BTC HYDROSTATIC TEST WATER ENVIRONMENTAL MANAGEMENT PLAN: Azerbaijan and Georgia
1.0 INTRODUCTION....................................................................................... 4 2.0 CONTRACTOR CONTROL PROVISIONS ............................................... 5 2.1 Inter Government Agreement, Host Government Agreement and National Legislation ......................................................................................................... 5 2.2 Construction Contractor Requirements........................................................... 5 2.3 Construction Contractor Procedures............................................................... 6 3.0 TECHNICAL DESCRIPTION .................................................................... 7 3.1 Initial Cleaning................................................................................................... 7 3.2 Pipeline Gauging............................................................................................... 7 3.3 Pipeline Filling................................................................................................... 7 3.4 Hydrostatic Testing........................................................................................... 8 3.5 Dewatering and Final Cleaning......................................................................... 8 3.6 Geometric Survey.............................................................................................. 8 3.7 Pipeline Drying .................................................................................................. 8 4.0 HYDROSTATIC TEST WATER SOURCES AND ABSTRACTIONS........ 9 4.1 Pre-fill Water Quality Testing.......................................................................... 10 4.2 Erosion and Fish Screening Controls............................................................ 10 4.3 Hydrostatic Test Water Composition............................................................. 10 5.0 SELECTION AND ASSESSMENT OF CHEMICAL TREATMENT......... 10 5.1 Chemical Protection Against Corrosion........................................................ 10 5.2 Chemical Selection and Assessment............................................................. 11 5.3 Biocide Selection............................................................................................. 11 5.4 Oxygen Scavenger Selection.......................................................................... 13 BTC HYDROSTATIC TEST WATER ENVIRONMENTAL MANAGEMENT PLAN: Azerbaijan and Georgia
6.0 DISCHARGE PROCESSES.................................................................... 14 6.1 Discharge Locations ....................................................................................... 14 6.2 Discharge options ........................................................................................... 14 6.3 Management of residual iron in the hydrotest water .................................... 15 7.0 IMPACT MITIGATION AND MANAGEMENT......................................... 16 1.0 INTRODUCTION The purpose of hydrostatic testing is to prove integrity of the pipeline following line pipe transportation and handling and construction of the pipeline.
A Pollution Prevention Contractor Control Plan (CCP) has been developed for each country involved in the BTC Project. This Hydrostatic Testing Strategy document addresses key aspects of pollution prevention, and as such is a supplementary document to the CCPs. This document applies to Azerbaijan and Georgia. A separate document has been prepared for Turkey
This document has been prepared to provide information on the strategy for mitigating the potential environmental and social impacts associated with hydrostatic testing of the pipeline that will be used across the three countries. Individual Construction Contractors within each country will prepare more specific documentation including procedures and detailed method statements to deal with site specific details. This document provides a consistent framework and approach by which hydrostatic testing will be managed, such that country specific details and construction contractor procedures will align with this overarching strategy.
Hydrostatic testing can have associated environmental and social impacts if not properly planned and managed. This Strategy document sets out the mitigation and management controls to be implemented to prevent or minimise impacts from the following activities:
Abstraction of water Chemical selection Discharge of water Drying In-situ testing of AGIs Groundwater/surface water contamination
The remainder of this document describes the hydrostatic testing strategy under the following section headings:
Section 2: Contractor Control Provisions Describes the legal framework and approval processes for hydrostatic testing and environmental protection as they relate the BTC Pipeline Project.
Section 3: Technical Description Provides a technical description of pipeline hydrostatic testing and pre-commissioning.
Section 4: Hydrostatic Test Water Abstraction and Discharge Sources Describes the assessment process for potential water abstraction and discharge sources.
Section 5: Selection and Assessment of Chemical Treatment Provides detailed information about the potential need for chemical additives, chemical selection and the chemical characteristic of biocides and oxygen scavengers. Provides an explanation of the fate and effect of the biocide and oxygen scavenger.
BTC HYDROSTATIC TEST WATER ENVIRONMENTAL MANAGEMENT PLAN: Azerbaijan and Georgia
Section 6: Discharge Processes Provides information about how hydrotest water discharge will be managed.
Section 7: Summary of Impact Mitigation and Management Provides a summary of the facts and a description of how the potential environmental and social impacts of hydrostatic testing will be avoided, mitigated and managed. 2.0 CONTRACTOR CONTROL PROVISIONS 2.1 Inter Government Agreement, Host Government Agreement and National Legislation The Pollution Prevention Contractor Control Plans contain more detailed information regarding relevant IGA, HGA, standards and legislative requirements e.g The IGA states that international standards and practices within the petroleum pipeline industry, be in no event less stringent than EU standards. The project is also bound to comply with lender guidelines (as detailed in the Environmental and Social Action Plan (ESAP)).
Azerbaijan The Host Government Agreement (HGA) requires that all project activities conform to the environmental standards and practicesgenerally observed by the international community with respect to petroleum pipelines comparable to the Project (Article 3, HGA; see ESIA-Draft for Disclosure, Section 6.1.5, pp 6-8). The two principal pieces of national legislation of relevance to pollution prevention in Azerbaijan are the Law on Environmental Protection (8 June 1999) and the Law on Ecological Safety (4 August 1999). These laws are applicable to the extent they do not conflict with the IGA and the HGA (ESIA-Draft for Disclosure, Section 6).
Georgia The contractual terms set for the construction programme require that all project activities shall conform with the environmental standards and practices set forth in this Appendix 3 [the Georgia Host Government Agreement (HGA); refer Appendix B Annex 1, ESIA-Draft for Disclosure] as well as those generally observed by the international community with respect to petroleum pipeline projects. In certain circumstances Dutch environmental standards are prescribed in Georgia. The principal national legislation that is relevant to hydrostatic testing includes Environmental Permits (1996) and Water (1997). 2.2 Construction Contractor Requirements The HSE requirements within the contracts awarded to the Construction Contractors require all Contractors to fully comply with the following BP documents and standards:
Getting HSE Right which details the overarching HSE expectations for all BP Projects Getting Health Right which outlines the overarching health expectations for all BP Projects AGT HSE Requirements - Major Contracts. Document Number 410088/00/L/SA/SP/006 AGT Personnel and People Management - Major Contracts. Document No 410088/00/L/SA/SP/018 BTC HYDROSTATIC TEST WATER ENVIRONMENTAL MANAGEMENT PLAN: Azerbaijan and Georgia
Of particular relevance to pollution prevention is Clause 16 HSE Performance Standards which states that The CONTRACTOR shall aim to achieve the following HSE Performance Standards throughout the CONTRACT period: no nuisance due to noise or dustno pollution of land, air or water anduse of fuel and energy as efficiently as current technology allows. 2.3 Construction Contractor Procedures Prior to commencement of hydrostatic testing the Construction Contractor must submit detailed procedures to BTC for approval, which require BTCs approval before work can commence. The procedure(s) will address the following topics:
List of nominated personnel who are to supervise the pressure testing operation, and their qualifications, tasks and responsibilities. Detailed schedule giving proposed dates of the main activities and all tests. Details of the pipeline pressure test sections including calculated volumes of water. Plans and procedures for the supply, storage and disposal of water. Details of the line-fill water, including source, water analysis, any treatment (pre- and post-test) method. Details of test equipment, including layouts, volumes and fill rates. Details of the test section preparation, including cleaning, gauging and filling. Details of the post-testing activities, including depressurising, discharge methods and relevant documentation. Details of monitoring/testing programme for source water and discharge water. Environmental and social assessment of proposed abstraction and discharge points. Justification and details of any chemical treatment package to be used, including relevant environmental and safety information. Details of mitigation methods to deal with potential environmental impacts associated with the following hydrotest activities:
Abstraction of water Chemical selection Discharge of water Drying In-situ testing of AGIs Groundwater/surface water contamination
Regulatory permits for abstraction and discharge of water (a copy must be provided to BTC prior to work starting in that section).
These procedures will be supported by detailed site specific method statements. Alternatively the Contractor may choose to consolidate the information into one detailed procedure. Whatever the approach, the above information will be provided, including site specific details, onsite supervision and monitoring for BTC approval before work can commence.
The Construction Contractors are required to undertake all hydrostatic pressure testing pre-commissioning operations in a manner that minimises impact to the environment. BTC HYDROSTATIC TEST WATER ENVIRONMENTAL MANAGEMENT PLAN: Azerbaijan and Georgia
The Construction Contractor must demonstrate that they have assessed the environmental and social impacts of water abstraction at the proposed abstraction and discharge sites prior to activities commencing.
Hydrostatic testing and pre-commissioning activities are 24 hour operations. The operation of pumps and compressors are typically low noise activities, however equipment will be sited to avoid close proximity to residences. Where this is unavoidable local screening will be employed to ensure night-time noise levels at residences are generally maintained below 45 dB(A).
BTC will oversee hydrotesting activities. 3.0 TECHNICAL DESCRIPTION This section briefly describes the general methods to be used to perform hydrostatic pressure testing and pre-commissioning of the BTC Crude Oil Export Pipeline and includes the following activities:
Pipeline cleaning. Pipeline gauging. Pre-testing and/or post-testing of all major river crossings Hydrostatic pressure testing on completed pipeline test sections. Dewatering and final cleaning. Geometric survey. Pipeline drying. 3.1 Initial Cleaning Prior to commencement of hydrostatic testing each pipeline section shall be cleaned of construction debris using trains of pigs fitted with brushes and magnets. To reduce total water requirements, the cleaning pigs will be propelled by air and separated by slugs of fresh water. The Construction Contractor will submit for BTC approval, a cleaning procedure stating the volumes of water to be used in front and between the pigs and the proposed discharge method and location. Water used for cleaning and proposed discharge locations will be selected to avoid areas in close proximity to residential areas and locations of environmental sensitivity. 3.2 Pipeline Gauging Prior to hydrostatic testing, either following cleaning activities or during line filling, the pipeline test sections will be checked for any buckles, dents and similar irregularities using a gauging plate attached to a pig. BTC will witness loading and removal of the gauge plate. Following completion of the gauging run, the plate will be inspected for damage and photographic record of the plate condition will be maintained. In the event a received plate is damaged, the pipeline defect location will be identified and the section repaired. When the cleaning and gauging activities have been completed satisfactorily the pipeline section is ready for pressurising. 3.3 Pipeline Filling The water quality at abstraction sources will be analysed prior to filling activities commencing. The decision to use chemical treatment will depend on the water analysis BTC HYDROSTATIC TEST WATER ENVIRONMENTAL MANAGEMENT PLAN: Azerbaijan and Georgia
and the duration the water will remain in the pipeline. The need for chemical treatment will be challenged, however should treatment be necessary the use of inhibitors and chemicals will be subject to BTC approval. This is covered in detail in Section 5.
The fill water will be of a quality that protects the pipeline test section from ingress of foreign matter, sedimentation, biological contamination and internal metal corrosion. The water will be filtered and pass through vented break tanks before entering the test section of the pipeline. Flow meter arrangements will be incorporated into the fill spread for monitoring the water volume.
Where pipeline test sections are not located near potential water sources, the hydrotest water will be transferred between test sections. 3.4 Hydrostatic Testing Following completion of filling activities the pipeline test section will be left for 24 hours to allow the temperature to stabilise. The pressure will be raised in a controlled manner until the correct test pressure is reached. Upon reaching the required test pressure the pressurising pump will be isolated and the pressure allowed to stabilise for a period of 2 hours. The test pressure will then be held for a minimum of 24 hours and a log of pipeline temperature, ground temperature and ambient temperature will be maintained at regular intervals throughout the hold period. The test will be considered successful if there are no changes, which cannot be attributable to temperature variation. 3.5 Dewatering and Final Cleaning Immediately following successful completion of the pressure test the pipeline section will be dewatered using air propelled swabbing pigs. The displaced water may be transferred to another section or discharged to an approved discharge location. The procedure will detail the water analysis limits, monitoring requirements and ensure energy stored in the displaced water is dissipated to prevent scour at the discharge location. Water will be discharged in a manner not to cause damage, pollution or flooding to the area.
Following completion of dewatering activities, the tested pipeline sections will be welded together ready for final cleaning. This will be carried out using trains of cleaning pigs to the satisfaction of BTC. 3.6 Geometric Survey The geometric survey will be carried out following BTC acceptance of the cleaned pipeline. This will confirm the pipeline is free from any dents, buckles, ovality or any other forms of deformation prior to drying.
3.7 Pipeline Drying Pipeline drying will be carried out by either desiccant drying or vacuum drying. The Construction Contractor will select the actual method used. Once dry, the pipeline will be packed (small positive pressure) with either dry air or inert gas. BTC HYDROSTATIC TEST WATER ENVIRONMENTAL MANAGEMENT PLAN: Azerbaijan and Georgia
4.0 HYDROSTATIC TEST WATER SOURCES AND ABSTRACTIONS The primary impacts associated with water abstraction are the potential for ground water abstraction and modification to river flows. Secondary issues include minimising erosion at intake locations and prevention of fish entrainment into pump suction intakes . Social impacts can also be a concern where water is in short supply and abstraction of water could impact water supplies remaining for the community.
No ground water will be abstracted for hydrostatic test use. Water will be abstracted from significant water sources such that ground water tables and river flows are not affected. As a guideline, an abstraction rate of approximately 10% of water flow in a river or channel would be adopted during water abstraction so as not to have a significant impact on environmental systems. The figure of 10% will be reviewed on a case by case basis. The maximum water abstraction rate from water pipelines will be subject to assessment to confirm that other users of the supply will not be adversely affected. Agreement will be required with the water authority and the environmental regulator, and the relevant permits obtained.
Establish through measurement the actual ambient flow rate at proposed time and location of abstraction Can rate of abstraction be kept below 10% of ambient flow? Yes No Proceed Is there a downstream user (community, irrigation, natural wetland) between point of abstraction and next downstream tributary? Monitor flow and abstraction rates No Yes Proceed Conduct an assessment, with community consultation, of effects, seek alternatives etc
Figure 4.1. Guidelines for Surface Water Abstraction
BTC HYDROSTATIC TEST WATER ENVIRONMENTAL MANAGEMENT PLAN: Azerbaijan and Georgia
4.1 Pre-fill Water Quality Testing Prior to abstraction of hydro-test waters from a source, a water quality analysis will be conducted to confirm its quality. Samples will be collected and analysed by an approved independent laboratory. Field exit water analysis will be conducted at discharge locations to determine iron (Fe) levels.
The key parameters and quality standards required for hydro test water are:
pH Total Dissolved Solids H 2 S Suspended Solids Appearance / Turbidity 6.5 to 10.5 Less than 30 Kg/m 3
Nil 0.005 Kg/m 3
Clear with no visible sediment 4.2 Erosion and Fish Screening Controls During water abstraction the following practices will be undertaken to minimise erosion at river intake locations
Suction pumps and hoses used to abstract water from waterways will be located so as to avoid bed ersosion and minimise disturbance to vegetation.
The pump suction intake will be secured above the watercourse bed to prevent river substrate entering into the pump head and will incorporate a fish screen. 4.3 Hydrostatic Test Water Composition The test water will consist of either potable, or canal, or river water. Final chemical dosage rates will be determined following a water analysis from the proposed sources taken no earlier than 1 month before operations commence, as water quality is dependent on seasonal variations. Any chemicals will be added to the water prior to introduction into the pipeline. The hydrostatic test water may remain in the pipelines for more than 30 days.
Before water is transferred from one hydrotest section to another, analysis will be undertaken to determine whether additional applications of biocide and oxygen scavenger are required to maintain the required concentrations. 5.0 SELECTION AND ASSESSMENT OF CHEMICAL TREATMENT 5.1 Chemical Protection Against Corrosion The decision to use chemical treatment will depend on the water analysis and the duration the water will remain in the pipeline. Chemical treatment will be avoided wherever practicable, however should treatment be necessary the use of inhibitors and chemicals will be subject to BTC approval.
Any water system that contains sulphate has the potential to support the growth of sulphate-reducing bacteria. The problem is not so much the bacteria themselves but rather the production of corrosive hydrogen sulphide and carbon dioxide gases caused by their metabolic pathway. BTC HYDROSTATIC TEST WATER ENVIRONMENTAL MANAGEMENT PLAN: Azerbaijan and Georgia
Carbon + SO 4 = CO 2 + H 2 S + Energy
Carbon dioxide and hydrogen sulphide are both known to be corrosive towards carbon steel. It is also difficult to control corrosion in the presence of oxygen. At levels as low as 5 ppb there can be significant corrosion observed. Water can contain up to 10 ppm of oxygen under ambient temperature and pressure. The chemical effect of oxygen against carbon steel is oxidation of the ferrous iron into ferric hydroxide, commonly known as rust:
O 2 + H 2 O + 4e- = 4 OH-
4 Fe (OH) 2 + O 2 + 2H 2 O = 4 Fe (OH) 3 (Rust)
In a closed system the above reaction is only concluded once all of the oxygen has been removed. The introduction of oxygen scavengers to the system removes oxygen to below 5 ppb thus it is not available for the above reaction. The exclusion of oxygen is extremely important for the successful use of other corrosion control methods. 5.2 Chemical Selection and Assessment Considerations in determining the best chemical to use in hydrostatic testing include:
Ability to protect the inner wall of the pipeline from oxidation and biological activity during filling, testing and dewatering prior to drying. Lowest level of toxicity to the environment and the health of workers.
BTC will only approve environmentally friendly chemicals that are biodegradable and non-toxic. 5.3 Biocide Selection BTC will accept proposals from the Construction Contractors for THPS (Tetrakishydroxymethyl phosphonium sulphate) based products as this is the preferred choice of biocide. This product is generally considered less hazardous to human health compared to the gluteraldehyde based products and is more effective at combating bacteria than the quaternary ammmonium salts. The THPS manufacturers Albright & Wilson received the US EPA Green Chemistry award in 1997 for the development of THPS as a biocide (this class of chemical had previously found industrial application as a flame retardant).
All products which are used in the North Sea offshore oil industry have to be evaluated under requirements of international legislation established by The Oslo Paris (OSPAR) Convention to monitor their environmental impact. The OSPAR Convention is believed to be the most stringent chemical control legislation in the world. Under the Convention, organic based compounds are subject to the Chemical Hazard Assessment & Risk Management model known as CHARM.
In accordance with UK legislation, products have been subject to assessment by CHARM as part of the registration process at the Centre for Fisheries and Aquaculture Science (CEFAS). CHARM assigns either a number or letter to a product depending on BTC HYDROSTATIC TEST WATER ENVIRONMENTAL MANAGEMENT PLAN: Azerbaijan and Georgia
which of the two methods of categorisation that has been used. The lower the number the less the environmental impact. The numbers are arranged into ranges, which are classified by colours with GOLD representing the least threat to the environment.
The CHARM model requires the biodegradation, bioaccumulation and toxicity of the product to be calculated. Testing the effect of the product on three different species of aquatic organism is carried out. This includes one of each of the following:
Algae Crustaceans Fish
The ACG Phase 1 and Shah Deniz Stage 1 projects have selected a THPS based chemical called TROSKIL 88 for hydrotesting the offshore oil and gas pipelines. TROSKIL 88 has a SILVER CHARM banding. A significant amount of work was completed to assess and reconfirm the toxicity ranking given to the product in the North Sea by using the Caspian Specific Ecotoxicity Procedure; a procedure adopted by the Azerbaijan Ministry for Environment and Natural Resources for this purpose. Fresh and aged mixtures of this THPS-based biocide were examined to gain a better understanding of the effects of the biologically active components, after realistic interactions and reactions had occurred. The evidence suggests that the biocide will begin to hydrolyse and react within the pipeline, with the result that concentrations at the time of discharge will be lower than the initial dose concentrations.
Based on the results of the Caspian Specific Ecotoxicity Tests and subsequent modelling and ecotoxicological risk assessment of the proposed biocide, the Azerbaijan Ministry for Environment granted Shah Deniz and ACG with approvals to use and discharge hydrotest water containing THPS. The hydrotest water will be discharged from the Shah Deniz platform directly into the Caspian Sea via a sub-surface caisson. ACG Phase 1 will discharge their hydrotest water into the coastal zone beyond Sangachal Bay after storing the water in a holding pond at Sangachal terminal. Within a short period of time the biocide will rapidly breakdown in the holding pond to levels safe enough for discharge into shallow nearshore waters.
THPS is one of the leading biocide chemicals in terms of biodegradation characteristics, positive biomagnification properties and rapid transformation to a non-toxic form upon controlled discharge. The United Nations Environment Programme, the International Labour Organisation and the World Health Organization jointly published a detailed report in 2000 (Environmental Health Criteria 218) on the fate and effects of THPS, under the International Programme on Chemical Safety. This document reported the comprehensive information on the biotic and abiotic degradation of THPS. This organic substance is readily degradable, hydrolyses in 7 days at pH 9, is water soluble and not bioaccumulative.
The biocide treatment would be applied pro rata to the hydrotest waters during the filling of the pipeline to uniformly distribute the product in order to kill all macro-organisms and microorganisms, to prevent biomass solids build up and bio-corrosion occurring. However, on discharge to the atmosphere the THPS will naturally deactivate to a non- toxic form Trihydroxymethyl phosphine oxide (THPO). BTC HYDROSTATIC TEST WATER ENVIRONMENTAL MANAGEMENT PLAN: Azerbaijan and Georgia
In addition to prudent chemical selection, confining the discharged water to a small area and monitoring the biodegradation process will further mitigate any residual risk to the environment.
The recommendation for use of a biocide with a THPS based chemical, therefore builds upon a significant amount of scientific work already completed by the ACG and Shah Deniz projects and approved by the Azerbaijan Ministry for Environment and Natural Resources. BTC recommends biocide chemical packages with a THPS base. However, the Construction Contractor can propose to use alternate chemical packages to THPS but must justify and present relevant information that the environmental performance is as good as that achieved by THPS. Similarly if an alternative toxicity assessment model is used as basis for selection, justification must be provided. 5.4 Oxygen Scavenger Selection OS -2 is an ammonium bisulphite solution, which is commonly used in the international oil and gas industry to scavenge (remove) oxygen from water. The product rapidly reacts with the dissolved oxygen in the water to provide an oxygen free environment.
The equation of the reaction is as follows:
2(NH 4 ) HSO 3 + O 2 (NH 4 )2SO 4 + H 2 SO 4
Products, which are not suitable for assessment by the CHARM model, are classified using the Oilfield Chemical Notification Scheme (OCNS). Like CHARM, this scheme uses ecotoxicity information in the assessment but the results are assigned a letter from A to E, with A being the least environmentally friendly and E being the most environmentally friendly. Ammonium bisulphite solution is categorised as D meaning it will have little to no effect on the environment. Ammonium bisulphite is also on the OSPAR List A, which defines substances that are considered of no risk to the environment and for which testing and risk assessment are not required.
The ACG Phase 1 and Shah Deniz Stage 1 projects have already received approvals to discharge their hydrotest waters, as described above, from the Azerbaijan Ministry for Environment and Natural Resources, based on the use of an Ammonium bisulphite oxygen scavenger.
Ammonium bisulphite is water-soluble. The ammonium is weakly bioaccumulated, but only at high concentrations. The substance does not biomagnify and exhibits very low toxicity. The oxygen scavenger treatment should be applied pro rata to the Hydrotest waters during the filling of the pipeline to uniformly distribute the product and to totally and instantaneously deoxygenate the Hydrotest waters to prevent corrosion occurring due to the presence of dissolved oxygen. The excess oxygen scavenger treatment ensures that the deoxygenating process is completed instantaneously i.e. reaction of ammonium bisulphite solution with dissolved oxygen will be immediate. The reaction product of ammonium bisulphite and oxygen is ammonium sulphate, ions that are commonly present in surface waters. Any excess or unreacted oxygen scavenger will BTC HYDROSTATIC TEST WATER ENVIRONMENTAL MANAGEMENT PLAN: Azerbaijan and Georgia
immediately react with atmospheric oxygen upon contact when discharged to the atmosphere.
In an open pond environment the oxygen concentration in the water will rapidly re- equilibrate thus resulting in the deactivation of the oxygen scavenger. The use of spray bars will assist with re-oxygenating the discharging water and the large surface area to volume ratio ponds will further assist this process.
Consequently, BTC recommends hydrotest chemical packages from the Construction Contractors that utilise ammonium bisulphite as the oxygen scavenger agent. However, the Construction Contractor can propose to use alternate chemical packages to ammonium bisulphite but must justify and present relevant information that the environmental performance is as good as that achieved by ammonium bisulphite. 6.0 DISCHARGE PROCESSES 6.1 Discharge Locations The project requirements for temporary and permanent land acquisition are published in the BTC Resettlement Action Plan (RAP), November 2002. Where additional land for carrying out hydrotest activities is required, the Construction Contractors will complete temporary land acquisition, for hydrotest water discharge, in line with the RAP. However, the additional landtake is expected to be minimal as the activities will be constrained to the ROW wherever possible.
Upon completion of the hydrotest activity, the area used will be reinstated to a quality that renders the land fit for pre-project land use opportunities, and returned to the owner or user.
The discharge locations proposed by the Contractor will require environmental and social assessment, and approval by BTC. In identifying these areas, consideration will be given to the environmental sensitivity and suitability of the proposed area with particular attention to avoidance of areas with a high water table, vulnerable aquifers and aquatically and ecologically important wetlands and avoidance of high-grade agricultural land (crops or intensive pasture). Test manifolds will be located outside of wetlands and riparian areas as far as reasonably practical. 6.2 Discharge options There are a number of options for disposal of hydrotest water. These include disposal to temporary breaktanks and / or holding ponds. The purpose of the break tanks is to dissipate energy. They will also assist in the reduction of suspended solids while holding ponds allow time for biocide degradation. The holding pond will be constructed to enable evaporation, infiltration through a soakaway or to allow water re-use dependent on site-specific circumstances. Exit water analyses will be conducted prior to any discharge to the environment.
If the use of soakaways is chosen as the preferred disposal route, a risk based approach will be used in line with accepted guidelines such as the UK Environmental Protection BTC HYDROSTATIC TEST WATER ENVIRONMENTAL MANAGEMENT PLAN: Azerbaijan and Georgia
Agencys (EPA) Methodologies for the Derivation of Remedial Targets for Soil and Groundwater to Protect Water Resources.
Hydrotest water disposal may also occur direct to water courses. In the case where very large volumes of water are expected, it will not be possible to utilise holding ponds or breaktanks. The objective will be to return the water into the same catchment from which it was abstracted in order to minimise any upsets to the water balance. In the case of water disposal direct to watercourses, a further objective will be to minimise the use of any chemical additives, such that the water discharge chemistry is as close as practicable to that abstracted.
The Construction Contractor will be required to prepare procedures covering their proposed hydrotest water disposal methods and locations, as well as undertaking environmental and social assessments. These procedures will require approval by BTC prior to work commencing. Any hydrotest discharge will meet Project Standards. If discharge is to an aquifer that is used as a potable water source, then the discharge will meet the least onerous of WHO potable water standards or the baseline condition of the aquifer at the receptor location.
The Construction Contractors Community Liaison Officers will notify any affected individuals or community members that would potentially be affected by hydrostatic test activities and ensure that they are adequately informed about the importance of the process and the controls that would be put in place to protect human health and the environment. These will include measures such as the fencing to prevent children gaining access to any holding ponds. Where possible holding ponds and break tanks will be located remotely from households or communities. 6.3 Management of residual iron in the hydrotest water It may be necessary to use chemicals for the control of corrosion in the water filled pipeline. Consequently the correct dosage / application of the chemicals and subsequent re-treatment of transferred water can be critical to the management of the hydrotest water. Water analysis will be conducted at abstraction locations as close as practically possible to the date of commencement of water fill to enable identification of correct dosage levels. An exit water analysis will be conducted before transfer or discharge of the test water to determine iron levels and chemical re-treatment dosage.
The residual chemical levels will be measured to determine whether minimum concentrations exist to provide continued protection in the next test section. The concentration will be increased if necessary by retreatment. This is to ensure that the necessary protection is given by applying the minimum amount of chemicals.
Despite chemical treatment in the pipeline, there will still be some suspended iron contained with the hydrotest waters, which will be discharged during the dewatering process. Iron is a natural background element in the environment and is not toxic to plants in aerated soils unless in abnormally high concentrations. Similarly, iron is not toxic to humans or livestock at low exposure levels although can be perceived as an aesthetic impact introducing an unpleasant taste, odour and colour into drinking water.
BTC HYDROSTATIC TEST WATER ENVIRONMENTAL MANAGEMENT PLAN: Azerbaijan and Georgia
Although iron is only problematic at high concentrations, any potential impact of iron on the receptor environment will be assessed and mitigated by careful selection of hydrotest discharge methods and locations. 7.0 IMPACT MITIGATION AND MANAGEMENT This table summarises the environmental aspects of hydrostatic testing and describes the mitigation measures to be implemented to minimise residual environmental impacts.
Activity Environmental aspect/issue Measures to minimize potential environmental impacts Abstraction of water Ecological
Community Water use
Ground water abstraction
Modified river flow
Water quality
Erosion, Flora and fauna
An assessment will be undertaken at all proposed abstraction sites to determine whether any ecological impacts are likely to occur based upon the sensitivity of the site
An assessment will be undertaken at all proposed abstraction sites to determine any negative community impact likely to be caused by abstraction
No ground water will be abstracted for hydrostatic test use.
Water will be abstracted in a controlled manner from significant water sources such that ground water tables and river flows are not affected.
Prior to abstraction of hydro-test waters from a source, a water quality analysis will be conducted to confirm its quality.
River intake locations will have:
Suction pumps and hoses used to abstract water from waterways will be located so as to avoid significant vegetation and minimise disturbance to other vegetation. The pump suction intake will be secured above the watercourse bed to prevent river substrate entering into the pump head and will incorporate a fish screen.
Chemical selection Residual toxicity on discharge Fate Chemical additives will be justified before use, and where they are approved as necessary, they will be selected to minimise environmental impact. BTC HYDROSTATIC TEST WATER ENVIRONMENTAL MANAGEMENT PLAN: Azerbaijan and Georgia
Activity Environmental aspect/issue Measures to minimize potential environmental impacts
Discharge of water Disposal of wastewater
Soil erosion
Hydrotest water may be disposed by a number of methods including to dewatering basins/soakaways, evaporation ponds or direct to water courses. In all cases, an environmental and social assessment will need to be undertaken including mitigation measures to minimise impacts and appropriate EU standards are met.
The use of spray bars within the confines of the settlement basin will assist in the re-oxygenation of the water resulting in deactivation of the chemical treatment package and may be utilised in certain circumstances. Soils with high clay content should be compacted. More permeable soils should be avoided or have a clay layer added to minimise the rate of percolation.
Where required, erosion control measures may include a combination of hay bales, riprap, silt fencing or other approved method.
Alternate methods of disposal differing from those above will need to be justified, assessed, and require approval by BTC.
Drying Noise emissions Noise monitoring per Project Noise Monitoring Procedure will be undertaken. Equipment to be sited away from residences. Noise levels at residences shall be no greater than: 70dB(A) LAeq (8 hours) during the day, 60dB(A) LAeq (1 hour) during the evening, and generally maintained below 45 dB(A) at night. In-situ testing of AGI-s Combustion gases
Stationary combustion plant shall achieve the following standards: Particulates: 50 mg/Nm 3 NOx 150 mg/Nm 3 SOx 0.2% w/w S in fuel CO 150 mg/Nm 3
VOCs and hydrocarbons 100mg/Nm 3
Groundwater/ Surface water contamination Possible contamination of ground water by hydro test chemicals or by imported test Where biocide and oxygen scavenger is used, it will of a type that willneutralise, readily biodegrade, and not bio-accumulate in the soil.
Test water will be sourced from a potable water pipeline, river or canal and will not contaminate the BTC HYDROSTATIC TEST WATER ENVIRONMENTAL MANAGEMENT PLAN: Azerbaijan and Georgia
Activity Environmental aspect/issue Measures to minimize potential environmental impacts water of different quality to local ambient groundwater.
groundwater at discharge locations.
The Contractor is required to submit procedures for hydrostatic testing to BTC for approval prior to commencing any hydrotest works. Prior to implementing the hydrostatic test programme, the Contractor shall complete an environmental assessment for each water disposal location. These contractual requirements will enable BTC to ensure that environmental and social aspects of hydrotest operations are appropriately managed and controlled.