Escolar Documentos
Profissional Documentos
Cultura Documentos
VOLUME 1
14 May 2008 Hotel Mtropole Brussels
BGGG - GBMS
BBRI
Proceedings of the International Symposium Ground Anchors Limelette test field results 14 May 2008, Brussels, Belgium Volume 1
TABLE OF CONTENTS
PREFACE INTRODUCTORY ADDRESS ORGANISATION WORKING GROUP GROUND ANCHORS AKNOWLEDGEMENTS CONTRIBUTIONS General Framework and Viewpoint with regard to Ground Anchors, Soil Nails and Tension Piles Prof. J. Maertens (Jan Maertens bvba & K.U. Leuven) Ground Anchors : Overview of Types, Installation Methods and Recent Trends Ir. F. De Cock (Geo.be) Full Scale Load Test Program in Limelette : Overview of the Test Campaign, Set up & General Results Ir. N. Huybrechts & Ir. O. Tomboy, (BBRI), Prof. J. Maertens (Jan Maertens bvba & K.U. Leuven) & Prof. A. Holeyman (UCL) Excavation of the Anchors : Measurements and Observations Ir. O. Tomboy & Ir. N. Huybrechts (BBRI) Integrated Analysis of the Load Test Results & Suggestions for a Harmonised Anchor Design and Test Methodology in Belgium in the Eurocode 7 Framework Ir. N. Huybrechts, Ir. M. De Vos & Ir. O. Tomboy (BBRI) & J. Maertens (Jan Maertens bvba & K.U. Leuven) Practical Experience of TUC RAIL with Ground Anchors and Micro-Piles Ir. W. Maekelberg, Ir. Q. Bollens, Ir. J. Verstraeten, Ir. F. Theys, E. De Clercq (TUC RAIL) & Prof. J. Maertens (Jan Maertens & Partners bvba & K.U. Leuven) Experience with Ground Anchors of the Federal Public Buildings Service Ir. Ph. Debacker (Federal Public Buildings Agency) Experience with Ground Anchors of the Flemish Ministry Ir. I. Marin (Ministry of Flemish Community) Design Guidelines for Non-driven Tension Piles Underneath under Water Concrete Slabs Ir. A.C. Vriend, reporter C-152 & Accon (NL) Experience in France with Ground Anchors Prof. J.P. Magnan (LCPC, F) Application of Ground Anchors, Nails and Tension Piles in Europe and Current Status of the EN 1537 Ground Anchors Dr.-Ing. W.R. Linder Chairman of CEN TC 288 Execution of Special Geotechnical Works & Brckner Grundbau (DE) Dr. Caesar Merrifield, Convener of CEN TC 288 WG 14 Anchors & Coffey Geotechnics (UK)
PREFACE
Ground anchors are commonly used in Belgium in different building and civil engineering applications (anchorage of retaining walls, submerged structures, quay walls, stabilisation of slopes, ). Unfortunately, up to now no Belgian geotechnical standards, which deal with such elements, exist. As a consequence, the project specifications of different owners integrate generally, without coherence, different design and test methodologies coming from other countries, mostly from French and German standards. In addition a lot of new anchoring techniques, for which the current geotechnical codes are in general not yet adapted, appeared the last decade on the Belgian market. Particular situations are those where not all the anchors are tested and/or pre-stressed. Finally, within the framework of the European standardisation, which is fully developing, the construction sector experienced a strong need for a better understanding of the applied anchoring techniques and appropriate design methods, in particular for the establishment of the Belgian national annex of the Eurocode 7. All the above-mentioned aspects encouraged the Belgian Building Research Institute (BBRI - CSTC - WTCB) to undertake the establishment of a uniform guidance for the execution, the design and the testing of anchoring systems in Belgium. In order to address this issue the BBRI initiated in 2004 a national research project on ground anchors. The project is guided by an inter-professional Working Group under supervision of the project partners K.U. Leuven (Prof. J. Maertens) and UCL (Prof. A. Holeyman). Financial support for the research project has been obtained from the Belgian Federal Public Service Economy and the Belgian Normalisation Institute. Backbone of the research project is the extended real scale load test campaign on approximately 50 ground anchors performed at the proof station of the BBRI in Limelette. During this symposium the various aspects of this extended load test campaign in Limelette (B) will be reviewed : soil investigation, anchor installation methods, load testing and interpretation, as well as observations related to the excavated anchors. Suggestions for an approach to design and test ground anchors in Belgium following the Eurocode 7 principles will be put forward. Moreover attention will be paid to the experience with ground anchors of three main organisations on the Belgian building market: Tuc Rail, the Federal Public Buildings Service, and the Ministry of the Flemish community. Finally three contributions from neighbouring countries (NL, F & DE) will deal with developments in anchoring techniques and design approaches in their country and/or in Europe. It is the hope of the organizers that the results of the Limelette load test campaign and the discussions held during this international symposium might be of value in the development of European geotechnical standardization. The organization committee
INTRODUCTORY ADDRESS
Research has historically been performed in Belgium by common efforts of independent bodies and individual contractors. It is only recently that the BBRI introduced the concept of more global research projects starting a few years ago with the research on screw piles, and the development of new guidelines for the design of piled foundations in the frame of the NAD of the EC7. In this context, the creation of the Belgian Federation of Foundations Contractors (ABEF) has filled in a gap as corresponding partner to the BBRI and other Federal bodies, in order to globalize the reflections and interests of the Foundation Industry, as a whole. This can be considered as a major achievement and a clear progress towards the past. Until recently, as stated by Nol Huybrechts, Belgium was characterized by the absence of codes or guidelines. This situation, which the contractors relatively easily could deal with, was judged, with some reason, dangerous and difficult by administrations and consulting offices. It was also difficultly compatible with the introduction of the European codes and norms. The BBRI has launched several projects in order to remediate this situation, inscribing its efforts in the global perspective of the Eurocodes. ABEF naturally contributed to consolidate the Contractors views, adding some entrepreneurial perspective to these efforts. ABEF was created in 1998 by 6 founding members, gathering the biggest contractors in the field of Deep Foundations. It has welcomed in the meantime 6 new members, and currently represents 80 % of the Belgian Deep Foundations market. Establishing a solid base for sound competition and reliable and safe execution of deep foundations is our global objective. Contributing to this research is part of this global objective. Other concrete steps over the last years are: o Work out a specific education program for workmen of the different members together with VDAB/FOREM structured around 3 modules corresponding to 3 levels of education. o Develop common Working Conditions in order to improve the contractual and technical quality of the relationship with the clients/general contractors. o Actively participate in the different working groups and research programs TIS National Annex of the Eurocode 7 (piles) Research Program on Screw Piles Research Program on retaining walls o Participate in the activities of the European Federation of Foundation Contractors and other international Working Groups TC288: Bored piles and Slurry Walls Contract & Qualification Working Group of the EFFC As President of ABEF, I am particularly pleased to welcome you all, to this seminar. What will be presented today is the result of years of efforts, installation and testing which the Deep Foundation Industry has contributed to both financially and intellectually. We hope you will benefit of this investment. Enjoy your stay in Brussels. ir Maurice Bottiau ABEF President BGGG/GBMS Vice-President Franki Foundations Group Belgium Group Commercial Director
ORGANIZATION
SYMPOSIUM ORGANISING COMMITTEE
Ir. G. Breyne, Chairman of the Technical Committee Structural Work of the Belgian Building Research Institute (BBRI) & SERCK Prof. A. Holeyman Catholic University of Louvain (UCL) Ir. N. Huybrechts, Belgian Building Research Institute (BBRI) Prof. C. Bauduin Besix & University of Brussels (VUB) Ir. M. Bottiau Chairman of ABEF (Belgian Member Society of EFFC) & Franki Geotechnics B Prof. J. Maertens Jan Maertens bvba & Catholic University of Leuven (K.U.Leuven) Ir. G. Simon Ministry of Equipment and Transport of the Walloon Region, Geotechnical Direction Ir. O. Tomboy Belgian Building Research Institute (BBRI)
ACKNOWLEDGEMENTS
The BBRI staff, responsible for the research program ground anchors, wishes to thank: for the financial support of the research project on Ground Anchors: - The direction of the Belgian Building Research Institute - The Belgian Federal Public Service Economy - The Belgian Standardization organization NBN - The sponsors of the test program in Limelette, in particular: ABEF (financial contribution) BACHY (financial contribution & installation on own cost) CVR (installation on own cost1) DENYS (installation on own cost) DSI (strands, Dywidrill hollow bars and hydraulic jacks) EURODRILL (financial contribution) ISCHEBECK (titan hollow bars) FONDEDILE (financial contribution) FONTEC (financial contribution) FREYSSINET (strands and hydraulic jacks) OLIVIER (financial contribution) PROFFUND (financial contribution) SMET F& C (financial contribution)
for the project elaboration: - The project partners K.U.Leuven (Prof. J. Maertens) and UCL (Prof. A. Holeyman) for their expertise during the research program - The Working Group Ground Anchors (practical elaboration of the project) - Mr. A. Bernard, Mr. R. Bonsangue and Mr. C. Verbeke from the Belgian Building Research Institute (for their technical support and contributions, and their hard and fine work during the whole project).
for the development of the inclined CPT device and the performance of the inclined CPT: - Ministry of Flanders, MOW, Geotechnics Division
for the organization of the Symposium Ground Anchors Limelette test field results: - The Symposium Organizing Committee
CONTRIBUTIONS
BBRI
BGGG GBMS
General Framework and Viewpoint with regard to Ground Anchors, Soil Nails and Tension Piles
Prof. Ir Jan Maertens Jan Maertens & Partners bvba and KU Leuven
1.
INTRODUCTION
When starting the BBRI research program on ground anchors there was a lot of discussion within the Working Group concerning the types of anchors to be tested. This was mainly due to the fact that there is no clear definition and/or classification of ground anchors. So the difference between ground anchors, soil nails and tension piles is not always clear. The existing European Standards for ground anchors, micropiles and soil nailing contain a lot of valuable information. However a lot of cases exist which are not covered by the existing execution standards and/or by Eurocode 7.
2.
Figure 1: sketch of a ground anchor details of anchor head and head protection omitted.
Chapter 9.7. acceptance test: Each working anchor shall be subjected to an acceptance test. The objectives . Comment : According to EN 1537 1999 a ground anchor has an anchor head, a free anchor length and a fixed anchor length and has to be subjected to an acceptance test.
General framework and viewpoint with regard to ground anchors, soil nails and tension piles
Chapter 3 : Terms and definitions 3.15. soil nail: reinforcement element installed into the ground , usually at a sub-horizontal angle that mobilises resistance with the soil along its entire length. Chapter 9 : Supervision, testing and monitoring 9.3.2.1. The frequency and procedures for soil nail load testing should be based on a consideration of the consequence of failure, as defined in EN 1990 , EN 1997 and EN 1990. 9.3.2.2. Table 1 describes the principal types of soil nail load tests, their purpose, when they are required and actions to be taken in the event of an noncompliant test result. Annex A gives guidance on test procedures, acceptance
General framework and viewpoint with regard to ground anchors, soil nails and tension piles J. Maertens 14.05.2008 p. 4/9
criteria and the equipment to be used for soil nail load tests. Table 2 suggests the frequency of soil nail load tests based on the category of geotechnical structure.
General framework and viewpoint with regard to ground anchors, soil nails and tension piles
3.
General framework and viewpoint with regard to ground anchors, soil nails and tension piles
- Prestressing : not possible. Comment : This anchor types should be considered as tension piles (= micropiles working in tension) or soil nails. The major problem with ground anchors in Belgium is that actually: - there is no clear definition of a ground anchor; - the design is done for all types of anchors with almost the same unit shaft resistances and with the same factors of safety. So in most cases the execution method and the number of tests is not taken into account in the design.
4.
PROPOSAL
In order to cover all types of ground anchors which are actually installed in Belgium the following classification is proposed : - prestressed ground anchors; - passive ground anchors; - tension (micro)piles; - soil nails. a) Prestressed ground anchors : - prestressed ground anchors may have a tendon element of high strength or low strength steel. - they always have a free length and a fixed length; - the fixed length is installed behind the so called active wedge and in this way that the necessary factor of safety is available for the overall stability; - they are always tested. When testing is not possible due to an excessive deformation of the retaining wall or the reaction system a higher value of the safety factor has to be introduced. - they are always prestressed by means of a hydraulic jack. b) Passive ground anchors: - passive ground anchors always have a tendon element of low strength steel; - they always have a free length and a fixed length; the fixed length is installed behind the so called active wedge and in this way that the necessary factor of safety is available for the overall stability; - the number of tests to be performed has to be clearly specified in the tender documents and/or in the method statement; - it has to be demonstrated that the displacement of the anchor head is smaller than the allowable displacement of the retaining structure. c) Tension Piles: - tension (micro)piles may have a tendon element of high strength or of low strength steel; - they have only a fixed length;
4.1. Classification
General framework and viewpoint with regard to ground anchors, soil nails and tension piles
- the length of the piles is determined in this way that the necessary factor of safety is available for the overall stability, cfr. figure R 66-1 from EAU Recommendations.
- the number of tests to be performed has to be clearly specified in the tender documents and/or method statement. Tests on working piles can only be performed for vertical piles. For inclined piles a free length of min. 2 meters has to be provided ( = especially installed piles); - it has to be demonstrated that the displacement of the pile head is smaller than the allowable displacement of the retaining structure. d) Soil nails: - soil nails have always a tendon element of low strength steel; - they have only a fixed length; - soil nails are used as soil reinforcement and not as anchors.
4.2. Design
The ultimate skin friction over the fixed length is determined taking into account the applied drilling and injection technique. The factors of safety to be introduced are determined based on the type and number of executed tests : - preliminary tests - tests on sacrificial anchors - acceptance tests on working anchors.
General framework and viewpoint with regard to ground anchors, soil nails and tension piles
- suitability tests on working anchors?? (= not foreseen in EC7) - acceptance tests on all working anchors. b) Passive ground anchors: - preliminary tests on sacrificial anchors - suitability tests on sacrificial anchors - suitability tests on working anchors?? (= not foreseen in EC7) - acceptance tests on working anchors. c) Tension piles: - preliminary tests on sacrificial piles - suitability tests on sacrificial anchors or on selected working anchors (provided with a free length for inclined anchors) - acceptance tests on selected working anchors (provided with a free length for inclined anchors). d) Soil nails: - preliminary tests on sacrificial nails - suitability tests on sacrificial nails.
5.
CONCLUSIONS
In Belgium there is actually a lot of confusion concerning the design of ground anchors. This is mainly due to the fact that almost always the same design method is used regardless the installation method and the type and the number of tests performed. The information given in the available European Standards is not precise enough to allow a correct design of all the types of anchors that are actually installed. In order to obtain a better agreement with the actual daily practice it is necessary to extend EN 1537 with passive ground anchors and to define in EN 1997 (= EC 7) the safety factors which have to be taken in to account when acceptance tests are not performed on all working anchors. Further on it is proposed to elaborate a technical document dealing with the use of tension (micro)piles as anchoring elements.
General framework and viewpoint with regard to ground anchors, soil nails and tension piles
BBRI
BGGG GBMS
1.
INTRODUCTION
Together with the large variety in applications, ground conditions, specific project demands, local experience, etc. a wide panoply of ground anchor types has been developed over the last 40-50 years. The developments have meanly been focussing on: improving the soil-anchor interaction, allowing for higher capacities or shorter anchor lengths simplifying, improving or accelerating the installation process assuring faster or longer activity of the anchor. The scope of the execution code EN 1537:1999 is limited to anchors consisting of an anchor head, a free anchor length and a fixed anchor length which is bonded to the ground by grout, whereby ground encompasses both soil and rock. Our overview of anchor types and their installation methods is both broader and narrower, since: also mechanical non grouted anchors and expander bodies are considered rock anchor types are only included as far as their components and installation process is similar to their use in soil. Are not considered : deadman anchors, specific rock bolts.
2.
Ground anchors: overview of types, installation Methods and recent trends ir. Flor De Cock 14.05.2008
p. 3/23
3.
1. 2. 3. 4. 5. 6. 7. 8. 9. 10.
Anchorage point at jack during stressing Anchorage point at anchor head in service Bearing plate (or anchor plate) Load transfer black Structural element to be anchored Soil-rock Borehole Debonding sleeve Tendon Grout body (if any)
The tendon bond length Ltb (which is the bond length to be considered in the design) corresponds to the part of the tendon that is bonded directly to the grout and may be equal to or less than the fixed anchor length depending on location of the end point of the debonding sleeve.
4.
Ground anchors: overview of types, installation Methods and recent trends ir. Flor De Cock 14.05.2008
p. 4/23
We also considered the different aspects that may distinguish the anchors : The shape and configuration of the anchor : e.g. cylindrical, with bulb(s), with anchor plate or helix, with one or several tendon elements (multi stage), The nature of the tendon or anchoring body; e.g. steel strands, bars, wires, tubes, plates, ; glass fibre, The bonding material : cement-grout, mortar, resin, The installation method : drilling tools and auxiliaries, one phase or 2-phase installation, The grouting method (if any) The terms of use : temporary or permanent, recoverable, The method(s) of corrosion protection Prestressed or not The method of anchor-soil interaction. The proposed classification is given in Figure 3, which starts from the latter aspect, related to the fixation method of the anchor body to the ground. In parallel, the grouting method (which is an essential influencing factor for the anchor capacity) as well as the term of use, are incorporated in the classification scheme.
METHOD OF FIXATION TO THE GROUND
By Friction
Tensile type anchor e.g. strand anchor threadbar anchor hollow bar anchor TMD anchor Compressive type anchor e.g. Duplex anchor e.g. plate anchor helix anchor expander body e.g. Grouted screw anchor
By ground pressure
Combined
GROUTING METHODS
* primary gravity grouting * primary pressure grouting * primary jetgrout pressure * secondary pressure grouting - global post-grouting - selective post-grouting Primary low pressure grouting during screwing-in of the anchor
(IGU-BE)
(IGU-FR) (IRS-FR)
TERM OF USE
Temporary
* remaining in the ground * recoverable * partially removable (free length) * entirely removable (free length and bond length) * destructable
Permanent
* remaining in the ground
The various anchor-soil interaction systems are scheduled in Figure 4 : Friction anchors own their capacity from the bonding stress (shear stress) at the tendon/grout or the grout/ground interface. In tensile type anchors, the mobilisation of the bonding stress starts at the proximal end of the fixed
Ground anchors: overview of types, installation Methods and recent trends ir. Flor De Cock 14.05.2008
p. 5/23
length; the distribution along the bonding length depends on the soil shearcharacteristics (shear stress as a function of displacement) and the anchor tendon elasticity. When this shear stress has reached the maximum shear strength and drops to a residual value, progressive debonding occurs as anchor load increases and the bonding is more and more transferred towards the distal end of the fixed length. To reduce this detrimental effect of the progressive debonding, the concept of multiple anchors may be used (Barley, 1997). This system involves the installation of a multiple of unit anchors into a single borehole. Each unit anchor has its own individual tendon, its own unit fixed length of borehole, and is loaded with its own unit stressing jack. The loading of all the unit anchors is carried out simultaneously by a multiple synchronised jacks which ensures that the load in all unit anchors is always identical. Compressive type anchors also use the shear stress at the grout/ground interface, but contrary to the tensile type anchors, the total anchor load is transferred to the very end of the anchor by a central steel tendon which is fixed to the end cap and the outer steel compression tube. As the elasticity of this tube and the surrounding grout mantle under compression is smaller than the elasticity of the steel tendons in tensile type anchors, the distribution of the bonding stress initiated at the anchor end is more uniform than with tensile type anchors and so the progressive failure effect is less pronounced. Plate or helix anchors meanly consist of a steel tendon which transfers the anchor load to a steel end blade. The anchor load generates compressive ground pressures at the blade/ground interface which tends to develop a slip surface in the ground. These anchors also may be called end bearing.
Ground anchors: overview of types, installation Methods and recent trends ir. Flor De Cock 14.05.2008
p. 6/23
Figure 4c and 4d : Anchor-ground interaction for compressive and end bearing type anchors
5.
AND
Ground anchors: overview of types, installation Methods and recent trends ir. Flor De Cock 14.05.2008
p. 7/23
Complementary to the above mentioned general installation process, the following details and remarks need to be added. 1. THE DRILLING Instead of water, also drilling-muds or water-bentonite may be used. In e.g. rock or hard clays, percussion or rotary-percussion drilling with air pressure is common. Alternatively, the very-high-pressure grouting method (Jetgrouting) (Figure 6) is used for drilling and grouting. After drilling of the rods using water- or groutflush (phase 1), the rods are slowly rotated and extracted, while cement-grout is injected under very high pressure through the injection nozzles nearby the drill bit (phase 2). As such, a cemented grout-body with diameters of 0.3-0.4 m or more is formed, in which the anchor body is installed (phase 3).
Ground anchors: overview of types, installation Methods and recent trends ir. Flor De Cock 14.05.2008
p. 8/23
Figure 6: installation of friction anchors using the very high pressure technique (Jetgrouting)
Drilling tools can be : outer casing and inside drill rod, each with a specific recovered drill bit casing with slightly enlarged recovered drill bit drill rod with enlarged sacrificial drill bit. The different methods, their advantages and inconveniences are further discussed in 6. 2. THE PRIMARY GROUTING The primary grouting may be a low pressure grouting (+/- gravity filling or < 5 bars) or a medium pressure (> 5 bars) grouting. The latter case is indicated in the classification table and hereafter (see ) as the IGU-BE type (Injection Globale Unique Belgium). 3. THE ANCHOR BODY : tendon, sheathing, tubes, grout The anchor tendon for friction type anchors can be: (Figure 7) steel strands, typically 2 to 7 seven-wire strands, steel grade 1570/1770 or 1670/1860 N/mm, yield load of about 220 to 250 kN per strand
Ground anchors: overview of types, installation Methods and recent trends ir. Flor De Cock 14.05.2008
p. 9/23
500/550 N/mm up to 1080/1230 N/mm and so with yield loads in the range of 400 to 1.500 kN (occasionally) also steel wires or tubes, or glass fiber
Figure 7 : strand anchors composition, assembled strand tendon with post-grouting tube
Ground anchors: overview of types, installation Methods and recent trends ir. Flor De Cock 14.05.2008
p. 10/23
For specific needs and demands of the client, the anchor tendon can be made partially or entirely removable, e.g. : For threadbars : by using a specific coupler between free length and bond length or at the anchor foot For strands : by incorporating a weaker breaking point between free length and bond length (Figure 9)
Over the free anchor length, the tendon strands or threadbar are surrounded by a smooth sheathing, often in PVC, to allow for a friction-free extension of the free tendon length. Finally, over the free anchor length as well as the bond length, the tendon and its surrounding first grout mantle, a plastic or steel sheathing for corrosion protection may be incorporated. 4. THE SECONDARY GROUTING (Post-grouting) The secondary grouting is started when the primary grout has achieved its initial set, in general after 16-20 hours. It may be performed in 1 or 2 stages. The device for this secondary grouting can consist of a small diameter perforated grout tube (diameter 20 mm), a central plastic TAM with the strands distributed around this tube, a steel TAM with the strands or threadbar inside. Depending on whether the grouting is global (that means that the entire device is pressure-grouted over its full length) or selective (when the injection valves or manchettes are pressurised individually using a double packer injection tube), one uses the notations : IGU-FR : Injection Globale Uniforme IRS-FR : Injection Rptitive Slective.
Ground anchors: overview of types, installation Methods and recent trends ir. Flor De Cock 14.05.2008
p. 11/23
Figure 10a and 10 b: schematical drawing of self boring anchors (DSI and Ischebeck)
The outer diameter of the bars typically goes from about 30 mm up to 70 mm. With steel yield strengths of about 500 to 600 N/mm, the yield load ranges from about 200 kN up to 1200 kN. The oversized drill bit type is chosen as a function of the ground conditions. The main advantages of the system are : the high productivity
Ground anchors: overview of types, installation Methods and recent trends ir. Flor De Cock 14.05.2008
p. 12/23
the flexibility and simplicity to adjust and assemble the anchor length the ability to work with small drill rigs in confined conditions
The drilling method, the type, flow and injection pressure of the flushing material and the penetration speed (including sometimes a moving up and down of the bars) shall be chosen adequately in order to stabilize the bore hole and to minimize soil disturbance and relaxation. After drilling the required anchor length, cement grout with low W/C ratio (in the order of 0.5) is pumped through the hollow bar and the drill bit, while the drill hammer continues rotating. It is claimed that the effect of this grouting in combination with the rotating and vibrating rods, is similar to a pressure grouting as in the conventional anchor types.
Ground anchors: overview of types, installation Methods and recent trends ir. Flor De Cock 14.05.2008
p. 13/23
Ground anchors: overview of types, installation Methods and recent trends ir. Flor De Cock 14.05.2008
p. 14/23
120 mm to 350 mm. The structural strength of the anchor lies in the order of 100 kN up to 400 kN.
Ground anchors: overview of types, installation Methods and recent trends ir. Flor De Cock 14.05.2008
p. 15/23
Ground anchors: overview of types, installation Methods and recent trends ir. Flor De Cock 14.05.2008
p. 16/23
6.
Ground anchors: overview of types, installation Methods and recent trends ir. Flor De Cock 14.05.2008
p. 17/23
the advantage of having as such an increased anchor diameter, the enlarged bore hole may collapse and result in soil disturbance and subsidence. (Phase 2) After reaching final depth, the bore hole is cleaned and filled with grout by means of a flexible that is lowered in the casing. (Phase 3) The further procedure is similar to the double drill system. Compared to the double drill system, the installation procedure is easier and faster, and therefor also more economical. However, it should not be used for drilling underneath existing structures or in collapsible soils. The grout consumption is likely to be higher than in the double system, but the grout pressure is generally smaller. 3. Single drill system with drill rod (Phase 1) This drilling method differs from the former by the use of a drill rod with an oversized sacrificial drill head (e.g. drill head of 150mm for rods 90mm). One often uses a stabilising fluid, such as bentonite or cementbentonite, to prevent collapse of the bore hole. The ground spoil is evacuated by the stabilising fluid at low pressures and low flow rate. Consequently, there is no increased bore hole diameter, nor any risk for instability of the bore hole. (Phase 2 and 3) After replacement of the bentonite with cement-grout (gravity filling) and extraction of the drill rods, the anchor body with post-grouting devices or a steel TAM is inserted. (Phase 4) As the single rod system does not allow for a primary pressure grouting, a post-grouting is required. One of the methods, referred to as the IRSmethod, is described hereunder. 4. Rammed casing The casing is provided with a sacrificial end bit which is soil- and watertight. The casing is driven by high frequency percussion drilling. At final depth, the casing is internally cleaned with water, the drill bit is disconnected, after which the further procedure as mentioned in point 3. is followed. Basically, the soil is not removed but laterally displaced during the driving. This is beneficial for the grouting effect and the anchor capacity. But because of inconveniences, such as frequent material brake by hard driving or early driving stop, the method has lost interest. It only remains frequently and successfully used in hard clays and soft rocks (e.g. marl, shale, chalk) by using percussion drilling and air-flush to evacuate the cuttings.
Ground anchors: overview of types, installation Methods and recent trends ir. Flor De Cock 14.05.2008
p. 18/23
Ground anchors: overview of types, installation Methods and recent trends ir. Flor De Cock 14.05.2008
p. 19/23
Ground anchors: overview of types, installation Methods and recent trends ir. Flor De Cock 14.05.2008
p. 20/23
Ground anchors: overview of types, installation Methods and recent trends ir. Flor De Cock 14.05.2008
p. 21/23
Photos 6-1 to 6-4 : Steel TAM for post-grouting in IRS-FR anchor type
The whole is inserted in the bore hole, filled with fresh cement grout. The casings (if any) are extracted. One allows now for the grout to set, what generally takes about 12 hours. After that, the post-grouting operation can start. Therefore, a single packer (in the case of a global post-grouting IGU-FR) or a double packer (in the case of the IRS-FR) is used. Photos 6-5 and 6-6 show the packer devices in un-inflated and inflated situation. The un-inflated double packer is inserted in the grouting tube and positioned in front of a manchette. The 2 rubber packers are pneumatically inflated by means and cement-grout is pumped in the closed space in between both packers; this fresh grout escapes through the manchette openings, breaks the initial grout mantle and permeates in the surrounding ground. This operation is repeated at every single manchette.
Photos 6-5 and 6-6 : packer for post-grouting in IRS-FR anchor type
Ground anchors: overview of types, installation Methods and recent trends ir. Flor De Cock 14.05.2008
p. 22/23
7.
REFERENCES
Barley, A.D. The single bore multiple anchor system. ICE seminar. London 1997. EN 1537:1999 Execution of special geotechnical work Ground anchors. CEN Samwoo. Company website www.swanchor.com.
Ground anchors: overview of types, installation Methods and recent trends ir. Flor De Cock 14.05.2008
p. 23/23
BBRI
BGGG GBMS
Full Scale Load Test Program in Limelette: Overview of the Test Campaign, Set up & General Results
Ir. Noel Huybrechts & Ir. Olivier Tomboy Belgian Building Research Institute (BBRI) Geotechnical & Structural Division
Prof. Ir. Jan Maertens Jan Maertens bvba & Catholic University of Leuven (KUL)
1.
INTRODUCTION
The Belgian Building Research institute (BBRI) initiated in 2004 a research program on ground anchors (BBRI 2004-2008). This research program is subsidized by the Belgian Federal Public Service Economy and the Belgian standardization institute NBN. The main objective of the project is the establishment of a uniform guidance for the execution, the design and the testing of anchoring systems in Belgium. Such guidance should be complementary to the content of European standards addressing anchors. The research program was elaborated under supervision of the project partners K.U.Leuven (prof. J. Maertens) and UCL (prof. A. Holeyman) and in collaboration with the inter-professional BBRI Working Group Ground anchors, composed of all relevant parties, the anchorage contractors in particular. Within the framework of the project a major real scale load test campaign has been organized on the Limelette test field. At this occasion, different types of ground anchors were installed in different soil layers encountered in Limelette (quaternary loam, heterogeneous clayey sand and tertiary Bruxellian sand) and load tested. This contribution gives a general overview of the test campaign, the set up and its results. Where relevant, reference is made to the other contributions to this symposium.
2.
p. 3/18
Limelette - Test site ground anchors CPT E10-E11-E34 -21 qc (MPa) 0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 0 -1 -2 -3 -4 -5 -6 -7 -8 -9 -10 -11 -12 -13 -14 -15 -16 -17 -18 -19 -20 -21 -22 -23 -24 -25 -26 -27 -28 -29 -30 -31 -32 -33 -34
Figure 1 : Some typical CPT results on the ground anchor site in Limelette
The following layers can be identified on Figure 1 : R - 1.50m R - 6.50 m Quaternary loam (silt) R - 6.50 m R- 9.50 m Heterogeneous clayey sand containing silex stones (only in the upper part of this layer). This layer appear in lenses as was only present at a limited part of the test site R - 9.50 m Tertiary Bruxellian sand layer; at larger depths sand stone layers occur All three layers were found interesting to install and test ground anchors but it was however decided to operate in two phases. In phase 1 a preliminary test campaign on 5 classical IGU ground anchors (Injection Globale et Unique) was performed in 2005. The aim of these preliminary tests was: - to have a first estimate of the ultimate anchor capacity in the loam (silt) layer, for which the grout body is situated at limited depth ( 4m below the soil surface) , and to verify the total stability of the ground mass above the anchor during the tests, - to have a first estimate of the anchor capacity in the dense Bruxellian sand layer, - to evaluate the feasibility of the instrumentation principles for strand anchors that were worked out in the laboratory; - to evaluate the usefulness of a supplementary extended load tests campaign on different ground anchor types at the Limelette test site. Based on the results of the preliminary tests and the discussions in the Working Group Ground Anchors, phase 2 of the test program (extended test campaign) was established: 49 more anchors of the following anchor types, significant for the techniques applied on the Belgian market, were installed and load tested (44) in 2006: - strand anchors for which the drilling is performed with casing and inner tubes (IGU or 2T) in Tertiary Bruxellian sand and in a heterogeneous clayey sand layer - strand anchors for which the drilling is performed with casing and lost oversized point (1T) in the Tertiary Bruxellian sand layer - strand anchors of the previous type but with provision to perform a two stage post-injection (1T+inj) in Tertiary Bruxellian sand and in the heterogeneous clayey sand layer - self boring hollow bar anchors from the Dywidrill type in the Quaternary loam layer and in Tertiary Bruxellian sand - self boring hollow bar anchors from the Ischebeck Titan type in Tertiary Bruxellian sand and in the heterogeneous clayey sand layer. In Figure 2, the position of the different test anchors is given. With regard to Figure 2 it should be remarked that: All the cone penetration tests were performed with an electrical E1 cone. It concerns also a series of inclined CPT. With regard to the results of these CPT, reference is made to Volume 2 of the proceedings of this symposium. The heterogeneous clayey sand layer (see figure 1) was only significantly present in the zone E5-6 to E12-13.
p. 5/18
Reference is made to phase 3 of the test campaign : it concerns 8 more ground anchors: 5 self boring hollow bar anchors performed in sand with intensive percussive drilling and 3 anchors of the IRS type (Injection Rpititive et Slective) installed in the loam (silt) layer. These anchors were recently installed (March and April 2008) and will be load tested in May/June 2008. The results of the supplementary tests in phase 3 are not reported in the proceedings of this symposium. A supplementary Addendum dealing with the phase 3 load tests will be published later.
VE15 VE14 E14 VE13 E37 E13 E12 VE12 E11 VE11 E36
E16-17
E15
E16
E17
E18
-1 E15
E35
3 E1 -1
2E1
E17-18
E18-19
E19-2 0
E2 1-2 2
VE10
E10 E34
E2 0 -2 1
E1 5 4- 1
E24
VE9
E9
E1
E9 10
E2 2
E1 112
E25
-2 3
13
0-1
E2
24 3E2 425
6 is 5-2 -27b E2 E26 7 -2 8 bis E26 E27-2 8 E27-2 E28-29 bis E28-29
E26
VE8
E8
E27
E33
E8-9
VE7
E7
E7-8
E6-7
E28
E29
E32 E6 VE6 E5
E5-6
E29-30
E30
E30-3 1
E4-5
E31
E34
-3 E2
L3 E2 VE2 E1 VE1 L4
L2 LCM2 LCM1
L1
SCM3 SCM2 S1
SCM1
L0
S2
VERTICAL CPTE
6
INCLINED CPTE
5
4 3 2
INCLINED ANCHORS (PHASE 2) VERTICAL ANCHOR (PHASE 2) INCLINED ANCHORS (PHASE 3) VERTICAL ANCHOR (PHASE 3)
Figure 2 : Ground anchor test site Limelette : position of the ground anchors phase 1 (2005); Phase 2 (2006-2007); Phase 3 (2008) and position of the inclined and vertical CPTE
With the extensive load test program on anchors in Limelette it has been envisaged to obtain more information with regard to the several aspects and parameters that are summarised below:
p. 6/18
Ultimate anchor capacity of the different anchorage systems in loam (silt), heterogeneous clayey sand and tertiary Bruxellian sand. Influence of the installation method on the anchor capacity. Influence of the inclination on the anchor capacity. Influence of the drill diameter on the anchor capacity. Friction losses in the free length (Lfree) of the anchor, and in particular the effectiveness of the free length (Lfree) of self boring hollow bar anchors. A comparison of the (French) maintained load test procedure TM3 with the (German) cyclic test procedure TM1 (see EN1537 and Pr EN ISO 22477-5). The (non-) lineair increase of anchor capacity with Lfixed, and the way the friction resistance is mobilised over Lfixed Performance of the double corrosion protection system(s). The influence of the absence of spacers between the strands. Relation between anchor dimensions, installation methodology, and anchor capacity.
3.
ANCHOR INSTALLATION
Different types of ground anchors, significant for the systems applied on the Belgian market, were installed on the Limelette test site. The different systems are briefly illustrated in the Figures 3 to 5. For a detailed report of the installation, and the observations and monitoring data during installation, reference is made to Volume 2 of the proceedings of this symposium. For a more general overview of ground anchors types, reference is made to the contribution of F. De Cock (2008) to this volume.
Figure 3 : Installation of IGU anchors drilling with casing water flushing via inner tubes stepwise grout injection procedure of Lfixed
p. 7/18
Figure 4 : Installation of 1T anchors drilling with casing only at its end provided with an oversized lost point flushing with water
Figure 5 : Installation of SA anchors drilling with hollow bar at its end provided with an oversized drill bit flushing with water- cement mix
p. 8/18
With regard to the anchor installation in Limelette, it should however be remarked that: The technique called IGU (Injection Globale et Unique) as applied in Belgium differs from the IGU technique in France, where a global injection is performed starting from a tube manchettes (TAM), cfr. AFNOR (1992) and De Cock (2008). Some of the IGU anchors have on purpose been gravity filled with grout; these anchors are symbolized with 2T-grav. For the IGU and 1T anchors in Limelette the tendon existed out of strands of pre-stressed steel. Almost all these tendons have been instrumented with strain gauges (cfr. Volume 2). Some of the 1T anchors were executed with reduced dimensions of the casing and a lost oversized point; these anchors are symbolized with 1Tred. Some other 1T anchors were provided with a 2-stage post-grouting system and are symbolized with 1T+inj. For the SA anchors, different drill bit diameters have been applied. In order to realize a free length, plastic tubing was provided between the coupling sleeves. For the SA anchors, two variants have been executed: one variant without post-grouting (SA-xx-Dy) and the other variant with post grouting (SA-xxIs). As these anchors were installed with limited (SA-xx-Dy) or no (SA-xxIs) percussion during drilling, it has recently been decided to install in Limelette some supplementary SA anchors with intensive percussive drilling (phase 3). The SA anchors were rinsed after installation. In this way it was possible to install a retrievable extensometer system, developed by BBRI, in the hollow bars upon testing. According to the Belgian practice for temporary anchors, the tendons were not provided with centralizers. Some of the strand anchors were even on purpose installed without spacers between the strands. As mentioned before, recently three supplementary IRS anchors have been installed in the loam (silt) layer (phase 3). Via this installation technique the tendons have been fixed to ground by means of 2 post injection stages via a TAM (tube manchettes)
4.
p. 9/18
Load procedure : TM3 110 100 90 80 load [% Pp] 70 60 50 40 30 20 10 0 0 50 100 150 200 250 300 Time [min] 350 400 450 500 550 600
# step
% Pp Period of 0 60 60 60 60 60 observation [min](*) (*) Reduced period of 30 to 45 min has been generally applied for Steps 1 & 2
Datum load 10
Step 1 20
Step 4 60
Step 5 70
Step 6 80 60
Step 7 90 60
Step 8 100 60
Figure 6 : General test scheme Test Method 3 of the prEN ISO 22477-5: MLT-procedure
Load procedure : TM1 110 100 90 80 load [% Pp] 70 60 50 40 30 20 10 0 0 20 40 60 80 100 120 Time [min]
Load level [% Pp] Cycle 1 10 Minimum period of observation for adopted TM1 [min]
140
160
180
200
220
240
Cycle Cycle Cycle Cycle Cycle Cycle Cycle 2 3 4 5 6 7 8 10 10 10 10 10 10 10 1 20 40 50 60 70 80 90 1 20 40 50 60 70 80 90 100 15 (60 or 180)(*) 20 40 50 60 70 80 90 1 10 10 10 10 10 10 10 10 1 (*) Cycle 8 -Extended period of observation for creep-displacement monitoring at Pp (60 min in noncohesive soil; 180 min in cohesive soil)
Figure 7 : General test scheme Test Method 1 based on prEN ISO 22477-5: cyclic procedure
p. 10/18
For the maintained load test procedure TM3 it was the aim to obtain anchor failure in 8 load steps, starting from a datum load Pa = Min[50kN;10%Pp], with Pp the maximum estimated test load. In reality anchor failures have been obtained after 5 to 15 load steps. This corresponds with 70 to 150 % of the estimated maximum load. In general the first two load steps have been reduced to 30 or 45 minutes For the cyclic load tests, some slight changes have been integrated in the test procedures TM1 of the PrEN ISO 22477-5 (6 cycles until maximum load). The magnitude of the load step Q was determined, in order to obtain anchor failure after 8 cycles. The duration of the load steps has been based on the evaluation of the creep (). Hereby the load was maintained until was constant. For the cyclic tested anchors in Limelette, anchor failure was in general obtained after 7 to 9 cycles. Two tests have on purpose been performed with a very low number of cycles (5) and a very high number of cycles (14), in order to evaluate the possible effect of the number of cycles on the ultimate anchor load. Figure 8 gives some illustrations from the load test set up for the inclined and the vertical anchors.
The load was applied by means of hollow hydraulic jacks and transmitted to the reaction wall (inclined anchors) or bearing plates on the ground surface (vertical anchors). The force was regulated by means of a high precision PLC-controlled 700 bar hydraulic central of the BBRI. In this way it is possible to ensure a
p. 11/18
continue regulation of the applied load in a very accurate way (0.1% of the maximum jack capacity). Measurements of the hydraulic jack pressure (digital manometer on hydraulic central), the applied force (dynamometer), the anchor head displacement (displacement transducers), and the deformation measurements of the tendon (strain gauges or extensometer) were automatically and continuously recorded (each 10 seconds). The displacement of the reference system was regularly controlled by means of optical measurements. The results of the load test on each individual anchor is reported in Volume 2 of the proceedings of this symposium. Figures 9 to 16 illustrate the reported test results on one anchor. With regard to the execution of the tests it should be remarked that: Only with load cells with a sufficient maximum load capacity with regard to the maximum test load and with a height of at least 2 times the load cell diameter, reliable load measurements were obtained for inclined anchor testing. For some inclined anchors, flat load cells were used, resulting in unstable measurements. The load Pcorrelation expressed in the figures below, is based on a correlation analysis between the load cell measurements Pload cell and the hydraulic pressure readings, and represents in our opinon the most reliable assessment of the applied load. Most of the anchors failed at the grout-ground interface. However for some anchors, when loaded up to the maximum test load Pmax, determined by the steel limit, geomechanical failure did not yet occur. Some of those anchors were submitted to a cyclic loading between datum load Pa and Pmax. In the most cases a limited number of cycles was needed to obtain geomechanical failure of these anchors. In one case mechanical rupture of some steel wires in the strands occurred under an applied load of 80% of the characteristic load capacity of the tendon. With regard to the creep curve : the creep values have for each load step been deduced from the anchor head displacement measurements (s) with time on a logarithmic scale (see Figure 15) and in general according to the definitions in prEN ISO 22477-5. It has been found that it is not always evident to obtain a nice and smooth creep curve, even for load tests applied under laboratory conditions as it was the case in Limelette. The creep values are very sensible to various factors, the precision with which the applied load can be kept constant on first instance. To anticipate on this, it is necessary to perform continuous measurements of load, hydraulic pressure and anchor head displacement in order to detect, explain and possibly correct irregularities in the creep curve. Finally it should be remarked that for the cyclic test method TM 1 in general creep curves of better quality were obtained.
p. 12/18
12
16
28
32
36
40
44
Ext 5 Ext 6
Figure 10 : Position of anchor E13-14 with regard to nearby CPT, position of instrumentation
p. 13/18
BBRI Research 'Ground Anchors' - Site Limelette Anchor E13-14 (SA - sand) 1600 1400 Load P (kN) - Pressure (bar) 1200 1000 800 600 400 200 0 0:00 P_load cell (kN) P_correlation (kN) Pressure (bar) s (mm) 160 140 120 100 80 60 40 20 0 10:00 11:00 12:00 Anchor head displacement s (mm)
1:00
2:00
3:00
4:00
5:00
6:00
7:00
8:00
9:00
Time (hours:minutes)
Figure 11 : Time data (each 10 sec.) of Pload cell, hydraulic pressure, and the anchor head displacement s(mm)
BBRI Research 'Ground Anchors' - Site Limelette Anchor E13-14 (SA - sand)
3000 Deformation measurements Lfixed (strain) 2700 2400 2100 1800 1500 1200 900 600 300 0 0:00 EXT 11 EXT 12 EXT 4 EXT 2 EXT 1 EXT 6 EXT 5 Theor.
1:00
2:00
3:00
4:00
5:00
6:00
7:00
8:00
9:00
10:00
11:00
12:00
Time (hours:minutes)
p. 14/18
BBRI Research 'Ground Anchors' - Site Limelette: Anchor E13-14 (SA-sand) Load Pcorrelation (kN) 0 0 20 40 60 (6') 80 100 120 140 200 400 600 800 1000 1200 1400 1600
(a) (b)
After 6' in step 8 (918 kN), s accelerated. The anchor has been unloaded
(a) (b)
After 6' in step 8 (918 kN), s accelerated. The anchor has been unloaded
p. 15/18
BBRI Research Ground Anchors - Site Limelette Anchor: E13-14 Time (logarithmic scale) 1 0 step 1 : 178 kN step 2 : 353 kN step 3 : 469 kN 20 step 4 : 560 kN step 5 : 650 kN step 6 : 740 kN step 7 : 831 kN Anchor head displacement (mm) 40 step 8 : 918 kN 10 100
60
80
100
120
Figure 15 : log t s diagram (time t on a logarithmic scale)
p. 16/18
BBRI Research 'Ground Anchors' - Site Limelette: Anchor E13-14 (SA-sand) 5 5' --> 60' 30' --> 60' 4 (6') 3 (mm) Pmax
0 0 200 400 600 800 Load Pcorrelation (kN) 1000 1200 1400 1600
5.
CONCLUSIONS
This contribution has given a general overview of the set up of a real scale load test campaign on different ground anchor types in Limelette. It concerns phase 1 (5 preliminary test anchors) and phase 2 (extended test campaign on 44 anchors) in particular. It has been shown that an overall quality control for the project planning, the anchor installation, and the load testing itself has been assured in order to obtain test results of high quality. For more details reference is made to Volume 2 of the proceedings of this symposium. Furthermore 29 of the tested anchors have been excavated. A summary of the observations and measurements of the real anchor dimensions is given in the contribution of Tomboy et al. (2008) in this Volume. Volume 2 contains all detailed measurements. The interpretation of the test results, taking into account a.o. the observations on the excavated anchors, is addressed in the contribution of Huybrechts et al (2008) to this symposium. Finally, a 3rd phase of the test campaign in Limelette has been activated. 8 more ground anchors have recently been installed (March and April 2008) and will be load tested in May/June 2008. It concerns 5 self boring hollow bar anchors performed in sand with intensive percussive drilling and 3 anchors of the IRS type installed in the loam (silt) layer. A supplementary Addendum to these Volumes, dealing with the phase 3 load tests, will be published later.
p. 17/18
6.
REFERENCES
AFNOR 1992, Fondations profondes pour le btiment, NFP 11-212, DTU 13.2 CEN, 1999. EN1537 - Execution of special geotechnical works Ground anchors CEN, 2004. Pr EN ISO 22477-5 Geotechnical investigation and testing Testing of geotechnical structures Part 5: Testing of anchorages De Cock, F. 2008. Ground Anchors : overview of types, installation methods and recent trends, Proceedings of the international symposium on ground anchors, May 14th 2008, Brussels Huybrechts, N., De Vos, M., Tomboy, O. & Maertens, J. 2008. Integrated analysis of the anchor load test results in Limelette and suggestions for a harmonized anchor design and test methodology in Belgium in a EC7 framework, Proceedings of the international symposium on ground anchors, May 14th 2008, Brussels Ministre de lEquipement, du Logement, et des Transports, 1993. Fascicule 62-V, Rgles techniques de conception et de calcul des fondations des ouvrages de gnie civil, cahier des clauses techniques gnrales applicables aux marchs publics se travaux (France) Tomboy, O. & Huybrechts, N. 2008. Excavation of the ground Anchors: measurements and observations, Proceedings of the international symposium on ground anchors, May 14th 2008, Brussels Van Alboom, G. & Whenham, V. 2003. Soil investigation campaign at Limelette (Belgium):Results, Proceedings of the 2nd Symposium on screw piles, May 7th 2003, Brussels PrEN ISO 22477-5, Geotechnical investigation and testing Testing of geotechnical structures Part 5: Testing of anchorages EN1537, Execution of special geotechnical works Ground anchors
p. 18/18
BBRI
BGGG GBMS
Ir. Olivier Tomboy & Ir. Noel Huybrechts Belgian Building Research Institute (BBRI) Geotechnical & Structural Division
1.
INTRODUCTION
Within the framework of the BBRI Research program on ground anchors and more specifically at the location of the extended test campaign in Limelette it was decided to excavate a number of the tested anchors. The main reason for this decision was: - to measure the real dimensions and shape of the different anchor types, - to determine the real position (inclination) of the anchors, - to observe the effects of post-grouting operations on the shape and the dimension of the anchor, - to look at the surface roughness, - to observe fissuring patterns. All this information has been analysed in detail and an overview is given in this contribution. For more details about the results of the investigation, reference is made to Volume 2 of the proceedings of this symposium. The further objective of the excavation is to link this detailed information with: - the anchor installation procedures and the observed installation parameters, - the nominal values of anchor material and/or drill tools applied on the site, - the theoretical imposed position of the anchors, - the results of the anchor load tests. This integrated analysis is summarized in the contribution of Huybrechts et al. (2008a) to this volume,
2.
p. 3/26
E15
E16
E17
E18
E36
E 15 -16
E17-18
E18-19
E19-2
VE10
E2 1-2 2
E10 E34
E1 1-
E2 0 -2 1
5 4- 1 E1
E24
0
3 -1
E25
VE9
E9
E1 0-1 1
E910
12
E26
25 4E2 6 5-2 2 E -27 E26
VE8
E8
E27
E33
E 89
E7 VE7
E7-8
E6-7
E28
8
E27-2
E28-29
E29-30
E29
E30
E30-3 1
E4-5
E31
4 E3-
E4 VE4 E3 VE3
E2
-3
L3 E2 VE2 E1 VE1 L4
L2 LCM2 LCM1
L1
SCM3 SCM2 S1 S2
SCM1
L0
CPTE
VERTICAL ANCHOR
Figure 1: Selected zone for the excavation Table 1: Excavated anchors: anchor type, nominal dimensions INCLINED ANCHORS VERTICAL ANCHORS
Anchor n
E02-03 E03-04 E04-05 E05-06 E06-07 E07-08 E08-09 E09-10 E10-11 E11-12 E12-13 E13-14 E14-15 E15-16 E16-17 E17-18
Anchor type
IGU SA-175-Is IGU IGU SA-175-Is IGU SA-130-Is IGU 1T + inj. 1T + inj. IGU SA-130-Is 1T red. IGU IGU 1T
nom [mm]
140 175 140 140 175 140 130 140 180 180 140 130 150 140 140 180
Anchor n
VE3 VE4 VE5 VE6 VE7 VE8 VE9 VE10 VE11 VE12 VE13 VE14 VE15
Anchor type
2T-grav. IGU 1T SA-150-Dy SA-150-Is 1T SA-150-Dy 2T-grav. IGU IGU IGU 1T + inj. 1T + inj.
nom [mm]
140 140 180 150 150 180 150 140 140 140 140 180 180
p. 4/26
Particular remarks to be made with regard to the excavation works are the following: - the excavation is realised with a crane of CAT 330C type (Figure 3), - permanent standby of BBRI staff was provided in order to guide the crane operator, and to avoid damage of the ground anchors (Figure 3), - the soil in the direct neighbourhood of the anchors was manually removed, - observations detected during the excavation works were noted by the site staff. Due to the limited bending stiffness of the vertical anchors and due to the effect of load testing on the anchor grout, a lot of material in the free length of the vertical anchors was lost during the excavation works. In order to limit the loss of information with regard to Lfree of the vertical anchors, it was decided to perform as much as possible observations and measurements during the excavation works and to cut them off at regular levels. This implied that excavation process was a very delicate operation.
p. 5/26
p. 6/26
BBRI Research Ground Anchors Site Limelette. Anchor E13-14 ( SA-130-Is Sand)
0 0.5 m
0.5 1.0 m
1.0 1.5 m
1.5 2.0 m
2.0 2.5 m
2.5 3.0 m
3.0 3.5 m
3.5 4.0 m
4.0 4.5 m
4.5 5.0 m
5.0 5.5 m
5.5 6.0 m
L Fixed
L Free
p. 7/26
6.0 6.5 m
6.5 7.0 m
7.0 7.5 m
7.5 8.0 m
8.0 8.5 m
8.5 9.0 m
9.0 9.5 m
9.5 10.0 m
p. 8/26
Figure 5: Example of detailed report on excavated anchors: description of the encountered soil, fissuring patterns and general remarks with regard to the observations
p. 9/26
13
D meas. D nom
12
16
qc (MPa) 20 24 28 32 36 40
44
12
11
10
CPT E13 CPT E14 CPT E36 total station pressure sensor CSTC pressure sensor VLAAO
-1 -200
-100
100
-12.3 200
Figure 6: Example of detailed report on excavated anchors: measured versus nominal anchor diameter (left) - measured versus theoretical anchor position (right)
p. 10/26
Figure 7: Overview of the grout degradation of vertical anchors near the ground surface (left) Typical fissuring patterns in Lfixed for strand anchors (right)
p. 11/26
Figure 8. Grout surface for IGU system (left), SA system (centre), and 1T + inj. System (right)
p. 12/26
Figure 10. Example of decentred tendons for inclined and vertical anchors
p. 13/26
overall borehole deviation tolerance should be limited to 1/30 of the anchor length.
p. 14/26
14 13
D meas. D nom
13
D meas. D nom
-5.8 13
-5.8
D meas. D nom
-5.8
13 12 11 10 9 8 7 6 5
D meas. D nom
-6.3
11 -7.3
-6.8
10
-7.3
9 8 7 6 -9.3 -9.8 4 3 -10.8 2 1 0 -11.3 -11.8 -10.8 -11.3 -11.8 5 -9.8 4 -10.3 3 2 1 0 5 6 7 8
-7.8
-8.3
-8.8
-9.3
-9.8
-9.8 4
-10.3
free-fixed
-10.3
-10.8
-11.3
-11.8
-100
100
-12.3 200
-1 -200
-12.3 200
-1 -200
-100
100
-1 -200
-100
100
Dmeas,Lfixed = 1.07*Dnom
Dmeas,Lfixed = 1.11*Dnom
Dmeas,Lfixed = 1.10*Dnom
Dmeas,Lfixed = 1.14*Dnom
Figure 11. Dmeas versus Dnom for the inclined IGU anchors in sand (inclination 25: with regard to the horizontal)
p. 15/26
14
D meas. D nom
13
-6.3
12 -6.3
D meas. D nom
-5.8
13
-5.8 13 12 11 10 9 8 7 6 5
-9.8 4 3
D meas. D nom
-5.8
D meas. D nom
12
-6.8
11 10 9 -7.8 -8.3 -8.8 -9.3
free-fixed
-6.3
-6.8 -7.3
11
-7.3
-6.8
10
-7.3
9
8 7 6 5 -9.8 4 -10.3 3 2 1 0
-1 -200 5 6 7 8
-7.8
-8.3
-8.8
-9.3
free-fixed
-9.8
-10.3
-10.8
2 1 0
-10.3 3
-10.8 -11.3 -11.8
2
-11.3 -11.8
-10.8
2 1 0
-11.3
-11.8
-1 -200
-100 Equivalent radius (mm) 0 100
-100
100
-12.3 200
-1 -200
-12.3 200
-100
100
-1 -200
-100
100
Figure 12. Dmeas versus Dnom for the inclined IGU anchors in the heterogeneous clayey sand layer (inclination 25: with regard to the horizontal)
p. 16/26
2
D meas. D nom
1
0
0
soil surface
soil surface
D meas. D nom
0
-1
-1 -2 -3 -4 -5 -6 -7 -8 -9 -10 -11 -12
bottom
bottom free-fixed
top
-1
-2
-2 -3 -4 -5 -6 -7 -8 -9 -10 -11 -12 -13 -14
-1
soil surface
-2
-3 -4 -5 -6 -7 -8
free-fixed
soil surface
-3
-4
-5
-6
-7
-9 -10 -11 -12 -13 -14 -15 -200 Equivalent radius (mm) -100 0 100 200
-14 -200 -100 0 100 Equivalent radius (mm) -13
-8
-9
free-fixed
-10
-11
free-fixed
-12
bottom
-13
bottom
-14
-200
-100
100
200
200
-200
-100
200
Figure 13. Dmeas versus Dnom for the vertical IGU anchors, Lfixed mainly in sand
p. 17/26
D meas. D nom
0
top
-1
soil surface
-1 -2
soil surface
-2 -3 -4 -5 -6 -7 -8 -9
free-fixed
-10 -11 -12 -13 -14 -200 Equivalent radius (mm) -100 0 100 200 -14 -200 -100 -13
200
Figure 14. Dmeas versus Dnom for the vertical 2T-grav anchors, Lfixzd mainly in sand
p. 18/26
14
-4.8
13
D nom
D meas. D nom
-5,8
-5.3 12 -6.3
BBRI Research 'Ground anchors' Anchor E14-15 (Sand 1Tred.150) 14 D meas. -5.8 D nom 13
13
13
-6,3
D nom
12
-5.8 11 -6.8
12
12 11 10 9 8 7 6
11
-6,8 -7,3
10
-7.3
9 8
-6.8
-7.3
8 7 6 5 4
7 6 5 -9.8 4 -10.3 3
-7.8 7
-8.3
free-fixed
-8.8
-9,8 4
-10,3
-9.3
3
-10.8
-10,3 3
-10,8 -11,3 -11,8
-9.8 2
2 1 0
2 1 0
-10.3 1 -11.3
-10.8
-1 -200
-100
100
-11.3 200
-1 -200
-100
100
-1 -200
-100
100
Figure 15. Dmeas versus Dnom for the inclined 1T and 1T-red anchors in sand and the inclined 1T+inj anchors in the heterogeneous clayey sand layer (for all anchors : inclination equals 25 with regard to the horizontal and Dnom corresponds with the diameter of the lost drill point)
p. 19/26
2 1
D nom D meas. D nom
D meas. D nom
top
1 0
D nom
0 -1
soil surface
top
0 -1
top
-1
-1 -2 -3 -4 -5 -6 -7
soil surface
-2 -3 -4 -5 -6 -7 -8
free-fixed
soil surface
-2 -3 -4 -5 -6 -7 -8 -9 -10 -11
bottom free-fixed
soil surface
-2
-3
-4
-5
-6
-7
-8 -9 -10 -11 -12 -13 -14 -200 Equivalent radius (mm) -100 0 100 200 -13 -14 -200 -100 0 -12
free-fixed
-8 -9 -10 -11
bottom
-9
free-fixed
-10
-11
-12
bottom
-13
-14
-200
-100
100
200
-200
-100
200
Figure 16. Dmeas versus Dnom for the vertical 1T and 1T+inj anchors with Lfixed mainly in sand (Dnom corresponds with the diameter of the lost drill point)
p. 20/26
14
-5.8
13
12 11 10 9 -7.8 -8.3 -8.8 -9.3
free-fixed
D meas. D nom
-5.8
-6.3 12 11 10 9 8 7 6 5 -9.8 4
-10.3 3
BBRI Research 'Ground anchors' Anchor E06-07 (Heterog. SA-175Is) 14 D meas. -5.8 D nom 13
BBRI Research 'Ground anchors' Anchor E08-09 (Heterog. SA-130Is) 14 D meas. -5.8 D nom 13 -6.3 -6.8 -7.3 -7.8 -8.3 -8.8 -9.3
free-fixed
12
11 10 9 -7.8 -8.3 -8.8 -9.3
free-fixed
-6.3
-6.8
11
-7.3
-6.8
-7.3
-6.8
10
-7.3
9
8
-7.8
8 7 6 5
8
7 6 5 -9.8 4
-8.3
-8.8
-9.3
free-fixed
Relative depth (R+xxm) -9.8 4 -10.3 3 -10.8 -11.3 -11.8 2 1 0 -10.8 -11.3 -11.8
-9.8
4
3
-10.8
-10.3
2
-10.3
3
2 1 0
2
1 0 -1 -200 -100 Equivalent radius (mm) 0 100 -12.3 200 -11.8 -11.3
-10.8
-11.3
-11.8
-1 -200
-100
100
-12.3 200
-1 -200
-100
100
-1 -200
-100
100
Figure 17. Dmeas versus Dnom for the inclined self boring hollow bar anchors SA-xx-Is in sand and in the heterogeneous clayey sand layer (for all anchors : inclination equals 25 with regard to the horizontal and Dnom=xx corresponds with the diameter of the drill bit)
p. 21/26
-1
top soil surface
-2
-2 -3 -4 -5 -6 -7 -8 -9 -10 -11
free-fixed
-2 -3 -4 -5 -6 -7 -8 -9 -10 -11
free-fixed
-3
-4
-5
-6
-7
free-fixed
-9
-10
-11
bottom
-12
bottom
-8
bottom
-13
-200
-100
-200
-100
100
200
-200
-100
200
Figure 18. Dmeas versus Dnom for the vertical self boring hollow bar anchors SA-150-Dy and SA-150-Is, Lfixed mainly in sand (Dnom corresponds with the diameter of the drill bit)
p. 22/26
3.
3.1. Introduction
5-
10-
15-
p. 23/26
Figure 20 presents for both anchors the measured diameter as a function of the length from the anchor bottom. Due to the presence of the ground water level, it was not possible to excavate the last 50 cm of the anchors. Moreover, the stability of the surrounding slopes enforced the site staff to stop the excavation of the anchor A1 at 1.5 m from the bottom. Due to this, the effect of the postgrouting operation at the anchor bottom could not be observed. Figure 20 shows that the measured diameter of the anchor is in good agreement with the nominal diameter (90 mm). A ratio Dmeas,av/Dreal of about 1.1 is found.
180
A1 A2
measured anchor diameter [mm] 150
120
90
60
30
Figure 20: Dmeas versus Dnom for the inclined self boring hollow bar anchors SA-90Is investigated on the work site of Knokke
4.
CONCLUSIONS WITH REGARD TO THE REAL ANCHOR DIAMETER & COMPARISON WITH LITERATURE DATA
Table 2 summarises for each anchor type an overview of the average ratios of Dmeas/Dnom along Lfixed, that were obtained from the observations in Limelette and Knokke From the values in Table 2 and the observations mentioned before the following conclusions can be drawn: For the IGU anchors it can in general be concluded that the measured diameter is somewhat higher than the nominal anchor diameter due to local thickenings induced during the drilling For the systems with lost oversized drill point (1T) or drill bit (SA), it can be concluded that the real anchor diameter Dmeas and the obtained anchor shape depend strongly on the drilling procedure, i.e. the flow rate of the drill fluid and/or the ratio between flow rate en drilling diameter in particular. The comparison between the diameter measured on 1T-red and 1T anchors shows
p. 24/26
clearly this effect. For SA installed on the Limelette site, it can be stated that the flow rate (and/or the pressure) of the drill fluid, cement grout in this case, was probably too low in order to realise an increase of the real anchor diameter with regard to the drill bit diameter Dnom. For the 1T+inj system that was provided with two post-grouting tubes, the effect of the post-grouting operations has clearly been observed. Along the zone of Lfixed where the manchettes were present, a significant increase of the diameter up to 30% may be expected with regard to Dnom (in sand and heterog. layer)
Table 2 Overview of the Dmeas/Dnom ratios along Lfixed deduced from the investigated sites VERTICAL ANCHORS TYPE Dmeas Dnom [mm]. [mm]. 144 140 IGU 194 180 1T 180 1T+inj. 233 150 SA-150 156 INCLINED ANCHORS 154 140 IGU 201 180 1T 180 1T+inj. 216 150 1T+red. 209 90 SA-90(*) 98 130 SA-130 136 166 175 SA-175
(*)
Dmeas. / Dnom. [-] 1.03 (1.00 - 1.08) 1.08 (1.07 & 1.09) 1.29 (1.28 & 1.30) 1.04 (1.03 - 1.07) 1.10 1.12 1.20 1.40 1.09 1.05 0.95 (1.04 - 1.14) (1.15 - 1.24)
These results can be compared with the values in Table 3 that contains data concerning empirical factors (EXP) that accounts for an increase of the anchor dimension in Lfixed with regard to the nominal diameter.
Table 3. Value of the coefficient commonly used in Belgium [TA 95 (1995) and EBA (2004)] Soil Gravelly sands Fine to coarse sands Silt Clay IRS (after TA 95) 1.5 1.6 1.4 1.5 1.4 1.6 1.8 - 2 IGU (after TA 95) 1.2 1.3 1.1 1.2 1.1 1.2 1.2 SA (after EBA) 2.0 1.5
When comparing the values in Tables 2 & 3, one can concluded that the values of EXP obtained from the observations in the framework of the BBRI research on ground anchors deviate from the literature data, in particular for the self boring hollow bar anchors. With regard to those self boring hollow bar anchors, supplementary tests (phase 3) are actually performed on the Limelette test field in order to assess the influence of the drilling procedure (intensive percussive drilling) on the real anchor diameter and on the anchor capacity. During this phase 3 of the test program, IRS anchors were installed in the loam layer and are actually load tested as well. In the coming months, some of the IRS and SA anchors installed in the loam will probably be excavated in order to assess their real dimensions. The results of these observations will be subject of an addendum to the Volumes of this symposium.
p. 25/26
Finally, based on the observations made in the (clayey) sand layer on IGU systems and systems with lost point (1T) or drill bit (SA), it is proposed for the moment to introduce Dnom (diameter of the casing, lost point or drill bit) in the design.
5.
REFERENCES
Huybrechts, N., De Vos, M., Tomboy, O., and Maertens, J. 2008. Integrated analysis of the anchor load test results in Limelette and suggestions for a harmonized anchor design and test methodology in Belgium in a EC7 framework, Proceedings of the international symposium on ground anchors, May 14th 2008, Brussels. Huybrechts, N., Tomboy, O. Maertens, J. and Holeyman, A. 2008b. Full scale load test program in Limelette: overview of the test campaign, set-up & general results, Proceedings of the international symposium on ground anchors, May 14th 2008, Brussels. Recommandation TA 95 - Tirants dancrage 1995, Recommandations concernant la conception le calcul, lexcution et le contrle. Bustamante, M. & Doix, B. 1985. Une mthode pour le calcul des tirants et des micropieux injects, In Bull. liaison laboratoire des Ponts et Chausses, n 140, Nov.-Dec. page 75-92 EBA Zulassung2004. Verwendung von Verpresspfhlen System Ischebeck TITAN zur temporren Sicherung von Baugrubenwnden bei den Eisenbahnen des Bundes.
p. 26/26
BBRI
BGGG GBMS
Annex A
A1
Type : Inclined 35 SA-90-Is 8.5 : : : : NA NA Sand 20-30
Installation method :
Anchor information
Lbehind retaining wall [m]: Instrumentation
Annex A - p. 3/13
0 0.5 m
0.5 1.0 m
1.0 1.5 m
1.5 2.0 m
2.0 2.5 m
2.5 3.0 m
3.0 3.5 m
3.5 4.0 m
4.0 4.5 m
4.5 5.0 m
5.0 5.5 m
5.5 6.0 m
The lengths are given with respect to the retaining wall. The anchor bottom is situated at 8.5 m from the retaining wall.
Annex A - p. 4/13
6.0 6.5 m
6.5 7.0 m
7.0 7.2 m
The lengths are given with respect to the retaining wall. The anchor bottom is situated at 8.5 m from the retaining wall.
Annex A - p. 5/13
Soil description
0 7.2 m Yellow/white coloured dune sand
Fissures description
Not fissured except at 2.0 m where a longitudinal fissure occurred.
General comments : - Visual aspect : relatively straight anchor with some local deviations (picture a) - Surface shows traces due to the drilling procedure. The traces disappear along the 2 last meters close to the bottom. - Due to practical reasons, the anchor bottom could not be excavated, no enlargement due to post-injection could consequently be observed - Local small enlargement at 3m (picture b)
Picture a
Picture b
Annex A - p. 6/13
D meas. D nom
assumed end
Annex A - p. 7/13
Annex A - p. 8/13
A2
Type Installation method : : Inclined 35 SA-90-Is 8.5 : : : : NA NA Sand 20-30
Anchor information
Lbehind retaining wall [m]: Instrumentation
Annex A - p. 9/13
0 0.5 m
0.5 1.0 m
1.0 1.5 m
1.5 2.0 m
2.0 2.5 m
2.5 3.0 m
3.0 3.5 m
3.5 4.0 m
4.0 4.5 m
4.5 5.0 m
5.0 5.5 m
5.5 6.0 m
The lengths are given with respect to the retaining wall. The anchor bottom is situated at 8.5 m from the retaining wall.
Annex A - p. 10/13
6.0 6.5 m
6.5 7.0 m
7.0 7.2 m
The lengths are given with respect to the retaining wall. The anchor bottom is situated at 8.5 m from the retaining wall.
Annex A - p. 11/13
Soil description
0 8.0 m Yellow/white coloured dune sand
Fissures description
Not fissured
General comments : - Visual aspect : relatively straight anchor with some local deviations (picture a) - Surface shows traces due to the drilling procedure. The traces disappear along the 2 last meters close to the bottom - Due to practical reasons, the anchor bottom could not be excavated, no enlargement due to post-injection could consequently be observed
Picture a
Annex A - p. 12/13
D meas. D nom
assumed end
Annex A - p. 13/13
BBRI
BGGG GBMS
Integrated Analysis of the Anchor Load Test Results in Limelette & Suggestions for Harmonised Anchor Design and Test Methodology in Belgium in a EC7 Framework
Ir. Noel Huybrechts, Ir. Monika De Vos & Ir. Olivier Tomboy Belgian Building Research Institute (BBRI) Geotechnical & Structural Division
Prof. Ir. Jan Maertens Jan Maertens bvba & Catholic University of Leuven (KUL)
1.
INTRODUCTION
This contribution summarizes the analysis of the load test results on different anchor types performed in the framework of phase 1 and phase 2 of the anchor test campaign in Limelette. In the contributions of Huybrechts & Maertens (2008) and Tomboy & Huybrechts (2008) to this Volume a general overview has been given of the anchor installation techniques, the test results and the observations and measurements on the excavated anchors. In this contribution it is the objective to summarize the methodology that has been applied to analyse the test data taking into account all available data and to formulate some general conclusions with regard to the Limelette anchor test campaign. For a detailed report of this integrated analysis, reference is made to Volume 2 of the proceedings of this symposium. Finally, some suggestions for a harmonised anchor design and test methodology in Belgium taking into account Eurocode 7 principles and anchor practice in Belgium are formulated.
2.
2.1. Determination of Pu
p. 3/21
Table 1 : Ultimate anchor load Pu of the anchors tested in Limelette Pu determined out of creep curve following prEN 22477-5 conventional criteria =5 (TM3) or =2 (TM1)
(*)Preliminary anchors
p. 4/21
Load (kN)
1000
(increasing)
Pmax Pu
0
E16-17 E28-29 E15-16 E27-28
Figure 1 : Comparison of ultimate anchor load Pu versus maximum applied test load (the value between brackets equals the time in minutes that Pmax has been maintained before the anchor failed when increasing is noted that means that the anchor failed during increasing the load for the next step if no value is given than Pmax corresponds with mechanical steel limit or Pu)
p. 5/21
900 800 700 600 stress (MPa) 500 400 300 200 100 0 0 500 1000 1500 2000 Fellenius Ischebeck TITAN 73/45 (A=2260mm) Fellenius Dywidrill T76N (A=1900m) Fellenius strands (A=1057 mm) theoretical relationship (E=210 GPa) fy TITAN 73/45 fy T76N 2500
-6
3000
3500
4000
4500
strain (10 )
With this approach the following could be obtained for several anchors; the friction losses in the free length Lfree, which exist out of internal friction losses between tendon and plastic tubing and out of friction mobilised along the outer of the grout column in Lfree the load distribution in the anchors fixed length Lfixed the mobilisation curves of the unit shaft friction (qsi curves). For the anchors installed in the heterogeneous clayey sand and the tertiary sand layer, this analysis revealed average total friction losses in Lfree of 14% of the ultimate anchor load Pu for the strand anchors and 19% of Pu for the self boring hollow bar anchors. For the anchors installed in loam, the load losses in Lfree corresponding with the ultimate anchor load Pu have been estimated on 7% (based on limited information). For more details with regard to this analysis reference is made to Volume 2 of the proceedings of this symposium.
p. 6/21
Belgium based on CPT data; i.e. curves from TA95 (CFMS, 1995) for IGU and IRS anchors and an empirical rule which states that qs=0.0033.qc with a maximum of 466 kPa.
BBRI project Ground Anchors - Result Limelette qs(qc) in Sand & Heterogeneous layer 1000 900 800 700 600 qsu (kPa) 500 400 300 200 100 0 0 4 8 12 16 20 qc,av (MPa) 24 28 32 36 40 qs = [Pu-W tot]/(..Dnom.Lfixed) - with real or average if not available - with real loss W tot or average if not available IGU-TA95 IRS-TA95 qc/30 IGU-sand-TM3 IGU-sand-TM1 IGU-Verticaal-TM3 IGU-Verticaal-TM1 IGU-Het.-TM3 IGU-Het.-TM1 1T-sand-TM3 1T-Dred.-sand-TM3 1T-Verticaal-TM3 1T+inj-Verticaal-TM3 1T+inj-Het.-TM3 SA-sand-TM3 SA-Verticaal.-TM3 SA-Het.-TM3 2T-grav -Verticaal
Figure 3 : qsu-qc,av for anchors tested in tertiary sand and clayey sand in Limelette only the real load on the fixed length is considered (by taking into account friction losses in Lfree and the real anchor diameter)
BBRI project Ground Anchors - Result Limelette qs(qc) in Silt layer 300
250 IGU-TA95 200 qsu (kPa) IRS-TA95 qc/30 150 IGU-silt-TM3 SA150-silt-TM3 100 qs = [Pu-W tot]/(..Dnom.Lfixed) - with = 1 for SA and IGU - with average loss W tot SA76mm-silt-TM3
50
0 0 2 4 qc,av (MPa) 6 8 10
Figure 4 : qsu-qc,av for anchors tested in silt (loam) in Limelette - only the real load on the fixed length is considered (by taking into account friction losses in Lfree - is assumed to be 1)
p. 7/21
method,
real
anchor
In Volume 2 of the proceedings of this symposium, an attempt has been made to represent on some figures some important anchor installation data together with the measured anchor dimensions, the test method and the test results. Two examples are given in Figure 5 for a 1T+inj anchor and an IGU anchor.
Figure 5 : Dmeas versus Dnom for an inclined 1T+inj anchor in the heterogeneous clayey sand layer and an inclined IGU anchor in the tertiary sand layer - inclination equals 25 with regard to the horizontal and Dnom corresponds with the diameter of the lost drill point(1T+inj.) or diameter of the casing (IGU).
p. 8/21
3.
Figure 6 : qsu qc curves of the anchors tested in clayey sand and sand - only the real load on the fixed length is considered (by taking into account friction losses in Lfree and the real anchor diameter)
p. 9/21
On the same Figure 6 it can be observed that: the variation of the results is o very high for the IGU anchors, o lower for the 1T anchors, o considerably low for the SA anchor; the result of the gravity filled anchors 2T-grav are situated in the intervals of the 1T and SA anchors; the results of the IGU anchors that are situated in the area of the 1T and SA anchors are almost all vertical anchors. Out of these observations it might be concluded that the 1T and the SA anchors that have been performed at the Limelette test site can be considered as gravity filled anchors. This is not surprising when looking at the installation monitoring of these anchors (almost no pressure during injection). The fact that for the SA anchors the results can be situated in a narrower interval is probably due to the very regular form of these anchors (see Tomboy, 2008). Moreover the high variation obtained for the IGU anchors evidences the effect of the stepwise grout injection procedure, and the beneficial effect of pressure grouting on the obtained qs values. It is not surprising that the qsu values of vertical IGU anchors are situated in the zone of the gravity filled anchors, as it could in general be observed that the grout injection procedure was not very successful for the vertical anchors (probably due to the shorter lengths Lfixed and Lfree). Moreover, the shape of the vertical anchors seems in general to be some what more regular than the shape of the inclined anchors. The beneficial effect of pressure grouting and an irregular anchor form on the anchor capacity is also confirmed by the results obtained for the 1T+inj anchors. Anchor capacity of the different anchorage systems in silt (loam) For the anchors of which Lfixed is installed in loam, the real unit shaft friction has been determined based on limited information: only for one anchor the friction losses in the free length were determined, and based on observations for the sand anchors it has been assumed that Dreal = Dnom. This leads to the following results in loam with cone resistances between 3.4 and 4.5 MPa (see Figure 4). For the IGU anchors : For the SA-150-Dy : For the SA-76-Dy : qsu = 0.040 to 0.045 qc,av qsu = 0.030 to 0.040 qc,av qsu = 0.045 to 0.072 qc,av
Based on these results one can conclude that: The variation of the results obtained for the IGU anchors is rather low. This can probably be explained by the fact that the dimensions of the IGU anchors in the loam layer are regular (assumption based on observation in Lfree of excavated IGU anchors). Moreover it has been observed during installation that the grout pressures that could be realised in loam are comparable for the different anchors. With regard to this stepwise grout injection it was found that the realised pressures were not high (maximum 8 bar, mostly 5 bar) and that for each injection step grout leakage to the surface occurred.
p. 10/21
For the SA-150-Dy anchors installed with a drill bit with diameter of 150 mm, the qsu values that are obtained are somewhat lower than those obtained for the IGU anchors. Out of the differences between the results of the IGU and the SA-150-Dy anchors in loam, and out of the observations during installation, one could conclude that the SA-150 anchors in loam can be considered as gravity filled anchors and that the grout injection procedure for the IGU anchors show some beneficial effect but less significant than in sand. For the SA-76-Dy anchors installed with a drill bit with diameter of 76 mm, the obtained qs values are 50% higher than the SA-150-Dy. As in general it is assumed that in cohesive layers the unit shaft friction is independent from the anchor diameter (cfr. Ostermayer & Barley, 2003), especially for gravity filled anchors, this could possibly indicate that the real diameter is considerably higher than the nominal drill bit diameter. Influence of the inclination on the anchor capacity (anchors in sand) On first instance, looking at the ultimate anchor load deduced from the test results (see Table 1), it was found that for all systems the capacity of the vertical anchors was significantly lower than the capacity of the inclined anchors. However, after corrections for friction losses in the free length and taking into account the measured anchor dimensions to determine the anchors real unit shaft friction, this difference becomes insignificant for the SA anchors and less significant for the 1T anchors. Only for the IGU anchors the vertical anchor capacity remains significantly lower than the inclined anchor capacity, but as explained before, the main reason for this is probably the less successful grout injection procedure compared to that of the inclined IGU anchors. Probably the less regular form and straightness of the inclined anchors might explain some of the remaining differences as well. Based on this argumentation it can be concluded that the inclination in itself has no significant influence on the anchor capacity in the Limelette sand layer. This was also confirmed by the comparison between cone resistances obtained with vertical and inclined CPT showing no significant differences (See Volume 2 of the proceedings of this symposium). With regard to the influence of the length on the bond stress, the bond stress evolution and/or the (non-) linear increase of anchor capacity with Lfixed Based on the obtained information about bond stress evolution along Lfixed as deduced from the load distribution measurements (see Volume 2) it can be concluded that: For SA anchors with Lfixed up to 6 m in heterogeneous clayey sand and tertiary sand tested according to the maintained load test procedure (TM3), the value of the unit shaft friction qsi in the different anchor zones in Lfixed continue to increase; no peak value and consecutively no residual value of qsi have been observed. For some of these anchors that did not fail under Pmax such behaviour was however observed when the anchor was submitted to subsequent Pa-Pmax cyclic loading.
p. 11/21