QUALITY ASSURANCE PLAN

TEMPLATE

TM-PPQA-03 V1.0
JULY 11, 2006

Systems Engineering Process Office, Code 20203


Space and Naval Warfare Systems Center San Diego
53560 Hull Street
San Diego, CA 92152-5001

Approved for public release; distribution is unlimited


Blank QA Plan Template
TM-PPQA-03 v1.0
7/11/06

PREFACE

This document is a template of a Quality Assurance (QA) Plan using the guidelines provided in the Quality
systems – Model for quality assurance in design, development, production, installation and servicing,
International Organization for Standardization ISO 9001. This template is designed for small scale
projects or projects that do not follow tradition systems/software/technical service activities. Large scale
projects or projects that do apply systems/software/technical service activities may also wish to review the
QA Plan Template, TM-PPQA-01 that exemplifies an expanded implementation of QA.

This template should be supplemented with project-specific information to produce a QA Plan that
accurately describes the project’s QA organization, tasks, roles, and responsibilities. The planning and
documenting of QA activities must agree and be consistent with the project’s Project Management Plan
(PMP) or other project-planning document. Additionally, the QA Plan must comply with Space and Naval
Warfare (SPAWAR) Systems Center (SSC) San Diego Systems/Software Engineering Management (SEM)
Policy, which provides management with appropriate visibility into the process being used by the project
and of the products being built.
This document supplements the QA Process, PR-PPQA-01. Refer to Section 2.4.3, of the QA Process for
a description on the use of this template.
Tailoring of this template is required to ensure that the scope of the project, the standards governing the
project’s operation, and the goals and objectives specific to the project, are represented.
The SSC San Diego Systems Engineering Process Office (SEPO) assumes responsibility for this document
and updates it as required to meet the needs of users within SSC San Diego CA. SEPO welcomes and
solicits feedback from users of this document so that future versions will reflect improvements, based on
organizational experience and lessons learned.
Users of this document may report deficiencies or corrections using the Document Change Request (DCR)
found on the next page or online through the SSC San Diego Process Asset Library (PAL) at
http://sepo.spawar.navy.mil/. Updates are performed in accordance with the SEPO Configuration
Management Procedure.

Introduction - ii
Blank QA Plan Template
TM-PPQA-03 v1.0
7/11/06

DOCUMENT CHANGE REQUEST (DCR)


Document Title: Blank Quality Assurance Plan Template Tracking Number:

Name of Submitting Organization:

Organization Contact: Phone:

Mailing Address:

DCR Description: Date:

Change Location:
(use section #, figure #, table #, etc.)
Proposed change:

Rationale for Change:

Note: For the Systems Engineering Process Office (SEPO) to take appropriate action on a change request,
please provide a clear description of the recommended change along with supporting rationale.
Send to: Commanding Officer, Space and Naval Warfare Systems Center, Code 20203, 53560 Hull Street, San
Diego, CA 92152-5001
Fax to: (619) 553-6249
Email to: sepo@spawar.navy.mil
Submit online: http://sepo.spawar.navy.mil/ DCR Form 3/2006

Introduction - iii
Blank QA Plan Template
TM-PPQA-03 v1.0
7/11/06

RECORD OF CHANGES
*A - ADDED M - MODIFIED D - DELETED
NUMBER OF A* CHANGE
VERSION
DATE FIGURE, TABLE OR M TITLE OR BRIEF DESCRIPTION REQUEST
NUMBER PARAGRAPH D NUMBER

Introduction - iv
Blank QA Plan Template
TM-PPQA-03 v1.0
7/11/06

DOCUMENT CONVENTIONS

This document is a Quality Assurance (QA) Plan template. As such, wording in this document should be
supplemented with project-specific information to produce a QA Plan that accurately describes the project
QA organization and tasks. Therefore, appropriately tailor (add, delete, change, or expand) the information
provided in this document
Standard conventions are used within this document to direct the reader to specific sections of the text.
These sections provide instructions and explanations, and require users to substitute their own project-
specific information for the generic information provided or to "fill in a blank."
[[Text]] Global changes. Items that appear in regular text and are surrounded by double brackets
represent changes that can be made globally throughout the document. For example, if the
sentence reads, "The purpose of this document is to define QA responsibilities, resources,
and procedures to be used during the development and maintenance of the [[project title]]
system," the user can use a global command to change all occurrences of [[project title]] to a
new system-specific title.
Bold Italics Items that appear in bold italics font represent variables that require changes on an
individual basis. For example, if the sentence reads, "Document Title of plan/manual
number 1," the user enters a specific document title.
Items that appear in a box titled “Guidance” represent instructions to the user and are not to
Italics appear in the completed version of the document. For example, if the statement reads,

Guidance
If the list of organizations is long, it may be appropriate to create numbered paragraph
headings for each organization

the writer may simply follow the directions. The user is not required to create separate,
numbered paragraphs, but the option is suggested.
Watermark. To further assist in drafting the required information, some sections contain a sample of a
hypothetical project. A watermark has been placed diagonally across the page to indicate
that the text is an example of the type of information that should appear in each section.
The samples have been constructed such that if extracted from the template with their
associated paragraph number they would create a good first draft of a QA Plan.
In cases where information may be found in another project document, like the Project Management Plan
(PMP), refer to that document rather than duplicate the information in the project QA Plan.
The template begins with the Project QA Plan cover sheet on the next page. Delete all pages prior to the
Project QA Plan cover sheet in the final format of the project QA Plan. Update the header to reflect the
document configuration identifier for the project QA Plan.

Introduction - v
[[Project Title]] QA Plan
[[Document Configuration Identifier]]
[[Document Date]]

Guidance
The Cover Page for the project QA Plan may be tailored in accordance with the project’s defined
documentation standard.

[[PROJECT TITLE]]

QUALITY ASSURANCE PLAN

[[DOCUMENT CONFIGURATION IDENTIFIER]]

[[DOCUMENT DATE]]

[[Add your organization name here]]


Space and Naval Warfare Systems Center San Diego
53560 Hull Street
San Diego, CA 92152-5001

Guidance
Tailor this distribution notice in accordance with project requirements. If possible, refrain from using
terminology in this plan that would require security classification.

Approved for public release; distribution is unlimited


[[Project Title]] QA Plan
[[Document Configuration Identifier]]
[[Document Date]]

Guidance
The Cover Page for the project QA Plan may be tailored in accordance with the project’s defined
documentation standard

[[PROJECT TITLE]]

QUALITY ASSURANCE PLAN

[[DOCUMENT CONFIGURATION IDENTIFIER]]

[[DOCUMENT DATE]]

QA Plan Approvals:

______________________ ____________
QA Manager Date

______________________ ____________
Project Manager Date

______________________ ____________
Program Manager Date

ii
[[Project Title]] QA Plan
[[Document Configuration Identifier]]
[[Document Date]]

PREFACE
This document contains the Quality Assurance (QA) Plan for the [[Project Title]]. The QA activities
described in this plan are consistent with the [[Project Title]] Project Management Plan and other project
planning documents. This document has been tailored from the QA Plan Template, TM-PPQA-01.
The [[Code/Project/Office]] assumes responsibility for this document and updates it, as required, to meet
the needs of [[Project Title]]. Users of this document may report deficiencies or corrections using the
Document Change Request found at the end of the document. Updates to this document will be performed,
at least annually, in accordance with the [[Project Title]] Configuration Management Process.

iii
[[Project Title]] QA Plan
[[Document Configuration Identifier]]
[[Document Date]]

RECORD OF CHANGES
*A - ADDED M - MODIFIED D - DELETED
NUMBER OF A* CHANGE
VERSION
DATE FIGURE, TABLE OR M TITLE OR BRIEF DESCRIPTION REQUEST
NUMBER PARAGRAPH D NUMBER

iv
[[Project Title]] QA Plan
[[Document Configuration Identifier]]
[[Document Date]]

TABLE OF CONTENTS
Section Page

SECTION 1. INTRODUCTION.............................................................................................. ..................1


1.1 Purpose........................................................................................................................................ ......1
1.2 Scope...................................................................................................................................... ...........1
1.3 Identification ............................................................................................................................... ......1
1.4System Overview.................................................................................................................. ..............1
1.5 Document Overview.................................................................................................. ........................2
1.6 Relationship to Other Plans.................................................................................... ...........................2
1.7 Reference Documents................................................................................................ ........................2
SECTION 2. MANAGEMENT............................................................................................................... ...4
2.1 Organization................................................................................................................... ...................4
2.2 Resources.................................................................................................................. ........................5
2.2.1 Facilities and Equipment............................................................................................................ 5
2.2.2 Personnel..................................................................................................................... ..............5
2.2.3 QA Tools, Techniques and Methodologies...................................................... ............................5
2.3Risk Management............................................................................................................. ..................6
SECTION 3. QA ACTIVITES....................................................................................... ............................7
3.1Process Quality Assurance .......................................................................................................... .......7
3.1.1 Task: [Title of Process Verification Activity].............................................................................. .7
3.2Product Quality Assurance.................................................................................................................. 7
3.1.2 Task: [Title of Product Verification Activity]........................................................ ......................7
3.3Responsibilites.......................................................................................................................... ..........8
SECTION 4. QA SCHEDULE.................................................................................................... ................9

SECTION 5. STANDARDS, PRACTICES, CONVENTIONS AND METRICS.......................... ..........10


5.1 Standards, Practices and Conventions........................................................................................ ......10
5.2 Metrics.................................................................................................................. ..........................10
SECTION 6. QA PROBLEM REPORTING AND RESOLUTION................................... ......................11
6.1 QA Audit Report............................................................................................................... ...............11
6.1.1 Submittal and Disposition of QA audit report............................................................ ...............11
6.1.2 Escalation Procedure for Resolution of Non-Concurrence on QA audit report.........................11
SECTION 7. QA TRAINING............................................................................................................. ......13

SECTION 8. REVIEW OF QA ACTIVITIES WITH HIGHER LEVEL MANAGEMENT....................14

SECTION 9. COLLECTING IMPROVEMENT INFORMATION...................................... ...................15

APPENDIX A. LIST OF ACRONYMS............................................................................. ........................1

LIST OF FIGURES

v
[[Project Title]] QA Plan
[[Document Configuration Identifier]]
[[Document Date]]

Figure Page

FIGURE 2-1. [[PROJECT TITLE]] ORGANIZATION............................................................... ..............4

FIGURE 6-1. QUALITY ASSURANCE AUDIT REPORT............................................. ........................12

LIST OF TABLES
Table Page

TABLE 7-1. QA TRAINING MATRIX............................................................................................ ........13

vi
[[Project Title]] QA Plan
[[Document Configuration Identifier]]
[[Document Date]]

SECTION 1. INTRODUCTION

1.1 PURPOSE
The purpose of this plan is to define the [[Project Title]] Quality Assurance (QA) organization, tasks and
responsibilities; provide reference documents and guidelines to perform the QA activities; provide the
standards, practices and conventions used in carrying out QA activities; and provide the tools, techniques,
and methodologies to support QA activities, and reporting.

1.2 SCOPE
This plan establishes the QA activities performed throughout the life cycle of the [[Project Title]].
This plan is written to follow the Space and Naval Warfare (SPAWAR) Systems Center (SSC) San Diego
Systems/Software Engineering Management (SEM) Policy, reference (a), for [[Project Title]]. Specifically,
this QA Plan will show that the QA function is in place for this project. It will show that the QA group has
a reporting channel to senior management that is independent of the project manager, the project’s systems
and software engineering groups, and related groups that include Configuration Management (CM),
Systems and Software Test, Logistics, and Technical Services.
The goal of the QA program is to verify that all products and documentation to be delivered meet all
technical requirements. The QA procedures defined herein shall be used to examine all deliverable products
and documentation to determine compliance with technical and performance requirements.
Guidance
List the life cycle processes for the system or software or technical service(s) being performed, which
are being audited by QA.
The following project-level life cycle processes are applicable to this project and considered subject to QA:
List the appropriate life cycle processes (and cite the relevant standard of guideline from which they
are derived).

1.3 IDENTIFICATION
Guidance
Reference the list of project items (e.g., Configuration Items (CIs), project processes, products, tools,
facilities, etc.) from the appropriate document (Project Management Plan, CM Plan, etc.) to which this
QA Plan will apply or provide a list in this section.
The [[Project Title]] Configuration Management Plan, reference (b), lists the Configuration Items
(CI) that are subject to this QA Plan.

1.4 SYSTEM OVERVIEW


Guidance
Insert an overview figure depicting the system receiving QA, if appropriate. If the project involves
technical services, rename this section to “technical services overview” or as appropriate.

The [[System Name]] complete the sentence by providing a description of the system or technical
service and the intended use of the system or technical service. The system includes [[enter the number
of subsystems, e.g., 4]] subsystem(s) within the system.

1
[[Project Title]] QA Plan
[[Document Configuration Identifier]]
[[Document Date]]

1.5 DOCUMENT OVERVIEW


This document identifies the organizations and procedures to be used to perform activities related to the
[[Project Title]] QA program as specified in Quality Systems – Model for quality assurance in design,
development, production, installation and servicing, International Organization for Standardization (ISO)
9001, reference (c).
Section 1 identifies the system to which this QA Plan applies; provides an overview of the system and its
functions; summarizes the purpose and contents of the QA Plan; and describes the relationship of the QA
Plan to other management plans and lists all documents referenced in this QA Plan.
Section 2 describes each major element of the organization that influences the quality of the product.
Section 3 describes the various QA tasks
Section 4 describes the schedule of QA activities
Section 5 lists the quality assurance metrics.
Section 6 describes problem reporting and corrective action.
Section 7 describes QA training requirements.
Section 8 describes the review of QA activities with higher-level management
Section 9 describes the collection of improvement information to optimize the performance of QA
Appendix A provides a list of acronyms.

1.6 RELATIONSHIP TO OTHER PLANS


QA evaluation of the project processes throughout the life cycle is based on the processes defined in the
[[Project Title]] Project Management Plan (PMP), reference (d). Reference (d) and its implementation
procedures establish the QA evaluation criteria.

1.7 REFERENCE DOCUMENTS


This section lists the documents referenced in this QA Plan.
Guidance
For the following, add or delete documents that are referenced in the QA Plan.
a. Systems/Software Engineering Management Policy, SSC San Diego Instruction 5234.2, SSC San
Diego.
b. [[Project Title]] Configuration Management Plan, Document Configuration Identifier, Document
Date.
c. Quality Systems – Model for quality assurance in design, development, production, installation and
servicing, International Organization for Standardization (ISO) 9001, Jul 1994.
d. [[Project Title]] Project Management Plan, Document Configuration Identifier, Document Date.
e. Project Management Policy, SSC San Diego Instruction 5234.1A, Nov 2004.
f. Quality Assurance Process, PR-PPQA-01, SSC San Diego.
g. Quality Assurance Plan Template, TM-PPQA-01, SSC San Diego.
h. Space and Naval Warfare System Center San Diego Standard Process Definition (Draft), PR-
OPD-35, SSC San Diego.

2
[[Project Title]] QA Plan
[[Document Configuration Identifier]]
[[Document Date]]

i. Risk Management Process, PR-SPP-04, SSC San Diego.


j. Military Handbook, Configuration Management Guidance, MIL-HDBK-61A, Feb 2001.
k. Peer Review Process, PR-PR-02, SSC San Diego.
l. Institute of Electrical and Electronics Engineers (IEEE) Standard for Software Productivity
Metrics, IEEE Std 1045-1992, Sep 1992.
m. IEEE Standard for a Software Quality Metrics Methodology, IEEE Std 1061-1992, Dec 1992.
n. IEEE Standard Dictionary of Measures to Produce Reliable Software, IEEE Std 982.1-1988, Jun
1988.
o. IEEE Guide for the Use of IEEE Standard Dictionary of Measures to Produce Reliable Software,
Std 982.2-1988, Sep 1988.
p. Technical Reviews and Audits for Systems, Equipments, and Computer Software, MIL-STD-1521,
Jun 1995.
q. Software Development and Documentation, Data Item Descriptions (DIDs), Military Standard
(MIL-STD)-498, Dec 1994. NOTE: Although ISO/IEC Std 15288 and IEEE 12207 have
superseded MIL-STD-498, the DIDs for MIL-STD-498 are still considered applicable for the
support of developing software engineering procedures and supporting documentation.

3
[[Project Title]] QA Plan
[[Document Configuration Identifier]]
[[Document Date]]

SECTION 2. MANAGEMENT
This section describes each major element of the organization that influences the quality of the product and
processes.

2.1 ORGANIZATION
Good project management practice requires a measure of independence for the QA group. This
independence provides a key strength to QA; that is, QA has the freedom, if the quality of the product is
being jeopardized, to report this possibility directly above the level of the project. While in practice this
rarely occurs, for almost all problems are correctly addressed at the project level, the fact that the QA
group can go above the project level gives it the ability to keep many of these problems at the project level.
Figure 2-1 shows the QA organization with relation to the project organization.
L in e M a n a g e m e n t

IV & V SEPO

P r o je c t
M anagem ent

C M Q A

S y s te m s P ro d u c t P ro d u c t S y s te m L o g is t ic s
E n g in e e r in g D e s ig n / D e v lp t Test Test

Figure 2-1. [[Project Title]] Organization


Guidance
Replace Figure 2-1 with the project’s organizational structure or reference the organizational chart’s
location. The project may wish to keep a single chart in a central location and reference all of its plans
and procedures to that chart to facilitate maintaining the organization chart. Provide a description of
the functional responsibilities for each functional group in the organizational structure.
In describing the functional responsibilities, answer the questions listed below:
a. Who interacts with QA?
b. Who has authority and delegates responsibilities of interacting functions?
c. What are the reporting relationships among the interacting elements identifying
independence
/dependence?
d. Who has product release authority?
e. Who approves the QA Plan?
f. What are the reporting lines for escalating conflicts and the method by which conflicts are
resolved among the elements?

4
[[Project Title]] QA Plan
[[Document Configuration Identifier]]
[[Document Date]]

In each case, add or delete the functional responsibilities that apply.

2.2 RESOURCES
2.2.1 Facilities and Equipment
QA will have access to the facilities and equipment as described in reference (d). QA will have access to
computer resources to perform QA functions such as process and product evaluations and audits.
2.2.2 Personnel
Guidance
Identify the qualification requirements of the QA
Manager. The “product” or products for which
related technical discipline familiarity is required
should be explicitly stated, e.g.
hardware/software/systems engineering, technical
documentation standards, etc. The project should
exercise flexibility in its approach to designating
personnel to perform QA. For example, where
appropriate, one or two full time people may be
designated for a moderate to large-scale project, or
several part-time people, or someone external to the
project organization may be assigned. Objective
verification may be performed by project personnel
under the supervision of the QA Manager ONLY when
they inspect processes or products OUTSIDE of their
project role and responsibilities.
2.2.3 QA Tools, Techniques and Methodologies
Guidance
Identify the special tools, techniques, and methodologies that support QA, state their purposes, and
describe their use.
Hardware Tools – QA hardware tools include, but are not limited to, simulators, monitors, stress or
environmental measurement equipment, etc.
Software Tools - QA software tools include, but are not limited to, operating system utilities, debugging
aids, documentation aids, checklists, structuring preprocessors, file comparators, structure analyzers,
code analyzers, standards auditors, simulators, execution analyzers, performance monitors, statistical
analysis packages, software development folder/files, software traceability matrices, test drivers, test
case generators, static or dynamic test tools, and information engineering Computer Aided Software
Engineering (CASE) tools.
Techniques - techniques include review of the use of standards, software inspections, requirements
tracing, requirements and design verification, reliability measurements and assessments, and rigorous
or formal logic analysis.
Methodologies - methodologies are an integrated set of the above tools and techniques. The
methodologies should be well documented for accomplishing the task or activity and provide a
description of the process to be used.
The QA Group will utilize the following tools to perform audit/inspection events:

5
[[Project Title]] QA Plan
[[Document Configuration Identifier]]
[[Document Date]]

Guidance
List the tools, techniques and methodologies used; use Section 4, QA Schedule, to specify when special
tools are required

2.3 RISK MANAGEMENT


Guidance
Identify the risk management strategy for QA. If the project has identified an overall risk management
strategy in its PMP, or as a separate Risk Management Plan, reference this document. If the QAP is
written as a stand-alone document, describe the Risk Management activities for the QA function:
a. The identified QA risks, with estimates of severity and impact.
b. The person(s) responsible for managing QA risks.
c. The criteria (e.g. risk thresholds, conditions, etc.) necessary to commence risk management
activities.
d. The risk mitigation strategies for each risk.
e. Etc.
Use the Risk Management Process, reference (i), as a guide for documenting the project QA risk
management process.
Guidance
Also discuss QA’s role in auditing and verifying project Risk Management activities and artifacts.

6
[[Project Title]] QA Plan
[[Document Configuration Identifier]]
[[Document Date]]

SECTION 3. QA ACTIVITES
Guidance
Development of this section requires the cooperation of the project manager and QA manager to
identify the system, software or technical support life cycle processes, and the work products that are
applicable to the project. Whether the project is a full service development effort, or is focused on a
subset of engineering activities, or provides a specific technical support service (e.g. concept
development, proposal development, test and evaluation, logistic support, etc.) should dictate which
activities this QA Plan should address. This QA Plan should reflect verification of those activities, and
as well the products derived from the activities. Describe the portion of the project life cycle covered
by this QA Plan, the tasks to be performed with special emphasis on QA activities, and relationship
between these tasks and the planned major checkpoints. The sequence of the tasks should be indicated.
Tailor this section to reflect those tasks and project products being verified that relate to the project’s
current/projected activities. The QA Group should work with the PM to ensure that QA activities are
coordinated with those of the project being evaluated.

3.1 PROCESS QUALITY ASSURANCE


Guidance
Describe the project processes that will undergo QA verification. Where appropriate, cite the
governing technical or administrative standard that describes the requirements for performing the
process being verified. For each documented process, include a checklist of activities that are verified.
The completed checklist provides an artifact of QA activity for the project’s processes.
3.1.1 Task: [Title of Process Verification Activity]
QA shall conduct evaluation of the state the project process Process, verifying that project processes are
defined and implemented to obtain a product or service in accordance with acquirer requirements.
QA will use cite the checklist used to perform the verification as a guide for conducting the evaluation.

3.2 PRODUCT QUALITY ASSURANCE


Guidance
Describe the project products that will undergo QA verification. Where appropriate, cite the governing
technical or administrative standard that describes the requirements for engineering the product, or
for producing the service-related products being verified. For each product, include a checklist of
activities that are verified. The completed checklist provides an artifact of QA activity for the project’s
products.
3.1.2 Task: [Title of Product Verification Activity]
QA shall conduct evaluation of the state the project product, verifying that product or service is provided
in accordance with acquirer requirements.
QA will use reference the checklist used to perform the verification as a guide for conducting the
evaluation.

7
[[Project Title]] QA Plan
[[Document Configuration Identifier]]
[[Document Date]]

3.3 RESPONSIBILITES
Guidance
This paragraph should identify the specific organizational elements responsible for each task. It is
recommended that the Project Manager, together with the QA Manager, develop a matrix that provides
an overview of the responsibilities for conducting each of the aforementioned QA tasks. It is
recommended that the project’s higher-level sponsor QA personnel, if available, participate in project
QA activities.

8
[[Project Title]] QA Plan
[[Document Configuration Identifier]]
[[Document Date]]

SECTION 4. QA SCHEDULE

Guidance
Ensure that the QA schedule is coordinated with the project schedule. Schedule the performance of QA
audits and inspections in accordance with project schedule and milestones. Ensure the appropriate
checklists are developed and provided to coincide with the scheduled QA audit events. Establish a
process for conducting the schedule, e.g., announce the upcoming QA event(s), request stakeholder
artifact availability for audit/inspection, prepare audit findings/recommendation, resolve outstanding
issues, etc. Ensure that provisions are included for resolving issues that cannot be resolved within the
project as described in Section 6.
The QA schedule should also specify the tools, techniques, and methodologies described in Section
2.2.3 that are required to prepare for and conduct each QA event.

9
[[Project Title]] QA Plan
[[Document Configuration Identifier]]
[[Document Date]]

SECTION 5. STANDARDS, PRACTICES, CONVENTIONS AND


METRICS

5.1 STANDARDS, PRACTICES AND CONVENTIONS


Guidance
Identify the standards (mandatory requirements) to be applied. State how compliance with these items
is to be monitored and assured. Tailor this section to reflect the actual project products, e.g. hardware,
software, documentation, etc.
It should be noted that whenever a project product reflects TAILORING of a governing guideline or
standard, e.g. MILSPEC, QA should verify that the project has fully described the scope of tailoring
with supporting rationale in the PMP or similar document.

5.2 METRICS
Guidance
Identify or reference the standards, practices, and conventions to be used in the definition, collection
and utilization of measurement data. Cite any internal (e.g., project, corporate) and external (e.g.,
user, customer) requirements or standards with which metrics practices must comply. IEEE Std 1045-
1992, IEEE Standard for Software Productivity Metrics, reference (m) describes conventions for
counting the results of the development processes. IEEE Std 1061-1992, IEEE Standard for a Software
Quality Metrics Methodology, reference (n), provides a methodology for selecting and implementing
process and product metrics. IEEE Std 982.1-1988, IEEE Standard Dictionary of Measures to
Produce Reliable Software, reference (o) and IEEE Std 982.2-1988, IEEE Guide for using reference
(o), reference (p) provide various measures for use in different life cycle phases to gain confidence in
the building of reliable software. To keep metrics simple, an example of cost and schedule metrics is
offered.

10
[[Project Title]] QA Plan
[[Document Configuration Identifier]]
[[Document Date]]

SECTION 6. QA PROBLEM REPORTING AND RESOLUTION


Guidance
Describe the practices and procedures to be followed for reporting, tracking, and resolving problems
identified in both products and processes. State the specific organizational responsibilities concerned
with their implementation.

6.1 QA AUDIT REPORT


Guidance
Use or tailor the format shown in Figure 6-1 to document QA Audit Reports.
6.1.1 Submittal and Disposition of QA audit report
6.1.2 Escalation Procedure for Resolution of Non-Concurrence on QA audit report

11
[[Project Title]] QA Plan
[[Document Configuration Identifier]]
[[Document Date]]

QUALITY ASSURANCE AUDIT REPORT


TRACKING IDENTIFIER:____________
LEAD AUDITOR:______________________________________ DATE OF REPORT:_____________
AUDIT TEAM:_______________________________________________________________________
____________________________________________________________________________________
PROJECT NAME:____________________________________________________________________
DATE OF AUDIT:_______________________ EFFORT EXPENDED:________________(total hours)
PRODUCT/PROCESS/PROCEDURE AUDITED:___________________________________________
AUDIT CHECKLIST/PRODUCT VERIFICATION USED: (Attach)_____________________________
AUDIT FINDINGS: (Check one.)
_____ Product/Process/Procedure Acceptable
_____ Product/Process/Procedure Conditionally Acceptable
(Subject to satisfactory completion of action items listed below)
Conditions noted:
_____ Product/Process/Procedure Unacceptable
(Subject to satisfactory completion of action items listed below)
Conditions noted:
ACTION ITEM (AI):
AI # TITLE ASSIGNED TO: DUE DATE: COMP DATE:___
____________________________________________________________________________________
____________________________________________________________________________________
CORRECTIVE ACTION:
____________________________________________________________________________________
____________________________________________________________________________________
RECOMMENDATIONS/SUGGESTED IMPROVEMENTS:
____________________________________________________________________________________
____________________________________________________________________________________
DISPOSITION: APPROVE CANCEL DEFER
Project Manager: DATE:
____________________________________________________________________________________
AI CLOSURE:
QA Sign-off: DATE:
(FILE COMPLETED FORM IN QA EVALUATION RECORD.)

Figure 6-1. Quality Assurance Audit Report

12
[[Project Title]] QA Plan
[[Document Configuration Identifier]]
[[Document Date]]

SECTION 7.  QA TRAINING
Guidance
Identify the training activities necessary to meet the needs of the QA Plan. Tailor the contents of Table
7-1 below to reflect the project’s requirements.
Table 7-1 provides a matrix that identifies the required skills to perform QA tasks to implement this
[[Project Title]] QA Plan. The training schedule will be compatible with the project schedule. In some
cases, training will be conducted as On-the-Job Training (OJT).
TABLE 7-1. QA TRAINING MATRIX
TASK SKILL REQUIREMENTS TYPE SOURCE
Code Reviews Source Language, Peer Classroom/ SEPO, Peer Review
Reviews OJT Process and Workshop
Hardware Reviews Hardware orientation training, Classroom/ Hardware Vendor or
technical knowledge OJT organization hardware
expert
Documentation System Development and Classroom/ SEPO, Peer Review
Reviews Documentation standards and OJT Process and Workshop
guidelines, Peer Reviews
Process Audits System Development Life Classroom/ ISO/IEC-15288, IEEE/EIA
Cycle Processes, Audit OJT 12207
techniques
Testing Testing Methodologies OJT
QA Management Project Management Classroom/ SEPO, Project Management
OJT Core Course (PMCC)
Metrics Data Collection and Analysis Classroom/ SEPO, PMCC
OJT
Problem reporting and Configuration Management Classroom/ SEPO, CM Practitioner's
correction action OJT Training
Tools Vendor supplied training Classroom/ Vendor
OJT
Code, Media, and Configuration Management Classroom/ SEPO, CM Practitioner's
Supplier Control OJT Training
Risk Management and Classroom/ SEPO, PMCC, Risk
Analysis OJT Management Process
Project Management Classroom/ SEPO, Introduction to Best
OJT Practices, PMCC, PMG

13
[[Project Title]] QA Plan
[[Document Configuration Identifier]]
[[Document Date]]

SECTION 8. REVIEW OF QA ACTIVITIES WITH HIGHER LEVEL


MANAGEMENT
Guidance
The project QA, collaborating with the project manager, should establish and document in the PMP, or
QA Plan the appropriate agenda items for review during these meetings; the process for these meetings
should also establish required attendees from higher level management, and any reports or action
items that are documented to facilitate managing QA activities.

14
[[Project Title]] QA Plan
[[Document Configuration Identifier]]
[[Document Date]]

SECTION 9. COLLECTING IMPROVEMENT INFORMATION

Guidance
This section describes the requirements for collecting, assessing, reporting, and acting upon measures
of activities and work products derived from planning and performing the QA process to support the
future use and improvement of the project and the organization’s defined QA process and process
assets.

15
[[Project Title]] QA Plan
[[Document Configuration Identifier]]
[[Document Date]]

APPENDIX A. LIST OF ACRONYMS


Guidance
Tailor this Appendix as appropriate.
AI Action Item
CASE Computer-Aided Software Engineering
CI Configuration Item
CM Configuration Management
DCR Document Change Request
DID Data Item Description
EIA Electronic Industries Association
IEC International Electrotechnical Commission
IEEE Institute of Electrical and Electronics Engineers
ISO International Organization for Standardization
IV&V Independent Verification and Validation
MIL-STD Military Standard
OJT On-the-Job Training
P/CR Problem/Change Report
PMCC Project Management Core Course
PMG Project Management Guide
PMP Project Management Plan
QA Quality Assurance
QAP Quality Assurance Plan
SDP Software Development Plan
SEM Systems/Software Engineering Management
SEPO Systems Engineering Process Office
SPAWAR Space and Naval Warfare
SPI Systems/Software Process Improvement
SSC SPAWAR Systems Center
STD Standard
STR Software Trouble Report

A-1
DOCUMENT CHANGE REQUEST (DCR)
Document Title: [[Project Title]] Quality Assurance Plan Tracking Number:

Name of Submitting Organization:

Organization Contact: Phone:

Mailing Address:

DCR Description: Date:

Change Location:
(use section #, figure #, table #, etc.)
Proposed change:

Rational for Change:

Note: For the [[Project Title]] to take appropriate action on a change request, please provide a clear
description of the recommended change along with supporting rationale.
Send to: Commanding Officer, Space and Naval Warfare Systems Center, Code 2XX, 53560 Hull Street,
San Diego, CA 92152-5001
Fax: add appropriate fax number
Email: add appropriate email
Submit online: add appropriate URL