Você está na página 1de 84

Evaluation Report 4/2012

Evaluation of the Sustainable Neighbourhood Programme


in Mavoko Municipality, Kenya

Evaluation of the
Sustainable Neighbourhood
Programme in Mavoko
Municipality, Kenya

HS:HS/003/14E

UNITED NATIONS HUMAN SETTLEMENTS PROGRAMME


P. O. Box 30030, 00100 Nairobi GPO KENYA
Tel: +254-020-7623120 (Central Office)
Fax: +254-20-76234266/7
infohabitat@unhabitat.org
WWW.unhabitat.org/publications

www.unhabitat.org FEBRUARY 2012


Evaluation Report 4/2012

Evaluation of the
Sustainable Neighbourhood
Programme in Mavoko
Municipality, Kenya

FEBRUARY 2012
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
ii MUNICIPALITY, KENYA

Evaluation Report 4/2012


Evaluation of the Sustainable Neighbourhood Programme in Mavoko
Municipality, Kenya
This report is available from http://www.unhabitat.org/evaluations

First published in Nairobi in December 2012 by UN-Habitat.


Copyright © United Nations Human Settlements Programme 2012

Produced by the Evaluation Unit


United Nations Human Settlements Programme (UN-Habitat)
P. O. Box 30030, 00100 Nairobi GPO KENYA
Tel: 254-020-7623120 (Central Office)
www.unhabitat.org

HS:HS/003/14E

Disclaimer
The designations employed and the presentation of the material in this publication do not imply
the expression of any opinion whatsoever on the part of the Secretariat of the United Nations con-
cerning the legal status of any country, territory, city or area or of its authorities, or concerning the
delimitation of its frontiers of boundaries.

Views expressed in this publication do not necessarily reflect those of the United Nations Human
Settlements Programme, the United Nations, or its Member States.

Excerpts may be reproduced without authorization, on condition that the source is indicated.

Front Cover: Photographs of Mavoko Municipality © UN-Habitat

Acknowledgements
Author: Kathleen Webb
Editor: Edward Miller
Design & Layout: Phyllis Githua
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
iii

Table of Contents

ACRONYMS AND ABBREVIATIONS v

EXECUTIVE SUMMARY vi
i Introduction vi
ii Methodology vii
iii Key Findings and Assessment of the Programme vii
iv Conclusions xiii
v Lessons Learned xiv
vi Recommendations xv

1. INTRODUCTION 1

1.1 Background 1
1.2 Objective, Purpose, and Scope of the Evaluation 3
1.3 Outline of the Report 3

2. OVERVIEW OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME 4


2.1. Overview of The Sustainable Neighbourhood Programme for the Period
August 2002 to April 2011 4
2.2. Overview of The Sustainable Neighbourhood Programme for the Period
April 2011 to January 2012 9

3. EVALUATION PROFILE AND METHODOLOGY 10

4. EVALUATION FINDINGS AND ASSESSMENT 11


4.1 Achievements 11
4.2 Assessment of Relevance 15
4.3 Assessment of Effectiveness 17
4.4 Assessment of Efficiency 19
4.5 Assessment of Cross-Cutting Issues 22

5. CONCLUSIONS, lessons learned and RECOMMENDATIONS 26


5.1 Conclusions 26
5.2 Lessons Learned 28
5.3 Recommendations 29

5. ANNEXes
Annex I: Terms of Reference 31
Annex II: Bibliography 38
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
iv MUNICIPALITY, KENYA

Annex III: List Of People Interviewed 45


Annex IV: Detailed methodology and revised evaluation work plan 48
Annex V: Evaluation Questionnaires 53
Annex VI: Sustainable Neighbourhood Programme Nairobi Plot Project
Budget Implementation Phase) 60
Annex VII: Sustainable Neighbourhood Programme—Nairobi Financial
Report as at 31 December 2008 62
Annex VIII: Sustainable Neighbourhood Programme Timeline 64
Annex IX: Implementation Schedule (No-Cost Extension) 65

LIST OF FIGURES AND TABLES

Figure 1.1: UN-Habitat Proposed Subdivision of L.R. No. 27664 (28/06/2010) 2


Table 2.1: Activity Status, December 2004 7
Table 4.1: Summary of Findings of the Evaluator with Respect to the
Achievement of the Four Immediate Outcome Objectives 13
Table 4.2: Planning Requirements for Housing 15
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
v

ACRONYMS AND ABBREVIATIONS

CBO Community-based organization


CTA Chief Technical Adviser
EUR Euro
GROOTS Grassroots Organizations Operating Together in Sisterhood
KENSUP Kenya Slum Upgrading Programme
KES Kenya shilling
KEWLAT Kenya Women Land Access Trust
MOU Memorandum of Understanding
NGO Non-Governmental Organization
ROAAS Regional Office for Africa and the Arab States
RTCD Regional Technical Cooperation Division
SNP Sustainable Neighbourhood Programme
TOR Terms of Reference
UN United Nations
UN-Habitat United Nations Human Settlements Programme
USD United States Dollar
YEP Youth Empowerment Programme
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
vi MUNICIPALITY, KENYA

EXECUTIVE SUMMARY

I. INTRODUCTION Kenya, would lead project implementation


with funding provided by the Government
The Sustainable Neighbourhood Programme
of Finland (EUR 750,000) and the United
(SNP) was designed as a 27-month,
Nations Human Settlements Programme
experimental, community-driven slum
(UN-Habitat) in kind (USD 160,000).
resettlement project, expected to address
1

the housing crisis in Kenya by focusing on After an impasse, a new development


improving the lives and livelihoods of people process for the SNP was initiated in April
living in 26 slum settlements in Mavoko, 2011, to be implemented in collaboration
Kenya.2 with the Government of Kenya and
other stakeholders. At the time of
A 55-acre3 piece of land in Mavoko
the evaluation, the new development
Municipality4 was provided for the project
process had started (Phase 1) and was
by the Government of Kenya through a
in the process of determining the
debt swap with the Government of Finland,
feasibility and possible redesign of the
and the SNP was then to be implemented
project.
from August 2002 to April 2005. The Kenya
Slum Upgrading Programme (KENSUP), This evaluation was a response to a
a secretariat body within the Ministry of request by the Government of Finland for
Housing mandated to upgrade slums in a final evaluation of the achievements,
experiences, challenges, and lessons
1 The terms ‘resettlement’ and ‘relocation’ are learned. The end-of-project evaluation of
used interchangeably in this document and have
a similar meaning: slum dwellers moving to an the programme was carried out between
improved location. 1 December 2011 and 31 January 2012 by
2 The 26 slum settlements included 25 Mavoko an independent consultant, Ms. Kathleen
slum settlements and one additional site that
housed those working in Athi River but living in Webb. The Regional Office of Africa and
Kibera slums. See Situation Analysis and Evalu- the Arab States (Kenya Unit) managed the
ation Report population estimates (UN-Habitat
Progress Report, 2004, page 2), which estimated evaluation, with technical support from
the Mavoko slum population at 26,000 persons the Evaluation Unit. The purpose of the
living in 25 slum settlements. There was no popu-
lation estimate for the Kibera slum settlement.
evaluation was to assess the extent to which
3 55 acres = 22.21 hectares the development objective and immediate
4 The Government of Kenya allocated 55 acres of outcome objectives of the SNP were
land for the UN-Habitat SNP project through a achieved between 2002 and 2011.
debt swap with the Government of Finland. The
land is registered as L.R. 27664, with the title
granted on 22 June 2009. The site is about 30 km
from Nairobi, the capital of Kenya.
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
vii

II. METHODOLOGY to the evaluation to ensure the study was


professional, objective, and impartial.
The evaluation covered the period from
inception in 2003 up to April 2011. The There were no significant limitations, other
period thereafter up to January 2012, the than the challenge of getting some infor-
time of the evaluation, was not evaluated. mation. Many key stakeholders had moved
However, information on progress during away and could only be reached by email
that period was included to give an overview or phone, and conducting the evaluation
of the project and follow-up by UN-Habitat. during the December holidays meant many
people were away.
As this was the first evaluation of the SNP
and several years had passed since its
inception, the evaluation methodology used III. KEY FINDINGS AND
by the consultant evaluator relied mainly on ASSESSMENT OF THE
documentation from multiple sources and PROGRAMME
interviews with the stakeholders involved in This section presents an overview of the
the programme. This meant the study and achievements of the SNP and an assess-
analysis of 174 reports, minutes of meetings, ment of relevance, effectiveness, efficiency,
and emails provided by UN-Habitat, SNP, the impact, and sustainability, as well as cross-
Kenya Women Land Access Trust, the Youth cutting issues.
Empowerment Project, and others.

Seventy-five persons were interviewed from


A. KEY FINDINGS
UN-Habitat, the Government of Kenya, Achievements
non-governmental organizations (NGOs), The evaluator finds that the SNP made an
and 11 slum cooperatives. The interviews overall contribution to the development
were conducted mainly as focus group objective set for the project as it delivered
discussions and key informant interviews, activities and outputs, which contributed to
in order to generate discussion and also that objective: “to strengthen the role and
understand the project’s history. The capacity of the informal and community
interview questionnaires were designed sector in the provision of housing,
in advance and structured in line with the services and infrastructure.”5 The project
evaluation criteria (relevance, efficiency, strengthened community capacity through
effectiveness, impact and sustainability, the sensitization, mobilization, and training
and the cross-cutting issues of gender and of men, women, and youth living in 26
human rights). They were then revised Mavoko slum settlements who were then
in collaboration with UN-Habitat, which able to better define their role in creating
facilitated the selection of interviewees healthy, sustainable neighbourhoods and
and administering of questionnaires. The also implement steps to improve their
standards of the UN-Habitat Monitoring own lives, by working together in 30
and Evaluation Guide and the United
Nations Evaluation Group were applied 5 SNP project foundation document, page 12.
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
viii MUNICIPALITY, KENYA

community-based organizations (CBOs) and • Formation of 30 community-based or-


six cooperatives. ganizations as a result of extensive sen-
sitization, social mapping training, and
An analysis of the achievements of the
retraining of slum residents.
project against the four immediate outcome
objectives set for the project find that the • Mobilization and formation of six Ma-
outcome objectives were partially achieved, voko cooperatives, with an average
as the project was able to deliver some of membership of 500 persons per group
the planned outputs and carry out some and a savings range of KES 3–5 million,
of the planned activities. The project was by the time of the evaluation.
not able to deliver all planned outputs • Extensive networking and research done
contributing to the achievement of the four with the participation and commitment
immediate outcome objectives due to a late of more than 50 institutions, organiza-
start, the complexity of the project design, tions, and companies in the fields of ap-
and management challenges faced during propriate technology, housing, commu-
the life of the project. nity development, and credit granting,
which can be applied to future project
Despite these challenges, the evaluator finds
needs.
high standard and in-depth completion of
many foundational activities of the project Implementation Arrangements
and the establishment of strong linkages The roles and contributions of KENSUP and
with stakeholders in both the public and UN-Habitat were not realized from the year
private sectors. These made an overall 2005 due to differences between the two
contribution to the development objective bodies related to the nature, location, and
of the project. Of important mention target population of the SNP and the proce-
are the following foundational outputs dures for carrying it out. These differences
and activities which contributed to the were not resolved despite efforts by both
development objective: parties, and the Executive Committee soon
• Geographic and hydro-geological sur- ceased to function.
veys done for part of the land. KENSUP continued to develop mixed-in-
• Situation analysis, community action come dwellings on their part of the SNP
plans, and social mapping carried out in land, adjacent to the UN-Habitat SNP land,
26 slum settlements of Mavoko. in an effort to meet Kenya country demands
for housing. UN-Habitat started two new
• The title for the land was released6.
projects on the UN-Habitat SNP land using
• SNP office equipped and studies separate funding:
archived.
A women’s empowerment project start-
6 Grant Number I.R 117250 allocated L.R. 27664 to
the Permanent Secretary to the Treasury of Kenya ed with Kenya Women Land Access Trust
as trustee of the UN-Habitat Housing Project, 22.1 (KEWLAT), whereby five cooperatives
hectares of land in Mavoko Municipality in June
2009. (drawn from slum settlements outside Ma-
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
ix

voko) received cooperative training and four project is also relevant to the United Nations
low-cost model houses were constructed Millennium Declaration (2000), with the
A youth centre, constructed as part of the goal of significantly improving the lives of
Youth Empowerment Project (YEP), which at least 100 million slum dwellers globally
served as a central training site for more by the year 2020 using domestic resources
than 500 youth on mainly low-cost con- and new technologies. UN-Habitat states
struction technology. in its 2003 report The Challenge of Slums:
Global Report on Human Settlements
The lack of collaboration between KENSUP
that “the accepted best practice for
and UN-Habitat was a major factor in the
housing interventions in developing
project not meeting all of its four immedi-
countries is now participatory slum
ate outcome objectives7. Project implemen-
improvement...the best examples are
tation was further constrained by a compli-
holistic approaches to neighbourhood
cated project design, which was unclear as
improvement, taking into account
to how the concepts would be factored into
health, education, housing, livelihood
the implementation of activities.
and gender.”8 The agency’s development
objective has the potential to address the
B. ASSESSMENT
housing needs of highly impoverished
Relevance communities in Kenya. The evaluator finds
The SNP is in line with UN-Habitat global that the SNP project goal (development
priorities and specifically the Addis Ababa objective) and four immediate outcome
Declaration on Human Settlements in objectives were therefore consistent with
the New Millennium, which stresses the UN-Habitat global priorities and the donor’s
need to enhance the capacity of the policies.
private sector to develop housing, increase
There were gaps in the design which limited
employment opportunities, promote the
the degree to which the project could be
mobilization of domestic resources for
implemented. The various concepts in the
shelter development, and promote the use
SNP were never developed to show how they
of new technologies for the development
would be applied in the model. The design
of low-cost housing and infrastructure. The
is also not in line with the National Housing
Policy for Kenya (currently under review),
7 The SNP had four outcome objectives: 1) enhance
the role and capacities of the communities in the which specifies building standards for slums
provision of housing, services, and infrastruc- but does not address the use of innovative
ture; 2) strengthen the capacity of small-scale
contractors and building material producers in housing materials.9 Another tenet of the
shelter and infrastructure provision; 3) enhance definition of a sustainable neighbourhood
the capacity of public agencies to act as enabling
authorities for community-led housing and specified in the proposal is the integration
infrastructure delivery; and 4) prepare and imple-
ment a pilot project in sustainable neighbourhood
8 UN-Habitat (2003), The Challenge of Slums:
Global Report on Human Settlements 2003,
development. For the purpose of this evaluation,
Earthscan, London, UK.
outcomes are defined as ‘outcome objectives’
reflecting the ‘immediate objectives’ formulated 9 Republic of Kenya (July 2004), National Housing
in the SNP foundation project document. Policy for Kenya,Sessional Paper No. 3, July 2004.
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
x MUNICIPALITY, KENYA

of sustainable livelihoods within the SNP. far within the local and national domain to
To realize this goal, the SNP should have attract as many interested parties as possible
linked to other relevant ministries dealing who are experienced in the areas of credit,
with livelihoods. The sustainable livelihood housing, and training. The SNP team brought
model in the proposal should have been in professionals from many sectors, such as
expanded into specific activities which could health and education sector personnel from
have been factored into the project. the Mavoko Municipal Council, who were
able to provide community education on
Effectiveness many issues relevant to a better lifestyle.
The evaluator finds that the SNP made an
overall contribution to the development Efficiency and Budget
objective set for the project, “to strengthen The project faced many challenges with
the role and capacity of the informal and respect to efficiency, but on the whole,
community sector in the provision of despite turnover of the Chief Technical
housing, services and infrastructure” as Advisers (CTAs) and the absence of a Project
it delivered activities and outputs which Manager for an extended period, the day-
contributed to four outcome objectives.10 to-day management of the SNP was good.
The project strengthened community
The Project Manager and three fieldworkers
capacity through the sensitization,
worked closely together, giving each other
mobilization, and training of more than
regular feedback, liaising closely with
3,000 men, women, and youth living in 26
communities, and making great effort to
Mavoko slum settlements, who were then
document plans and events. There were
able to define their role better in creating
frequent meetings among the leaders,
healthy, sustainable neighbourhoods and
project management, and communities,
also implement steps to improve their own
in which issues and challenges were
lives, by working together in 30 community-
brought forth. The three field officers and
based organizations and six cooperatives
the Project Manager were available to
(derived from the CBOs). People developed
address the emerging challenges of the
a close and trusting relationship with
community-based organisations when they
the project, which also promoted female
were formed, as well as the six cooperatives
participation, resulting in 25 per cent female
as they developed from the community-
representation in the community-based
based organizations. The reports produced
organisations and cooperatives. In addition
by these activities can support future
to joining and participating, people acquired
programming.
skills in leadership and group dynamics and
began to save. The SNP fieldwork that was carried out
in the communities by the SNP staff was
The identification of stakeholders in both the
professional and in-depth and many
public and private sector was also effective,
community action plans, social mapping,
as the project team searched and reached
and other studies were completed using
10 SNP project foundation document, page 12.
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
xi

project funds. The Ministry of Cooperative interaction (including problem solving)


Development training successfully placed with the slum communities of Mavoko.
the communities into six cooperatives, with As a result, shortages in funding
significant savings. for transport, communication, and
stationery caused frequent delays in
The budget, when compared with the
activity implementation.
financial report of 31 December 2008,
showed no irregularities and was subjected • The project funded several exchange
to an audit. Some examples of prioritized/ trips (e.g., to the Third Session of the
not prioritized activities and outputs in the World Urban Forum held in Vancouver,
budget include: Canada, in June 2006), local retreats in
Kenya (Mombasa, Kitale, Nakuru), and
• Sensitization and social mobilization a house design competition,12 which
among the communities was not well gave exposure to those slum dwellers
budgeted for and had to be covered who were in leadership positions in the
under the training budget, which at community-based organizations and six
only USD 37,000 was too low to meet cooperatives. The annual World Habitat
the needs.11 There was no budget for Day celebrations held in Athi River,
the process of sensitizing the public and Kenya, gave many slum dwellers the
private sectors to the extent necessary. opportunity to meet and discuss progress
There was little or no funding for in savings mobilization.13 The events
major components of the project such were all planned for and provided some
as architect studies, the savings and value for money in terms of awareness
credit programme, construction of the raising and training.
technology workshop, materials and
• Cluster groups formed by the Executive
supplies for the construction training,
Committee of the SNP brought together
etc.
many professionals from the public and
• Monitoring, which was to be carried private sectors who provided expertise
out by field staff and others, did not on housing design, training, and
receive enough funding. The project credit and savings mobilization. These
provided stipends, not salaries, to the contributions were not acted upon, as
three field staff, yet they were key to the the project activities lapsed by 2005.
substantive field work and community
The collapse of activities in late 2004 and
the intention of UN-Habitat between 2005
11 UN-Habitat (2003), ‘Agreement and Budget’
(Government of Finland and UN-Habitat), Nairobi:
Each community meeting (50 persons, inclusive
12 The competition ‘The Sustainable City’ was a
student design competition in 2005 for Kenyan
of trainers) cost an average of USD 500 per day
and Finnish university students. There were no
(transport, stationery, etc.). On average, commu-
entries from Kenya. The designs were expected
nities were visited at least five times to mobilize
to present innovative sustainable solutions in
people and train them in community-based
terms of affordability, ecology, and social/cultural
organization (and later cooperative) develop-
integration.
ment. Training costs for manual development and
production were also not included in the budget. 13 SNP Monthly Report October 2005, page 2.
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
xii MUNICIPALITY, KENYA

and 2007 to utilize the land resulted in The project also impacted positively on the
memorandums of understanding with private sector of Mavoko, linking industry
Kenya Women Land Access Trust regarding and the public sector together for the mutual
empowerment of women and the trust’s goal of sharing resources (financial and
use of land at the SNP site. A UN-Habitat physical) for the sake of the slum dwellers.
youth empowerment project entitled ‘YEP’ If the project had been sustained from 2002
was implemented, and a centre was erected to 2011, it is likely that the pledges of these
on the SNP land. The informal allocation of groups would have provided significant
land to YEP, KEWLAT, and the six Mavoko support. Nonetheless, the interactions from
cooperatives did not contribute to the 2004 indicate that private industries are
expected results of the SNP, as both the interested in participating in a sustainable
YEP and KEWLAT projects differed greatly neighbourhood. The training conducted by
from the SNP in many areas, such as focus, the Ministry of Cooperative Development
beneficiaries, mode of implementation, enabled the cooperatives to save extensively,
and training content. There was also no placing them in an advantageous position
rationale to allocate land to the six Mavoko for accessing credit from credit-granting
cooperatives. institutions and purchasing housing units in
the future.
Impact and Sustainability
The anticipated positive impact of SNP, with The Way Forward for the Sustainable
sustained change, was limited, as the project Neighbourhood Programme
did not deliver all expected outputs planned After the closure of the SNP project in 2010,
for the four immediate outcome objectives. there was new development when, in April
However, the close interaction of UN-Habitat 2011, the UN-Habitat Executive Director
and the SNP field staff impacted positively, initiated a new development process for
as it benefited the Mavoko community the SNP to be implemented in collaboration
at large, empowering community-based with the Government of Kenya and other
organizations and cooperatives. stakeholders through the 22-member
As a result of the SNP, people now have Mavoko Development Advisory Committee,
more hope and some have changed their which was formed in September 2011.
lifestyles, engaging in preventive health The revived development process follows
practices for healthier living. In some cases, the same outcome objectives for the SNP
people in the Mavoko slum communities as set in 2002, but with the necessary
also developed better environmental changes and improvements to reflect
practices in their existing slum settlements current realistic, practical requirements; a
due to interaction with the SNP. These project brief is currently under discussion.
practices have lasted over time, and some The evaluator finds that the new start of
groups have raised funds to expand them the project is a positive step which can
further, creating safe environments for their help contribute to the process of creating
families. low-cost housing if it addresses the design
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
XIII

gaps and misinformation of the early years. Opportunities for Research


At the time of the evaluation, the new Under-explored
development process had started Phase 1, Research is still needed on experimental
the financial and technical appraisal of the low-cost housing development with regard
project which will determine the feasibility to slum resettlement/relocation. There
of the project (and whether to proceed or remains a lack of clarity on the meaning
not). of ‘sustainable neighbourhoods’ and how
they will contribute to the development of
IV. CONCLUSIONS Mavoko Municipality, in which the SNP is
Complex Project Design Limiting situated. The SNP project has partly reached
its goal, but it did not succeed in fully
The lack of clarity of the project design—in
reaching its intended goal; the project was
terms of timing, roles, functions, gender,
very ambitious, and the results achieved
and activities to be completed—limited
have to be taken in the context of its
the project’s implementation and potential
experimental and innovative nature.
positive impact for the period under
evaluation. Specifically, the evaluation Capacity Building Carried Out
found the following:
Capacity building is a critical aspect of
• There were limitations in the project UN-Habitat’s role. Despite not fully achieving
design with respect to the time needed the outcome objectives set for the project,
for sensitization and implementation. the SNP gave hope to thousands in Mavoko
It was not clear if the project was who had never experienced anything but
developmental or experimental, poverty and forced relocation. Specifically,
although the budget suggests it was the evaluation found the following:
experimental, as the funds were
• The project successfully empowered
insufficient to support the expected
men, women, and youth—approximately
activities.
3,000 persons (500 per cooperative)—
• For the project to have achieved its with life skills, primary health care
outcome objectives fully and impacted knowledge, savings mobilization, and
positively in the Kenyan context, it should better community dynamics, to name a
have been better designed in terms of few.
its scope, key stakeholders, modalities
• Although local authorities participated,
for operation, and funding. The capacity
the project was not able to build the
building of the Mavoko Municipal
capacity of local authorities to any
Council and its key departments related
extent.
to social services was critical for the
project’s sustainability but was not done. • The skills relevant for participatory
research and surveys were developed
among UN staff and members of the
slum communities, who learned how to
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
XIV MUNICIPALITY, KENYA

do social mapping, situational analyses, allows the development project’s design


and community action plans. These skills to benefit from the experimental findings.
can assist in the activities planned for the Models such as the sustainable neighbour-
SNP in 2012. hood, which have worked well in developed
countries, may not work in a developing
Networking and Linkages
country such as Kenya. Similarly, Kenya is
Established
diverse in terms of ethnicity and culture—
The formation of the Executive Committee replication has to be preceded by research
in 2004 provided an opportunity for and testing. When this is not done, innova-
UN-Habitat to develop significant tive housing projects cannot succeed.
partnerships in both the public and the
private sectors. This included private Risk Management during
industries such as East African Portland Implementation
Cement, as well as many NGOs. Specifically, A well-designed project has to give the
the evaluation found the following: time, funding, and staffing necessary to
mitigate the challenges which may occur,
The project identified key players at the
in order to minimize risk in the delivery
university level who can carry out further
of planned activities and outputs and
research to understand the dynamics of
the achievement of expected outcome
slum neighbourhoods and how best to
objectives. For example, the context of
develop sustainable neighbourhoods.
Kenya at the time of the evaluation is one
The SNP’s new development process initiat- of emerging ‘election fever’ in anticipation
ed by UN-Habitat and KENSUP in April 2011 of presidential and parliamentary elections.
can build on the networking and linkages This means an increased risk of political
already made. instability, disruption, and poor governance.
In the given implementation context,
V. LESSONS LEARNED projects that are carefully designed, tested,
and subjected to feasibility studies are more
The evaluation deduced a few key lessons
likely to succeed. Meanwhile, networking
learned relating to the design of research
with various players in government and
and development projects and risk manage-
other sectors through positive agreements
ment during implementation.
is important and necessary to minimize the
Research and Development possibility of corruption.
Projects The complex arena of land allocation,
Research projects termed ‘experimental’ management, and subdivision is usually
should not be combined with development best managed by several ministries. There
projects. The research needed should be are many gaps in the ability of KENSUP to
carried out first in a separate and/or parallel manage slum upgrading—the Ministry of
project, and then the lessons learned can be Lands also has an important role. Several
applied to the development projects. This ministries had to play a strong role in the
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
XV

management of the SNP in order to tackle in this area, inclusive of their contact
some of the challenges this project faced. addresses and proposed roles, with a
Working with several ministries and a wide view to involving them where possible
range of key players will make it possible and feasible. The gaps in the project’s
to implement the project with minimal risks. conceptual design and management
structure should be addressed in the
VI. RECOMMENDATIONS next phase of the SNP project through
redesign. These include clarification and
The new start of the project in April 2011
agreement on central concepts (e.g.,
is a positive step which can help contribute
sustainable neighbourhoods), how the
to the process of creating low-cost
project will integrate livelihoods into
housing if it addresses the design gaps and
housing development, and how new
misinformation of the early years.
concepts for housing for the disabled
1. It is recommended that the studies and and youth will be factored in. The
reports archived in the SNP offices project design should also consider
be organized and synthesized by infrastructure and services for labour-
UN-Habitat or an NGO specializing in saving devices which can support female
this area, so as to garner information workloads and home management for
and findings which can benefit the next the disabled.
phases of the SNP.
4. The anomalies in the Housing Act of
2. The SNP offices were facilitated through Kenya regulations with respect to low-
funding and the donation of facilities cost, innovative housing are under
by the Mavoko Municipal Council. The review by the Ministry of Housing: the
offices are equipped with computers Mavoko Development Advisory Council
and furniture and should be closed should keep abreast of the changes to
down officially by UN-Habitat if they are ensure that the conceptual issues related
not to be used. This process of closure to the SDP are incorporated into the
or handover will clarify the expectations new laws.
of the council with respect to the
5. An appropriate project management
sharing of premises. On the other hand,
structure is to be created by UN-Habitat
the continued use of the premises, for
and the main partners in a Phase 2 of
example as a library or training centre,
the programme, building on the lessons
could save resources, which would be
learned of the project. Identification of
needed for an SNP office in the next
beneficiaries and credit modalities are
phase.
required, but it is recommended that the
3. A directory of all the stakeholders who project form subcommittees to address
collaborated with the project during the needs of the youth, female-headed
this time period should be prepared households, the disabled, and those liv-
by UN-Habitat or an NGO specializing ing with HIV/AIDS. The subcommittees
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
XVI MUNICIPALITY, KENYA

can address measures to develop and equipment and support development in-
protect vulnerable groups. terventions for specific groups.

6. It is recommended that in a Phase 2, 7. An environmental impact assessment


the project should bring in the numer- is planned, soon to be underway. This
ous stakeholders such as industries and study should rely on past studies con-
NGOs identified in the early years of the ducted under the umbrella of the SNP,
project. It should first be determined if which identified hazards specific to the
they are relevant to this phase. These relevant geographic areas in 2002 and
stakeholders could be part of a social discussed how to alleviate them.
initiative and can contribute funds and
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
1

1. INTRODUCTION

1.1 Background new technologies for the development of


low-cost housing and infrastructure. The
In September 2002, the Sustainable
project was also in line with the goal of
Neighbourhood Programme started as
the United Nations Millennium Declaration
a collaboration among the Government
(2000): “Making significant improvements
of Kenya, the Ministry of Housing
in the lives of 100 million slum dwellers
(under the auspices of the Kenya Slum
globally by the year 2020”.16 In the case
Upgrading Programme), and two partners,
of Kenya, an estimated one out of every
namely the Government of Finland and
three Kenyans lived in urban slums in
UN-Habitat.14 The SNP was expected to
1999, a figure expected to increase by 50
address the housing crisis in Kenya through
per cent by 2015. The project assumption
an experimental, community-driven slum
was that a community-driven approach in
resettlement project. Specifically, the project
a slum resettlement project would result in
focus was on improving the lives and
sustainable development.
livelihoods of an estimated 26,000 persons
living in 26 slum settlements.15 A 55 acre (22.21 hectare) piece of land
situated in Mavoko Municipality, 15 km
Kenya was considered to be an excellent
south-east of Nairobi, Kenya, was selected
location, as its capital, Nairobi, hosts the
in 2001 for the Government of Finland/
UN-Habitat Headquarters, the focal point for
UN-Habitat-funded SNP (see Figure 1.1:
the implementation of the Habitat Agenda.
UN-Habitat Proposed Sub-division L.R.
The project was in line with UN-Habitat
27664). Mavoko Municipality was found
global priorities, specifically the Addis
to be the best location for a sustainable
Ababa Declaration on Human Settlements
neighbourhood project, as the communities
in the New Millennium, which stresses the
living there suffered from an acute housing
need to enhance the capacity of the private
problem.
sector to develop housing and increase
employment opportunities, and to promote 16 The UN-Habitat Project Foundation Document,
the mobilization of domestic resources page 4, states “The United Nations Conference on
Human Settlements (Habitat II), held in Istanbul
for shelter development and the use of in June 1996, adopted the Habitat Agenda as a
global response to the urban crisis. It challenged
governments to use shelter development as a tool
14 UN-Habitat (2001), UN-Habitat Foundation Project to break the vicious circle of poverty, homeless-
Document (FS-GLO-03-S19/A), Nairobi.
ness and unemployment and called governments
15 ‘SNP Launching and PR Summaries’, 2002–2004, to support community-based, private and non-
UN-Habitat. There were 26 slum settlements to be governmental organizations, and to promote pro-
assisted. This comprised 25 Mavoko slum settle- grammes that integrate credit, finance, vocational
ments (as of 2001) and one additional site hosting training and technological transfer programmes
those working in Athi River but living in Kibera in support of small enterprises in shelter develop-
slums, making 26 slum settlements in total. ment.”
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
2 MUNICIPALITY, KENYA

Figure 1.1: Un-Habitat Proposed Subdivision Of L.r. No. 27664 (28/06/2010)


EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
3

This was largely due to an influx of job The purpose of the evaluation was to
seekers trying their luck in the various assess the extent to which the development
emerging industries along Mombasa Road objective and four immediate outcome
(many within Mavoko Municipality), as well objectives of the SNP were achieved during
as an acute shortage of low-cost housing in the period between August 2002 and April
Nairobi which forced people to live farther 2011.
away. By 2002, Mavoko Municipality
The evaluation report findings are intended
had an estimated 26,000 people living in
to be used by the Government of Finland
squalor, with all the urban challenges and
and UN-Habitat.
struggles faced by slum dwellers, including
mass eviction. Mavoko Municipality was
therefore identified by the Government of 1.3 Outline of the Report
Kenya in the KENSUP strategy (2005–2020) The evaluation is presented in seven
as a major area for slum resettlement chapters, with the content and format in
and upgrading, in collaboration with its line with the UN-Habitat standard format
partners.17 Finally, the SNP was expected for evaluation reports. Chapter 1 is the
to contribute to a new paradigm for slum introduction and presents the background
housing and infrastructure development of the SNP; the objective, purpose, and
through community participation, which scope of the evaluation; and the outline of
could then be replicated elsewhere in the the report. Chapter 2 gives an overview of
region. the programme from August 2002 to April
2011, as well as the new development
1.2 Objective, Purpose, and period from April 2011 to January 2012.
Scope of the Evaluation Chapter 3 describes the evaluation
approach and methodology. Chapter 4
In light of the intervention background, the
presents the main evaluation findings,
context of Kenya (as a developing country
with an emphasis on the achievements
with a high level of poverty), and the SNP
and assessment of the programme based
project being at its end stage (and closed as
on the evaluation criteria of relevance,
of 2011), the Government of Finland, in its
effectiveness, efficiency, impact, and
capacity as donor, requested that an end-
sustainability, plus cross-cutting issues.
of-project evaluation be carried out (Annex
Chapter 5 presents the conclusions,
I: Terms of Reference). The programme was
lessons learned, and recommendations for
evaluated based on the evaluation criteria
the future of the programme.
of relevance, effectiveness, efficiency,
impact, and sustainability.

17 The Government of Kenya KENSUP Implementa-


tion Strategy (2004) lists the following character-
istics of Kenyan slums: inadequate shelter, unem-
ployment, delinquency, crime, unavailability of
clean water, inadequate drainage and sanitation,
lack of adequate public transport, environmental
degradation, and urban poverty.
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
4 MUNICIPALITY, KENYA

2. OVERVIEW OF THE SUSTAINABLE


NEIGHBOURHOOD PROGRAMME

2.1. OVERVIEW OF THE an end date of June 2005. Three additional


SUSTAINABLE NEIGHBOURHOOD no-cost extensions were later approved
(Annex IX: Implementation Schedule). The
PROGRAMME FOR THE PERIOD
development objective of the project was
AUGUST 2002 to April 2011
to improve the lives and livelihoods of the
In early 2002, a project entitled the slum dwellers living in specific informal
Sustainable Neighbourhood Programme was settlements in Mavoko, and one in the
approved for funding by the Government of Kibera slums, with the aim of relocating
Finland (EUR 750,000), with a contribution them.
of USD 160,000 from UN-Habitat. The
To realize the development objective,
project was expected to start in August
four immediate outcome objectives19
2002 and proceed for 27 months until 31
were outlined in the project document
March 2005. This was to include a three-
and remained unchanged at the time
month preparatory phase, a six-month
of the end-of-project evaluation.
capacity-building phase, and an eighteen-
month pilot implementation phase (Annex
Outcome Objective 1 was “to enhance
VIII: Sustainable Neighbourhood Programme
the role and capacities of the communities
Timeline).
in the provision of housing, services and
The dates were later revised in the infrastructure”. By the end of the project,
memorandum of understanding18 and work the following four training outputs were to
plan to indicate a start date of July 2003 and be delivered for Outcome Objective 1.

One hundred persons would receive training


18 The memorandum of understanding (MOU) in this
case refers to the MOU made after the tripartite in sustainable neighbourhood development
meeting of UN, Government of Finland, and Gov- as follows:
ernment of Kenya on 17 December 2004, which
was to take precedence over the Government
of Finland/UN-Habitat MOU. The revision was to 1. Earth construction techniques (i.e., mud
formalize the integration of the SNP in KENSUP. bricks, stabilized soil bricks, and com-
The evaluator was also provided with an MOU
between UN-Habitat and KEWLAT for women’s
pressed earth blocks)
empowerment and a description of activities of
the UN-Habitat YEP project; neither of these are 2. Low-cost road construction (i.e., roads,
part of the SNP, and they implemented their own bicycle lanes, and footpaths)
activities. As KEWLAT and YEP were later to oc-
cupy some acreage of the land allocated for the
SNP project, the consultant makes reference to 3. Sustainable water supply (i.e., wells,
them in the report. It remains unclear whether or
not the Government of Kenya signed the MOU, 19 For the purpose of this evaluation, ‘outcome ob-
in which case the binding document of the SNP jectives’ are defined by the immediate objectives
remains the project document. of the SNP foundation project document.
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
5

dams, reservoirs, piping; water harvest- able neighbourhood development. The four
ing, etc.) planned outputs were as follows:

4. Sustainable waste management (i.e., 1. Technical framework of the pilot project


composting, recycling, reuse, etc.)
2. Financial set-up of the pilot project
Outcome Objective 2 was “to strengthen
3. Implementation of the pilot sustainable
the capacity of small-scale contractors and
neighbourhood unit (200 dwelling units)
building materials producers in shelter and
infrastructure provision”. The two planned 4. Selection of small-scale contractors
outputs of this outcome objective were as through competitive bidding
follows:
The roles and contributions of the various
1. Training programme in low-cost building stakeholders are spelled out in the
material production (compressed earth memoranda of understanding, namely the
blocks; precast stone blocks; ferro-ce- first signed MOU between the Government
ment roofing channels), 25–30 trainees of Finland and UN-Habitat dated 5 August
2003 and a second MOU (Government of
2. Contractor development programme for
Kenya, Government of Finland, UN-Habitat)
emerging contractors, 25–30 trainees
developed after the 17 December 2004
Outcome Objective 3 was “to enhance tripartite meeting and expected to be ready
the capacity of public agencies to act as by 18 January 2005. The second MOU was
an enabling authority for community-led not signed; instead, collaboration among
housing and infrastructure delivery”. The the partners continued, based on the process
planned outputs were the following: that was agreed in the minutes of the
meeting and the agreement of cooperation
1. An action plan to enhance community–
between UN-Habitat and the Government
government partnership in shelter and
of Finland. The ‘roles and contributions’ in
infrastructure development and services
this section of the evaluation report refer
provision
to the project document and the first MOU
2. A workshop on enhancing community- between the Government of Finland and
driven housing and infrastructure devel- UN-Habitat.
opment (for government, the municipal-
It was agreed that the Government of Kenya
ity, small-scale contractors, NGOs, and
would provide land and assign counterpart
community-based organisations)
staff for the three-month preparatory phase
3. An annual programme for community- of the project20, while the Government
led housing and infrastructure develop- of Finland would provide funding for this
ment
20 The project had three phases to be followed
over a 27 month period. Phase 1 was a 3-month
Outcome Objective 4 was to prepare preparatory period, Phase 2 was a 6 month
and implement a pilot project in sustain- capacity-building phase, and Phase 3 was an 18
month pilot implementation phase.
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
6 MUNICIPALITY, KENYA

phase and receive the SNP land in Mavoko procedures of the SNP and those of KENSUP.
Municipality via a debt swap, to be held One of the differences between UN-Habitat
in trust with the Ministry of Finance. UN- and KENSUP was that the former preferred
Habitat was to provide international a community-driven approach while the
professional staff, office space, and government suggested it would be too time
secretarial services. consuming. The government also wanted
full control over procedures related to the
Although there was a situation analysis
use of contractors. There were many other
carried out from August 2002 up to the
issues related to authority and responsibility
first quarter of 2004, the project started its
between the two parties which were never
expected activities on 1 March 2004, when
resolved and resulted in an impasse at the
it recruited a Chief Technical Advisor and
17 December 2004 tripartite meeting.
a Project Manager.21 In 2004, the project
Following this, the Executive Committee
also recruited three local field staff from the
eventually stopped functioning. Table 2.1
private sector who were also residents of
shows activities completed as of December
the Mavoko slums. The Mavoko Municipal
2004, presented at the tripartite meeting by
Council provided a free office for the
KENSUP in its capacity as lead agency at the
project, inclusive of electricity, computers,
time.
and some furniture. UN-Habitat provided a
computer and some office furniture. A perusal of the tripartite meeting minutes
shows that there were a number of
After many preparatory meetings, an
outstanding issues and activities at the time
Executive Committee under a Joint Project
of the meeting, before KENSUP and UN-
Planning Team was formed, comprising
Habitat stopped their collaboration. These
all three parties (UN-Habitat, KENSUP, and
were as follows:
the Government of Finland) and more
than 50 cluster members drawn from the i. There was no title for the land and no
public and private sectors. It was to meet authority to subdivide.
monthly, or more often if necessary, and
ii. An environmental impact assessment
report to the planning team, which was to
was not done.
meet annually. The Executive Committee
held its first meeting on 29 March 2004, iii. Local staff had been recruited, but
chaired by the UN-Habitat Programme their terms and conditions and type of
Manager. During the meeting the project contract were not specified.
discrepancies emerged, related to the
nature, location, target population, and iv.
Local authority training was not
designed, despite being essential to the
21 The SNP was led by three different CTAs between
2004 and 2008. One Project Manager was hired, project’s preparatory phase.
terminated, and re-hired. The UN-Habitat office
responsible for the project was also shifted during v. Use of the socio-economic mapping was
this time period from the Human Settlements
Financing Division to the Regional and Technical
not defined within the implementation
Cooperation Division/Regional Office for Africa activities.
and the Arab States.
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
7

Table 2.1: Activity Status, December 2004


No Activity Completed Activities Ongoing Activities Outstanding activities
1 Land Completed for 22.4 ha
registration

2 Land survey • Land survey of 100 haa • Development of


• Geographic information master plan—100
system for 22.4 ha ha

• Hydrological and geological • Geographic


survey for 22.4 ha information
system for Mavoko
• Situation analysis done Municipal Council to
• Social mapping done cover 477 km
3 Project manage- Management committee in place Integration within • Capacity building
ment (membership consists of relevant KENSUP of local authority
Government of Kenya depart- • Review of
ments, University of Nairobi— institutional
Faculty of Architecture, Design framework for
and Development), the private shelter, services,
sector, NGOs, and and infrastructure
UN-Habitat)
4 Community • Community organization • Cooperative • Identification of
empowerment and sensitization in place formation training needs/
• Community Umbrella • Community trainees/trainers of
Committee in place action plans trainers

• Community action plans in implementation • Identification of


place • Community beneficiaries
mobilization • Preparation of
training programme
and materials
• Livelihood skills
training
5 Socio-economic Completed Finalization of report
mapping
6 Partnership • Establishment of NGOs, • Capacity building
building community based in networking and
organizations, and faith- communication
based organizations as • Integration of
members of the Executive the private sector
Committee and trained in into community
participatory methodologies empowerment
of community organization activities
• Thematic clusters
established
7 Housing design Initial design briefs available Joint review of designs
Student design competition Announcement of
winners
Source: KENSUP Minutes of 17 December 2004 Tripartite Meeting
a The 100 hectares covers all land, including the 22.21 hectares of the Government of Finland-funded SNP.
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
8 MUNICIPALITY, KENYA

vi. MOUs were not developed with partners Within the next three years, there was
for construction, training, and credit. some progress in project implementation.
These developments are outlined in the UN-
vii. Financial mechanisms for credit, savings,
Habitat six-month progress report dated 30
loans, and cost recovery were not de-
September 2005. For example, the socio-
fined.
economic profiling report was finalized. In
viii. Bottlenecks to community–government addition, there was agreement on common
partnerships were not addressed. ground among the many identified partners,
such as the National Cooperative Housing
ix. Building associations were not identified. Union and Practical Action, on housing
design, infrastructure, credit, and training.
Subsequent to the 2004 meeting, the
Government of Kenya began to develop New partners joined the Executive Committee
its part of the SNP land located adjacent during this period of time, including the
to the UN-Habitat SNP project land. The Housing and Building Research Institute, the
construction of an estimated 450 mixed Association of Local Governments of Kenya,
housing units is underway. They are and the Export Processing Zones Authority.
expected to cater for mainly low-income The Mayor of Mavoko assumed leadership
howuseholds, but also some middle- and of the SNP Executive Committee. However,
high-income households. This Government the Executive Committee meetings with
of Kenya project was stalled at the time KENSUP participation were never restarted.
of the evaluation due to problems with Social mobilization continued and the
contractors. UN-Habitat also started two total communal savings of the Mavoko
new projects from 2007 to 2008, under low-income population (CBOs) in the pre-
separate funding. This decision followed the cooperative period under SNP supervision
signing of a memorandum of understanding exceeded KES 5 million. In June 2009,
with KEWLAT for a women’s empowerment the title L.R. No. 27664 for the SNP land
project and an internal agreement made was issued to the project. Six Mavoko
within UN-Habitat to start the Youth cooperatives were formed from the 30
Empowerment Project. A second MOU CBOs. These were trained by the Ministry of
was signed with KEWLAT in August 2010 Cooperative Development and registered,
to manage the 55 acres. Both projects had and the members began mobilizing their
built structures situated on the UN-Habitat members to save. These savings reached
SNP land by the time of the evaluation. KES 3–5 million per group by the time of
the evaluation. On 30 August 2010, there
Despite unresolved issues between KENSUP
was an official handover of the Moonbeam
and UN-Habitat, project activities related to
Youth Centre and the KEWLAT model houses
the preparatory and capacity-building phases
to YEP and KEWLAT, respectively. During the
of the SNP continued. These are outlined
same year, all three parties—YEP, KEWLAT,
in the ten progress reports submitted on
and the six Mavoko cooperatives—were
the SNP project between 2004 and 2006.
informally allocated acreage of the SNP
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
9

land. The six Mavoko cooperatives protested doors for funding by reawakening donor
to UN-Habitat about the land allocation to interest and trust. The potential beneficiaries
KEWLAT, because they felt that the KEWLAT of the resettlement project have been
cooperative members were outsiders. identified as members of the 11 cooperative
groups, given their past activities and
2.2. OVERVIEW OF THE savings towards the acquisition of a housing
SUSTAINABLE NEIGHBOURHOOD unit.22

PROGRAMME FOR THE PERIOD The new project will be delivered in two
APRIL 2011 to January 2012 phases: Phase 1, now underway, is a
feasibility study by Shelter Afrique to
In April 2011, the UN-Habitat Executive
determine the feasibility of a resettlement
Director initiated a new development
project and recommend an informed
process for the SNP, to be implemented
decision as to whether to proceed or not;
in collaboration with the Government of
Phase 2 would involve the implementation
Kenya and other stakeholders through
of activities yet undefined. The indicators
the 22-member Mavoko Development
and planned outputs have already been
Advisory Committee, which was formed in
determined for this phase, and some
September 2011. The membership of the
deliverables have already been met,
committee is wide reaching and inclusive
such as appointments and contracting
of Shelter Afrique, legal personnel, and
requirements (Annex IX: Implementation
two community development organizations
Schedule). The new initiative has appointed
(GROOTS Kenya and KEWLAT), as well as UN-
members to a committee, the Mavoko
Habitat and the Ministry of Housing. Efforts
Development Advisory Committee, which
are ongoing to improve the relationship
is inclusive of the government, UN-Habitat,
between the government and UN-Habitat,
Shelter Afrique, legal personnel, the two
with both parties participating in correcting
community-based organisations (GROOTS
misinformation about the project.
Kenya and KEWLAT), and representatives
The revived development process follows of the 11 cooperative groups. GROOTS
the same outcome objectives for the SNP Kenya is responsible for the six Mavoko
as set in 2002, but with changes and cooperatives, while KEWLAT is responsible
improvements to reflect the current situation for the other five. GROOTS Kenya is in the
and realistic, practical requirements. A process of carrying out a socio-economic
project brief is now under discussion to see survey of all 11 cooperatives and validating
how a project for Phase 2 can be designed an estimated 3,000 members.
which will improve local governance
and strengthen the capacity and role of
the informal and community sectors in
22 This includes the six Mavoko cooperatives and five
developing environmentally sustainable KEWLAT cooperatives. The KEWLAT cooperatives
neighbourhoods. The purpose of the new were first targeted by UN-Habitat in a women
empowerment project initiated on the UN-Habitat
development from April 2011 is to open the
SNP land using other funding.
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
10 MUNICIPALITY, KENYA

3. EVALUATION PROFILE AND METHODOLOGY

The purpose of the evaluation was to identified by these institutions, with regard
conduct an end-of-project study of the SNP to the development objective, immediate
project from its inception period in 2003 to outcome objectives, plans, expectations,
its closure in April 2011, to assess the extent and standards of performance set for the
to which the development and immediate project. It was also to serve as a research tool
objectives and accomplishments of the SNP for accountability (i.e., performance and
were achieved (Annex I: Terms of Reference). results). Therefore, the evaluator attended
several jump-start and informative meetings
The evaluation was designed to be a
with UN-Habitat at the beginning, in the
summative one, with a systematic and
middle, and at the end of the evaluation
objective assessment of the complete project
to gain clarification and more in-depth
with respect to its design, implementation,
knowledge on some issues and also identify
and results. A consultant, Ms Kathleen
areas for learning to inform decision making
Webb, was commissioned to conduct the
related to UN-Habitat programme direction.
evaluation. The external evaluator worked
Cross-cutting issues such as gender and
in close contact with UN-Habitat and with
human rights were incorporated into
its guidance, which made the evaluation
the evaluation by developing a detailed
participatory. In order to satisfy quality
questionnaire that captured these areas
standards with due concern for factual
(Annex V: Questionnaires). The evaluation
accuracy and impartiality, the evaluator
plan and methodology, as well as the
relied on the UN-Habitat standards for
questionnaires, were reviewed with UN-
monitoring and evaluation, as well as other
Habitat and then revised (Annex IV: Detailed
global standards, including those of the
Methodology and Revised Evaluation Work
United Nations Evaluation Group.
Plan).
As a significant time period had passed since
The evaluator received full support,
the project started, and therefore many of
including a tentative list of persons
the staff working on the project had moved
with their contacts. The only limitations
on, there was heavy reliance on using
faced related to the challenge of getting
several sources of documentation. A total
information during the holiday season and
of 174 documents were studied (Annex II:
also getting appointments when many
Bibliography).
key stakeholders had moved on and could
The secondary purpose of the evaluation was only be reached by email or telephone
to provide feedback to the Government of (Annex III: List of People Interviewed).
Finland, UN-Habitat, and other stakeholders
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
11

4. EVALUATION FINDINGS AND ASSESSMENT

4.1 ACHIEVEMENTS
The evaluator finds—based on the analysis iii. Over 350 young women and men have
of the achievements of the project against acquired practical and marketable skills
the four immediate outcome objectives set in construction. Of these, some 100
for the project—that the SNP delivered some women and men have received training
of the key planned activities and outputs and in sustainable house construction, road
partially achieved the outcome objectives in construction, water supply, sanitation,
terms of their planned outputs and activities and waste management; 50 have
and success indicators. The project was not received training in the production of
able to achieve all of the planned outputs building materials and efficient contract
and activities related to the four immediate management; and 200 have received
outcome objectives due to a late start, the on-the-job training in community
complexity of the project design, and the construction by participating in the
management challenges faced during the community-based construction of
life of the project. services and infrastructure.

The four immediate outcome objectives iv. A model savings and loan scheme has
were to be achieved through the delivery been established to serve the needs of
of nine outputs. At completion, the project the low-income groups who cannot
was to have achieved the following overall access bank loans. A model housing
results,23 as specified in the foundation association has been established and is
project document: serving its 200 members. Communities
have emerged that are capable of
i. Approximately 200 households have participating in the local decision making
initiated the construction of their that affects their living environment and
incremental houses. development.
ii. A model sustainable neighbourhood has v. Over 50 key actors in the community-
been planned, surveyed, and partially based housing process, including
built. representatives of the government, local
23 The overall results are summarized results based government, NGOs, private sector, and
on the planned outputs and activities and not
directly correlated to the outcome objectives
communities, have received training in
[immediate objectives] in the foundation project community-driven housing processes.
document. This evaluation has assessed the extent
to which the outcome objectives were achieved, vi. Counterpart staff drawn from public
and planned outputs and activities delivered.
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
12 MUNICIPALITY, KENYA

agencies have, through on-the-job • Extensive networking and research


training, learned to facilitate community- was done, with the participation and
driven shelter, infrastructure, and service commitment of more than 50 institutions,
delivery. organizations, and companies in
the fields of appropriate technology,
vii. A new paradigm for housing and infra-
housing, community development, and
structure development through commu-
credit granting, which can be applied to
nity participation and management will
future project needs.
have been demonstrated, tested, and
evaluated. There was some degree of achievement of
many activities and outputs related to the
The project carried out significant in-depth four immediate outcome objectives. Three
and professional activities from 2004 up of the four outcome objectives were partially
to April 2011, but did not fully achieve the achieved and one outcome objective was
overall results of the project and therefore not achieved (Table 4.1). The project carried
partially achieved the immediate outcome out many preparatory activities (related to
objectives of the projects. The following Outcome Objective 1: Enhance the role and
activities were implemented and outputs capacities of the communities in the provision
delivered: of housing, services, and infrastructure), the
most effective being the mobilization of
• Geographic and hydro-geological
slum communities in Mavoko Municipality,
surveys were done for part of the land.
empowering them in terms of their human
• A situation analysis, community action rights and mobilizing them to save. This was
plans, and social mapping were carried achieved by developing a close and trusting
out in 26 slum settlements of Mavoko. relationship with the slum dwellers, first
• The title for the land was released.24 mobilizing them to form CBOs and later to
organize themselves into cooperatives.
• The SNP office was equipped and studies
archived. Female participation was also impressive, at
more than 25 per cent of the members. In
• Thirty CBOs were formed as a result of
addition, the process of social mapping and
extensive sensitization, social mapping
the socio-economic studies were in-depth
training, and retraining of slum residents.
and professionally done to identify the
• Mobilization occurred and six Mavoko sociocultural and economic characteristics
cooperatives were formed, with an of slum communities. The identification of
average membership of 500 persons per stakeholders in both the public and private
group and with a savings range of KES sector also was effective, as the project team
3–5 million. reached far within the local and national
24 Grant Number I.R 117250 allocated L.R. 27664 to domain to attract many interested parties
the Permanent Secretary to the Treasury of Kenya in the areas of credit, housing, and training.
as trustee of the UN-Habitat Housing Project, 22.1
hectares of land in Mavoko Municipality in June
2009.
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
13

Table 4.1: Summary of Findings of the Evaluator with Respect to the


Achievement of the Four Immediate Outcome Objectives
No. Immediate Planned outputs Degree of achievement Remarks of evaluator
outcome objective
1 Enhance the role i. Four training courses in Partially achieved. The 2004–2007 SNP (and
and capacities of sustainable neighbourhood Training courses were not partners) held multiple courses
the communities development (in total 100 done on the specific topics and sensitization on basic
in the provision of trainees) in the project document, but health care, how to organize
housing, services, and many activities and courses did themselves as community-based
infrastructure enhance community capacities organizations, and how to form
in group formation, savings cooperatives and save.
mobilization, and healthy living,
all of which will contribute to
a sustainable neighbourhood
in which they participate
in housing, service, and
infrastructure provision.

2 Strengthen the i. Training programme in Not achieved. YEP was a completely separate
capacity of small-scale low-cost building material The capacity building was not UN-Habitat project intended
contractors and production (compressed done through the project, but to benefit Kibera youth, not
building material earth blocks; precast 20 Mavoko youth drawn from the SNP beneficiaries or the
producers in shelter stone blocks; ferro-cement the six Mavoko cooperatives SNP project, and therefore its
and infrastructure roofing channels), 25–30 benefited from training from training programmes cannot be
provision trainees YEP in 2008. credited to the SNP.
ii. Contractor development No contractor development
programme for emerging programme was done.
contractors (25–30
trainees)

3 Enhance the i. An action plan to Partially achieved. The Executive Committee was
capacity of public enhance community– Community action plans were too large, at more than 50
agencies to act as government partnership in developed in 2005–2006 for the members, and the clusters were
enabling authorities shelter and infrastructure 30 Mavoko community-based ineffective. Since 2004, the
for community- development and service organisations, but they do not two key players had not been
led housing and provision clearly show how government able to agree. The public and
infrastructure delivery partnership will occur. One private agencies (which were
ii. Workshop on enhancing
action plan consolidating the 30 ready and willing to participate)
community-driven
community-based organizations were too diverse and numerous
housing and infrastructure
plans was not done. and could not carry out their
development (for
proposed programmes without
government, municipality,
the umbrella of the two key
small-scale contractors,
The workshop was not held. players.
NGOs, and community-
based organisations)
iii. An annual programme The annual programme was not
for community-led developed.
housing and infrastructure
development
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
14 MUNICIPALITY, KENYA

4 Prepare and i. Technical framework of Partially achieved. The rift between UN-Habitat
implement a pilot the pilot project The pilot project was and KENSUP made it impossible
project in sustainable implemented in terms of studies, to proceed on housing
ii. Financial set-up of the
neighbourhood mapping exercises, architects’ design. The issue of how to
pilot project
development drawings, land preparation, and accommodate the cooperatives
iii. Implement the pilot title allocations. in terms of acreage and housing
sustainable neighbourhood type was never resolved.
The financial allocations were
unit (200 dwelling units)
not set up.
iv. Selection of small-scale
Four units were built by KEWLAT
contractors through
as part of a separate initiative.
competitive bidding

4.1.1 FINDINGS ON LOW- issues needed more in-depth discussion by


INCOME HOUSING the Executive Committee:

A major achievement of the SNP was the i. Modalities for mixed housing for various
multitude of low-income housing project income groups, including construction
designs produced by industries, businesses, and socio-economic issues.
and NGOs. Figure 1.1 shows one of the
ii. Role of a technology workshop and/
suggested housing layouts provided to UN-
or youth centre in promoting both
Habitat. Many others were developed by
appropriate technology and livelihood
both the public and private sectors, e.g., by
development.
Rimba Planning and COMAC Investments25.
There was also a global competition for a iii. Adobe and cob techniques and ferro-
low-income housing design which received cement applications26.
several entries from Finland, but no entries
from Kenya. The SNP project document states iv. Ministry of Housing technical design re-
that the project was to be experimental, but finement (May 2006).
also states that one of the overall results
When designing the prototype, due
at the end of the project would be model
consideration should have been paid to
housing for 200 households. These studies
the housing situation and cost estimates
went a long way towards developing low-
and their implications, as contained in the
cost housing concepts. The many options
KENSUP implementation strategy. Criteria
were not explored by the project clusters
for the design of prototypes should have
by the time the project stalled, and there
taken this into consideration, but additional
was not enough input from KENSUP on
options which would have made the project
government guidelines and requirements
a sustainable neighbourhood needed to be
(especially the Housing Act), which could
added. KENSUP and UN-Habitat did not
have guided the project. The following
26 Nordberg, Rainier (2004 and 2012), Handover
25 Executive Committee meeting, 22 September Note, CTA 2002–2004 and email interview,
2004888. Nairobi.
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
15

agree on the additions which would make the United Nations Millennium Declaration,
the neighbourhood ‘community driven’ and both directed at significantly improving the
‘sustainable’, and this area remains to be lives of at least 100 million slum dwellers
addressed in the new phase of the project. globally by the year 2020, using domestic
Table 4.2 is extrapolated from the KENSUP resources and new technologies. UN-Habitat
strategy (2004). These show the minimum states in its 2003 report that “the accepted
requirements for schools and other facilities best practice for housing interventions in
no matter what type of housing is being developing countries is now participatory
undertaken. However, requirements for a slum improvement... the best examples
sustainable neighbourhood go beyond what are holistic approaches to neighbourhood
KENSUP advocates and include local-level improvement, taking into account health,
neighbourhood development committees education, housing, livelihood and
and others. These need to be factored into gender”. 27

any resettlement/relocation project but were


The model for the project appears to
not.
be extrapolated from several developed
countries, sustainable neighbourhood
4.2 ASSESSMENT OF RELEVANCE
projects, and specifically a Finnish model
The evaluator finds that the SNP project goal “where local authorities formulated
(development objective) and four immediate their own agendas for sustainable
outcome objectives were consistent with development.”28 The meaning of the
UN-Habitat global priorities and the donor’s
policies. The project is also in line with 27 UN-Habitat (2003), The Challenge of Slums:
Global Report on Human Settlements 2003, Earth-
the Addis Ababa Declaration on Human scan, London, UK.
Settlements in the New Millennium and 28 SNP (2002), SNP Project Document, page 9.

Table 4.2: PLANNING REQUIREMENTS FOR HOUSING

Population Number of households Facility to be provided Quantity (No.)

10,000 2,500 Primary school 1.0


20,000 5,000 Secondary school 1.0
2,500 625 Nursery school 1.0
10,000 2,500 Community centre 1.0
20,000 5,000 Health centre 1.0
10,000 2,500 Open market 1.0
10,000 2,500 Police post 1.0
5,000 1,000 Religious facility (churches and 1.0
mosques)

Source: Republic of Kenya (2005), Kenya Slum Upgrading Programme (KENSUP) Implementation Strategy 2005–
2020, Volume 1, Nairobi, UN-Habitat, page 8; Ministry of Lands and Housing (2004), Physical Planning Handbook
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
16 MUNICIPALITY, KENYA

concept ‘sustainable neighbourhood’ is also not factored into the project design. It was
not well defined in the project document, also not specified with what means the
and was not understood by many of the slum dwellers would develop their own
key stakeholders. The ‘woonerf’29concept ‘incremental’ type of low-cost housing or
was then introduced in the SNP Executive how disaster and environmental risk would
Meeting of 22 September 2004, and two be managed. The design is also not in line
representatives of the Physical Planning with the National Housing Policy for Kenya
Department and Urban Development (currently under review), which specifies
Department were sent to the Netherlands building standards for slums but does not
to gather information. Indices to define address innovative housing materials.30
the various concepts, however, were never An international design contest for a
developed to show how they could be applied sustainable neighbourhood was held, but
in various alternative approaches and how there were no entries from Kenya. It is not
they fit into the local situation. Examples clear why this was the case; several Finnish
of these concepts are ‘community-driven designs were submitted but not utilized.
implementation’, ‘incremental housing’, and However, there was still value added due to
‘innovative building materials’, which were awareness creation and training to produce
applied in non-slum settlements in the two the designs.
models referred to in the project foundation
Another tenet of the definition of a
document. It was not defined how the
sustainable neighbourhood specified in
stakeholders would apply these concepts in
the proposal is the parallel promotion
the current situation in Kenya where slums
of livelihoods alongside better housing.
are demolished with little consideration for
To realize this goal, the SNP should have
the human rights of the slum dwellers.
linked to other relevant ministries dealing
The Kenyan context is also one where slums with livelihoods, namely the Ministries of
are highly vulnerable to disasters such as fires, Agriculture and Livestock Development,
which can be caused by fuel leakages from Labour, Education, Science and Technology,
nearby pipelines and houses with unsafe Environment, Special Programmes, and
and flammable building materials. The high Water. It may not have been realistic to expect
population density and heavy traffic make KENSUP to take a major leadership role
the situation even more unstable. The SNP without clarifying areas with discrepancies
design emphasizes the use of innovative and collaborating with other ministries and
building materials, but these require time NGOs. The sustainable livelihood model
for development and testing, which was in the proposal was not expanded into
activities and factored into the project.
29 A woonerf (Dutch plural: woonerven) in the Neth-
erlands and Flanders is a street where pedestrians
and cyclists have legal priority over motorists. The
techniques of shared spaces, traffic calming, and
low speed limits are intended to improve pedes- 30 Republic of Kenya (July 2004), National Housing
trian, bicycle, and automobile safety. Policy for Kenya, Sessional Paper No 3, July 2004.
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
17

4.3 ASSESSMENT OF i. The budget was inadequate to deliver


EFFECTIVENESS the planned outputs. For example,
research to study the new concepts and
The evaluator finds that in terms of types of housing options, development
effectiveness,31 the SNP made an overall of indices of liveability, and community
contribution to the development objective mobilization and training required much
set for the project, as it delivered outputs more time than the budget allowed
and activities which contributed to that (efficiency).
objective—“to strengthen the role and
capacity of the informal and community ii. The quality and quantity of the expected
sector in the provision of housing, result on ‘housing’ was not well defined
services, and infrastructure.”32 The project or agreed upon between UN-Habitat
strengthened community capacity through and KENSUP (relevance).
the sensitization, mobilization, and training
iii.
Executive Committee leadership by
of men, women, and youth living in Mavoko
KENSUP and UN-Habitat was not well
slum settlements who were then able to
defined or cohesive on most aspects
better define their role in creating healthy,
of the project—housing type, selection
sustainable neighbourhoods and also
of beneficiaries, financing, etc. The
implement steps to improve their own lives,
differences between the two were not
such as by working together in community-
resolved in a timely manner (efficiency).
based organizations and cooperatives.
iv. The size of the Executive Committee
Specifically, SNP has empowered more
proved to be cumbersome and the
than 3,000 people who have joined
composition unworkable when clusters
cooperatives and are enjoying the benefits
were added, which complicated
of membership (e.g., potential savings).
operations (efficiency).
Thirty CBOs were developed in Mavoko
slum settlements through social mapping v. External factors related to the Kenyan
and other participatory techniques, which context impinged on political will with
enabled men, women, and the youth to respect to boundaries and use of land
communicate their needs, some for the first (relevance).
time.
At the end point of the project (April 2011),
The project, however, did not fully achieve the expected beneficiaries did not have their
its development objective, as it only partially needs met in terms of housing and training
achieved the four immediate outcome needs. The large number of public and private
objectives, for reasons related mainly to stakeholders brought on board through the
relevance, effectiveness, and efficiency: eight clusters did significant research and
made feasible proposals, but the project did
31 Effectiveness in this case refers to the immediate
outcome objectives, not the development objec- not take off due to design and management
tive. challenges. These challenges were identified
32 SNP project foundation document, page 12.
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
18 MUNICIPALITY, KENYA

Programme participants at Sustainable Neighbourhood Programme Youth Centre displaying a bamboo ladder
made by the youth,UN-Habitat, 2012 © Kathleen Webb

from the start and brought to the attention which was also not well captured in
of the Executive Committee meetings, yet the project design. The success of the
the necessary changes were not made. The programme was not only dependent on the
decision to allocate acreage to two new willingness of the local authorities to allow
projects (KEWLAT and YEP) and to the six community autonomy, as this issue would
Mavoko cooperatives complicated matters be defined in local by-laws as well as the
further, as the project goals and outcome laws of the land.
objectives for the KEWLAT and YEP projects
Many persons learned leadership skills, and
differed from those of the SNP project.
the improved group dynamics expanded
The Mavoko cooperatives could not move
community resources. This has the
forward without support. Misinformation
potential to develop livelihoods in these
on the project’s expected outcomes and
slum settlements, as people met through
benefits increased over time. This resulted
the community development meetings
in frustration among all parties, particularly
called by the SNP and were given hope.
the slum dwellers.
The SNP team brought in professionals
Finally, the management did not address from many sectors, such as health and
risk management, especially the aspect of education personnel from the Mavoko
local authorities and community autonomy, Municipal Council, who were able to
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
19

provide community education on many 37,000.34 There was no costing for the
issues relevant to healthy living. Many sensitization of others in the public and
people attended more than five meetings private sectors.
and found them to be very informative with
ii. There was no provision for salaries for the
respect to improving their lifestyles. This
three field staff, who received stipends
sensitization will benefit the new phase of
which were not enough to cover costs.
the SNP or indeed any development project
being undertaken in those slum settlements iii. The three unsalaried field staff were key to
which participated. the substantive fieldwork and community
interaction (including problem solving) in
4.4 ASSESSMENT OF EFFICIENCY the slum communities of Mavoko. They
The greatest challenge the project faced was depended on stipends and as a result,
using the various expected activities and shortages in funding for transport,
outputs to transform the available financial communication, and stationery caused
and human resources into the expected frequent delays. More than half of
results. In terms of finance, the Government the combined financing (Government
of Finland contribution of EUR 750,000 and of Finland and UN-Habitat) went to
UN-Habitat contribution of USD 160,000 international and national staff, and the
were inadequate to meet the project needs of field staff were not anticipated.
requirements33. Cost of living and high iv. Offices were provided by the Mavoko
inflation were not factored in. This meant Municipal Council, inclusive of electricity
that, although funding was utilized as per and two computers. UN-Habitat did not
the agreed budget as planned and on time, cover internet, communication, and
the cash flow was not enough for day-to-day stationery costs for the field staff. The
management, and the quality of the work field staff suggested that the computer
and communication were seriously affected. provided by UN-Habitat was an older
The following are examples of prioritized/ model, and much of the information
not prioritized activities and outputs in the stored in it was difficult to retrieve and
budget: therefore not available to the field staff.
i. Sensitization and social mobilization in v. Monitoring to be carried out by the field
the 26 settlements was not budgeted staff and others did not receive enough
for and had to be covered by the funding.
training budget, which was only USD

34 UN-Habitat (2003), ‘Agreement and Budget’


33 The budget was too small to realize the expected (Government of Finland and UN-Habitat), Nairobi:
outputs for the four objectives, and the budget Each community meeting (50 persons, inclusive
did not accommodate all expected results. of trainers) cost an average of USD 500 per day
However, at the end of 2008, USD 104,933 still (transport, stationery, etc.). On average, communi-
remained, and this was attributed the project ties were visited at least five times to mobilize
coming to a standstill when UN-Habitat and KEN- people and train them in CBO (and later coopera-
SUP faced challenges. The total balance was USD tive) development. Training costs for manual de-
92,861 plus USD 12,072 (UN-Habitat AOS) for a velopment and production were also not included
grand total of USD 104,933. in the budget.
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
20 MUNICIPALITY, KENYA

vi. The project vehicle arrived late (more and attended by many interested parties
than a year after the 2004 activities from both the public and private sectors,
started) and was not made available to who made many contributions regarding
the field staff on most occasions. funding, credit, and training. At least seven
more meetings were held in 2004. The
vii. The project funded several exchange
reports from the meetings show there was
trips (the Third Session of the World
enthusiasm and interest in the SNP. The
Urban Forum, held in Vancouver,
cluster groups met frequently in 2004 and
Canada, in June 2006) and retreats
did much work in research, networking,
(Mombasa, Kitale, and Nakuru), as well
and attracting local industries to invest in
as a house design competition35 (which
the project.
had no entries from Kenyan applicants,
but did provide value through awareness The cluster groups were the following:
creation about the project).
Cluster 1: Project management, surveys,
viii. There was little or no funding for major land use planning, and tenure issues and
components of the project such as the options.
architectural studies, the savings and
Cluster 2: Researching product develop-
credit programme, technology workshop
ment and architectural design.
construction materials, and supplies for
the construction, training, etc. Cluster 3: Infrastructure and regional and
neighbourhood water, sanitation, and
The proposal that KENSUP would lead the
roads.
SNP project and head monthly meetings did
not take off. According to the minutes of the Cluster 4: Social mobilization and capacity.
first meeting of the Executive Committee,
the “differences in nature, location, target Cluster 5: Institutional collaboration and
population and procedures”36 between UN- partnership.
Habitat and KENSUP eventually caused an
Cluster 6: Resource mobilization and hous-
impasse in 2004, but it was decided that
ing finance.
the Executive Committee would be headed
by UN-Habitat and work divided into seven Cluster 7: Monitoring, evaluation, and
clusters. The first documented meeting of reporting.
the committee thereafter was held on 27
KENSUP took on the role of managing
May 27 2004; it was chaired by UN-Habitat
Clusters 1 and 3, while the others
35 The competition ‘The Sustainable City’ was a were chaired by various ministries.
student design competition in 2005 involving Ke-
nyan and Finnish university students. There were UN-Habitat headed Cluster 7. The Ministry of
no entries from Kenya. The design was expected Environment was not involved in the clusters
to present innovative, sustainable solutions relat-
ing to affordability, ecology, and social/cultural or the general management, although the
integration. situation analysis conducted several years
36 UN-Habitat (12 May 2004), ‘First SNP Steering back brought out many environmental
Committee Meeting’, Nairobi, page 2.
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
21

issues which may have warranted greater and working to harmonize their proposals.
participation of environment specialists in Unfortunately, the rift that occurred
the public sector.37 Some of the industrial between UN-Habitat and KENSUP in late
groups sent their environmental managers, 2004 resulted in all Executive Committee
but the provided documentation showed activities eventually stopping. This meant
no evidence of planning to address that the SNP eventually stalled, and the
environmental risks. findings and outcomes of the clusters in the
Executive Committee were not synthesized
The following are some examples of cluster
or integrated into the SNP between 2004
group deliverables which could have ben-
and 2010.
efited the project but were not acted upon
by the SNP: Given the collapse of activities in late 2004,
UN-Habitat had the intention between 2005
i. House design: Rimba Planning, COMAC
and 2007 of utilizing the SNP land, which
Investments38.
resulted in memoranda of understanding
ii. Capacity building (training): Intermedi- with KEWLAT on empowerment of women
ate Technology Development Group, and use of land at the SNP site. UN-Habitat
Housing and Building Research Institute. also implemented the Youth Empowerment
Project, which also erected a centre on
iii. Credit granting: Experimental Reimburs- the SNP land. The informal allocation of
able Seeding Operations. land to YEP, KEWLAT, and the six Mavoko
cooperatives did not contribute to the
iv. Land and credit: Bamburi Cement and
expected results of the SNP, as both the YEP
others.
and KEWLAT projects differed greatly from
The Executive Committee reports of 2004 the SNP in many areas (focus, beneficiaries,
indicate that there was cooperation between mode of implementation, and training
KENSUP and UN-Habitat during the early content). The six Mavoko cooperatives
Executive Committee meetings until the fenced their part of the land but lacked the
third quarter of 2004. KENSUP chaired all know-how and means to develop it. The
Executive Meetings, with participation from allocation of land to YEP and KEWLAT was
numerous members, including UN-Habitat. seen by the six cooperatives as an invasion
The CTAs and Project Manager did an by outsiders. A sense of unrest was created.
exemplary job leading the project activities, The MOUs and informal agreements with
considering the challenge of working with UN-Habitat were later terminated. This
multiple stakeholders in the seven clusters decision by UN-Habitat was a positive one,
37 The UN-Habitat situation analysis (undated, but as the two projects were not in line with the
likely 2001–2002) brought out many environmen- SNP concept and had caused much friction
tal issues. Examples include damage by surface
murram quarrying, pollution from industrial
with the original six cooperatives.
waste, an animal–agriculture conflict, and ex-
pected pollution from the high population density. In terms of timeliness, the SNP has not been
38 Executive Committee meeting, 22 September able to complete its activities and deliver the
2004.
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
22 MUNICIPALITY, KENYA

planned outputs. There are many reasons for into six cooperatives, with savings averaging
this, but time allocation was a factor, as the KES 3–5 million per group by the time of
period was too short—especially the three- the evaluation. These savings place the
month preparatory phase, considering that cooperatives in an advantageous position
the project was expected to be experimental for accessing credit from credit-granting
and innovative. Since the issue of timeliness institutions and taking other steps towards
emerged in the first Executive Committee purchasing housing units in the future.
meeting in 2004 and in subsequent
The budget, compared with the financial
meetings, it should have been resolved by
report of 31 December 2008, shows no
the two donors (the Government of Finland
irregularities and was subjected to audit
and UN-Habitat) at that time.
(Annex VI: Sustainable Neighbourhood
On the whole, despite the turnover of the Programme Budget—Nairobi Pilot
CTAs and absence of a Project Manager Project, Implementation Phase, and
for an extended period of time, the day- Annex VII: Sustainable Neighbourhood
to-day management of the SNP was Programme—Nairobi Plot Project Financial
good. The Project Manager and three field Report as at 31 December 2008).
workers worked closely together, gave each
other significant feedback, liaised closely
with communities, and made an effort to 4.5 ASSESSMENT OF CROSS-
document plans and events. There were CUTTING ISSUES
frequent meetings among leaders, the
project management, and the communities, The cross-cutting issues of environment,
in which issues and challenges were brought gender, and human rights were analysed to
forth. assess the extent to which environmental
impact and the different needs of specific
The SNP field work that was carried out in beneficiaries in terms of gender and
the Mavoko communities by the SNP staff human rights had been taken into account.
was in-depth, and many community action
plans and social mapping and other studies 4.5.1 Environmental Aspects of the
were completed. The three field officers Project
and the Project Manager were available to
address the emerging challenges of the 30 By the time of the end-of-project evaluation,
community-based organizations when they the SNP had not completed all the planned
were formed and the six cooperatives as activities, especially those which would im-
they developed from the community-based pinge on the arid/semi-arid environment of
organizations. The reports produced by these Mavoko Municipality. KEWLAT and YEP had
activities can support future programming. put up structures for their own projects, but
The subsequent Ministry of Cooperative these were not fully utilized at the time of
Development training was conducted this evaluation. It was noted that drainage
successfully and placed the communities and septic systems were not in place for
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
23

the KEWLAT and YEP structures, as water, and grevillea should be selected to pre-
sanitation, and other services had not been vent erosion.
connected. No environmental damage was
vi. Sewer and vehicular emissions exist due
noted or documented.
to heavy industrial activity, and plastic
The Executive Committee’s Cluster 3 was waste causes blockage of drainage sys-
to deal with infrastructure and regional and tems.
neighbourhood water, sanitation, and roads.
If the above and other issues are not ad-
Though representation from the Ministry of
dressed prior to large-scale construction,
Environment was necessary, there was no
they could potentially jeopardize the sustain-
environment expert from the government
ability of the project in the future or cause
in the cluster. Some of the private industries
significant negative environmental effects.
represented in the Executive Committee
sent their environmental managers to
4.5.2 Gender and Human Rights
meetings, but there was little reference to
the environment or to an environmental Since the project was not able to fully realize
impact study, despite the delicate nature its four immediate outcome objectives,
of the environment as identified in the the issue of taking gender aspects into
situation analysis. consideration does not apply. However,
there were findings on gender with respect
The following are some of the areas iden- to the project design and activities which
tified in the situation analysis as ‘sensitive’ were completed. First of all, the project was
with respect to potential environmental risk: intended to be more experimental than
i. There is a need for an ecological sanita- developmental. Therefore, beneficiaries
tion system and rainwater harvesting to were loosely identified as ‘slum dwellers’,
alleviate water shortages. and gender data was gathered without
setting a minimal number for females,
ii. Attention must be given to urban agri- youth, etc., which should have been done.
culture, recreation, and employment lo- Not disaggregating the data limited what
cations to ensure the proper use of water the project could target and measure
and to prevent contamination. with respect to gender equity. Still, the
slum settlements that were sensitized and
iii. Presence of suitable ingredients for mak-
organized first into community-based
ing ‘Habitat blocks’ for construction.
organizations and later into cooperatives
iv. Quarrying is extensive in the area and can were very disadvantaged in that they had no
cause erosion and damage to natural legal shelter and were impoverished.
drainage systems; there is a need to cre-
The questionnaires used in the social
ate earth embankments to dam rainwa-
mapping exercise had several questions on
ter run-off for use in the dry season.
gender, but final reports did not disaggregate
v. Landscaping vegetation such as acacia gender issues from the other subject matter.
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
24 MUNICIPALITY, KENYA

Subgroups were not identified within the environmental practices. These practices
six cooperatives formed by the project, and have lasted over time and there is evidence
comparisons were not well documented of benefits and some positive impact.
among the sites with respect to gender,
Several NGOs and industries also benefited
disadvantaged groups, and especially the
from the project, as they got to participate
disabled. With respect to the seven cluster
in the cluster groups and gained a greater
groups in the Executive Committee, there
understanding of development. There was
was no group specifically incorporating
a general intention among these groups
gender issues, and with respect to
to share resources (financial and physical)
technology training, there could have been
for the sake of the SNP. If the project
more emphasis on household labour-saving
had been sustained, it is likely that these
devices, which would minimize women’s
groups would have provided significant
workload and increase the accessibility of
support. Nonetheless, their interaction
the disabled to various services. Since local
between 2004 and 2008 indicated that
technology training, the development of a
they remained interested in participating.
technology centre, and livelihood activities
This is a positive and unintended impact,
were not carried out as project activities, no
as industries are not generally included in
evaluation is made of these with regard to
development activities of this type.
the participation of women, youth, and the
disabled. There was less impact on the local authorities
such as the Mavoko Municipal Council, as
4.5.3 Assessment of Impact and they required substantive capacity building
Sustainability to participate in the project. This was one
In order for the project to have the expected of the expected activities, but it did not take
positive impact on the beneficiaries, place. However, the council played a positive
full completion of at least one of the role by providing free accommodation on
four immediate objectives would have council premises for the project. They also
been necessary. This did not happen, attended most meetings and showed a
but significant activities occurred which willingness to support the project at all
benefited the general Mavoko population, times.
30 community based organizations and
When the collaboration broke down
six local cooperatives. The benefits of
between UN-Habitat and KENSUP, the
empowerment emerged due to the close
Executive Committee tried to continue
interaction of the SNP staff (CTAs, the
but finally had to cease operations. This
Project Manager, and the three field staff)
has resulted in some disappointment,
with the communities. The empowerment
especially among the stakeholders in the
has given people hope and changed their
Mavoko Municipal Council, but not to a
lifestyles towards healthier living. In some
level where it can be termed a negative
cases within the slum communities, people
impact, as it is in the process of being
started to use or develop better health and
reversed. The same applies to the sense of
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
25

unrest which developed in the six Mavoko are addressing setting up management
cooperatives when KEWLAT and YEP were mechanisms, including collaboration with
brought into the picture and allocated land new players such as Shelter Afrique. These
on the project site. This escalated because have the potential to stimulate operational
the Mavoko cooperatives were misinformed sustainability, if financial mechanisms are
about the project and saw the KEWLAT and also put in place.
YEP members as outsiders. This also was
The continuation of cooperation between
not a negative impact, as it has been easily
KENSUP and UN-Habitat can ensure
reversed.
that certain activities can be adopted by
If the project design and budget had various institutions in the government and
been better defined and factored into the private sector. This can only happen if the
implementation programme, the project concept of the sustainable neighbourhood
would likely have met its immediate and all its components are redefined and
objectives fully and made an impact at both applied to the Kenyan context, where the
the macro level and micro (household) level. demand for housing cannot be matched
Because all the expected project results were with affordability unless innovative options
not achieved, the sustainability (or ‘ability of are found. The sustainability of the project
the intervention to generate a structure or will depend on the political situation in
practices’) of the SNP is not a reality. The Kenya and the willingness to address
financial mechanisms were not adequate for land management issues. Nonetheless,
sustainability, as the project was experimental the perception of the intervention by the
in nature and its design did not provide for beneficiaries is now very positive due to the
local financial sustainability. Operational UN-Habitat activities from April 2011, which
sustainability has partly occurred in that a can also benefit bilateral relations and future
title was issued and communities mobilized. replication.
The new developments from April 2011
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
26 MUNICIPALITY, KENYA

5. CONCLUSIONS, lessons learned and


recommendations

Members of a registered cooperative society with a ‘Best Savers’ trophy, UN-Habitat, 2012 © Kathleen Webb

5.1 Conclusions sensitizing, and organizing communities


with a total population of 26,000 in a high-
A. Unclear design and inadequate fund-
density area required time. There were
ing limited the project’s implementation
many misconceptions about the housing,
and potential positive impact
and some expected it to be free. As time
There were limitations in the project passed, people became frustrated with the
design with respect to the time needed project, as they had formed community-
for sensitization and implementation. A based organisations and then cooperatives,
27 month period was inadequate to carry only to have the project delayed. It was
out the sensitization in the slums—besides not clear if the project was developmental
being challenging work, the areas were or experimental; the budget suggests it
difficult to penetrate. The funding for was experimental, as the funds were not
training, which would cover sensitization, enough to support the expected activities.
was very low compared to other budget For the project to have succeeded and made
items such as expatriate salaries, which a positive impact in the Kenyan context,
were much higher. The task of reaching, it should have been better designed in
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
27

terms of its scope, key stakeholders, and therefore not fully achieved its development
modalities for operation and funding. The objective. However, the project was very
capacity building of the Mavoko Municipal ambitious, and its results have to be taken
Council and its key departments related to in the context of its experimental and
social services was critical for the project’s innovative nature. The project should have
sustainability but was not done. looked at alternatives and done more
research before implementation—for
B. Research is still needed on experi-
example, developing various experimental
mental low-cost housing development
housing models and testing them on a small
vis-à-vis slum resettlement/relocation
number of slum dwellers. The approach
This need for additional research is partly that was taken placed UN-Habitat under
due to the lack of clarity on the meaning of extreme pressure to provide housing for the
‘sustainable neighbourhoods’ and that the slum neighbourhoods, yet its intention was
Government of Finland (co-financing the to provide a limited number of test or model
SNP with UN-Habitat) acquired land set aside houses in a resettlement project. If this had
for slum resettlement. In one of the earliest been clarified from the start, the project
studies of sustainable neighbourhoods, would have been better understood and
author Per Berg (1997) presents case studies likely more successful. Instead, from the very
of successful sustainable neighbourhoods beginning it was seen as a slum-upgrading
in Sweden. He characterizes them as small project, not a resettlement project being
communities of 500 persons or less, where implemented by UN-Habitat using KENSUP
people’s lives have evolved step by step so guidelines. After KENSUP withdrew as the
that they become mutually dependant on implementer, UN-Habitat was seen more as
each other for survival.39 an implementer and less as a facilitator.42 If
the project had restricted itself to research
Five years on, a project proposal for a and not to providing housing, it would
sustainable neighbourhood was funded40 have achieved its research aim, but not its
in an impoverished part of Kenya, not in housing resettlement aim.
the affluence of a developed country. In
fact, Mavoko Municipality is characterized C. Capacity building
by extreme poverty and is one of the slums
Despite not fully meeting the outcome
surrounding the Nairobi-Mavoko-Kitengela
objectives set for the project, the SNP
industrial axis.41 The SNP has partially
gave hope to thousands in Mavoko who
achieved its outcome objectives and
had never seen anything but poverty and
forced relocation. The project successfully
39 Berg, Per et al. (1997), Sustainable Neighbour-
hoods: A Qualitative Model for Resource Manage-
ment in Communities, Landscape, and Urban 42 Letter from R. Nabutola, Permanent Secretary,
Planning, Stockholm, pages 1–130. Ministry of Foreign Affairs, dated 13 November
2002, on ‘upgrading of slums’. The evaluator
40 UN-Habitat (2001), UN-Habitat Foundation Project noted in interviews with Mavoko Municipal Coun-
Document (FS-GLO-03-S19/A), Nairobi.
cil, cooperatives, and youth that there was no
41 UN-Habitat (undated), UN-Habitat SNP Situation clear perception of ‘sustainable neighbourhoods’
Analysis, Nairobi, UN-Habitat, page 22. and the role of UN-Habitat and KENSUP.
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
28 MUNICIPALITY, KENYA

empowered men, women, and youth who in both the public and the private sectors.
benefited from community mobilization, This included private industries such as East
sensitization, training, and the formation African Portland Cement and NGOs such
of community-based organisations and as the National Cooperative Housing Union
cooperatives. The project built the capacity and Practical Action, among many others. In
of approximately 3,000 persons (500 per addition, the project identified key players
cooperative) in life skills, primary health at the university level who will be ready to
care knowledge, savings mobilization, and carry out further research to understand
community dynamics, to name a few. the dynamics of slum neighbourhoods
and develop sustainable neighbourhoods.
The SNP staff (i.e., UN-Habitat Chief Technical
The new developments from April 2011,
Advisers, the Project Manager, and the three
now under process with UN-Habitat and
field workers) designed and implemented
KENSUP, can build on the networking and
a community strategy to identify, sensitize,
linkages already made, as the expertise
and build up the skills of the slum dwellers
of the organizations and institutions can
to form 30 community-based organisations.
support the design of activities and sourcing
These groups gained confidence because of
of additional funding.
the project and were able to form umbrella
groups and, eventually, six cooperatives.
5.2 Lessons Learned
The groups give credit to the SNP for
empowering them to save money through The experience of the SNP, which met many
cooperatives. The project was not able to obstacles and challenges and eventually
build the capacity of local authorities to faced an impasse, provides many lessons
any extent, although the local authorities that can support future projects.
did participate in the SNP. Provision of the
Some of these are the following:
necessary training (for example, in project
management and general management) 1) Research projects termed ‘experimental’
would have enabled them to better lead should not be combined with
some aspects of the project. Skills relevant development projects. The research
for participatory research and surveys were needed should be carried out first in a
developed among UN staff and members of separate and/or parallel project, and
the slum communities, who learned how to then the lessons learned can be applied
do social mapping, situational analysis, and to the development projects. This
community action plans. These skills can enables the design of the development
assist in the future activities planned for the project to benefit from the experimental
SNP in 2012. findings. Models such as the sustainable
neighbourhood, which worked well in
D. Networking and linkages
developed countries, may not work in
The formation of the Executive Committee a developing country such as Kenya. In
in 2004 provided an opportunity for UN- addition, Kenya is diverse in terms of
Habitat to develop significant partnerships ethnicity and culture—replication has
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
29

to be preceded by research and testing. 5.3 Recommendations


When this is not done, innovative
1. It is recommended that the studies and
housing projects cannot succeed.
reports archived in the SNP offices be or-
2) A project has to give the necessary time, ganized and synthesized by UN-Habitat
funding, and staffing to mitigate any or an NGO specializing in this area, so
challenges it may encounter in order to as to garner information and findings
minimize the risk of delays in the delivery which can benefit the next phases of the
of the planned outputs and outcomes. SNP.
For example, the context of Kenya at the
2. The SNP offices were facilitated through
time of the evaluation is one of emerging
funding and the donation of facilities
‘election fever’ in preparation for the
by the Mavoko Municipal Council. The
general elections of 2012. This increases
offices are equipped with computers and
the risk of political instability, disruption,
furniture and should be closed down
and poor governance. It means that
officially by UN-Habitat if they are not
projects which are carefully designed,
to be used. This process of closure or
tested, and subjected to feasibility studies
handover will clarify the expectations of
are more likely to succeed in the given
the council with respect to the sharing
implementation context. Networking
of premises. On the other hand, the
and making agreements with various
continued use of the premises (for
players in government and other sectors
example, as a library or training centre for
is important and is necessary to minimize
the time being) could save the resources
the possibility of corruption.
that would be needed for an SNP office
3) The complex arena of land allocation, in the next phase.
management, and subdivision is usually
3. A directory of all the stakeholders who
best managed by several ministries.
collaborated with the project during
There are many gaps in the ability of
this time period should be prepared
KENSUP to manage slum upgrading—
by UN-Habitat or an NGO specializing
the Ministry of Lands also has an
in this area, inclusive of their contact
important role. Several ministries had to
addresses and proposed roles, with a
play a strong role in the management of
view to involving them where possible
the SNP in order to tackle some of the
and feasible. The gaps in the project’s
challenges this project faced. Working
conceptual design and management
with several ministries and a wide range
structure should be addressed in the
of key players will make it possible to
next phase of the SNP project through
implement the project with minimal
redesign. These include clarification and
risks.
agreement on central concepts (e.g.
sustainable neighbourhoods), how the
project will integrate livelihoods into
housing development, and how new
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
30 MUNICIPALITY, KENYA

concepts for housing for the disabled be shared between the KENSUP mixed
and youth will be factored in. The project housing complex on the SNP land (ad-
design should also consider infrastructure jacent to the UN-Habitat SNP site) and
and services for labour-saving devices the proposed project housing. These
which can support female workloads facilities will include health centres, but
and home management for the disabled. infrastructure such as sports fields and
a community centre for youth and peer
4. The anomalies in the Housing Act of Ke-
educators should also be developed, as
nya regulations with respect to low-cost,
these can support HIV/AIDS programmes
innovative housing are under review by
and other community programmes.
the Ministry of Housing: the Mavoko De-
velopment Advisory Council should keep 6. It is recommended that in a Phase 2, the
abreast of the changes to ensure that the project should bring in the numerous
conceptual issues related to the SDP are stakeholders (industries and NGOs) iden-
incorporated into the new laws. tified in the early years of the project.
It should first be determined if they are
5. An appropriate project management
relevant to this phase. These stakehold-
structure is to be created by UN-Habitat
ers could be part of a social initiative and
and the main partners in a Phase 2 of
can contribute funds and equipment and
the programme, building on the lessons
support development interventions for
learned of the project. Identification of
specific groups.
beneficiaries and credit modalities are re-
quired, but it is recommended that the 7. An environmental impact assessment
project form subcommittees to address is planned, soon to be underway. This
the needs of the youth, female-headed study should rely on past studies con-
households, the disabled, and those liv- ducted under the umbrella of the SNP,
ing with HIV/AIDS. The subcommittees which identified hazards specific to the
can address measures to develop and relevant geographic areas in 2002 and
protect vulnerable groups. For example, discussed how to alleviate them.
it is understood that some facilities will
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
31

ANNEX I: Terms of Reference

1. Background information and in facilitating the implementation phase of


rationale the programme and in capacity building at
both community and municipal levels. Key
The Sustainable Neighbourhood Programme
partners have included building associations
(SNP) started in 2003 as a programme with-
which were established by the target popu-
in the Kenya Slum Upgrading programme
lation during the programme, NGOs special-
(KENSUP). The SNP is a collaboration be-
ized in appropriate technologies, small-scale
tween the Government of Kenya, the Gov-
private contractors and municipalities. The
ernment of Finland and UN-Habitat.
main beneficiaries of the programme were
The SNP’s focus is to improve the lives and to be inter alia the local communities and
livelihoods of the slum dwellers living in slum-dwellers.
the 25 Mavoko informal settlements and
The financial contribution of the Govern-
the Kibera slums with the aim of relocating
ment of Finland was EUR 750,000 while
the slum dwellers to the piece of land (55
UN-Habitat provided additional funding of
acres, L.R. 27664) in Mavoko municipality
USD 160,000. This evaluation is at the re-
made available by the Government of Kenya
quest of the Government of Finland, in its
through a debt swap with the Government
capacity as donor of SNP.
of Finland. The overall development objec-
tive of the SNP is to strengthen the role and 2. Objectives of the programme
capacity of the informal and community
The programme’s objectives and expected
sector in the provision of housing, services
outputs were:
and infrastructure with a view to developing
sustainable neighbourhoods. Objective 1: Enhance the role and capacities
of the communities in the provision of hous-
The KENSUP Secretariat has been in charge
ing, services and infrastructure.
of SNP’s programme coordination, moni-
toring and evaluation. Routine monitor- Expected outputs of objective 1
ing has also been carried out by the SNP
Executive Committee. The Government Four training courses in Sustainable Neigh-
of Kenya has had the overall responsibility bourhood Development (in total 100 train-
of the programme. The obligations of the ees) in the following areas:
Government of Kenya included inter alia al-
• Earth construction techniques (mud-bricks,
location of the required land, provision of
stabilized soil bricks, compressed earth
counterpart staff to work with the develop-
blocks)
ment team. UN-Habitat’s main role has been
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
32 MUNICIPALITY, KENYA

• Low-cost road construction (roads, bicy- Objective 4: To prepare and implement a


cle lanes, footpaths) pilot project in sustainable neighbourhood
development.
• Sustainable water supply (wells, damns
reservoirs, piping, water harvesting, etc.) Expected outputs of objective 4
• Sustainable waste management (com-
• Technical framework of the pilot project
posting, recycling, re-use etc.)
• Financial set-up of the pilot project
Objective 2: Strengthen the capacity of
small-scale contractors and building mate- • Implementation of the pilot sustainable
rials producers in shelter and infrastructure neighbourhood unit (200 dwelling units)
provision. • Selection of small-scale contractors
through competitive bidding
Expected outputs of objective 2
The SNP expected accomplishments were
• Training programme in low-cost building
materials production (compressed earth • Construction of incremental house initi-
blocks; precast stone blocks; ferro-ce- ated by approximately 200 households.
ment roofing channels) (25-30 trainees)
• A model sustainable neighbourhood,
• Contractor development programme for planned, surveyed and partially built.
emerging contractors (25-30 trainees)
• Over 350 women and men trained in
Objective 3: To enhance the capacity of pub- marketable skills in construction.
lic agencies to act as an enabling authority
• A model savings and loans scheme es-
for community-led housing and infrastruc-
tablished to serve the credit needs of the
ture delivery
low-income groups who cannot have
Expected outputs of objective 3 access to bank loans.
• Over 50 key actors in the community-
• An Action Plan to enhance Community-
based housing process (including rep-
Government Partnership in shelter and
resentatives of the government, NGO,
infrastructure development and services
private sector and communities) trained
provision.
in community-driven housing processes.
• Workshop on enhancing community-
• A new paradigm for housing and infra-
driven housing and infrastructure de-
structure development through com-
velopment (for Government, municipal-
munity participation and management
ity, small-scale contractors, NGOs and
demonstrated, tested and evaluated
CBOs), and
2.1 Results of previous reviews
• An Annual Programme for community-
led housing and infrastructure develop- The program has undergone various re-
ment views. The reports are available.
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
33

3. Objectives of the evaluation how well the various activities transformed


the available resources into the intended re-
The overall objective of the evaluation is to
sults in terms of quantity, quality and timeli-
assess the extent to which the objectives
ness. Comparison should be made against
and expected accomplishments of the SNP
what was planned.
have been achieved.
• How well did the activities transform
3.1 Evaluation criteria and evaluation
the available resources into the intend-
questions
ed outputs/results, in terms of quantity,
Assessment of the various aspects of the quality and time?
SNP will be guided by the use of five key • Can the costs of the program be justified
evaluation criteria: Relevance, effectiveness, by the results?
efficiency, sustainability and impact on the
• Were the contributions by the partner
intended beneficiaries.
country and the donor(s) provided as
3.1.1 Relevance planned?

The extent to which the objectives of a de- • Were administrative matters (reports,
velopment intervention are consistent with usage of funds) handled in an efficient
country needs, global priorities, and part- matter?
ners’ and donors’ policies. The question of • Quality of technical assistance?
relevance often becomes a question as to
• Quality of the day-to-day management?
whether the objectives of a program or proj-
Were possible problems in implementa-
ect or its design are still appropriate given
tion adequately addressed?
changed circumstances:
• What was the quality of work planning,
• Were the objectives and achievements of
monitoring and reporting incl. use of in-
the program consistent with the needs
dicators, resource and personnel man-
and priorities of the stakeholders, includ-
agement, financial management, coop-
ing the final beneficiaries?
eration and communication between
• Were the objectives and achievements stakeholders?
of the program consistent with Finland’s
3.1.3 Effectiveness
development policies?
The effectiveness is a measure of the merit
• Were the objectives consistent with Ken-
or worth of an activity, e.g., the extent to
ya’s development policy?
which a development outcome is achieved
• Are the objectives and achievements through interventions. The extent to which
of the program consistent with global a programme or project achieves its planned
goals, commitments and principles? results, i.e., goals, purposes and outputs,
3.1.2 Efficiency and contributes to outcomes.

The efficiency of a program is defined by • Is the quality and quantity of the pro-
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
34 MUNICIPALITY, KENYA

duced results and outputs in accord- Includes both static sustainability—the


ance with the plans, how are the results/ continuous flow of the same benefits set
outputs applied by the beneficiaries and in motion by the completed project or pro-
other intended stakeholders? gramme to the same target groups; and dy-
namic sustainability—the use or adaptation
• To what extent did the programme
of programme results to a different context
achieve its purpose?
or changing environment by the original tar-
• Have the planned benefits been deliv- get groups and/or other groups. It reflects
ered and received, as perceived by all key whether the positive change in the develop-
stakeholders? ment situation will endure.
• Are the results/outputs and the pro-
• Have the benefits produced by the pro-
gramme purpose making a contribution
gramme been maintained?
towards reducing poverty and inequal-
ity, and promoting sustainable develop- • Who has taken over the responsibility of
ment? financing the activities, or have they be-
come self-sustaining?
• Were important assumptions identified?
Were risks appropriately managed, in- • What are the possible factors that en-
cluding flexible adaptation to unforeseen hance or inhibit sustainability?
situations? 3.2 Cross-cutting objectives
3.1.4 Impact
A number of cross-cutting issues need to be
The totality of positive and negative, primary taken into account in carrying out evalua-
and secondary effects produced by a devel- tion studies. They include the need to in-
opment intervention, directly or indirectly, volve local communities in the evaluation
intended or unintended. Impact is the lon- process (participatory evaluation); gender
ger term or ultimate result attributable to a mainstreaming, environmental aspects and
development intervention. The concept of capacity building and/or institutional devel-
impact is closely related to development ef- opment impact.
fectiveness.
3.2.1 Gender mainstreaming
• Has progress been made towards achiev-
Gender aspects should be taken very care-
ing the overall development objective of
fully into account when carrying out an
the programme?
evaluation of any project in which they
• Do the indicators for the overall objective could be of significance. All development
show that the intended changes have actions touch male and female beneficia-
started to take place? ries, and very often these two groups as
well as other groups of beneficiaries as
3.1.5 Sustainability
other sub-groups of beneficiaries will
Durability of positive programme results have different needs, responsibilities and
after the termination of that programme. potential for benefit from the projects.
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
35

The following questions regarding gender • Do women/other vulnerable groups par-


should be considered: ticipate in the different phases of project
implementation? (The number of wom-
• Are the beneficiaries clearly identified?
en employed by the project is not neces-
Sub-groups, socio-economic status, etc.,
sarily an indication of female beneficiary
“poor” and “women” are not homog-
participation).
enous groups, so are more details need-
ed? • Are monitoring and information-gather-
ing gender differentiated?
• Have these groups been consulted?
• Are gender aspects in the project main-
• Have their needs, resources and con-
streamed or are there specific services for
straints to access the project services
women?
been identified?
• How can the access of women/other vul-
• Have solutions been sought?
nerable groups to services and resources
• Where relevant, how well does the pro- be ensured?
ject take account of gender roles in com-
• Have there been capacity-building ef-
munity management?
forts to make local institutions aware of
• How well does it address gender-relat- gender issues, capable to carry out gen-
ed needs that are (i) practical: access to der analysis and implement projects in a
food, water, shelter; social services; paid gender sensitive manner?
work (ii) strategic: reducing inequalities
• Did socio-cultural and gender aspects
in access to certain services; (iii) politics,
endanger the sustainability of the pro-
rights to land and property; credit; edu-
ject during implementation or, especially
cation, etc.?
termination of donor assistance?
• Does the programme respond to real
• Did opportunities for men and women
needs formulated by the intended ben-
to benefit equally from the project con-
eficiary groups?
tinue after its implementation, for exam-
• Have appropriate delivery modes for ser- ple through women’s and men’s partici-
vices to reach all beneficiary subgroups pation in decision-making? (The issue of
been identified and implemented? ownership of the project activities by the
various beneficiary groups and imple-
• Has the traditional division of tasks been
mentation agencies should also be dis-
taken into consideration?
cussed).
• Have changes (by the project) to work-
• How could better results have been
load been considered?
achieved? How could beneficiary par-
• Who has access/control of project in- ticipation as between women and men
puts? have been improved?
• Is training provided to the right groups,
given the project’s objectives?
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
36 MUNICIPALITY, KENYA

3.2.2 Environmental aspects to June 2011. It will focus on processes and


activities of the SNP in Mavoko, Kenya. The
• Many projects impact on the physical en-
analysis should include both technical and
vironment, both directly and indirectly.
financial aspects of the programme. Chal-
For any project to be truly sustainable, it
lenges and lessons learned and recommen-
is important that issues of environmental
dations based on key findings will be pre-
impact are taken into account. The follow-
sented in the evaluation report.
ing are some key questions from which
the most appropriate should be selected: The evaluation will include all the stake-
holders involved in the programme:
Was an environmental impact assess-
ment made?
• Government of Kenya (Ministry of Fi-
• Was environmental damage done by or nance, KENSUP Secretariat, SNP Execu-
as a result of the project? tive Committee, local authority/munici-
• Did the project respect traditional ways pality, and others)
of resource management and produc- • Government of Finland (Ministry for For-
tion? eign Affairs, Embassy of Finland in Nai-
robi)
• Were environmental risks managed dur-
ing the course of the project? Will these • UN-Habitat
continue to be managed? • Key program partners (building associa-
• Overall, will the environmental effects of tions, NGOs, private contractors, munici-
the project’s activities and results jeop- palities)
ardize the sustainability of the project it- • Other possible stakeholders
self or reach unacceptable levels?
5. Approach and Methodology
3.2.3 Capacity building
The consultant is expected to outline the
Capacity development refers to the process details of the proposed methodology in the
by which individuals, groups, organizations draft report and this may include, but is not
and countries develop, enhance and orga- limited to, the following aspects:
nize their systems, resources and knowl-
edge, all reflected in their abilities, individu- • In-depth document review and analysis
ally and collectively, to perform functions, • Interviews with key stakeholders, both
solve problems and set and achieve objec- face-to-face and by telephone and
tives. This is a critical aspect of much of UN- email. Key stakeholders include UN-Hab-
Habitat’s role. itat staff, officials from the embassy of
Finland, national project partners and
4. Scope of the Evaluation
the slum community members involved
This evaluation will cover the activities of in the project
the SNP from its inception period 2003 up
• Field visits to project site in Mavoko
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
37

6. Governance and Accountability The evaluation will be carried out by an in-


dependent consultant recruited through a
The Director, Regional Technical Coopera-
competitive process. The consultant should
tion Division (RTCD) of UN-Habitat will pro-
have at least 10 years professional experi-
vide the overall administration of this evalu-
ence in the field of development and moni-
ation. Additional support will be provided
toring and evaluation. Experience in urban
by the Habitat Programme Manager and
management and slum upgrading projects
the Head, Kenya Unit. The main SNP find-
will be an added advantage.
ings will be presented to the Government of
Finland and UN-Habitat in the form of a final 10. Key background documents for the
evaluation report. evaluation

7. Deliverables and Schedule • SNP Project Document


Output / Activity Timeframe • MOU on administrative arrangements
Presentation of the Draft Report End of third week • Agreements of Cooperation between
Submission of Final Report End of fourth week UN-Habitat and the Government of Fin-
land

The UN-Habitat format for structure and • Mavoko land (L.R. No. 27664)
contents of an evaluation report should be documents
used as a guide when formulating the report. • Project progress reports
The relevant stakeholders will submit com-
• Financial reports
ments on the draft report to the consultant.
• Review reports

8. Timeline • UN-Habitat Monitoring and Evaluation


Guide—Recommended content list for
The evaluation is expected to start in July an evaluation report
2011 and last for a period of four weeks.
• Other documents as requested and rel-
The consultant shall present the final report
evant
to the stakeholders.

9. Professional Qualifications
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
38 MUNICIPALITY, KENYA

ANNEX II: BIBLIOGRAPHY

Aarhus Paige (15-12-11) Slum Residents KEWLAT (undated) Kenya Women Land
to build homes without seeking Access Trust Brief, Nairobi, KEWLAT
government help, Nairobi, Nation
KEWLAT (2008) Sample certificate and
Newspapers
by-laws: Imani Women Housing Co-
Berg Per et al (1997) Sustainable operative Society, Nairobi, KEWLAT
Neighbourhoods-a qualitative model for
Mavoko Municipal Council (April 2005) SNP
resource management in Communities,
Socio-Economic Report, Nairobi
Landscape and Urban Planning 39 (1997)
m117-135, Stokholm. Mavoko Municipal Council (23-06-05)
Minutes of Special Full Council Meeting
CIDA (2000) How to Perform Evaluations
(UN-Habitat and others) , Nairobi, SNP
– Evaluation Work plans, Quebec, Canada,
Canadian International Development Mavoko Municipal Council (2009) SNP
Agency (CIDA) Master Plan Notes, Nairobi
Embassy of Finland (2002) Correspondence Mavoko Municipal Council (undated)
on SNP funding (Embassy of Finland and Mavoko Strategic Development Plan
UN-Habitat), Nairobi, Embassy of Finland Brief, Mavoko
Hayford, Kakra Taylor (undated) Women Miller, Thomas et al (Jan 2011) Evaluation
Land Access Trust, Concept Note of the UN-Habitat Youth Programme
Nairobi, UN-Habitat
KENSUP (undated) Brief on SNP, Nairobi,
KENSUP Moonbeam Youth Training Centre (2010)
Youth Empowerment Programme in
KENSUP (17-12-04) Minutes of Tripartite
Kenya, Progress Report October 2007-
Meeting on SNP) Nairobi, KENSUP
July 2010, Nairobi, YEP
KENSUP (undated) Draft MOU GOK, GoF,
Nordberg, Rainier (2004 & 2012) Handing
UN-Habitat, Nairobi, KENSUP
over Note CTA 2002-2004 & email
KENSUP (2011) Map of the SNP site) interview, Nairobi
Nairobi, KENSUP
Old Mulolongo Housing Co-operative
KEWLAT (undated) Kenya Women Land Society Ltd (31-12-10) Balance Sheet and
Access Trust, PowerPoint presentation, Final Accounts as at 31st December
Nairobi, KEWLAT 2010, Mavoko, CS/No. 11257
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
39

Onyiro George (undated) The Land Factor, SNP (2002-2004)Launching and PR


Nairobi, UN-Habitat summaries, 2002-2004, ( A series of
presentations by UN-Habitat, His Worship
Onyiro George (January 2006) Project
the Mayor, etc. UN-Habitat
Handover Report, Nairobi, UN-Habitat
SNP (2002) Budget 2002-2004, Nairobi,
Onyiro George (2010) Meeting with Six
UN-Habitat
Cooperatives, Nairobi, UN-Habitat
SNP (27-05-04) Executive Committee
Republic of Kenya (July, 2004) National
Meeting, Nairobi, SNP
Housing Policy for Kenya, Sessional
paper No. 3, Nairobi, Government of Kenya SNP (27-05-04) Executive Committee
Meeting, Nairobi, SNP
Republic of Kenya (2005) Kenya Slum
Upgrading Programme (KENSUP), SNP (10-06-04) Executive Committee
Implementation Strategy, 2005-2020, Meeting, Nairobi, SNP
Volume 1, Nairobi, UN-Habitat
SNP (22-07-04) Executive Committee
Republic of Kenya (2005) Kenya Slum Meeting, Nairobi, SNP
Upgrading Programme (KENSUP),
SNP (26-08-04) Executive Committee
Financing Strategy, 2005-2020, Volume
Meeting, Nairobi, SNP
11, Nairobi, UN-Habitat
SNP (21-09-04) Executive Committee
Republic of Kenya (February, 2006)
Meeting, Nairobi, SNP
Architects Proposed Mavoko SNP
(KENSUP) Housing Scheme, Nairobi, SNP (22-09-04) Executive Committee
Government of Kenya Meeting, Nairobi, SNP
Republic of Kenya (May, 2006) Brief on SNP (undated) ERSO MAVOKO Project
Technical Design Refinement for SNP, plan linkages, Nairobi, SNP
Nairobi, Government of Kenya
SNP (from 2004) Cooperatives Financial
Republic of Kenya (April, 2007) Title Deed Reports (6), Nairobi, SNP
SNP, Nairobi, Government of Kenya
SNP (Jan 2005) Village Visit Report, Nai-
Seguin, Anne Marie et al (Dec 2002) robi, SNP
Urban Poverty-Fostering Sustainable
and Supportive Communities, Ottawa, SNP (Feb 2005) Village Visit Report, Nai-
Canada Policy Network robi, SNP

SIDA (2004) looking Back, Moving SNP (11-02-05) Meeting on Social Map-
Forward Evaluation Manual, Edita, ping Exercise (UN-Habitat, ITDG, KEN-
Stockholm SUP, NACHU), Nairobi, SNP
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
40 MUNICIPALITY, KENYA

SNP (March 2005) Village Visit Report, SNP (July 2005) Community Representa-
Nairobi, SNP tives Report, Nairobi, SNP

SNP (March 2005) Follow-up/Monitoring SNP (August 2005) Village Visit Report,
Report, Nairobi, SNP Nairobi, SNP

SNP (April 2005) Follow-up/Monitoring SNP (Sep 2005) Village Work plan, Nai-
Report 1 & 2, Nairobi, SNP robi, SNP

SNP (April 2005) Village Visit Report, Nai- SNP (Sep 2005) Follow-up/Monitoring
robi, SNP Report, Nairobi, SNP

SNP (April 2005) Follow-up/Monitoring SNP (Oct 2005) Village Visit Report, Nai-
Report on CAPs, Nairobi, SNP robi, SNP

SNP (Apr 2005) Cooperatives Savings SNP (Oct 2005) World Habitat Day Prepa-
Group Report, Nairobi, SNP ratory Meeting Report, Nairobi, SNP

SNP (April 2005) Village Work plan, Nai- SNP (Nov 2005) Follow-up/Monitoring
robi, SNP Report, Nairobi, SNP

SNP (May 2005) Follow-up/Monitoring SNP (Dec 2005) MCC and Village Visit Re-
Report on clusters, Nairobi, SNP port, Nairobi, SNP

SNP (May 2005) Village Visit Report, Nai- SNP (2005) Sample Social Mapping Exer-
robi, SNP cise, Nairobi, SNP

SNP (03-05-05) Village Work plan, Nai- SNP (2005) SNP Overview of Project Im-
robi, SNP pact, Nairobi, SNP

SNP (June 2005) Cooperatives Savings SNP (17-01-06) Progress Report (UN-Hab-
Group Report, Nairobi, SNP itat, MCC and SNP), Nairobi, SNP

SNP (June 2005) Village Visit Report, Nai- SNP (Jan 2006) Village Visit Report, Nai-
robi, SNP robi, SNP

SNP (June 2005) Cluster 2 Meeting, Nai- SNP (Jan 2006) Follow-up/Monitoring Re-
robi, SNP port, Nairobi, SNP

SNP (June 2005) Follow-up/Monitoring SNP (09-02-06) Progress Report (UN-Hab-


Report, Nairobi, SNP itat, MCC and SNP), Nairobi, SNP

SNP (July 2005) Follow-up/Monitoring SNP (Feb 2006) Village Visit Report, Nai-
Reports 1-3, Nairobi, SNP robi, SNP

SNP (July 2005) Village Visit Report, Nai- SNP (March 2006) Nakuru/Kitale Ex-
robi, SNP change Trip Report, Nairobi, SNP
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
41

SNP (April 2006) Village Visit Report, Nai- Reports 1-4, Nairobi, SNP
robi, SNP
SNP (02-11-06) Capacity Building and
SNP (April 2006) Cooperatives Merging Communication Training Report, Nairobi,
Report, Nairobi, SNP SNP

SNP (03-04-06) Pre-Cooperative Training SNP (07-11-06) MEMO TO Lars Reuter-


Report, Nairobi, SNP ward on contracts, Nairobi, SNP

SNP (03-04-06) Strategic Planning Train- SNP (Dec 2006) Village Visit Report, Nai-
ing Report, Nairobi, SNP robi, SNP

SNP (May 2006) Report on Strategic Plan- SNP (2006) Summary field visits to coop-
ning Retreat in Mombasa, Nairobi, SNP eratives, Nairobi, SNP

SNP (June 2006) Village Work plan, Nai- SNP (Jan 2007) Follow-up/Monitoring Re-
robi, SNP ports 1 & 2, Nairobi, SNP

SNP (June 2006) Village Visit Report, Nai- SNP (Mar 2007) Follow-up/Monitoring
robi, SNP Report, Nairobi, SNP

SNP (July 2006) Follow-up/Monitoring SNP (March-April 2007) Village Work plan,
Report, Nairobi, SNP Nairobi, SNP

SNP (Aug 2006) Follow-up/Monitoring SNP (April 2007) Cooperatives Formation


Report, Nairobi, SNP Report, Nairobi, SNP

SNP (Aug 2006) Ministry of Housing SNP (April 2007) Cooperative Member
Monitoring Report, Nairobi, SNP Training Report, Nairobi, SNP

SNP (Aug 2006) Follow-up/Monitoring SNP (04-04-07) Management and Super-


Reports 1-44, Nairobi, SNP visory Committee Training Report, Nai-
robi, SNP
SNP (Sep 2006) Follow-up/Monitoring
Report, Nairobi, SNP SNP (April 2007) Pre-Cooperative Training
for Housing Societies Report, Nairobi,
SNP (Sep 2006) Village Work plan, Nai-
SNP
robi, SNP
SNP (May 2007) Village Work plan, Nai-
SNP (Sep 2006) Village Visit Report, Nai-
robi, SNP
robi, SNP
SNP (June 2007) Village Work plan, Nai-
SNP (24-10-06) MEMO to UN-HABITAT,
robi, SNP
Nairobi, SNP
SNP (July 2007) Village Work plan, Nai-
SNP (Oct 2006) Follow-up/Monitoring
robi, SNP
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
42 MUNICIPALITY, KENYA

SNP (July 2007) SNP Executive Committee SNP (04-01-10) Quarterly Report SNP ac-
Meeting to develop selection criteria, tivities, Nairobi, SNP
Nairobi, SNP
SNP (04-01-10) Quarterly report Sep-Dec
SNP (July 2007) Cooperatives Savings 2010, Nairobi, SNP
Group Report, Nairobi, SNP
SNP (19-01-10) Minutes for Meeting (SNP
SNP (July 2007) Awareness Creation Re- and Cooperatives), Nairobi, SNP
port, Nairobi, SNP
SNP (02-02-10) Minutes for Meeting (SNP
SNP (August 2007) Village Work plan, and Cooperatives), Nairobi, SNP
Nairobi, SNP
SNP (04-03-10) Minutes for Meeting (UN-
SNP (2008) Description of six coopera- Habitat, SNP and Cooperatives),Nairobi,
tives, Nairobi, SNP SNP

SNP (04-03-2008) SNP office meeting SNP (03-05-10) Quarterly Report SNP ac-
(UN-Habitat),Nairobi, SNP tivities, Nairobi, SNP

SNP (26-03-08-2008) Analysis of data on SNP (undated) Cooperative Training Pro-


cooperatives, Nairobi, SNP posal, Nairobi, SNP

SNP (20-05-08) Minutes of meeting with SNP (2010) Progress activities summary
UN-Habitat, Nairobi, SNP of the six Mavoko cooperatives, Nairobi,
SNP
SNP (Sep-Dec 2008 & Jan 2009) Activity
Report, Nairobi, SNP UNDP (2002) Results Based Management

SNP (01-04-09 Sample of meeting bud- UN-Habitat (2001) UN-Habitat Founda-


get, Nairobi, SNP tion Project Document (FS-GLO-03-
S19/A, Nairobi, UN-Habitat
SNP (04-05-09) Quarterly report Feb-
April 2009, Nairobi, SNP UN-Habitat (2001) Agreement of Cooper-
ation (UN-Habitat and KEWLAT), Nairobi,
SNP (1-09-09) Quarterly Report SNP ac-
UN-Habitat
tivities, Nairobi, SNP
UN-Habitat (2003) Monitoring and Evalu-
SNP (26-11-09) Report on Meeting (MCC
ation Guide, Nairobi, UN-Habitat
and SNP), Nairobi, SNP
UN-Habitat (2003) Mavoko Land Devel-
SNP (10-12-09) Protest by Mavoko Slum
opment, Nairobi, UN-Habitat
Dwellers, Nairobi, SNP
UN-Habitat (2003) Agreement and Bud-
SNP (2009) Report on May-June 2009 ac-
get (GoF and UN-Habitat) Nairobi,
tivities, Nairobi, SNP
UN-Habitat
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
43

UN-Habitat (2004) Report on the Training UN-Habitat (June, 2005) Financial Prog-
of Community Representatives, Nairobi, ress Report, Nairobi, UN-Habitat
UN-Habitat
UN-Habitat (30-09-05) Progress Report 1
UN-Habitat (29-04-04) First SNP Project March 2004-30 June 2005, Nairobi, UN-
Steering Committee Meeting, Nairobi, Habitat
UN-Habitat
UN-Habitat (2005) Memorandum of Un-
UN-Habitat (28-04-2004) Correspondence derstanding (GoF, UN-HABITAT) Nairobi,
to KENSUP to integrate SNP in KENSUP UN-Habitat
(J. Maseland), Nairobi, UN-Habitat
UN-Habitat (2006) Extract from Report
UN-Habitat (12-05-04) First SNP Steering World Urban Forum 111 Vancouver,
Committee Meeting, Nairobi, UN-Habitat Canada

UN-Habitat (June, 2004) Proposed Budget UN-Habitat (April 2007) Africa on the
Revision (UN-Habitat to GoF), Nairobi, Move- 21st Session of Governing Coun-
UN-Habitat cil, Nairobi, UN-Habitat

UN-Habitat (June, 2004) Report on the UN-Habitat (June, 2007) Financial Prog-
Proposed No-Cost Budget Revision (UN- ress Report, Nairobi, UN-Habitat
Habitat to GoF), Nairobi, UN-Habitat
UN-Habitat (2008) SNP Financial Report
UN-Habitat (2004) Progress Report Execu- as at 31 December 2008, Nairobi, UN-
tive Summary, Nairobi, UN-Habitat Habitat

UN-Habitat (01-09-04) Progress Report UN-Habitat (Feb 2009) SNP Strategic De-
July-August 2004, Nairobi, UN-Habitat velopment Plan, Nairobi, UN-Habitat

UN-Habitat (20-09-04) Six Months Prog- UN-Habitat (undated) Youth Empower-


ress Report 1 March 2004-31st August ment Programme in Kenya, PowerPoint
2004, Nairobi, UN-Habitat Presentation, Nairobi, UN-Habitat

UN-Habitat (17-12-04) Minutes of Tripar- UN-Habitat (30-08-10) Launch and Hando-


tite Meetings on SNP, Nairobi, UN-Habitat ver of Moonbeam Youth Training Cen-
tre and KEWLAT Model Houses, Nairobi,
UN-Habitat (21-01-05) Minutes of the
UN-Habitat
JPPT Meeting on SNP, Nairobi, UN-Habitat
UN-Habitat (Nov 2010) Progress Report
UN-Habitat (01-05-05) Progress Report
November 2010, Nairobi, UN-Habitat
March-April 2005, Nairobi, UN-Habitat
UN-Habitat (Feb 2011) Evaluation of Gen-
UN-Habitat (06-06-05) Minutes of the SNP
der Mainstreaming in UN-Habitat, Nai-
Cluster 2 meetings at ITDG, Nairobi, UN-
robi, UN-Habitat
Habitat
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
44 MUNICIPALITY, KENYA

UN-Habitat (Sep 2011) Evaluation of the YEP (2009) Briefing notes to the Execu-
UN-Habitat Youth Programme and Ur- tive Director- January to June 2009, Nai-
ban Youth Fund, Nairobi, UN-Habitat robi, UN-Habitat

UN-Habitat (2011) SNP History (IN-HABI- YEP (2009) Progress report October 2007-
TAT support staff), Nairobi, UN-Habitat July 2010 sent to GoF, Nairobi, UN-Habitat

UN-Habitat (Dec 2011) Project Status Re- YEP (2011) Database on Trainees, Nairobi,
port for Mavoko SNP, Nairobi, UN-Habitat UN-Habitat

UN-Habitat (03-12-11) Request for a No- YEP (undated) Progress on on-going ac-
cost extension for the SNP, Nairobi, UN- tivities, Nairobi, UN-Habitat
Habitat
YEP (undated) Youth Empowerment Pro-
UN-Habitat (undated) SNP Organigram gram in Kenya, Nairobi, UN-Habitat
with cluster groups, Nairobi, UN-Habitat

World Habitat Awards (2010) Chile-


From Slum to Neighbourhood, Internet
download on Innovation, sustainability and
Transfer
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
45

ANNEX III: LIST OF PEOPLE INTERVIEWED

Altogether, the evaluator interviewed 75 Kanyotu, Julius, Vice-Chairman, Mavoko


people, including members of the 11 coop- Cooperative
eratives43, youth trainees, involving ten face
Karongo, David, KEWLAT Cooperative
to face interviews, one telephone interview,
four focus group discussions and two site Khatumba, Mildred, KEWLAT Cooperative
visits.
Kiilu, Agnes, ex Field Coordinator, SNP
Listed below are some of the individuals par-
ticipating in these activities: Kioko, Mutisya, Chairman, Mavoko Coop-
erative
Adebanjo Modupe, Programme Manager,
Women Land Access Trust/HSO, RTCD, UN- Kiitemwa, Peyter, Community Coordina-
Habitat tor, Chairman, SNP

Alabaster, Graham, former Chief Technical Koigi, Patrick, KEWLAT Cooperative


Adviser, SDP, Water, Sanitation and Infra-
Kubo, Hellen, KEWLAT Cooperative
structure Branch, UN-Habitat
Kusienya, Cassius, Deputy Director, KEN-
Anantha Krishnan, Chief of Partners and
SUP, Ministry of Housing, Republic of Kenya
Youth Section, UN-Habitat
Kyao, John, Member, Mavoko Cooperative
Bech, Susanne, Programme Officer,
Society
Evaluation Unit, UN-Habitat
Kyuli, Janet, KEWLAT Cooperative
Chetambe, Eric, KEWLAT Cooperative
Lugongo, Benson, KEWLAT Cooperative
Ireri, Joseph, KEWLAT Cooperative
Macha Jacqueline, SNP Finance,
Jaaoko, Patrick Ochieng, YEP Member,
UN-Habitat
Kibera
Maigallo, Consolata, KEWLAT Coopera-
Kairu, John, KEWLAT Cooperative
tive
Kairu, Dinah, KEWLAT Cooperative
Maina, Paul, KEWLAT Cooperative
43 For ease of reference, the six original Makau, Pius, Philio, Chairman, Mavoko
cooperatives are referred to as ‘Mavoko
cooperatives’ and the five cooperatives Cooperative
formed when KEWLAT began operations,
are referred to as KEWLAT cooperatives.
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
46 MUNICIPALITY, KENYA

Makali, Peter, Former Town Planner, Ma- Mwanza, Michael, Secretary, Mavoko Co-
voko Council operative

Makau, Paul, Chairman, Mavoko Coopera- Nassur, Asha, YEP member, Kibera
tive Society
Ndegwa, Barack, KEWLAT Cooperative
Malombe, Patrick, Deputy Town Clerk,
Nduku, Teckla, Member, Mavoko Coopera-
Mavoko Municipal Council, Kenya
tive
Maroro, John, KEWLAT Cooperative
Ndunda, Anastasicia, Community Coordi-
Maseland, Dr. Joseph, Human Settlements nator, SNP
Advisor, Regional Office for Africa and the
Ndunge, Victoria, Chairperson, Mavoko
Arab States
Cooperative
Mbinda, Alois, Mavoko Cooperative
Ndungu, Franco, KEWLAT Cooperative
Mlimbo, Veronica, KEWLAT Cooperative
Ngure, Esther, KEWLAT Cooperative
Mohammed, Rajab, YEP member, Kibera
Ngigi, Amos, KEWLAT Cooperative
Mulwa, Angelina, Mavoko Cooperative
Njeru, Evanson, KEWLAT Cooperative
Muraguri, Leah, Director, KENSUP, Ministry
Nujguna, Njeri, KEWLAT Cooperative
of Housing, Republic of Kenya
Njuguna, Margaret, KEWLAT Cooperative
Mukuna, Samuel, Member, KEWLAT Co-
operative Nordberg, Rainier, ex CTA, SNP, UN-Hab-
itat
Musengo, Rose, Mavoko Cooperative
Nyagi, Joseph, KEWLAT Cooperative
Mutembei, Alikamjeri, Member, Mavoko
Cooerative Nyambura, Esther, KEWLAT Cooperative
Muthoni, Rose, KEWLAT Cooperative Nyanjui, Charles, KEWLAT Cooperative
Muthoni, Edith, KEWLAT Cooperative Nyokabi, Ikumgu, KEWLAT Cooperative
Mutunga, Rosermary, KEWLAT Coopera- Nzoiki, Agnes, YEP member from one of
tive the Mavoko Cooperatives
Musyoki, Sarah, KEWLAT Cooperative Nzuki, Josyline, Vice-Chairperson, Mavoko
Cooperative
Mwakima, George, KEWLAT Cooperative
Okongo, Timothy, KEWLAT Cooperative
Mwanbi, David, KEWLAT Cooperative
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
47

Olome, Patrick, KEWLAT Cooperative Von Brentano, Dorothee, Programme Co-


ordinator, Regional Office for Africa and the
Onyiro, George, ex PM, Habitat Pro-
Arab States, UN-Habitat
gramme Manager, Regional Office for Africa
and the Arab States, UN-Habitat Wambua, Grace, KEWLAT Cooperative

Orwa, Joseph, Chairman, Mavoko Coop- Wanjohi, Michael, YEP Member, Kibera
erative
Waweru, Agnes, KEWLAT Cooperative
Otieno, Millicent Auma, Chairperson, Ma-
Yegon, Catherine Khisa, Executive Officer,
voko Cooperative Society
KEWLAT
Oyaro, Mwamba, KEWLAT Cooperative

Sijenyi, Linus, YEP, UN-Habitat


EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
48 MUNICIPALITY, KENYA

ANNEX Iv: detailed methodology and revised


evaluation work plan

Overview of the Intervention being the Government of Kenya, namely the Min-
Evaluated istry of Finance, KENSUP Secretariat, SNP
Executive Committee and local authorities,
From 1988, global conferences have strate-
which was to support management with
gized and laid the policy framework for sus-
counterpart staff; the Government of Fin-
tainable shelter delivery for the urban poor.
land, which funded mobilization and train-
The United Nations Conference on Human
ing activities and UN-Habitat which was
Settlement (Habitat II) held in June 1996,
to facilitate the implementation phase and
challenged governments to use shelter de-
capacity building activities. Two key NGOs
velopment as a tool to break the cycle of
also featured in the project activities. These
poverty, homelessness and unemployment
were: The Women Land Access Trust and
by promoting integrated programs in sup-
the Youth Moonbeam Project. Several NGOs
port of shelter development. The foundation
with specialization in appropriate technolo-
for Habitat II was laid by pioneering housing
gies, small-scale private contractors and mu-
strategies formulated by Habitat and the
nicipalities also participated with the man-
Government of Finland between 1997-93.
agement to provide specialized training.
The Sustainable Neighbourhood Programme
Evaluation Purpose and Objective
(SNP) was functional from 2003-2008 in Ke-
nya. It was funded by the Government of The purpose of the evaluation is to provide
Finland/UN-Habitat, as an integrated pro- feedback to the Government of Finland,
gramme—directed at empowering commu- UN-Habitat and other stakeholders identi-
nities and local authorities to provide hous- fied (by Government of Finland, UN-Habitat)
ing, infrastructure and services to urban with regards to the prior objectives, plans,
poor from Mavoko and Nairobi slums. UN- expectations and standards of performance
Habitat has now recruited an independent set for the project, and also to serve as a re-
consultant to carry out a summative or final search tool for accountability (performance
evaluation of the project. and results) and learning (decision-making
for UN-Habitat programme direction). The
The SNP goal of ‘strengthening the role and
objective of the evaluation as stated in the
capacity of the informal and community
TOR is to assess the extent to which the ob-
sector in the provision of housing, services
jectives and expected accomplishments of
and infrastructure in a sustainable neigh-
the SNP have been achieved.
bourhood’ was to be realized through insti-
tutional arrangements of three key players:
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
49

Responsibilities and Accountabilities same time simple and easy to understand by


all stakeholders.
As the project evaluation is expected to
be a final or summative one, there will be While the evaluation is expected to be in-
more emphasis placed on the degree of dependent and verifiable, it will also be
achievement of the expected results, impact participatory to encourage greater involve-
of the project from 2008 and information ment and multi-stakeholder learning. The
about the general worth or relevance of the evaluator will design questionnaires in line
program. This is in contract to a formative with the UN-Habitat checklists for planning,
evaluation which expects to study more on implementing and reporting in participatory
progress of the project and revision of the evaluation45.
objectives. A summative evaluation means
As UN-Habitat has been in the forefront
gaining an understanding of the project
with the project at the various steps in the
cycle and performance of a project which is
project cycle, the consultant will work un-
no longer operational. The main evaluation
der the overall administration of the Direc-
criterions apply to both summative and for-
tor, Regional Technical Cooperation Division
mative evaluations; differences are as stated
(RTCD), and UN-Habitat. UN-Habitat will
above and reflected in the questions asked.
provide personnel to accompany the consul-
The consultant will be responsible for the tant during interviews and support as need-
draft and final reports by assessing and ed to fill in gaps. Transport to the field will
analysing findings from interviews and be provided by UN-Habitat. UN-Habitat will
documentation research. This means devel- also set up interviews and provide requested
opment of questionnaires which scrutinize documentation to the consultant.
the project to be used in interviews with
Profile of the Evaluation Team Members
the various players. The final report must
meet the standards stated in the UN-Habitat The consultant will rely on the UN-Habitat
Monitoring and Evaluation Guide. The UN- Code of Conduct and the United Nations
Habitat Code of Conduct also applies. In this Evaluation Group (UNEG) remaining profes-
respect, the questionnaires designed will be sional, objective and impartial. The evalu-
aligned to evaluation logic44 and make ref- ation will be assessed in relation to broad
erence to a logic model which responds to quality standards: propriety, feasibility, ac-
the project design as outlined in the project curacy and utility. The consultant has more
document. than 26 working years of experience, mainly
with disadvantaged communities, so is well
The consultant will incorporate all aspects of
prepared for the evaluation of this particular
the TOR related to the evaluation criterion
project. The consultant will be supported by
and a logic model, meaning questionnaires
UN-Habitat staff as decided by them.
for all parties will be exploratory, but at the

44 UN-Habitat (2003) Monitoring and Evalua- 45 UN-Habitat (2003) Monitoring and Evalua-
tion Guide, pages 16-17. tion Guide, pages 35-38.
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
50 MUNICIPALITY, KENYA

Proposed Methodology for key informant interviews with the fol-


lowing:
The consultant will design questionnaires to
be administered rather than handed out, ex- • UN-Habitat staff, officials from the em-
cept in some cases where face-to-face inter- bassy of Finland, national project part-
views are not possible. In these cases email ners and the slum community members
can be used. As several years have lapsed involved in the project
since the project concluded, the consultant
• Government of Kenya (Ministry of Fi-
will place great emphasis on literature re-
nance, KENSUP Secretariat, SNP Execu-
view provided by UN-Habitat and others, as
tive Committee, local authority/munici-
it will be more available and also noting that
pality, others?)
some interviewees’ level of recall may not be
high enough. In addition there will be study • Government of Finland (Ministry for For-
and research on other models for Sustain- eign Affairs, Embassy of Finland in Nai-
able Neighbourhoods, M & E, and gender. robi)
The reliance on literature and documenta- • UN-Habitat
tion will support the consultant in gaining
• Key program partners (building associa-
familiarization with the project. Every effort
tions, NGOs, private contractors, munici-
will be made to find more than one source
palities)
of information with respect to the project
cycle steps and to ask for clarification. Some • Trainers
documentation required includes:
Key informant interviews are selected as
• SNP Project Document they facilitate in-depth exploration of the
various evaluation criteria with respondents
• MoU on administrative arrangements
who are able to understand the subject mat-
• Agreements of Cooperation between ter.
UN-Habitat and the Government of Fin-
The third method of evaluation will be the
land
use of questionnaires to explore group dy-
• Mavoko land (L.R. No. 27664) docu- namics in terms of social mobilization, com-
ments munity commitment, gender issues, and de-
• Project progress reports gree of participation. This type of interview
or focus group discussion will be conducted
• Financial reports
for groups of five to ten persons separated
• Review reports by gender and whether they are youth or
adult. This method is very participative and
• UN-Habitat Monitoring and Evaluation
empowering. It will be used for trainees,
Guide—Recommended content list for
managers, local leaders, and entrepreneurs.
an evaluation report (page 44)
At the end of key informant and focus
• Other documents will be requested group discussions, the respondents will be
The consultant will develop questionnaires asked to make recommendations.
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
51

Finally, the consultant expects to make ob- v. Maintaining confidentiality of UN-Habi-


servations regarding environment, infra- tat and respect for local communities
structure and service quality, where these
vi. Encouraging participation
have been provided by the project. This
method is applicable in sites such as urban Work Schedule to provide Deliverables
housing where outputs can be observed.
The evaluation will be completed within
Validity and reliability of the evaluation will four weeks. Every effort will be made to
be ensured as follows: ensure the field work is done before the
holiday season so that the consultant can
i. Questionnaires will be shared with UN-
prepare the draft.
Habitat prior to use to enable re-design
and cover all issues. Annex a: Bibliography
ii. Triangulating will be put to use, i.e. con- CIDA (2000) How to Perform Evalua-
firming, validating findings by compar- tions—Evaluation Work plans, Quebec,
ing three sources. Canada, Canadian International Develop-
ment Agency (CIDA)
iii. Reliable models will be studied.
UNDP (2002) Results Based Manage-
iv. Comparisons of design with UN-Habitat
ment
mandate by studying UN-Habitat con-
cept papers provided. UN-Habitat (2003) Monitoring and Eval-
uation Guide, Nairobi, UN-Habitat.

Output / Activity Timeframe

Evaluation Plan developed Mid First week


Draft questionnaires developed Mid First week
Documentation study End First week
All field interviews and observations Beginning third week
Presentation of the Draft Report Beginning of fourth week
Submission of Final Report End of fourth week
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
52 MUNICIPALITY, KENYA

Annex b: List of Persons to be Interviewed

To be Interviewed
1 UN-Habitat
2 Government of Kenya point persons (finance, local authorities, etc)
3 Government of -Finland
4 KENSUP Secretariat
5 SNP
6 Women Land Access Trust

7 Youth Program
8 Trainees (males and females) for each course
9 Trainers
10 Homeowners in units constructed
11 Community organizations
12 Cooperatives
13 Housing groups
14 Savings groups
15 Building association
16 Contractors, building materials producers
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
53

ANNEX v: EVALUATION QUESTIONNAIRES

A. To be administered as focus group discussions or key informant interviews to Government of


Finland, UN-Habitat, Government of Kenya, including KENSUP

Question Evaluation Logic Documentation required

1. The SNP was implemented from 2002 and Relevance-design, inclusion of Timeline including delays,
expected to “strengthen the role and capacity stakeholders suspensions
of the informal and community sector in the
provision of housing, services and infrastructure.” Efficiency-investment, activities Minutes of early meetings
To what extent has this goal been met? Fully/ First Curriculums and training
Partly/Not met materials designed
Expected outcomes (27 month period) Design of SNP, association
• 200 HHs start constructing their homes Calendars set
• SNP neighborhood-planned, surveyed & List of beneficiaries
partly built
List of counterpart trainees
• 350 men & women trained: 100 sustainable
house construction, 50 building materials Other as provided
production, water supply, sanitation and
waste management, 50 building materials
& contract management, 200 on the job
training (GOK counterpart staff also get
trained)
• Model saving and loan scheme, model
housing association
• 50 key actors in community based housing
get training in community driven housing
Give reasons for your answers.

2. Project Objectives Effectiveness Monitoring results


Please rate the following objectives in terms of Progress reports
whether or not they were met (fully met, partly
Trainee reports
met/ not met) and give reasons for your answers:
Community feedback letter
Contractor development
programme
Tender documents
Membership lists
Other
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
54 MUNICIPALITY, KENYA

Objective 1: Enhance the role and capacities Activities for Objective 1:


of the communities in the provision of housing,
• Selection of the site for
services and infrastructure (Expected outputs=
the pilot sustainable
Four training courses in Sustainable Neighborhood
neighborhood
Development (in total 100 trainees);Earth
construction techniques (mud-bricks; stablised soil • Preparation of training
bricks; compressed earth blocks); Low-cost road programme
construction (roads, bicycle lanes; footpaths); • Preparation of training
Sustainable water supply (wells; dams, reservoirs; materials
piping; water harvesting etc.); Sustainable waste
management (composting, recycling, re-use etc.) • Selection of candidates for
the courses
• Selection of one training
institution as partner for
the project
• Train community
members in sustainable
neighbourhood
development

Objective 2: Strengthen the capacity of Activities for Objective 2: • Train artisans in low-
small-scale contractors and building materials cost building materials
• Identify an appropriate
producersin shelter and infrastructure provision production
institution (private, public
Expected outputs were: Training programme in low- or an NGO) to act as the • Preparation of the
cost building materials production (compressed focal point for training programme and training
earth blocks; precast stone blocks; ferro-cement programme materials
roofing channels) (25-30 trainees)
• Prepare the curriculum for • Selection of trainees
the training programme,
• Conduct contractor
procure tools and prepare
development
training materials
programme (focusing on
• Identify site and construct cost estimation, pricing,
the Technology Workshop competitive bidding, site
management, contract
• Identify and select,
management and
in consultation with
business management)
communities, the trainees
by giving priority to the • Facilitate access to
most vulnerable dwellers, credit
women and the youth
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
55

Objective 3: To enhance the capacity of public Activities for Objective 3:


agencies to act as an enabling authority for
community-led housing and infrastructure delivery. Review of the current institutional
Expected outputs: An Action Plan to enhance framework for shelter and
Community-Government Partnership in shelter and infrastructure delivery, identify
infrastructure development and services provision; bottlenecks and recommend
Workshop on enhancing community-driven housing measures to eliminate these
and infrastructure development (for Government, constraints
municipality, small-scale contractors, NGOs and
• Prepare an Action Plan
CBOs); An Annual Programme for community-
for developing the local
led housing and infrastructure development;
authorities into an enabling
Estimation of the demand for residential lots
authority for community-
for low-income groups; Assessment of the
driven provision of housing
implementation capacities of responsible agencies
and infrastructure
and local construction industry;Prepare an. annual
programme with an implementation schedule • Preparation of workshop
programme and training
material
• Selection of participants
• Implementing the workshop
on community-driven
housing and infrastructure
development
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
56 MUNICIPALITY, KENYA

Objective 4: To prepare and implement a pilot Activities for Objective 4: • Preparation of a socio-
project in sustainable neighbourhood development. economic profile of the
• Selection of site and
The expected outputs were: Technical framework participating households
allocation of land by the
of the pilot project; Financial set-up of the
Government/city; • Set-up a Building
pilot project; Implement the pilot sustainable
Association
neigbourhood unit (200 dwelling units); Selection • Preparation of design briefs
of small-scale contractors through competitive for standards (plots sizes, • Develop innovative
bidding infrastructure and services); housing finance system
• Preparation of site lay- • Develop cost recovery
out (using participatory plan
planning methods);
• Reinforce the
• Preparation of low-cost organisation of the
building types (using community
participatory design
• Create building brigades
methods);
for self-help house
• Preparation of engineering and infrastructure
designs for services and on- construction
site infrastructure; and
• Assign responsibilities
• Defining criteria for the to community members
selection of participants and define modalities
of work
• Selection of participants
according to the criteria • Preparation of
instructions for building
• Preparation of work
brigades
schedules to monitor
progress
• Provide technical support
and management
• Finalisation of tendering
documents
• Invite small-scale
contractors to bid
• Creation of a Local Contract
Committee
• Evaluation of proposals
and selection of small-scale
local contractors
• Provide technical support to
small-scale contractors
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
57

Design: The design of the SNP called for a Relevance Minutes of early meetings with
new paradigm of community participation and key actors and communities
Inclusion (of stakeholders) in early
management?
stages TNA
Was this achieved?
Surveys
Give reasons for your answers?
Organigram/list of GoK, UN-
Habitat counterparts
Letters bringing on board
other stakeholders, and credit
granting organization
Documentation of early
sensitization process of GOK,
communities on the concept,
credit granting
Other as provided
3. The design of the SNP clearly called for a community Relevance Minutes of early meetings
driven approach. What was the rationale for
Efficiency MOU and changes
KENSUP being in charge of the project?
Calendars set
List of KENSUP officials and
organigram used
Other as provided
4. The design refers to a development team, housing Relevance Documentation
association, and other groups to name a few. Were
Efficiency Lists of members
this formed? Explain.
5. The government’s role was two-fold: land allocation Efficiency- security of tenure Title
and staff to support the project. The land allocation
Surveys
was to be a minimum of 10 hectares in the first
six months of the project: Explain this process, Land allocation to YEP, KEWLAT
justification, delays (and reasons), changes, final
product? What caused delays and changes?
Describe the SNP land allocation to date:
Title, Name of owners, lease or freehold, hectares/
acres, land allocation – YEP, KEWLAT, annual land
rates, services
Legal issues: Government of Finland owning land
and allocating it, receiving funds as payment?
b. Did the government receive an action plan (or Receipts of land rates
participate in preparation of one) to involve the
Timeline including delays,
local authorities so they could provide a counterpart
suspensions
role. If yes, explain the role of this plan. If no, did
this affect the project’s efficiency? Who were the Minutes of early meetings
counterparts in the government and how did they Action plan
fulfill their role?
Other as provided
c. Were the contributions of UN-Habitat and
Government of Finland as expected?
d. Your monitoring role: What role did you take
in work planning, monitoring and reporting,
development of indicators, and communication
between stakeholders?
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
58 MUNICIPALITY, KENYA

6. The implementers (Government of Kenya, UN- Efficiency Institutional framework for


Habitat, and Government of Finland) were expected UN-Habitat, Shelter Afrique,
to review the current institutional framework for Government of Kenya
shelter and infrastructure delivery, identifying
bottlenecks? Is there a policy and framework
for slum dwellers?
7. Government of Kenya: Under which Relevance Government of Kenya
development initiative does this type of project development plan for the
fit? How consistent is it with GOK priorities? What district
about consistency with needs of slum dweller?
Other
8. UN-Habitat: To what extent is an SNP project Relevance Strategy papers
(community driven housing) fit in with your Kenya
Gender policy
strategy, global priorities? Has this changed from
2002? Other
9. Government of Finland: To what extent is an Relevance Strategy papers
SNP project consistent with Finland development
Gender policy
policy? Has this situation changed from 2002?
Other
10. What were the Government of Finland funds of US Efficiency- security of funds Original budget
695, 00.00 to be used for? Were these funds
Expenditure sheets and balance
used as intended? Give reasons for your
sheets
answers?
Correspondence
Your monitoring role: What role did you take in work
planning, monitoring and reporting, development Letters of acceptance, objection
of indicators, and communication between
stakeholders?
Were the contributions of other parties as expected?
11. What were the UN-Habitat funds of US 160,000 Efficiency- inputs and outputs Budget
to be used for? Were these funds provided
Expenditure sheets
and used as intended (including low cost
housing expert)? Give reasons for your answers? Balance sheets
Your monitoring role: What role did you take in work
planning, monitoring and reporting, development
of indicators, and communication between
stakeholders?
Were the contributions of other parties as expected?

12. What was the beneficiaries’ expected contribution? Efficiency- inputs and outputs Budget
Was this delivered? Why or why not?
Expenditure sheets
Trainees
Balance sheets
Youth Empowerment Programme land
KEWLAT land
13. Sustainability: With the project ended, who have Environmental impact study
you handed over to?
Situational analysis
How will outputs be maintained?
Handover documents
How will financing be maintained?
How will incomplete interventions be carried out?
Since, Government of Finland owns the land, how
will services be delivered in the future?
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
59

14. Cross-cutting issues: Impact, Relevance, Sustainability Selection sheets


How does your project activity define ‘poor’? How Feedback letters
do you make sure the ‘poor’ benefit?
Cross-cutting issues: Impact, Relevance, Sustainability Selection sheets
In the activities carried out so far , how did you Feedback letters
ensure:
1. Community participation in management
2. Community participation in selection of
beneficiaries
3. Gender benefits – practical and strategic

B. Interviews and On-site visits with YEP, KEWLAT)

1. Your project site is situated on the SNP land: Please explain how your Relevance Transfer documents
activity started? Were you allocated or donated land?
Efficiency Sales documents
2 Explain your project briefly in terms of management (formal and informal Relevance Organogram
structures). How are you linked to:
Efficiency Project description
Government of Finland (land owners)
UN-Habitat (which departments)
Others
3. Describe the activities you have been carrying out. Describe how they are Relevance Project description
linked to the SNP.
Effectiveness
4. Explain legal aspects of your being on the SNP land: titles, sub-titles, Relevance Documentation
payment, land rates, MOUs. Are you satisfied with these arrangements?
MOU
Explain.
5. Explain the process of beneficiary selection for training, committee Efficiency Selection list
representation and land ownership/rental? How were the beneficiaries
Mandates
for training selected? Explain the selection, vetting, security required.
How did you ensure you reached the original intended beneficiaries and Titles
involved women? Was there a selection committee?
6. Cross-cutting issues: Impact, Selection sheets
Relevance,
How does your project activity define ‘poor’? How do you make sure the Feedback letters
Sustainability
‘poor’ and women benefit? How does your project support the youth?

7. Review of SNP documentation ( Youth Empowerment Programme, Relevance TNA


KEWLAT) and Interviews
Effectiveness, Trainers
How well did the TNA, Curriculums, Trainers support the development efficiency, impact
Curriculums
of a sustainable neighborhood (community driven)? Please rate each in
terms of the quality, quantity and time spent delivering? Post training reports
Structures
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
60 MUNICIPALITY, KENYA

ANNEX vi: sustainable neighbourhood


programme nairobi plot project
budget implementation phase)
Source of Funding: Government of Finland

Budget Description 2003 2004 2005 Total Total


Line
w/m USD w/m USD w/m USD w/m Budget
441 Personnel
1101 Coordinator/CTA (L5) 6 70,650 12 141,300 6 70,650 24 282,000

1151 Consultants 15,000 15,000 15,000 45,000

National Professional

1701 Construction Manager 6 9,000 12 18,000 2 9,000 20 36,000

1702 Engineer 4 6,000 12 18,000 2 9,000 18 33,000

1703 Community 5 7,500 12 18,000 2 9,000 19 34,000


Development

1704 National Consultants 2 8,000 3 12,000 3 12,000 8 32,000


19 Component Total 17 116,150 39 222,300 9 124,650 65 463,100
443 Training & Capacity
Building
3201 Group Training 11,000 11,000 15,000 37,000

30 Component Total 11,000 11,000 15,000 37,000

444 Equipment and tools

4101 Expendable Equipment 1,300 2,363 5,137 8,500

4201 Non-expendable 30,000 30,000 5,000 65,000


Equipment

4301 Premises/Tehcnology 10,000


Workshop

Component Total 41,300 62,363 10,137 113,800

445 Miscellaneous

5101 Operation & 1,000 2,200 2,000 5,200


Maintenance of
equipment

5201 Reporting Costs 0 0 10,000 10,000


EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
61

5302 Information & 2,040 6,195 5,040 13,275


Evaluation

5301 Sundry 501 677 5,164 6,342

5401 Direct costs 5,000 5,000 5,000 15,000

59 Subtotal 8,541 14,072 27,204 49,817

99 Project Total 176,991 309,735 176,991 663,717

Programme Support 23,009 40,265 23,009 86,283


Cost (13%)
TOTAL BUDGET 200,000 350,000 300,000 750,000
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
62 MUNICIPALITY, KENYA

ANNEX viI: sustainable neighbourhood


programme-nairobi FINANCIAL
REPORT AS AT 31 DECEMBER 2008
Source of Funding: Government of Finland

Total Actuals Actuals Actuals Actuals Actuals Actuals Budget


Budget 2003 2006 2007 2008 2011
line
 Description Budget 2004 2005
US$ US$ US$ US$ US$ US$ US$ US$
1000 Personnel                

1101 Co-ordinator       -      
(7)

1102 International Expert 76,985      
113,298 23,343 12,970 -
Chief Technical
1103 43,630        
Advisor 218,371 118,741 56,000

1151 Consultants     -        
-
Administrative
1301        
Support Staff 47,454 7,856 22,318 17,280

1302 Driver      
15,826 5,417 1,202 9,183 25

1500 Official Travel     -        


-
Construction/Project
1701        
Manager 70,323 28,973 34,588 6,762

1702 Engineer        
31,467 29,233 3,068 (834)
Community
1703        
Development 13,201 1,457 9,514 2,230

1704 National Consultant   -        
9,999 9,999
Total Project
1900  
Personnel 519,939 120,615 223,562 131,596 41,904 2,255 -
2000 Sub Contracts                

2101 Demo Houses - - - - -  
40,000 40,000

2102 Support to CSO - 0 - - -  


- -
Support to region-
2201 - 0 - - -  
wide activities - -

2900 Total Sub Contract - - - - -  
40,000 40,000
3000 Training                
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
MUNICIPALITY, KENYA
63

Three Mavoko SNP



3201 coordinators (2009-  
106,163 27,829 78,116 (69,038) 39,809 9,197 20,250
2010)
Training and
3202            
Capacity Building 15,553 15,553


3900 Total Training -
121,716 27,829 78,116 (69,038) 39,809 35,803
9,197

4000 Equipment and Tools            


-
Expendable
4101        
Equipment 5,194 5,194
Non-Expendable
4201 16,899      
Equipment 43,921 23,198 2,324 1,500
Technology

4301 Workshop and 352        
522 51,798 (51,628)
Model House
Estb. Of Community
4302 Centre and Site              
-
office

49.00 Total - Equipment - -
49,637 17,251 28,392 54,122 (51,628) 1,500

50.00 Miscellaneous            
- -
Operation and

5101 Maintenance of  
15,617 1,000 1,721 542 2,164 1,200 8,990
Equipment

     
5201 Reporting costs 403 403      
Information and
2,759
5202 Evaluation 27,228 23,564 (952)       1857

75
5301 Sundry 15,741 9,334 1,332     289 4,711

   
5401 Direct Costs 1,055 1,055 -      
Total -
59.00 Miscellaneous 60,044 2,834 34,953 2,504 542 2,164 1,490 15,558

99 Project Total 791,336 140,700 314,736 266,338 (78,221) 44,228 10,687 92,861
UN-Habitat AOS
  (13%) 102,873 18,291 40,916 34,624 (10,169) 5,750 1,389 12,072

100 Grand Total 894,209 158,991 355,652 300,962 (88,389) 49,977 12,076 104,933

 Calendar of Payments EURO USD            


 2003: Total cash receive ( as at
31/12/03) 200,000 235,440            
 2005: Total cash receive ( as at
31/12/05) 200,000 239,260            

  750,000 894,210            
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
64 MUNICIPALITY, KENYA

ANNEX viII: sustainable neighbourhood


programme TIMELINE

Preparatory Phase (3 months) 1 August • Establish financial mechanisms and cost


2002-31 October 2002 recovery systems;

The most important activities during this • Train municipal staff in community par-
phase are: ticipation and mobilization;
• Analyse bottlenecks for Community-
• Conduct consultations with the Govern-
Government Partnerships and formu-
ment/city to allocate land for the pilot
late an Action Plan to eliminate the con-
Sustainable Neighbourhood Unit and the
straints; and
Technology Workshop;
• Initiate planning of the new Sustainable
• Identify and select land for the pilot Sus-
Neighbourhood.
tainable Neigbgourhood and the Tech-
nology Workshop; Phase II - Pilot Implementation (18
months) 1 May 2003-31 October 2004
• Identify implementing partners (public,
private and community sector); The most important activities include:
• Prepare and negotiate MOU’s with im-
• Organise a workshop on community-
plementing partners; and
driven housing process;
• Identify training institutions and exper-
• Plan, organise and manage self-help
tise at the local level and initiate the re-
construction of houses;
cruitment process for local staff.
• Plan, organise and manage community-
Phase I - Capacity building (6 months) 1
led infrastructure development and ser-
November 2002 -30 April 2003
vice provision;
The most important activities during this • Provide technical support to small-scale
phase are: contractors engaged in project activities;
• Prepare the curriculum and training ma- • Recommend policy reforms to eliminate
terial for the training programme; erect harmful constraints imposed by the reg-
the Technology Workshop; and com- ulatory framework that hinder low-in-
mence training activities; come groups access to shelter.
• Organize Building Associations (Neigh-
bourhood Development Committees);
Activities Estimate 2009 2010
Cost
(USD)
Phase I Phase II Phase III

F M A M J J A S O N D J F M A M J J A S O N D
1. Project Management (WSIB, MDB) 30,000
Establishment of Core Management Team/
Board with appropriate structures for roles and
responsibilities
Determination of entry points of Stakeholders
Undertake continuous monitoring of project
activities
2. Community Mobilization (Youth 20,000
Empowerment Programme, KEWLAT,
SNP)
Formation and registration of community-based
Housing Cooperatives
Socio-economic surveys and analyses
Promotion of Saving Schemes by Community-
based Housing cooperatives
(NO-COST EXTENSION)

3. Development of Infrastructural 200,000


Services (SNP)
Appraisal/selection of options
ANNEX IX: IMPLEMENTATION SCHEDULE

Systems Designs
Costing
Implementation
4. Land Administration (SNP, MDB, Youth 50,000
Empowerment Programme, KEWLAT)
Determination of land requirements by
stakeholders
MUNICIPALITY, KENYA
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO
65
66
Activities Estimate 2009 2010
Cost
(USD)
Phase I Phase II Phase III

Demarcation of Land/Plot for development by


MUNICIPALITY, KENYA

stakeholders
Determination of Desirable Land Tenure
Options
Environmental Impact Assessment
5. Development and Construction of 1,510,000
Housing Units (SNP, Youth Empowerment
Programme, KEWLAT)
Development of Low-cost (pro-poor) House 10,000
Plans
Preparation of Implementation Plans by 5,000
stakeholders
Identification and Production of low-cost 55,000
building materials
Develop housing financing packages
Determine potential sources of funding
Develop labour-intensive construction 190,000
EVALUATION OF THE SUSTAINABLE NEIGHBOURHOOD PROGRAMME IN MAVOKO

modalities
Implementation –250 unit @ USD 5,000.00 1,250,000

6. Reporting, dissemination & capacity 100,000


building (All)
Development/Management of toolkits
Training in construction systems, operation and
maintenance
Develop capacity building interventions based
on assessment
Undertake capacity building activities
Evaluation Report 4/2012
Evaluation of the Sustainable Neighbourhood Programme
in Mavoko Municipality, Kenya

Evaluation of the
Sustainable Neighbourhood
Programme in Mavoko
Municipality, Kenya

HS:HS/003/14E

UNITED NATIONS HUMAN SETTLEMENTS PROGRAMME


P. O. Box 30030, 00100 Nairobi GPO KENYA
Tel: +254-020-7623120 (Central Office)
Fax: +254-20-76234266/7
infohabitat@unhabitat.org
WWW.unhabitat.org/publications

www.unhabitat.org FEBRUARY 2012

Você também pode gostar