EXHIBIT B
Submitted to the Transportation, Public Works and
Independent Authorities Committee
from
iam E. Baroni Jr.
wil‘THE PORT AUTHORITY OF NY & NJ
December 19, 2013
Mr. Charles A. Buono, Jr.
Office of Legislative Services
State of New Jersey
State House Annex
P.O. Box 068
Trenton, New Jersey 08625
Dear Mr. Buono:
This letter is in response to the subpoena duces tecum, dated December 12, 2013, issued
to William J, Baroni by the Assembly Transportation, Public Works and Independent Authorities
Committee (the “Committee”). The documents, Bates stamped PA — BB - 000001 to PA - BB -
000349, which resulted from a search of Port Authority records, are responsive to the
Committee's request for all documents and correspondence, produced between August 1, 2013
and December 12, 2013 between the parties identified in the subpoena and concerning the
reduction from three to one of the eastbound Fort Lee, New Jersey access lanes to the George
‘Washington Bridge from September 9, 2013 through September 13, 2013.
Ifyou have any questions concerning the foregoing, kindly call me.
Very truly yours,
Delt
David R. Kromm
DRK/pg
DirectDial: (212) 435-3483Baroni, Bill
Friday, September 13, 2013 7:46 AM.
David Wildstein
Fwd: Fort Lee eastbound access to GWE.
Sent from my iPhone
Begin forwarded messag
From: "Foye, Patrick"
Date: September 13, 2013, 7:44:29 AM EDT
To: "Fulton, Cedrick” , "Durando, Robert”
Ce: "Baroni, Bill” , "Dunne, Joseph P." , "Koumoutsos,
Louis" , "Zipf, Peter” , “Samson, David”
, "Rechler, Scott" , "Buchbinder, Darrell"
Subject: Fort Lee eastbound access to GWB
[After reading lat night's media pendings, | made inquiries and recelved calls on this matter which is very
‘troubling, Here is what | learned: reversing over 25 years of PA GW operations, the three lanes in Fort
Lee eastbound to the GWB were reduced to one lane on Monday of this week without notifying Fort
Lee, the commuting public we serve, the ED or Media. A decision of this magnitude should be made only
after careful deliberation and upon sign off by the ED. Reports are that Fort Lee has experienced severe
traffic delays engulfing the entire Fort Lee area since Monday. | am appalied by the lack of process,
failure to inform our customers and Fort Lee and most of all by the dangers created to the public
interest, so |am reversing this decision now effective as soon as TBT and PAPD tell me itis safe to do so
today.
am making this decision for the following reasons:
1. This hasty and illadvised decision has resulted In delays to emergency vehicles. | pray that no
life has been lost or trip of a hospital- or hospice-bound patient delayed.
2. This hasty and ill-advised decision has undoubtedly had an adverse effect on economic activity
in both states. That is contrary to the directive we have from our Governors to do everything
possible to create jobs in both States.
3. Iwill not allow this hasty and ill-advised decision to delay the travels of those observing Yom
~ Kippur tonight or the holidays to follow.
4, I believe this hasty and ill-advised decision violates Federal Law and the laws of both States.
To be clear, | will get to the bottom of this abusive decision which violates everything this agency stands
for; tintend to learn how PA process was wrongfully subverted and the public interest damaged to say
nothing of the credibility of this agency.
Finally, lam open to considering changes to each of our facilites if there is a case to be made that
change will benefit the public interest. In the case of the Fort Lee eastbound access lanes, approval of
this action wilt eequire:
PA-B8 - 000001LL. Written sign off by TBT, Traffic Engineering and PAPD, That sign off was not sought or obtained
here.
2. Prior discussion with the local government and 2 communication plan and plenty of advance
notice to the commuting public, That did not occur here.
3, Consideration of the effects on emergency vehicles and sign off by PAPD. That did not occur
here.
4. Consideration of the financial impact on the PA in terms of O/T. That too did not occur here,
Cedric and Bob—please let this group know when access to three lanes in Fort Lee can be restored as
soon 2 possible today. This is a matter of public safety and time is of the essence.
Pat
PA-BB -000002Baroni, Bill
Friday, September 13, 2013 7:51 AM
David Samson
Fwd: Fort Lee eastbound access to GWB
General, can | call you on this now?
Sent from my iPhone
Begin forwarded message:
From: "Foye, Patrick”
Date: September 13, 2033, 7:48:29 AM EDT
To: "Fulton, Cedrick” , "Durando, Robert"
ce: "Baroni, Bll” , "Dunne, Joseph P." , "Koumoutsos,
Lovis" , "Zipf, Peter" , “Samson, David"
«, "Recher, Scott" , "Buchbinder, Darrell”
-
Subject: Fort Lee eastbound access to GWB
After reading last night's media pendings, | made inquiries and received calls on this matter which is very
troubling. Here is what | learned: reversing over 25 years of PA GWE operations, the three lanes in Fort
Lise eastbound to the GWB were reduced to one lane on Monday of this week without notifying Fort
tee, the commuting public we serve, the ED or Media. A decision of this magnitude should be made only
after careful deliberation and upon sign off by the ED. Reports are that Fort Lee haS‘experienced severe
traffic delays engulfing the entire Fort Lee area since Monday. 1am appalled by the lack of process,
failure to inform our customers and Fort Lee and most of all by the dangers created to the public
interest, so lam reversing this decision now effective as soon as TBT and PAPO tell me itis safe to do so
today.
1am making this decision for the following reasons:
41. This hasty and il-advised decision has resulted in delays to emergency vehicles. | pray that no
life has been lost or trip of a hospital- or hospice-bound patient delayed.
2. This hasty and illadvised decision has undoubtedly had an adverse effect on economic activity
in both states, That is contrary to the directive we have from our Governors to do everything
possible to create jobs in both States.
3. [will not allow this hasty and iladvised decision to delay the travels of those observing Yon
Kippur tonight or the holidays to follow.
44. believe this hasty and ill-advised decision violates Federal Law and the laws of both States.
To be clear, | will get to the bottom of this abusive decision which violates everything this agency stands
for, lintend to learn how PA process was wrongfully subverted and the public interest damaged to say
nothing of the credibility of this agency.
Finally, lam open to considering changes to each of our facilities if there is 2 case to be made that
change will benefit the public interest. In the case of the Fort Lee eastbound access lanes, approval of
this action will require:
PA-BB - 000008,1. Written sign off by TBT, Traffi
here.
2. Prior discussion with the local government and a communication plan and plenty of advance
notice to the commuting public. That did not occur here.
Consideration of the effects on emergency vehicles and sign off by PAPD. That did not occur
here.
14. Consideration of the financial impact on the PA in terms of O/T. That too did not occur here.
ic Engineering and PAPD. That sign off was not sought or obtained
Cedric and Bob—please let this group know when access to three lanes in Fort Lee can be restored a5
soon as possible today. This is a matter of public safety and time is of the essence.
Pat
PA- BB -000004- From: Baroni, Bll
jent: Friday, September 13, 2013 10:44 AM
To: Regina Egea
Subject: FW: Fort Lee eastbound access to GWB
Importance: High
Sent: Friday, September 13, 2013 7:44 AM
To: Fulton, Cedrick; Durando, Robert
Ce: Baroni, Bill; Dunne, Joseph P.; Koumnoutsos, Louis; Zipf, Peter; Samson, David; ‘Rechler, Scott’; Buchbinder, Darrell
‘Subject: Fort Lee eastbound access to GWB
Importance: High
After reading last night's media pendings, | made inquiries and received calls on this matter which is very troubling. Here
is what | learned: reversing over 25 years of PA GWE operations, the three lanes in Fort Lee eastbound to the GWE were
reduced to one lane on Monday of this week without notifying Fort Lee, the commuting public we serve, the ED or
Media. A decision of this magnitude should be made only after careful deliberation and upon sign off by the ED. Reports
are that Fort Lee has experienced severe traffic delays engulfing the entire Fort Lee area since Monday. 1am appalled by
the lack of process, failure to inform our customers and Fort Lee and most of all by the dangers created to the public
interest, so lam reversing this decision now effective as soon as TET and PAPD tell me its safe to do so today.
‘am making this decision for the following reasons:
1. This hasty and illadvised decision has resulted in delays to emergency vehicles. | pray that no life has been lost
or trip of a hospital- or hospice-bound patient delayed,
2. This hasty and ilkadvised decision has undoubtedly had an adverse effect on economic activity in both states.
‘That is contrary to the directive we have from our Governors to do everything possible to create jobs in both
States
3. Iwill not allow this hasty and ill-advised decision to delay the travels of those observing Yom Kippur tonight or
the holidays te follow.
4, I believe this hasty and ill-advised decision violates Federal Law and the laws of both States.
To be clear, | will get to the bottom of this abusive decision which violates everything this agency stands for; | intend to
earn how PA process was wrongfully subverted and the public interest damaged to say nothing of the credibility of t
agency.
Finally, | am open to considering changes to each of our facilities if there is a case to be made that change will benefit
‘the public interest. in the case of the Fort Lee eastbound access lanes, approval of this action will require:
1. Written sign off by TBT, Traffic Engineering and PAPO. That sign off was not sought or obtained here.
2. ror discussion with the local government and a communication plan and plenty of advance notice to the
commuting public. That did not occur here.
3. Consideration ofthe effects on emergency vehicles and sign off by PAPD. That did not occur here.
4. Consideration ofthe financial impact on the PA in terms of O/T. That too did not occur here
Bob—please let this group know when access to three lanes in Fort Lee can be restored as soon as possible
today. This is a matter of public safety and time is of the essence,
‘i
PA-BB - 000008,Pat
PA. 8B - 000008‘Samson, David dsamson@wolffsamson.com]
‘Tuesday, Seplember 17, 2015 8:59 PM
Baroni, Bill
Fwd: Briefing Notes for Press Availabilty
FYI
Begin forwarded message:
From: "Rechier, Scott’ >
Date: September 17, 2013 8:40:18 PM EDT
To: "Samson, David"
Subject: RE: Briefing Notes for Press Availabilty
‘After my intial cals | don’ think this is correc. | also called Baroni who did think tis was the case.
-Otiginal Message——
From: Samson, David [maltto:dsamson@wolffsamson.com]
Sent: Tuesday, September 17, 2013 8:02 PM
To: Rechler, Scott
‘Subject. Fwd: Briefing Notes for Press Availability
| am told the ED leaked to the WSJ his story about Fort Lee issues-very unfortunate for NY/NJ relations
Sent from my iPhone
Begin forwarded message:
From: "MacSpadden, Lisa
ecspadden@penyn) gov>,
ee ee ner@RXRReally.comemaito:SRechler@RXRRealty com>,"
Shick: >, “Baroni, Bir
TRparoni@panyr] gov-maito:bbaroni@panynj.gov>>
Faerie, prippe” >-
eee at cageren@panyr.govemalto dgarten@panyrj gov>, “Ma, John”
“Sensgeenyn| gover ma@panyn) gov>>, Widstein, avg?
iiestem@vanyn) gov>
Subject Briefing Notes for Press Availabilty
iit, Charman, Vice Chaitman, Pat and Bil, Attached, please find the briefing notes for tomorrow's press avaliblity post
Board meeting.
Lisa
NOTICE: THIS E-MAIL AND ANY ATTACHMENTS CONTAIN INFORMATION FROM THE PORT
[AUTHORITY OF NEW YORK AND NEW JERSEY AND AFFILIATES. IF YOU BELIEVE YOU HAVE
RECEIVED THIS E-MAIL IN ERROR, PLEASE NOTIFY THE SENDER IMMEDIATELY,
PERMANENTLY DELETE THIS E-MAIL (ALONG WITH ANY ATTACHMENTS), AND DESTROY ANY
PRINTOUTS.
PA-@8 - 000007-
“lease Note: The information contained inthis email message is a PRIVATE communication that may contain confidential
>
Date: September 18, 2013, 5:54:30 AM EDT
To: "Samson, David" >
Subject: Re: Briefing Notes for Press Availabilty
David - you know | am not naive to these issues but in this instance I don't agree with your assessment of Pats
involvement. Perhaps you or Bill have some different inteligence than mine that will change that view. Ted Mann is a
‘good reporter and was instructed to sniff out this story by his editors who were stuck in traffic. Pats intial emails out
there and sent because of our belief that the PA staff was running amuck (due to our lack of any other knowledge) and
likely led to the reference in the article. Let's not escalate this unless there is clear evidence that he truly spoke to the
WS.
Scott Recher
CEO and Chairman
RXR Realty
Srechler@rxrrealty.com
‘on Sep 18, 2013, at 5:45 AM, "Samson, David" >
wrote:
‘Scott | just read it and it confirms evidence of Foye's being the leak, stirring up trouble~this is yet another example of a
Story, we've seen it before, where he distances himself from an issue in the press and rides in on a white horse to save
the day (if you need prior examples | will provide)~in this case, he's playing in traffic, made a big mistake. D.
‘On Sep 18, 2013, at $:37 AM, "Rechler, Scott” > wrote:
‘Again... dont think Pat spoke to anyone at the WS: partculanty after reading the article this morning
‘Scott Rechier
CEO and Chairman
RXR Realty
Srechler@narealty.com -
‘On Sep 18, 2013, at 5:34 AM, "Samson, David" >
wrote:
More evidence of reckless, counter-productive behavior.
‘On Sep 17, 2013, at 9:36 PM, "Rechier, Scott” > wrote:
‘Seems strange based on my inquiries.
Original Message—
rom: Samson, David [mailto:dsamson@woltisamson.com}
Sent: Tuesday, September 17, 2013 6:59 PM
PA-8B 000008,To: Rechier, Scott
‘Subject Re: Briefing Notes for Press Availabilty
or whatever reason, he's not telling you the facts.
‘On Sep 17, 2013, at 8:40 PM, "Rechler, Scott” > wrote:
‘After my intial calls | don’t think this is correct. | also called Baroni who didn't think this was the case.
—Original Message—
From: Samson, David [mailto:¢samson@woltfsamson com)
Sent: Tuesday, September 17, 2013 6:02 PM
To: Rechler, Scott
Subject: Fwd: Briefing Notes for Press Availabifity
| am told the ED leaked to the WSJ his story about Fort Lee issues~very unfortunate for NY/NJ relations.
‘Sent from my iPhone
Begin forwarded message:
From: "MacSpadden, Lisa”
Cimsespacden@panyn} gov>
Date: September 17, 2013, 6:42:19 PM EDT
To: "Samson, David"
coconscos @wolisamson.com>, "Rechler,
eee ener@RXRReslty.comemaito:SRechler@RXRRealty.com>>, "Foye,
Pack’ epfoye @panyni gov>, "Baroni Bil”
EBbaroni@panyn gov>
Bene lees, Patippe” >
“Garten, David" >, "Ma, John"
-jhma@panyn gov>, “Wildstein, David"
>
Subject: Briefing Noles for Press Availabilty
Mr. Chairman, Vice Chairman, Pat and Bill, Attached, please find the briefing notes for tomiorrows press availabilty post
Board meeting,
Usa
NOTICE: THIS E-MAIL AND ANY ATTACHMENTS CONTAIN INFORMATION FROM THE PORT
AUTHORITY OF NEW YORK AND NEW JERSEY AND AFFILIATES. IF YOU BELIEVE YOU HAVE
RECEIVED THIS E-MAIL IN ERROR, PLEASE NOTIFY THE SENDER IMMEDIATELY,
PERMANENTLY DELETE THIS E-MAIL (ALONG WITH ANY ATTACHMENTS), AND DESTROY ANY
PRINTOUTS.
“
Please Note: The information contained in this email message is a PRIVATE communication that may contain confidential
fttomey-client information. If you are not the intended recipient, do not read, copy or use itor disciose it to others, If you
fave received this message in error, please notify the sender immediately by replying to this message and then delete it
‘rom your system.
PA-BB- 000010IRS CIRCULAR 230 DISCLOSURE: To ensure compliance with requirements imposed by the IRS, we inform you that any
USS. federal tax advice contained in this cocument (including any attachments) is not intended or written to be used, and
cannot be used by the recipient and any other taxpayer, for the purpose of () avoiding penalties under the Internal
Revenue Code oF (i) promoting, marketing or recommending to another party any transaction or matter addressed herein
2 PA-B8- 000011Baroni, Bill
Tuesday, September 17, 2013 10:17 PM
Samson, David
Re: Briefing Notes for Press Availabilty
General, | shall again make my concer known to the vice chairman,
bb
Sent from my iPhone
(On Sep 17, 2013, at 8:59 PM, "Samson, David" wrote
> FYL :
> Begin forwarded message:
> From: "Rechler, Scott” >
> Date: September 17, 2013 8:40:18 PM EDT
> To: "Samson, David" >
> Subject. RE: Briefing Notes for Press Availabilty
> After my inital calls ! don’t think this is correct. 1 also called Baroni who didn’ think this was the case.
> —Original Message—
> From: Samson, David {mailto:dsamson@wolfisamson.com]
> Sent: Tuesday, September 17, 2013 8:02 PM
> To: Rechler, Scott
Subject: Fwd: Briefing Notes for Press Availablity
> | am told the ED leaked fo the WS. his story about Fort Lee issues~very unfortunate for NY/NJ relation.
> Sent from my iPhone
> Begin forwarded message:
> From: “MacSpadien, Lisa"
‘>
> Date: September 17, 2013, 6:42:19 PM EDT
>To: "Samson, David"
>, "Rechier
‘Scott >, "Foye,
Patrick” >, "Baroni, Bill”
pany}. govemaite:bbaroni@panyn,gov>>
> Ce: "Danieldes, Philippe"
“->, "Ma, Joh
«jnme@panynj gov>, "Wildsten, Davi
>
> Subject: Briefing Notes for Press Availabilly
> Mr. Chairman, Vice Chairman, Pat and Bil, Attached, please find the briefing notes for tomorrow's press availabilty post
Board meeting.
> Lisa
“Garten, David"
PA-B8 - 00012> NOTICE: THIS E-MAIL AND ANY ATTACHMENTS CONTAIN INFORMATION FROM THE PORT
> AUTHORITY OF NEW YORK AND NEW JERSEY AND AFFILIATES. IF YOU BELIEVE YOU HAVE
RECEIVED THIS E-MAIL IN ERROR, PLEASE NOTIFY THE SENDER IMMEDIATELY,
> PERMANENTLY DELETE THIS E-MAIL (ALONG WITH ANY ATTACHMENTS), AND DESTROY ANY
> PRINTOUTS.
>
> Please Note: The information contained in this email message is a PRIVATE communication that may contain
‘confidential attorney-client information. If you are not the intended recipient, do not read, copy of use itor disclose it to
others, If you have received this message in error, please notify the sender immediately by replying to this message and
then delete it from your system.
you.
> IRS CIRCULAR 230 DISCLOSURE: To ensure compliance with requirements imposed by the IRS, we inform you that
any US. federal tax advice contained in this document (including any attachments) is not intended or written to be used,
‘and cannol be used by the recipient and any other taxpayer, for the purpose of (i) avoiding penalties under the Internal
Code or (i) promoting, marketing or recommending to another party any transaction or matter addressed herein,
PA--BB - 000013Baroni, Bill
Friday, September 13, 2013 9:03 AM
Foye, Patrick
‘MacSpadden, Lisa
Re: Fort Lee eastbound access to GWB
1am onway to office to discuss. There can be no public discourse.
Sent from my iPhone
‘On Sep 13, 2013, at 8:55 AM, "Foye, Patrick” wrote:
Bill we are going to fix this fiasco
oni, Bill
‘Sent: Friday, September 13, 2013 08:40 AM
To: Foye, Patrick; MacSpadden, Lisa
‘Subject: Re: Fort Lee eastbound access to GWB
Pat we need to discuss prior to any communications.
Sent from my iPhone
‘On Sep 13, 2013, at 8:28 AM, “Foye, Patrick" wrote:
‘Thanks, Bob. I'l set up meeting to discuss this issue.
Looping tisa~how do we get word out?
ee
From: Durando, Robert
Sent: Friday, September 13, 2013 08:
To: Foye, Patrick; Fulton, Cedrick
Ce: Baroni, Bil; Dunne, Joseph P.; Koumoutsos, Louis; Zipf, Peter; Samson, David;
‘sRechler@RXRRealty,com’ ; Buchbinder, Darrell
Subject: Re: Fort Lee eastbound access to GWB
We have restored the 3 toll lanes to Ft Lee.
From: Foye, Patrick
Sent: Friday, September 13, 2013 07:44 AM
To: Fulton, Cedrick; Durando, Robert
Ce: Baroni, Bil; Dunne, Joseph P.; Kouroutsos, Louis; Zipf, Peter; Samson, David;
"Rechler, Scott’ ; Buchbinder, Darrell
‘Subject: Fort Lee eastbound access to GWB
After reading last night's media pendings, | made inquiries and received calls on this
‘matter which is very troubling, Here is what | learned: reversing over 25 years of PA
GWB operations, the three lanes in Fort Lee eastbound to the GWB were reduced to
one lane on Monday of this week without notifying Fort Lee, the commuting public we
serve, the ED or Media. A decision of this magnitude should be made only after careful
1
PA- BB - 000014deliberation and upon sign off by the ED. Reports are that Fort Lee has experienced
severe traffic delays engulfing the entire Fort Lee area since Monday. | am appalled by
the lack of process, failure to inform our customers and Fort Lee and most of all by the
dangers created to the public interest, so | am reversing this decision now effective as
s00n as TBT and PAPD tell me itis safe to do so today.
|/am making this decision for the following reasons:
4L. This Hasty and illadvised decision has resulted in delays to emergency vehictes. |
pray that no life has been lost or trip of a hospital or hospice-bound patient
delayed
2, This hasty andilladvised decision has undoubtedly had an adverse effect on
‘economic activity in both states. That is contrary to the directive we have from
our Governors to do everything possible to create jobs in both States.
3, Iwill nt allow this hasty and ilkadvised decision to delay the travels of those
observing Yor Kippur tonight or the holidays to follow.
4. believe this hasty and iladvised decision violates Federal Law and the laws of
both states,
To be clear, ! will get to the bottom of this abusive decision which violates everything
thls agency stands for; | intend to learn how PA process was wrongfully subverted and
the public interest damaged to say nothing of the credibility of this agency.
Finally, | arm open to considering changes to each of our facilities if there is a case to be
made that change will benefit the public interest. In the case of the Fort Lee eastbound
access lanes, approval of this action will require:
1. Written sign off by 731, Traffic Engineering and PAPD. That sign off was not
sought or obtained here.
2._ Prior discussion with the local government and a communication plan and
plenty of advance notice to the commuting public. That did not occur here.
3. Consideration of the effects on emergency vehicles and sign off by PAPD. That
aid not occur here.
|4. Consideration of the financial impact on the PA n terms of O/T. That too did not
occur here.
Cedric and Bob—please let this group know when access to three lanes in Fort Lee can
be restored as soon as possible today. This Is @ matter of public safety and time is of the
essence.
Pat
PA- BB -000018Foye, Patrick
Friday, September 13, 2013 8:56 AM
Baroni, Bil, MacSpadden, Lisa
Re; Fort Lee eastbound access to GWE
Bill we are going to fix this fiasco
From: Baroni, Bil
Sent: Friday, September 13, 2013 08:40 AM
To: Foye, Patrick; MacSpadden, Lisa
Subject! Re: Fort Lee easthound access to GW
Pat we need to discuss prior to any commu
jons.
Sent from my iPhone
‘On Sep 13, 2013, at 8:28 AM, "Foye, Patrick” wrote:
‘Thanks, Bob. I'll set up meeting to discuss this issue.
Looping Lisa--how do we get word out?
From: Durando, Robert
Sent: Friday, September 13, 2013 08:04 AM
To: Foye, Patrick; Fulton, Cedrick
Cc: Baroni, Bill; Dunne, Joseph P.; Koumoutsos, Louls; Zipf, Peter; Samson, David;
"SRechler@RXRRealty.com’ ; Buchbinder, Darrell
‘Subject: Re: Fort Lee eastbound access to GWE
We have restored the 3 toll lanes to Ft Lee.
From: Foye, Patrick
Sent: Friday, September 13, 2013 07:44 AM
To: Fulton, Cedrck; Durando, Robert
Ce: Baroni, Bil; Dunne, Joseph P.; Koumoutsos, Louis; Zipf, Peter; Samson, Davi; 'Rechler, Scott’
-; Buchbinder, Darrell
Subject: Fort Lee eastbound access to GWB
‘After reading last night’s media pendings, ! made inquiries and received calls on this matter which is very
troubling. Here is what | learned: reversing over 25 years of PA GWB operations, the three lanes in Fort
Lee eastbound to the GWB were reduced to one lane on Monday of this week without notifying Fort
Lee, the commuting public we serve, the ED or Media. A decision of this magnitude should be made only
after careful deliberation and upon sign off by the ED. Reports are that Fort Lee has experienced severe
traffic delays engulfing the entire Fort Lee area since Monday. | am appalled by the lack of process,
failure to inform our customers and Fort Lee and most ofall by the dangers created to the public
interest, so lar reversing this decision now effective as soon as TBT and PAPD tell me itis safe to do so
today.
|lam making this decision for the following reasons:
PA-BB 0000181. This hasty and ill-advised decision has resulted in delays to emergency vehicles. | pray that no
life has been lost or trip of a hospital- or hospice-bound patient delayed.
2. This hasty and ill-advised decision has undoubtedly had an adverse effect on economic activity
in both states. That Is contrary to the directive we have from our Governors to do everything.
possible to create jobs in both States.
3. Iwill not allow this hasty and ill-advised decision to delay the travels of those observing Yom
Kippur tonight or the holidays to follow.
4. I believe this hasty and ill-advised decision violates Federal Law and the laws of both States.
‘To be clear, | wil get to the bottom of this abusive decision which violates everything this agency stands
for; | intend to learn how PA process was wrongfully subverted and the public interest damaged to say
nothing of the credibility of this agency. >
Finally, !am open to considering changes to each of our facilities ifthere is a case to be made that
change will benefit the public interest. In the case of the Fort Lee eastbound access lanes, approval of
this action will require:
1. Written sign off by TBT, Traffic Engineering and PAPD. That sign off was not sought or obtained
here.
2. Prior discussion with the local government and a communication plan and plenty of advance
notice to the commuting public. That did not occur here.
3. Consideration of the effects on emergency vehicles and sign off by PAPD. That did not occur
here.
4, Consideration of the financial impact on the PA in terms of O/T. That too did not occur here.
Cedric and Bob—please let this group know when access to three lanes in Fort Lee can be restored as
soon as possible today. This is a matter of public safety and time is of the essence,
Pat
PA-BB -000017From:
Baroni, Bit
Friday, September 13, 2073 6:41 AM
Foye, Patrick; MacSpadden, Lisa
Subject: Re: Fort Lee eastbound access to GWB
Pat we need to
-uss prior to any communications.
Sent from my iPhone
On Sep 13, 2013, at 8:28 AM, "Foye, Patrick" wrote:
Thanks, Bob, I'l set up meeting to discuss this issue.
Looping Lisa~-how do we get word out?
From: Durando, Robert
Sent: Friday, September 13, 2013 0
To: Foye, Patrick; Fulton, Cedrick
Ce: Baroni, Bil; Dunne, Joseph P.; Koumoutsos, Louis; Zipf, Peter; Samson, David;
"SRechior@RXRRealty.com’ ; Buchbinder, Darrel
Subject: Re: Fort Lee eastbound access to GWB
We have restored the 3 toll lanes to Ft Lee.
‘oye, Patrick
Sent: Friday, September 13, 2013 07:44 AM
To: Fulton, Cedrick; Durando, Robert
Ce: Baroni, Bil; Dunne, Joseph P.; Koumoutsos, Louis; Zipf, Peter; Samson, David; 'Rechler, Scott’
; Buchbinder, Darrell
‘Subject: Fort Lee eastbound access to GWB
After reading last night's miedia pendings, | made inquiries and received calls on this matter which is very
troubling. Here is what | learned: reversing over 25 years of PA GW operations, the three lanes in Fort
Lee eastbound to the GWB were reduced to one lane on Monday of this week without notifying Fort
Lee, the commuting public we serve, the ED or Media. A decision ofthis magnitude should be made only
after careful deliberation and upon sign off by the ED. Reports are that Fort Lee has experienced severe
traffic delays engulfing the entire Fort Lee area since Monday. 1am appalled by the lack of process,
failure to inform our customers and Fort Lee and most of a by the dangers created to the public
interest, so lam reversing this decision now effective as soon as TBT and PAPD tell me itis safe to do so
today.
11am making this decision for the following reasor
1, This hasty and ill-advised decision has resulted in delays to emergency vehicles. | pray that no
life has been lost or trip of a hospital- or hospice-bound patient delayed.
2. This hasty and ill-advised decision has undoubtedly had an adverse effect on economic activity
in both states. That is contrary to the directive we have from our Governors to do everything
possible to create jobs in both States.
3, {will not allow this hasty and ill-advised decision to delay the travels of those observing Yom.
Kippur tonight or the holidays to follow.
PA-BB 000018,4, ‘believe this hasty and ill-advised decision violates Federal Law and the laws of both States.
‘Fo be clear, | will get to the bottom of this abusive decision which violates everything this agency stands
for; | intend to learn how PA process was wrongfully subverted and the public interest damaged to say
nothing of the credibility of this agency.
Finally, | am open to considering changes to each of our facilities if there is a case to be made that
change will benefit the public interest. In the case of the Fort Lee eastbound access lanes, approval of,
this action will require:
1. Written sign off by TBT, Traffic Engineering and PAPD. That sign off was not sought or obtained
here.
2. Prior discussion with the local government and a communication plen and plenty of advance
notice to the commuting public. That did not occur here.
3. Consideration of the effects on emergency vehicles and sign off by PAPD. That did not occur
here.
4. Consideration of the financial impact on the PA in terms of O/T. That too did not occur here.
Cedric and 8ob—please let this group know when access to three lanes in Fort Lee can be restored as
soon as possible today. This is @ matter of public safety and time is of the essence.
Pat
PA~B8- 000018Reohier, Scott [SRechlen@RXRRealty com]
Friday, September 13, 2073 8:29 AM
Foye, Patrick
Fulton, Gedrick; Durando, Robert: Baroni, Bil; Dunne, Joseph P.; Koumoutsos, Louis; Zipf,
Peter, Samson, David; Buchbinder, Darrell
Subject: Re: Fort Lee eastbound access to GWB.
‘Thisis terribly disturbing and incomprehensible to me. How can a decision like this be made without it being discussed
and considered at the highest level? | am particularly disturbed thet this was occurring without regard to this being the
Jewish high holiday weekend.
Pat, please let us know what happened.
Thank you.
Scott
Scott Rechler
CEO and Chairman
XR Realty
Srechler@rxrealty.co
‘On Sep 13, 2013, at 7:44 AM, "Foye, Patrick wrote:
After reading last night’s media pendings, | made inquities and received calls on this matter which is very
troubling, Here is what | learned: reversing over 25 years of PA GWE operations, the three lanes in Fort
Lee eastbound to the GWB were reduced to one lane on Monday of this week without notifying Fort
Lee, the commuting public we serve, the ED or Media. A decision of this magnitude should be made only
after careful deliberation and upon sign off by the ED. Reports are that Fort Lee has experienced severe
traffic delays engulfing the entire Fort Lee area since Monday. 2m appalled by the lack of process,
failure to inform our customers and Fort Lee and most of all by the dangers created to the public
interest, so | am reversing this decision now effective as soon as TBT and PAPD tell me itis safe to do so
today.
1am making this decision for the following reasons:
1. This hasty and illadvised decision has resulted in delays to emergency vehicles. | pray that no
life has been lost or trip of a hospital or hospice-bound patient delayed.
2. This hasty and iltadvised decision has undoubtedly had an adverse effect on economic activity
in both states. That is contrary to the directive we have from our Governors to do everything,
possible to create jobs in both States.
3, will not allow this hasty and il-advised decision to delay the travels of those observing Yorn
Kippur tonight or the holidays to follow.
14. believe this hasty and il-advised decision violates Federal Law and the laws of both States.
‘To be clear, | will get to the bottom of this abusive decision which violates everything this agency stands
for; lintend to learn how PA process was wrongfully subverted and the public interest damaged to say
nothing of the credibility of this agency.
PA-BB -000020,Finally, | am open to considering changes to each of our facilities if there is a case to be made that
‘change will benefit the public interest. In the case of the Fort Lee eastbound access lanes, approval of
this action will require:
4. Written sign off by TBT, Traffic Engineering and PAPD. That sign off was not sought or obtained
here.
2. Prior discussion with the local government and a communication pian and plenty of advance
notice to the commuting public. That did not occur here.
3. Consideration of the effects on emergency vehicles and sign off by PAPD. That did not occur
here.
a
Consideration of the financial Impact on the PA in terms of O/T. That too did not occur here.
Cedric and Bob—please let this group know when access to three lanes in Fort Lee can be restored as
soon as possible today. This is a matter of public safety and time is of the essence.
Pat
NOTICE: THIS E-MAIL AND ANY ATTACHMENTS CONTAIN INFORMATION FROM THE PORT
AUTHORITY OF NEW YORK AND NEW JERSEY AND AFFILIATES. IF YOU BELIEVE YOU HAVE
RECEIVED THIS E-MAIL IN ERROR, PLEASE NOTIFY THE SENDER IMMEDIATELY,
PERMANENTLY DELETE THIS E-MAIL (ALONG WITH ANY ATTACHMENTS), AND DESTROY ANY
PRINTOUTS
PA- BB - 000021From: Foye, Patrick
vat Friday, Septernber 13, 2013 8:29 AM
7 Durando, Robert Fulton, Cedrick
Ce: : Baroni, Bil, Dunne, Joseph P.; Koumouts0s, Louis; Zipt, Peter; Samson, David
‘srechler@rcrealy.com’, Buchbinder, Darrel, MacSpadden, Lisa
Subject: Re: Fort Lee eastbound access to GWB
Thanks, Bob. "ll set up meeting to discuss this issue.
Looping Lisa~how do we get word out?
From: Durendo, Robert
‘Sent: Friday, September 13, 2013 08:04 AM
To: Foye, Patrick; Fulton, Cedrick
Ce: Baroni, Bil; Dunne, Joseph P.; Koumoutsos, Louis; Zipf, Peter; Samson, David; ‘SRechler@RXRRealty.com
<; Buchbinder, Darrell
Subject: Re: Fort Lee eastbound access to GWB
We have restored the 3 toll lanes to Ft Lee.
From: Foye, Patrick
Sent: Friday, September 13, 2013 07:44 AM
To: Fulton, Cedrick; Durando, Robert
Ce: Baroni, Bill; Dunne, Joseph P.; Koumoutsos, Louis; Zipf, Peter; Samson, David; ‘Rechler, Scott”
—~; Buchbinder, Darrell
ubject: Fort Lee eastbound access to GWB
[After reading last night's media pendings, | made inquiries and received calls on this matter which is very troubling. Here
is what | learned: reversing over 25 years of PA GWB operations, the three lanes in Fort Lee eastbound to the GWB were
reduced to one lane on Monday of this week without notifying Fort Lee, the commuting public we serve, the ED or
‘Media. A decision of this magnitude should be made only after careful deliberation and upon sign off by the ED. Reports
are that Fort Lee has experienced severe traffic delays engulfing the entire Fort Lee area since Monday. 1am appalled by
the lack of process, failure to inform our customers and Fort Lee and most of all by the dangers created to the public
interest, so | am reversing this decision now effective as soon as TT and PAPD tell me itis safe to do so today.
am making this decision for the following reasons:
4. This hasty and illadvised decision has resulted in delays to emergency vehicles. | pray that no life has been lost
or trip of a hospital or hospice-bound patient delayed.
2. This hasty and ill-advised decision has undoubtedly had an adverse effect on economic activity in both states.
‘That is contrary to the directive we have from our Governors to do everything possible to create jobs in both
States.
3. Iwill not allow this hasty and ill-advised decision to delay the travels of those observing Yor Kippur tonight or
the holidays to follow.
4, Ibelieve this hasty and ill-advised decision violates Federal Law and the laws of both States.
‘To be clear, | will get to the bottom of this abusive decision which violates everything this agency stands for; | intend to
learn how PA process was wrongfully subverted and the public interest damaged to say nothing of the credibility of this,
(agency.
PA- 88 - 000022Finally, | am open to cor
lering changes to each of our facilities if there is a case to be made that change will benefit,
the public interest. In the case of the Fort Lee eastbound access lanes, approval of this action will require:
1
2
3
4,
\Written sign off by TBT, Traffic Engineering and PAPD. That sign off was not sought or obtained here.
Prior discussion with the local government and a communication plan and plenty of advance notice to the
commuting public. That did not occur here,
Consideration of the effects on emergency vehicles and sign off by PAPD. That did not occur here
Consideration of the financial impact on the PA in terms of O/T. That too did not occur here.
Cedric and Bob—please let this group know when access to three lanes in Fort Lee can be restored as soon as possible
today. This is a matter of public safety and time is of the essence.
Pat
PA-B8 - 00028From: Koumoutses, Louis
“Rent: Friday, September 13, 2013 6:19 AM
> Foye, Patrick; Fulton, Cedrick; Durando, Robert
ce: Baroni, Bl, Dunne, Joseph P’; Zipf, Peter, Samson, David; ‘Rechler, Soot’; Buchbinder,
Darrell
Subject: RE: Fort Lee eastbound access to GWE.
Received
From: Foye, Patrick
Sent: Friday, September 13, 2013 7:44 AM
To: Fulton, Cedrick; Durando, Robert
Ce: Baroni, Bill; Dunne, Joseph P.; Koumoutsos, Louis; Zipf, Peter; Samson, David; ‘Rechler, Scott’; Buchbinder, Darrell
Subject: Fort Lee eastbound access to GWE
Importance: High
After reading last night’s media pendings, | made inquiries and received calls on this matter which is very troubling. Here
is what | learned: reversing over 25 years of PA GWB operations, the three lanes in Fort Lee eastbound to the GWE were
reduced to one lane on Monday of this week without notifying Fort Lee, the commuting public we serve, the ED or
Media, A decision ofthis magnitude should be made only ater careful deliberation and upon sign off by the EO. Reports
are that Fort Lee has experienced severe traffic delays engulfing the entire Fort Lee area since Monday. 1am appalled by
the lack of process, failure to inform our customers and Fort Lee and most ofall by the dangers created to the public
interest, so ! am reversing this decision now effective as soon as TBT and PAPD tell me its safe to do so today.
|/am making this decision for the following reasons:
1. This hasty ari ill-advised decision has resulted in delays to emergency vehicles. | pray that no life has been lost
or trip of a hospital- or hospice-bound patient delayed,
2. This hasty and ill-advised decision has undoubtedly had an adverse effect on economic activity in both states,
‘That is contrary to the directive we have from our Governars to do everything possible to create jobs in both
States.
3, Iwill not allow this hasty and ill-advised decision to delay the travels of those observing Yom Kippur tonight or
the holidays to follow.
4. I believe this hasty and il-advised decision viotates Federal Law and the laws of both States.
Jo be clear, l will get to the bottom of this abusive decision which violates everything this agency stands for; | intend to
learn how PA process was wrongfully subverted and the public interest damaged to say nothing of the credibility ofthis
agency.
Finally; 'am open to considering changes to each of our facilities if there is 2 case to be made that change will benefit
the public interest. In the case ofthe Fort Lee eastbound access lanes, approval ofthis action will require:
1. Written sign off by TBT, Traffic Engineering and PAPD. That sign off was not sought or obtained here.
2. Prior discussion with the local government and a communication plan and plenty of advance notice to the
‘commuting public, That did not occur here.
3. Consideration of the effects on emergency vehicles and sign off by PAPD. That did not occur here.
4. Consideration of the financial impact on the PA in terms of O/T. That too did not occur here,
Cedric and Bob—please let this group know when access to three lanes in Fort Lee can be restored as soon as possible
today. This is a matter of public safety and time is of the essence.
- 1
: PA. BB 000024Pat
PA--BB -000025Durando, Robert
Friday, September 13, 2013 8:04 AM
Foye, Patrick; Fulton, Cedrick
Baroni, Bill; Dunne, Joseph P.; Koumoutsos, Louis; Zip, Peter; Samson, David;
'SRechler@RXRRealty.com’; Buchbinder, Darrell
Re: Fort Lee eastbound access to GWB
We have restored the 3 toll anes to Ft Lee.
From: Foye, Patrick
Sent: Friday, September 13, 2013 07:44 AM
To: Fulton, Cedrick; Durando, Robert
Ce: Baroni, Bil; Dunne, Joseph P.; Koumioutsos, Louis; Zipf, Peter; Samson, David; ‘Rechler, Scott’
} Buchbinder, Darrell
“Subject: Fort Lee eastbound access to GWB
‘After reading last night’s media pendings, | made inquiries and received calls on this matter which is very troubling. Here
is what | learned: reversing over 25 years of PA GWB operations, the three lanes in Fort Lee eastbound to the GWB were
reduced to one lane on Monday of this week without notifying Fort Lee, the commuting public we serve, the ED or
Media. A decision of this magnitude should be made only after careful deliberation and upon sign off by the ED. Reports
are that Fort Lee has experienced severe traffic delays engulfing the entire Fort Lee area since Monday. | am appalled by
the lack of process, failure to inform our custamers and Fort Lee and most of all by the dangers created to the public
interest, so | am reversing this decision now effective as soon as TBT and PAPD tell me it is safe to do so today.
am making this decision for the following reasons:
1. This hasty and iltadvised decision has resulted in delays to emergency vehicles. | pray that no life has been lost.
or trip ofa hospital or hospice-bound patient delayed.
2, This hasty and iltadvised decision has undoubtedly had an adverse effect on economic activity in both states.
That is contrary to the directive we have from our Governors to do everything possible to create jobs in both
States.
3. 1 will not allow this hasty and ill-advised decision to delay the travels of those observing Yom Kippur tonight or
the holidays to follow.
44. believe this hasty and illadvised decision violates Federal Law and the laws of both States.
To be clear, | will get to the bottom of this abusive decision which violates everything this agency stands for; | intend to
earn how PA process was wrongfully subverted and the public interest damaged to say nothing of the credibility of this,
agency.
Finally, lam open to considering changes to each of our facilities if there isa case to be made that change will benefit
the public interest. In the case of the Fort Lee eastbound access lanes, approval ofthis action will require:
1. Written sign off by TBT, Traffic Engineering and PAPD. That sign off was not sought or obtained here.
2. Prior discussion with the local government and a communication plan and plenty of advance notice to the
commuting public. That did not occur here,
3. Consideration of the effects on emergency vehicles and sign off by PAPD. That did not occur here.
Consideration of the financial impact on the PA in terms of O/T. That too did not occur here.
Cedric and Bob—please let this group know when access to three lanes in Fort Lee can be restored as soon as possible
today. This is a matter of public safety and time is of the essence.
1
PA- BB - 000026Pat
PA-BB -o000z7‘Samson, David [dsamson@wolftsamson.com]
Friday, September 13, 2013 7:56 AM
Baroni, Bill
Re: Fort Lee eastbound access to GWB
(On Sep 13, 2013, at 7:51 AM, "Baroni, Bill > wrote
General, can | call you on this now?
Sent from my iPhone
Begin forwarded message:
From: "Foye, Patrick" >
Date: September 13, 2013, 744:29 AM EDT
To: "Futon, Cedrick’ >, "Durando, Rober”
>
Ge: "Baroni, Bil” >, “Dunne, Joseph P.
>, "Koumoutsos, Louis
, “Zit, Peter
>, “Samson, David"
>, "Rechler, Scot”
>, "Buchbinder, Darel"
>
Subject Fort Lee eastbound access to GWB.
‘After reading last night's media pendings, | made inquiries and received calls on this matter which is very troubling. Here
is what | learned: reversing over 25 years of PA GWB operations, the three lanes in Fort Lee eastbound to the GWB were
reduced to one lane on Monday of this week without nolifying Fort Lee, the commuting public we serve, the ED or Media.
‘A decision of this magnitude should be made only after careful deliberation and upon sign off by the ED. Reports are that
Fort Lee has experienced severe traffic delays engulfing the entire Fort Lee area since Monday. | ar appalled by the lack
of process, failure to inform our customers and Fort Lee and most of all by the dangers created to the public interest, so !
‘am reversing this decision now effective as soon as TBT and PAPO tell me itis safe to do so today.
|lam making this decision for the following reasons:
4. This hasty and iladvised decision has resulted in delays to emergency vehicles. | pray that no le has been lost or
trip of a hospital- or hospice-bound patient delayed.
2. This hasty and illadvised decision has undoubtedly had an adverse effect on economic activity in both states. That
is contrary to the directive we have from our Governors to do everything possible to create jobs in both States.
3. Iwill not allow this hasty and ilkadvised decision to delay the travels of those observing Yom Kippur tonight or the
holidays to follow.
4. _ I believe this hasty and ilkadvised decision violates Federal Law and the laws of both States.
“Tobe cer, | wil get othe botlom ofthis abusive daclgn which vclates eventhing this agency stands for, | intend to
iar tow PA process was wongily subverted sng mgybtcnterestdomages to say nohing oe cree of is
agency
inally, | am open to considering changes to each of our facilities if there is a case to be made that change will benefit the
public interest. In the case of the Fort Lee eastbound access lanes, approval ofthis action will require:
a
PA- BB - 000028,4. Written sign off by TBT, Trafic Engineering and PAPD. That signoff was not sought or obtained here
_2. Prior discussion with the local government and a communication plan and plenty of advance notice to the
muting public. That did not occur here,
3. Consideration of the effects on emergency vehicles and sign off by PAPD. That did not occur here.
4, Consideration of the financial impact on the PA in terms of O/T. Thal too did net occur here.
Cedric and Bob—please let this group know when access to three lanes in Fort Lee can be restored as soon as possible
‘today. This is a matter of public Safety and time is of the essence,
Pat
NOTICE: THIS E-MAIL AND ANY ATTACHMENTS CONTAIN INFORMATION FROM THE PORT
AUTHORITY OF NEW YORK AND NEW JERSEY AND AFFILIATES. IF YOU BELIEVE YOU HAVE
RECEIVED THIS E-MAIL IN ERROR, PLEASE NOTIFY THE SENDER IMMEDIATELY,
PERMANENTLY DELETE THIS E-MAIL (ALONG WITH ANY ATTACHMENTS), AND DESTROY ANY
PRINTOUTS.
Please Note: The information contained in this email message is a PRIVATE communication that may contain confidential
attorney-client information. If you are not the intended recipient, do not read, copy or use itor disclose it to others. If you
have received this message in error, please notify the sender immediately by replying to this message and then delete it
from your system.
hank you.
IRS CIRCULAR 230 DISCLOSURE: To ensure compliance with requirements imposed by the IRS, we inform you that any
USS. federal tax advice contained in this document {including any attachments) is not intended or written to be used, and
‘cannot be used by the recipient and any other taxpayer, for the purpose of (i) avoiding penalties under the Internal
‘promoting, marketing or recommending to another party any transaction or matter addressed herein.
PA-BB 000028Fulton, Cedrick
Friday, September 13, 2013 7.46 AM
Foye, Patrick; Durando, Robert
Baroni, Bll, Dunne, Joseph P.; Koumoutsos, Louis; Zipt, Peter, Samson, David; ‘Rechler,
Scott’; Buchbinder, Darrell
Re: Fort Lee eastbound access to GWB.
Understood.
Sent from my BlackBerry 10 smartphone on the Verizon Wireless 4G LTE network.
From: Foye, Patrick
Sent: Friday, September 13, 2013 7:44 AM
To: Fulton, Cedrick; Durando, Robert
Ce: Baroni, Bill; Dunne, Joseph P.; Koumoutsos, Louis; Zipf, Peter; Samson, David; ‘Rechler, Scott’; Buchbinder, Darrell
Subject: Fort Lee eastbound access to GWB
After reading last night's media pendings, | mace inquiries and received calls on this matter which is very troubling. Here
is what learned: reversing over 25 years of PA GW8 operations, the three lanes in Fort Lee eastbound to the GWS were
reduced to one lane on Monday of this week without notifying Fort Lee, the commuting public we serve, the ED or
Media. A decision of this magnitude should be made only after careful deliberation and upon sign offby the ED. Reports.
are that Fort Lee has experienced severe traffic delays engulfing the entire Fort Lee area since Monday. lam appalled by
the lack of process, failure to inform our customers and Fort Lee and most of all by the dangers created to the public
= interest, so | am reversing this decision now effective as soon as TBT and PAPD tell me itis safe to do so today.
11am making this decision for the following reasons:
1. This hasty and ilkadvised decision has resulted in delays to emergency vehicles. | pray that no life has been lost
of trip of a hospital- or hospice-bound patient delayed.
2. This hasty and ilkadvised decision has undoubtedly had an adverse effect on economic activity in both states
‘That is contrary tothe directive we have from our Governors to do everything possible to create jobs in both
states.
3. Iwill not allow this hasty and iltadvised decision to delay the travels of those observing Yon
the holidays to follow.
4, believe this hasty and ilkadvised decision violates Federal Law and the laws of both States.
pur tonight or
To be clear, | willget to the bottom of this abusive decision which violates everything this agency stands for; | intend to
learn how PA process was wrongfully subverted and the public interest damaged to say nothing of the credibility of this
agency.
Finally, | am open to considering changes to each of our facilities if there is case to be made that change will benefit
the public interest. Inthe case of the Fort Lee eastbound access lanes, approval of this action will require:
1. Written sign off by TBT, Traffic Engineering and PAPD. That sign off was not sought or obtained here.
2. Prior discussion with the local government and a communication plan and plenty of advance notice to the
commuting public. That did not occur here,
3. Consideretion of the effects on emergency vehicles and sign off by PAPD. That did not occur here.
4, Consideration of the financial impact on the PA in terms of O/T. That too did not occur here.
Cedric and Bob—please let this group know when access to three lanes in Fort Lee can be restored as soon as possible
today. This is @ matter of public safety and time is of the essence,
a
PA-BB 000030