provide rail cum road for shunt reactor also as commented for transfomer sincre the weight is much

more than 400 kv switchyrd.


This shall be decided based on the movement of ICT and location of jacking point etc. Please incorporate in the other civil drawings.

provided rail/road in full length of road from axis 436 W, since transformer weight is much more than for 400 kv switchyard
This shall be decided based on movement of reactor and jacking pad locations.