E10-A Concrete Beds m3 600.00 99.40 59,640.00
E10-B Concrete Filling to Hollow Walls m3 700.00 68.30 47,810.00
E10-C Concrete Filling Ends of Hollow Units m3 700.00 68.90 48,230.00
E10-D Concrete Ground Beams m3 10,900.00 74.70 814,230.00
E10-E Concrete Beds m3 300.00 66.30 19,890.00
E10-F Concrete Walls 150-450 thick m3 300.00 66.30 19,890.00
E10-G Grout Staucheon Bases nr 7,700.00 7.30 56,210.00
E10-H Formwork- Groundbeam & m 9,800.00 16.80 164,640.00
E10-I Formwork- 500- m 46,100.00 27.90 1,286,190.00
E10-J Formwork- m2 7,700.00 33.50 257,950.00
E20-B Form Recess- m 900.00 5.60 5,040.00
E20-C Kickers to lift Panels m 1,700.00 6.70 11,390.00
E20-E Reinforcement In-Situ Concrete t 304.00 648.00 196,992.00
E20-E 20 Nominal Reinforcement t 117.00 665.00 77,805.00
E20-F 20 Nominal Bent t 97.00 693.00 67,221.00
E20-G 16 Nominal Straight t 79.00 693.00 54,747.00
E20-H 16 Nominal Bent t 703.00 681.00 478,743.00
E20-I 12 Nominal Bent t 76.00 693.00 52,668.00
E20-J 10 Nominal Bent t 117.00 709.00 82,953.00
E42-K Bolt Assemblies nr 7,700.00 55.90 430,430.00
E60-A Precast Concrete Deck Slabs m2 9,170.00 56.90 521,773.00
E60-B Holes in Precast-generally m2 1,000.00 27.90 27,900.00
E60-C Galvanized Steel Straps nr 700.00 50.30 35,210.00
F-Brickwork
F10-A Masonry Brick Wall-one brick thick m2 9,600.00 54.20 520,320.00
F10-B 140 Thick Blockwork m2 4,900.00 40.20 196,980.00
F30-C Brick/Block Accessories m2 4,400.00 22.30 98,120.00
F30-D Damproof Courses m2 9,200.00 3.40 31,280.00
J-Damproofing
J40-A Damproof Membranes to Concrete m2 900.00 4.50 4,050.00
J40-B Dampproof Membranes to Precast Floor Units m2 93,300.00 3.40 317,220.00
P-Insulation
P Insulate Plain Areas m 1,000.00 11.20 11,200.00
P10B Bitumen Impregnated Board m2 2,000.00 8.40 16,800.00
P10-C Bitumen Impregnated Board Horizontal m 900.00 8.90 8,010.00