Escolar Documentos
Profissional Documentos
Cultura Documentos
for the CITY OF EASTHAMPTON MASSACHUSETTS OCT-DEC 2007 Revised July 2008 See EAP Summary Report
Prepared by
RENWEABLE ENERGY & CONSERVATION UPGRADES TABLE OF CONTENTS SECTION 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0 11.0 PAGE
INTRODUCTION ....................................................................................................... 2 BACKGROUND ......................................................................................................... 3 FEASIBILITY STUDY DELIVERABLES ................................................................ 4 CITY OFFICE BUILDING -ASSESSMENT ............................................................. 6 PUBLIC SAFETY ASSESSMENT ......................................................................... 7 SENIOR CENTER - ASSESSMENT ......................................................................... 8 HIGHWAY GARAGE - ASSESSMENT .................................................................. 9 WATER TREATMENT PLANT - ASSESSMENT ................................................ 11 WASTE WATER TREATMENT PLANT - ASSESSMENT ................................. 12 PROJECT ECONOMICS .......................................................................................... 14 CONCLUSIONS ....................................................................................................... 17
APPENDICES TABLE A
END OF REPORT
1.0
INTRODUCTION
The city of Easthampton, Massachusetts is considering installing a solar photovoltaics system on one or more of its municipal buildings. During the fall of 2007 Precision Decisions LLC was contacted to perform a feasibility study. This report details the results of the feasibility study. The study focused on six potential sites: o o o o o o City Office Building - 50 Payson Avenue Public Safety - 32 Payson Avenue Senior Center - 19 Union Street Highway Garage - 1 Northampton Street Water Treatment Plant - 109 Hendrick Street Waste Water Treatment Plant - 95 Ferry Street
Each of the sites was evaluated for their solar potential and the electrical and structural feasibility of each facility to be configured to accept a system.
C:\Documents and Settings\Owner.MAIN\My Documents\PD DOER\Easthampton\Reports\Summary\Report rev 7 commonwealth.docx Precision Decisions LLC -2-
2.0
BACKGROUND
The city of Easthampton, Massachusetts has made efforts to reduce energy consumption through audits and energy conservation measures (ECMs). The city has discussed the potential of installing solar photovoltaics (systems that produce solar electricity from the sunlight). It is the intention of the City that this project would be partially funded through one of the Massachusetts Technology Collaboratives (MTC) Renewable Energy Rebate Programs. In June of 2007 the City produced a request for proposal (RFP) for a consultant to perform design and implementation of a solar photovoltaic system. Precision Decisions LLC was the selected consultant from those that responded to the RFP. The project has been separated into three phases: I. The first phase will be to determine the feasibility of solar photovoltaics at six different facilities. This information will be reviewed by the city to determine which projects will move forward. II. The second phase will be to develop detailed plans and specifications for the selected site(s). These will be sent out for public bids. The rebate application(s) will then be submitted to the MTC. III. Once approved, the project will move into the third phase of construction and commissioning. This report summarized the results of Phase I. The initial indications were that the system(s) would have total combined capacity of up to 40 KW. The site specifics, total amount of funding available and potential project payback will ultimately determine the final system size(s).
C:\Documents and Settings\Owner.MAIN\My Documents\PD DOER\Easthampton\Reports\Summary\Report rev 7 commonwealth.docx Precision Decisions LLC -3-
3.0
A similar evaluation process was used for each of the six sites. This process was only fully assessed for the more promising sites as some of the sites had one or more attributes that eliminated them from solar system potential. The screening process for each site was as follows: