Charging Ordering Product Engineering Manufacturing
Start Finish Original Duration 45 22-MayELE200 Cabling work of Battery bank, Charger & its access... 17-Aug-12 ELE110 Erection of Battery bank, Charger & its accessories 12 13-Jul-12 30 13-Jul-12 ELE120 30 17-Aug-12 21-Sep-12
ELE130 ELE140 ELE150 ELE160 Ordering Manufacturing Supply of Power Cable & its accessories for Unit-1... Cabling work (Power cables) Ordering Manufacturing Supply for Unit-1 & 2 90 191 210 120 03-Aug-11 16-Nov-11 13-Mar-12 31-Jul-12 16-Nov-11 26-Jun-12 13-Nov-12 18-Dec-12 16-Nov-11 26-Jun-12 13-Nov-12 24-Jun-13 02-Jan-12 26-Nov-10 02-Jan-12 06-Mar-13 06-Dec-10 03-Mar-11 22-Nov-11 06-Mar-12 11-Oct-12 06-Mar-13 24-Jun-13 06-Dec-10 21-Mar-11 08-Sep-11 22-Dec-11
HJ H HJ
90 03-Aug-11 191 16-Nov-11 210 13-Mar-12 1433 23-Jul-09 A 815 23-Jul-09 A 324 23-Jul-09 A 575 15-Dec-09 A 821 26-Apr-10 A 90 26-Apr-10 A 75 07-Dec-10 226 04-Mar-11 150 14-Sep-11 30 07-Sep-12 28 02-Feb-13 931 26-Apr-10 A 90 26-Apr-10 A 90 07-Dec-10 147 22-Mar-11 150 01-Jul-11 Page 27 of 28
C&I SYSTEM
ENGINEERING
HI H H H H H H H H H H H
C&I100
EN120 Major Engineering EN121 Balance Engineering C&I10 Ordering C&I20 Product Engineering C&I30 Manufacturing C&I40 Supply of Vib Monitoring system & its accessories ... C&I50 Erection C&I60 Commissioning C&I70 Ordering C&I80 Product Engineering C&I90 Manufacturing Supply DCS System, Panel & its accessories for U...
Remaining Work Milestone Date Particulars 28-SEP-10 UNIT 1 STG PACKAGE - L2 SCHEDULE
Erection
C&I120 C&I130 C&I140 C&I150 C&I160 Checking and Setting of Interlocks and Protection Ordering Manufacturing Supply of C&I Cables & its accessories for Unit-1 & 2 Laying & Termination of Control Cables Ordering Product Engineering Manufacturing Supply of Various Field instruments & its accessori... Installation/Mounting Ordering Manufacturing Supply for Unit-1 & 2
H H H H H H H H
ENABLING
ENB100 TENDERING
105 04-Sep-10 A 16-Dec-10 90 04-Sep-10 A 16-Dec-10 18 17-Dec-10 03-Jan-11 15 17-Dec-10 547 23-Oct-12 469 23-Oct-12* 313 23-Oct-12* Page 28 of 28 03-Jan-11 22-Apr-14 22-Apr-14 22-Oct-13
SPARES
SPR20 SPR10
Supply of Mandatory Spares for Unit-2 Supply of Mandatory Spares for Unit-1
Project Baseline Bar Zl Actual Work Remaining Work Zl Critical Remaining Work Milestone
Date 28-SEP-10
LARSEN & TOUBRO LIMITED Power Project Management Services, Vadodara JOB NO: T209001
LARSEN & TOUBRO LIMITED Power Project Management Services, Vadodara JOB NO: T209001
LARSEN & TOUBRO LIMITED Power Project Management Services, Vadodara JOB NO: T209001
LARSEN & TOUBRO LIMITED Power Project Management Services, Vadodara JOB NO: T209001