ACTIVITIES OF COMMISSIONING

Air Leakage Test


Hydro Test Commissioning Checkpoints Equipments Trial Run Refractory Dry Out

Chemical Cleaning
Boiler Safety Protection Checking

ACTIVITIES OF COMMISSIONING

Grid Air pressure Drop Study


Control Instrumentation Checking Boiler Light up & Coal Firing Steam Blowing Safety Valves Floating

Steam Dumping
Synchronization

ACTIVITIES OF COMMISSIONING

Auto loop commissioning


Reliable Test run Performance test run

Air Leakage Test

Pressure parts

The aim of air leak test is to ensure that erection


of the pressure parts is completed and no major leaks are there.

Air leak test is conducted by introducing air into


the boiler pressure parts at a pressure of

approximately 7 - 8ksc

Air Leakage Test

Non Pressure parts

The purpose of air leak test of air, gas ducting & ESP
is to ensure leakage proof in ducts, welding joints, flange joints to ensure efficient operation of fans, boiler

Hydro Test All the pressure parts of the boiler, which are

subjected

to

high

operating

pressure

during

operation, should be checked to ensure that they withstand the high pressure so hydraulic test is conducted

Commissioning Checkpoints
Checklist have to be prepared for all equipments and all activities. After completion of equipments erection, check points to be made and the trial run of equipments

shall commence

Equipments Trial Run

No-load trial & load trials of following equipments are

completed after fulfilling the commissioning checkpoints

ID fan SA fan Loop seal blower

PA fan Feed pumps

Fuel feeders

Refractory Dry Out

In a boiler furnace, during the phase of erection


refractory is laid in many areas like furnace, second pass areas, cyclones, bed ash cooler etc,

Refractory drying is to be carried out by utilizing either light oil or gas

Chemical Cleaning During the process of erection, there might be entrainment of unwanted material like rust, dirt, mill

scale etc.

The internal surfaces of a boiler where demineralized water of high purity is to be evaporated, should be maintained free of all material which come in the way of efficient heat transfer and thus effect generation.

Chemical Cleaning cleaning procedures aim to removal of rust, dirt,

The

sand and also any foreign material entrained in the contour.

The

cleaning can be achieved by an alkali boil out or

alkali flushing and acid cleaning.

Boiler Safety Protection Checking Check the following equipments are having

interlocks

ID fan-I & I vs. loop seal blower

loop seal blower delivery damper open vs. loop


seal blower

IID Fan vs. SA Fan

ID Fan vs. PA Fan

Boiler Safety Protection Checking Check the following equipments are having

interlocks

PA Fan vs. Fuel Feeders

Drum Level very LOW vs. MFT


Deaerator Level Low vs. Feed pump Drum level Very High vs. Turbine

Furnace pressure Very high vs. MFT

Boiler Safety Protection Checking Check the following equipments are having

interlocks

Furnace pressure Very low vs. MFT

Grid Air pressure Drop Study Grid air pressure drop study is nothing but finding out the pressure drop across grid nozzle at different

air flows

The pressure drop values measured in grid pressure drop study are used to find out the bed height when the boiler is in running condition. i.e. at a particular air flow

Control Instrumentation Checking


Before boiler light-up, all control instruments have to

be checked i.e. to ensure whether the remote


operation of all equipments is in proper condition

Boiler Light up & Coal Firing Start up sequence

Steam Blowing
The objective of steam blowing is to remove dirts, loose

material, cutting bars etc, that might have been


entrapped in Super Heaters, Steam piping, re-heaters during manufacture, storage, erection at site.

Failure to remove the debris may result in damage to turbine blades, valves etc

Safety Valves Floating


The objective of the Testing Schedule is to test the safety valves by actually floating and ensuring that safety valves lift at recommended values.

Steam Dumping Steam dumping is nothing but allowing steam from re-heater through MSL and by by-passing the HP turbine the steam is send to re-heater via HRH line

and from re-heater it is send to condenser via CRH


line by by-passing IP turbine and LP turbine.

During initial commissioning steam dumping is done to achieve steam purity.

Steam Dumping Till achieving purity, the steam can be allowed to drain from CEP O/L to open drain. After achieving purity it can be taken to close circuit.

Synchronization After completion of all activities synchronization of the unit shall commence Synchronization is nothing but matching the

generator frequency with grid frequency using


syncro-scope

Reliable test Run Reliability run is Seven (7) days of Continuous Power Plant operation at various loads in which 72

hrs at full load and 2 hrs at 110% MCR capacity to be


demonstrated.

During this period two tripping allowed and after tripping

of the plant is plant to be

synchronization within 4 hrs to be demonstrated,

Performance test Run

Boiler performance test run is conducted

For For

understanding the current level of performance

of the boiler,
any trouble shooting of the boiler for

performance deviations

For proving the performance guarantees