1

3/1/12

3/1/12
Issuance of
Notice-to-Proceed
Dur: 0 days Slack: 0 days
3/1/12
3/1/12

3/1/12
4/29/12
Building Permits
Dur: 60 days Slack: 0 days
3/1/12
4/29/12

3/1/12

3/1/12
2/23/13
Submittals / Procurement /
Deliveries
Dur: 360 days Slack: 36 days
4/6/12
3/31/13

3/15/12
Mobilization
Dur: 15 days Slack: 0 days
3/1/12
3/15/12

3/9/12
3/23/12
Hoarding Works
Dur: 15 days Slack: 0 days
3/9/12
3/23/12

3/1/12
3/30/12
Temporary Facilities /
Temporary Utilities
Dur: 30 days Slack: 366 days
3/2/13
3/31/13

3/11/12
3/25/12
Bonds and Insurances
Dur: 15 days Slack: 371 days
3/17/13
3/31/13

3/19/12
3/25/12
Site Clearing
Dur: 7 days Slack: 0 days
3/19/12
3/25/12

3/26/12

4/24/12

Excavation Works
Dur: 30 days Slack: 0 days
3/26/12

4/24/12

3/26/12
4/15/12
Stage 1 of Excavation
Works
Dur: 21 days Slack: 0 days
3/26/12
4/15/12

4/4/12
4/24/12
Stage 2 of Excavation
Works
Dur: 21 days Slack: 0 days
4/4/12
4/24/12

3/26/12
5/24/12
Hauling and Disposal of
Excavated Materials
Dur: 60 days Slack: 311 days
1/31/13
3/31/13

3/29/12
6/6/12
Soil Stabilization and
Protection
Dur: 70 days Slack: 298 days
1/21/13
3/31/13

4/4/12

4/26/12
Gravel Bedding
Dur: 23 days Slack: 0 days
4/4/12
4/26/12
4/5/12
4/29/12
Concrete Reinforcement
Dur: 25 days Slack: 0 days
4/5/12
4/29/12

4/12/12

5/6/12
Formworks
Dur: 25 days Slack: 0 days
4/12/12
5/6/12

4/20/12
5/14/12
Concreting Works
Dur: 25 days Slack: 0 days
4/20/12
5/14/12

5/5/12
Concrete
Dur: 18 d
5/5/12

5/5/12
Roughing

Dur: 214 da
8/30/12

5/10/12
Backfill a
Dur: 15 da
3/17/13

5/15/12
Soi
Dur: 7 day
3/25/13

5/22/12
e Reinforcement
days Slack: 0 days
5/22/12

12/4/12
g-Ins (MEFP) - by
Others
ays Slack: 117 days
3/31/13

5/24/12
and Compaction
ays Slack: 311 days
3/31/13

5/21/12
il Treatment
ys Slack: 314 days
3/31/13

5/11/12

5/28/12
Formworks
Dur: 18 days Slack: 0 days
5/11/12
5/28/12

5/17/12
6/3/12
Concreting Works
Dur: 18 days Slack: 0 days
5/17/12
6/3/12

5/25/12
6/8/12
Concrete Reinforcement
Dur: 15 days Slack: 0 days
5/25/12
6/8/12

4/5/12
5/5/12
Perforated Pipes and Fitting
Dur: 30 days Slack: 331 days
3/2/13
3/31/13

5/17/12
12/2/12
Damproofing and
Waterproofing
Dur: 200 days Slack: 119 days
9/13/12
3/31/13

5/17/12
6/3/12
Geotextile Waterproofing
Dur: 18 days Slack: 301 days
3/14/13
3/31/13

5/30/12

6/13/12
Formworks
Dur: 15 days Slack: 0 days
5/30/12
6/13/12

6/4/12
6/18/12
Concreting Works
Dur: 15 days Slack: 0 days
6/4/12
6/18/12

6/9/12
6/23/12
Concrete Reinforcement
Dur: 15 days Slack: 0 days
6/9/12
6/23/12

6/14/12

6/28/12
Formworks
Dur: 15 days Slack: 0 days
6/14/12
6/28/12

6/14/12

11/10/12
Metal Decking
Dur: 150 days Slack: 141 days
11/2/12
3/31/13

6/19/12
7/3/12
Concreting Works
Dur: 15 days Slack: 0 days
6/19/12
7/3/12

Construction Sche

6/24/12
7/8/12
Concrete Reinforcement
Dur: 15 days Slack: 0 days
6/24/12
7/8/12

6/29/12

7/13/12
Formworks
Dur: 15 days Slack: 0 days
6/29/12
7/13/12

7/4/12
7/18/12
Concreting Works
Dur: 15 days Slack: 0 days
7/4/12
7/18/12

7/9/12
7/23/12
Concrete Reinforcement
Dur: 15 days Slack: 0 days
7/9/12
7/23/12

7/14/12

7/28/12
Formworks
Dur: 15 days Slack: 0 days
7/14/12
7/28/12

7/19/12
8/2/12
Concreting Works
Dur: 15 days Slack: 0 days
7/19/12
8/2/12

7/24/12
8/7/12
Concrete Reinforcement
Dur: 15 days Slack: 0 days
7/24/12
8/7/12

7/29/12

8/12/12
Formworks
Dur: 15 days Slack: 0 days
7/29/12
8/12/12

8/3/12
8/17/12
Concreting Works
Dur: 15 days Slack: 0 days
8/3/12
8/17/12

edule - HAU Project

8/8/12
8/22/12
Concrete Reinforcement
Dur: 15 days Slack: 0 days
8/8/12
8/22/12

8/13/12

8/27/12
Formworks
Dur: 15 days Slack: 0 days
8/13/12
8/27/12

8/18/12
9/1/12
Concreting Works
Dur: 15 days Slack: 0 days
8/18/12
9/1/12

8/23/12
9/6/12
Concrete Reinforcement
Dur: 15 days Slack: 0 days
8/23/12
9/6/12

8/28/12

9/11/12
Formworks
Dur: 15 days Slack: 0 days
8/28/12
9/11/12

9/2/12
9/16/12
Concreting Works
Dur: 15 days Slack: 0 days
9/2/12
9/16/12

9/7/12
9/21/12
Concrete Reinforcement
Dur: 15 days Slack: 0 days
9/7/12
9/21/12

9/12/12

9/26/12
Formworks
Dur: 15 days Slack: 0 days
9/12/12
9/26/12

9/17/12
10/1/12
Concreting Works
Dur: 15 days Slack: 0 days
9/17/12
10/1/12

9/17/12
11/30/12
Structural Steel Framing
Dur: 75 days Slack: 61 days
11/17/12
1/30/13

9/17/12

11/15/12
Metal Stairs
Dur: 60 days Slack: 114 days
1/9/13
3/9/13

9/17/12
11/30/12
Metal Fabrications
Dur: 75 days Slack: 114 days
1/9/13
3/24/13

9/22/12
10/6/12
Concrete Reinforcement
Dur: 15 days Slack: 0 days
9/22/12
10/6/12

11/1/12
12/30/12
Flashing and Sheet Metal
Dur: 60 days Slack: 61 days
1/1/13
3/1/13

11/1/12
1/29/13
Thermal Protection
Dur: 90 days Slack: 61 days
1/1/13
3/31/13

12/1/12

12/7/12
Metal Grating
Dur: 7 days Slack: 114 days
3/25/13
3/31/13

9/27/12

10/11/12
Formworks
Dur: 15 days Slack: 0 days
9/27/12
10/11/12

10/2/12
10/16/12
Concreting Works
Dur: 15 days Slack: 0 days
10/2/12
10/16/12

10/7/12
10/21/12
Concrete Reinforcement
Dur: 15 days Slack: 0 days
10/7/12
10/21/12

10/12/12
10/26/12
Formworks
Dur: 15 days Slack: 0 days
10/12/12
10/26/12

10/17/12
10/31/12
Concreting Works
Dur: 15 days Slack: 0 days
10/17/12
10/31/12

7/24/12

11/30/12
150mm thick
Dur: 130 days Slack: 0 days
7/24/12
11/30/12

7/24/12

11/30/12
100mm thick
Dur: 130 days Slack: 0 days
7/24/12
11/30/12

9/2/12
12/30/12
Portland Cement Plaster
Dur: 120 days Slack: 0 days
9/2/12
12/30/12

10/24/12
Doors and Fra
Dur: 100 days Slac
12/22/12

9/2/12
9/11/12
Non-Skid Concrete
Dur: 10 days Slack: 201 days
3/22/13
3/31/13

9/2/12

11/1/12
1/29/13
Gypsum Board Ceiling
Dur: 90 days Slack: 0 days
11/1/12
1/29/13

11/1/12
11/30/12
Fiber Cement Ceiling
Dur: 30 days Slack: 121 days
3/2/13
3/31/13

Interior Facili
Dur: 120 days Slac
12/2/12

12/1/12

Tiling Work
Dur: 90 days Slac
12/1/12

12/1/12
Wood Floori
Dur: 60 days Slack
1/31/13

12/1/12
Acoustic Ceil
Dur: 60 days Slack
1/31/13

1/31/13
ames
ck: 59 days
3/31/13

12/30/12
ities
ck: 91 days
3/31/13

10/24/12
1/31/13
Windows / Curtain Walls
Dur: 100 days Slack: 59 days
12/22/12
3/31/13

2/28/13
ks
ck: 0 days
2/28/13

12/3/12
1/31/13
Door Hardware
Dur: 60 days Slack: 59 days
1/31/13
3/31/13

1/29/13
ing
k: 61 days
3/31/13

1/29/13
ling
k: 61 days
3/31/13

12/31/12

2/28/13
Baseboard
Dur: 60 days Slack: 0 days
12/31/12
2/28/13

12/1/12

12/30/12
Stone Works
Dur: 30 days Slack: 91 days
3/2/13
3/31/13

2/25/13
3/26/13
Punchlisting and
Rectification
Dur: 30 days Slack: 0 days
2/25/13
3/26/13

12/27/12
3/26/13
As-Built Drawings
Dur: 90 days Slack: 5 days
1/1/13
3/31/13

12/31/12

1/29/13
Baseboard
Dur: 30 days Slack: 61 days
3/2/13
3/31/13

3/17/13
3/31/13
Cleaning and Clearing
Dur: 15 days Slack: 0 days
3/17/13
3/31/13

3/31/13
3/31/13
Project Turn-Over
Dur: 0 days Slack: 0 days
3/31/13
3/31/13

3/31/13
3/31/13
Demobilization
Dur: 0 days Slack: 0 days
3/31/13
3/31/13

Fields
Early Start
Early Finish
Name
Duration Total Slack
Late Start
Late Finish

Critical Task

Critical Milestone

Critical Summary

Noncritical Task

10

11

7/24/12
9/6/12
Pre-cast Concrete at Canopy
Dur: 45 days Slack: 206 days
2/15/13
3/31/13

12/1/12
Aluminum Ce
Dur: 60 days Slack
1/31/13

11/1/12
Painting and Co
Dur: 120 days Slac
11/1/12

12/1/12
Raised Floor
Dur: 90 days Slac
12/1/12

9/2/12
Concrete Finis
Dur: 60 days Slack
1/31/13

12/1/12
12/30/12
Gypsum Board Wall
Dur: 30 days Slack: 61 days
1/31/13
3/1/13

12/31/12

Glass Wall
Dur: 30 days Slack
3/2/13

12

1/29/13
eiling
k: 61 days
3/31/13

2/28/13
oating
ck: 0 days
2/28/13

12/16/12
2/13/13
Compartments and
Cubicles
Dur: 60 days Slack: 46 days
1/31/13
3/31/13

2/28/13
ring
ck: 0 days
2/28/13

12/31/12

1/14/13
Glazing
Dur: 15 days Slack: 76 days
3/17/13
3/31/13

10/31/12
shes
k: 151 days
3/31/13

12/31/12
1/29/13
Graphic Wall Films
Dur: 30 days Slack: 61 days
3/2/13
3/31/13

1/29/13
ls
k: 61 days
3/31/13

1/30/13

2/28/13
Signage
Dur: 30 days Slack: 31 days
3/2/13
3/31/13