Escolar Documentos
Profissional Documentos
Cultura Documentos
E WELLS REPORT
Checked Ong.G.L
Page 1 of 26
CONTENT
1. General 2. Introduction 3. Recharge Wells Requirement of LTA 4. QPD, Mott MacDonalds - Recharge Well Design 5. General Ground Condition 6. Recharge Well Objective 7. Recharge Well Installation 1. Location and Quantity of Recharge Well 2. Recharge Well Design 3. Actual Soil Profile at Recharge Well Locations 4. Recharge Well Design Approach 5. Recharge Well Drilling and Installation 6. Recharge Supply 7. Functioning Tests 8. Recharge Well Operation and Monitoring Procedure 9. Frequency of Recharge Well Operation 10. References ---- 3 ---- 3 ---- 4 ---- 4 ---- 4 ---- 5 ---- 6 ---- 6 ---- 6 ---- 9 ----15 ---- 18 ---- 19 ---- 20 ---- 21 ---- 21 ----22
Appendices
1. Recharge Well Layout Plan and Details (LTA Tender Drawing) 2. Recharge Well Layout Plan and Details ( QPD, MottMac Drawing) 3. Recharge Well Location of Water Tank, Piezometer, Water Standpipe and Monitoring Procedure
Page 2 of 26
1. General
The Contract includes the design and construction of two MRT stations, namely Little India Downtown Line Station and the TBM retrieval shaft for next to C920 project, Rochor Station including the TBM launching shaft which will be integrated with the station ab about out 345m long cut and cover tunnel and 55m long mind tunnel which will be undercrossing North North-Eastern Eastern MRT line, connecting two stations, and about 290m long bored tunnel connecting the Rochor Station with Bugis MRT Sta tation. In addition to the main transit stations and tunnels, the work also covers the building of temporary and permanent canal diversions, construction of Future Underground Infrastructure above the structure of Rochor Station as well as providing deep foundation for future development.
2. Introduction
This Recharge Well Report mainly presents the installation of recharge well fulfilling the Tender requirement and needs for the ground water control as preventive measurement for the shophouses build on the shallow foundation during bulk exca excavation of the Rochor Station. Mott MacDonald Singapore Pte Ltd has been engaged as QP QP(D ) for recharge well design based on LTAs requirement by SSY, SsangYong Engineering and Construction Co. Ltd Ltd. . As for site installation of the wells and pipe laying system tem was carried out by sub sub-contractor contractor M/S Soil Investigation Pte Ltd.
Page 3 of 26
Page 4 of 26
North bound
Kallang Fromation
FCBB JF OA
LTI
C&C
RCR
Bored Tunnel
Kallang Fromation
FCBB JF OA
South bound
Page 5 of 26
Total 101 number of recharge wells is required to install based on 5m spacing which is specified in tender drawing and QPD revised drawing.
Page 6 of 26
Three options of recharge well designs are proposed based on actual ground condition at recharge wells locations as following;
Page 7 of 26
Page 8 of 26
Page 9 of 26
Fill F1 sand
FCB
Fig. 2. Location and Soil Profile - Ellison building (7 nos of recharge wells)
Page 10 of 26
Fill F1 sand MC
OA
Fig. 3. Location and Soil Profile - Shophouses at Hastings Road(16 nos of recharge wells)
F1 sand
MC
OA
Page 11 of 26
Fig. 4. Location and Soil Profile - Shophouses at Dalhousie Lane and Madras Street(24 nos of recharge wells)
Fill F1 sand
MC
OA
Fill F1 sand
MC
OA
Page 12 of 26
Fig. 5. Location and Soil Profile - Shophouses at Perak Road ( 23nos of recharge wells)
Fill F1 Sand
F1 sand
OA
Fig. 6. Location and Soil Profile - Shophouses at Mayo Street Back Lane(24 nos of recharge wells)
Page 13 of 26
ln (r2/ r1) =
(h2 h1)
Page 14 of 26
q r1 r2
Shophouses G.L
F1 sand h1
Excavation
h2
Marine Clay
Diaphragm wall Recharge well line
OA
Assumed ground water at ground level and drawdown 2m close to the excavation, a direct calculation can be made using above equation for excavation as below parameter; Q= Rate of discharge D = Thickness of permeable layer h1= Maximum water drawdown (closet to excavation) h2= Ground water level (nearest to recharge well) r1 = Distance from excavation to maximum water drawdown r2= Distance from maximum water drawdown to recharge well line k = Coefficient of permeability
Page 15 of 26
Table. 1. Summary of Estimated Drawdown Due to Excavation Location of Recharge wells Distance from excavation (m) r1 Ellison Building Hasting Road Dalhousie Lane & Madras Street Perk Road Mayo Street Back lane 10 60 6.5 8.5 1x 10-5 5 1.3 24 29 10 60 6.5 8.5 1x 10-5 5.5 1.4 23 31.9 10 60 6.5 8.5 1x 10-5 6.5 1.6 24 39.4 10 60 6.5 8.5 1x 10-5 5 1.3 16 20.2 10 25 4 6 1x 10-5 3 1.5 7 10.4 r2 Assumed water drawdown (m) h1 h2 Coefficient of Permeability (m/s) Thickness of Permeable Layer (m) Rate of Water Number drawdown of wells (individual) (m3/h/well) Total drawdown (m3/hr)
Consideration on above estimated discharge volume, the recharge volume can be developed which with assumption of parameters using following equation based on the constant head and actual coefficient of permeable of the soil condition at recharge well location.
Q = 2 D k Hc / Ln (
Q = Rate of recharge
D = Thickness of high permeable recharge layer K = Coefficient of permeability Hc = Constant injection head (injection pressure)
Ln (
Page 16 of 26
Hc
Shophouses G.L
F1 sand
Excavation
R OA
Table . 2. Summary of Recharge Volume Location of Recharge wells Thickness of Coefficient Permeable of Permeability Layer (m) (m/s) Constant Rate of Water Number Injection Recharge Vol. of wells Head (m) (individual) above (m3/h/well) ground Total Recharge Vol. (m3/hr)
Ellison Building Hasting Road Dalhousie Lane & Madras Street Perk Road Mayo Street Back lane 5 6.3x 10-6 5 1.1 24 27.3 5.5 7.9x 10-6 5 1.6 23 37.7 6.5 8.6x 10-6 5 2.1 24 50.6 5 1.4x 10-5 5 2.64 16 42.2 3 3.5x 10-5 5 3.98 7 27.9
Page 17 of 26
Comparison of the figures from above two tables, rechargeable volume is higher than discharge and the recharge wells can deliver the required discharge amount due to excavation.
On/off valve
Flow meter
PUB water Flow meter and connection P.3. Connection to PUB water main pipe
Page 19 of 26
Page 20 of 26
Observation of Waster Operation Standpipes/ Piezometers Recharge Well Weekly Daily Standby In Operation
of Remark
If the piezometric and water level are found to be drops 0.5m from base line. Same as above
Weekly Monthly
Page 21 of 26
7.10. References
Whitlow.H, 1995, BASIC SOIL MECHANICS, 3rd Edition Das.B.M, 1994, Principles of Geotechnical Engineering, Third Edition Pulle.M, 1996, Deep excavations a practical manual, First published UFC (US ARMY CROPS OF ENGINEERS), 16 January 2004, DEWATERING AND GROUND WATER CONTROL
Page 22 of 26
Appendices
1. Recharge Well Layout Plan and Details (LTA Tender Drawing) 2. Recharge Well Layout Plan and Details ( QPD, MottMac Drawing) 3. Recharge Well Location of Water Tank, Piezometer, Water Standpipeand Monitoring Procedure
Page 23 of 26
Page 24 of 26
Page 25 of 26
3. Recharge Well Location of Water Tank, Piezometer, Water Standpipeand Monitoring Procedure
Page 26 of 26