Escolar Documentos
Profissional Documentos
Cultura Documentos
The cost of constructing underground transmission lines is determined by the local environment and the distances between splices and termination points . Other issues that make underground transmission lines more costly than overhead lines are right-of-way access and maintenance, construction limitations in urban areas, conflicts with other utilities, trenching construction issues, crossing natural or manmade barriers, and the potential need for forced cooling facilities.
Repair costs
Repair costs for an underground line are usually greater than costs for an equivalent overhead line. Leaks can cost $50,000 to $100,000 to locate and repair. A leak detection system for a HPFF (High-pressure, fluid-filled pipe) cable system can cost from $1,000 to $400,000 to purchase and install depending on the system technology. Molded joints for splices in XLPE (Cross-linked polyethylene) line could cost about $20,000 to repair. Field-made splices could cost up to $60,000 to repair. A fault in a directionally drilled section of the line could require replacement of the entire section. For example, the cost for directional drilling an HPGF cables is $25 per foot per cable. The cables in the directional drilled section twist around each other in the pipe so they all would have to be pulled out for examination. Easement agreements may require the utility to compensate property owners for disruption in their property use and for property damage that is caused by repairing underground transmission lines on private property. However, the cost to compensate the landowner is small compared to the total repair costs. Underground transmission lines have higher life cycle costs than overhead transmission lines when combining construction, repair and maintenance costs over the life of the line.
Siting Impacts
The impacts of underground transmission lines differ from those of overhead transmission lines during construction and afterwards. Underground lines generally cause greater soil disturbance due to trenching requirements, while overhead lines disturb the soil primarily at the location of the transmission poles. Trenching an underground line through farmlands, forests, wetlands, and other natural areas causes significant land disturbances. The ROW for underground transmission lines must be kept clear of trees and bushes, while small trees and bushes are allowed within the ROW under overhead lines. Post-construction issues such as aesthetics, concerns regarding electric and magnetic fields (EMF), and property values are usually less of an issue for underground lines. Underground lines are not visible after construction and have less impact on property values and aesthetics.
Background
The basic function of electrical cable in a power plant is to transmit instrument signals, control signals, and electrical power. In most non-nuclear power applications, cables are not required to function under adverse environmental conditions. For these cables, operability means that the cable will continue to conduct the signal or power, while maintaining satisfactory insulation characteristics such that unacceptable levels of signal attenuation or shorting do not occur. However, certain cables in safety-related applications in nuclear power plants may be required to function while exposed to harsh environmental conditions if an accident occurs. For these cables, operability includes the ability to remain functional during normal conditions while maintaining the capability to operate satisfactorily for a specific period in an accident environment (e.g., loss-of-coolant accident). Recently, cable installation and operability concerns were raised about low-voltage cabling in nuclear safety-related service that could potentially be exposed to accident
environments. The concerns were first raised as a result of installation practices that were alleged to have deviated from industry standard, accepted, or good practices. The deviations consisted of excessive lengths of unsupported vertical cable drops, reduced bending radii of cable during and after installation, installation of new cable in raceways in a manner that could damage existing cable, impact damage to cable during installation, and other related handling and installation concerns.
Scope of research
The scope of the research covered the following specific areas and their relevance to cable operability:
General cable construction features Cable applications Physical installation practices Environmental qualification practices Record of past cable performance Differences in medium-voltage power, low-voltage power, control, and instrumentation cable stresses during service and testing Efficacy of standard insitu testing for: 1. Suspect installations 2. General cable condition monitoring Significance of available ground plane at the surface of cable insulation in relationship to cable condition monitoring via electrical tests Cable performance in support of connected devices during accident conditions Operating voltage versus rated voltage Relationship between required safety function and intrinsic cable capability Efficacy of existing industry standards, codes, and guidelines
National Electrical Code design considerations as applied to Utility Substations (on photo: Mina Manama in Bahrein by Cebarco Bahrain)
This paper will discuss a few specific applications of the NEC while referencing the use of the more prevalent NESC and IEEE documents in utility applications.
One very effective way of lowering ground resistance is to drive ground electrodes deeper. Soil is not consistent in its resistivity and can be highly unpredictable. It is critical when installing the ground electrode that it is below the frost line . This is done so that the resistance to ground will not be greatly influenced by the freezing of the surrounding soil. Generally, by doubling the length of the ground electrode you can reduce the resistance level by an additional 40%. There are occasions where it is physically impossible to drive ground rods deeper-areas that are composed of rock, granite, etc. In these instances, alternative methods including grounding cement are viable.
Increasing the diameter of the ground electrode has very little effect in lowering the resistance . For example, you could double the diameter of a ground electrode and your resistance would only decrease by 0%.
#eneral Tec!nical Speci$ication %or &&'() S%* #as +nsulated etal Enclosed Switc!gear ,#+S&.
General Tender Technical Specification For SF6 Gas Insulated Metal Enclosed Switchgear (GIS) - photo by directindustry.com: ABB Gas insulated primary distribution switchgear
'eneral
The SF6 gas insulated metal enclosed switchgear shall be totally safe against inadvertent touch of any of its live constituent parts. It should be designed for indoor application with meteorological conditions at site ( winter 3C to 14 C and Summer 31 C to 46 C, seismic zone: IV ) . All parts of the switchgear should be three phase enclosed for 220kV GIS.
The arrangement of gas sections or compartments shall be such as to facilitate future expansion of incomer bay with any make on either end without any drilling, cutting or welding on the existing equipment. To add equipment, it shall not be necessary to move or dislocate the existing switchgear bays. The design should be such that all parts subjected to wear and tear are easily accessible for maintenance purposes . The equipment offered shall be protected against all types of voltage surges and any equipment necessary to satisfy this requirement shall be deemed to be included. The required overall parameters of GIS are as follows:
4. Rated Power frequency withstand Voltage (1 min) line to earth 5. Impulse withstands BIL 1.2/50/mic. 1050 kVp Sec) Line to earth 6. Switching impulse voltage (250/2500 mic-sec) 7. Rated short time withstand current (1 40 kA (rms) sec) 8. Rated peak withstand current 100 kA (peak) 9. Guaranteed maximum gas losses or As per IECcomplete installation as well as for all 62271-203 individual sections in %. 10. Seismic level Zone-IV, as per IS-1893,Year2002
The metal-enclosed gas insulated switchgear , including the operating devices, accessories and auxiliary equipment forming integral part thereof, shall be designed, manufactured, assembled and tested in accordance with the IEC- 62271-203/IEC-62271-200 publicationsincluding their parts and supplements as amended or revised to date.
Reference Standards
The metal-enclosed gas-insulated switchgear, including the operating devices, accessories and auxiliary equipment forming integral part thereof, shall be designed, manufactured, assembled and tested in accordance with the following International Electro-technical Commission (IEC) standards including their parts and supplements as amended or revised till date:
IEC 62271-203 - Gas Insulated metal-enclosed switchgear for rated voltages above 52KV. IEC 60376 - New sulphur hexafluoride IEC 62271- 100 High voltage alternating current Circuit breakers IEC 60694 - Common clauses for high voltage Switchgear and control-gear standards IEC 62271-102 - Alternating current disconnectors (isolators) and earthing switches. IEC 61128 Alternating current disconnectors. Bus-transfer current switching by disconnectors. IEC 61129 Alternating current earthing switches. Induced current switching IEC 66044-1 Current transformers IEC 66044-2 Voltage transformers IEC 60137 Bushings for alternating voltages above 1000 V IEC 60859 Cable connections for gas-insulated switchgear
IEC 60480 Guide to checking of sulphur hexafluoride taken from electrical equipment IEC 60099-1/4 Non-linear resistor type arresters for AC systems IEC 60439 Factory-built assemblies of low-voltage switchgear and control gear. IEC 60427 Report on synthetic testing of high-voltage alternating current circuit breaker. IEEE 80 (2000) IEEE Guide for Safety in AC Substation grounding. CIGRE-44 Earthing of GIS application guide. (Electra no.151, Dec93)
The components and devices which are not covered by the above standards shall conform to, and comply with, the latest applicable standards, rules, codes and regulations of the internationally recognized standardizing bodies and professional societies as may be approved by the Purchaser. The manufacturer shall list all applicable standards; codes etc. and provide copies thereof for necessary approval. In case the requirements laid down herein differ from those given in above standard in any aspect the switchgear shall comply with the requirements indicated herein in regard thereto.
o me / Do )n l o a d Ce nt e r / Bo o ks *n d ' ui d e s / +o )e r Su % st a ti o n s / 1i ti g a te , h e 1a g n et i c - ie ld E4p o su r e Ne ar , ra n sf o r me r Su % st a ti on
We were contacted by the owner of the apartment above the TS to estimate the field levels inside the apartment . First measurements shoved magnetic flux density up to values of 15 Tinside the apartment above the TS.
1easurements
Magnetic field is linearly correlated to the actual current load , but this can vary during the day depending on the present use. To obtain the detailed snapshot of the magnetic field in the apartment above the TS it is therefore not enough to make only spot measurements, but also 24-hour measurements to evaluate the time variability of the magnetic field and determine worst case condition.
For spot measurements we have used Wandel & Goltermann EM field analyzer EFA-3 with the B field probe. For 24-hour measurements we have used automatic measurement station PMM 8055 which measures the magnetic flux density continuously 24 hours per day. It consists of measurement probe for ELF magnetic flux density HP-051, control unit with the GSM modem to send the measurements from the measurement station to the server connected to the internet, housing with solar cells and accumulator. After the data are automatically transferred to the server, they could be viewed by everyone through an internet application. According to the Slovenian legislation and the international standards (IEC 61786) the magnetic flux density is measured at the height of 1 or 1.5 m above the ground . But in the apartment, it is not uncommon that the children have their beds on the floor or do they play on the floor and with measurements 1 m above the ground the exposure would be greatly underestimated. Therefore all the measurements spot and continuous 24-hour were taken at the height of 0.2 m above the ground.
Numerical calculations
We used program package Narda EFC-400EP for numerical modeling of the magnetic flux density in the vicinity of the TS. It is based on segmentation method where each conductor is presented with finite segments. Corresponding material and electromagnetic characteristics are assigned to all the segments and the resulting magnetic field is the sum of the contributions of all the segments .
Electrical shock
There is no way to tell if an electrical conductor or terminal is alive just by looking at it, it should be tested using an appropriate approved tester. Thereafter it should be made safe in such a manner that it cannot be energised by someone else whilst it is being worked on.
Electrical %urns
With medium voltage it is not necessary to touch a conductor or terminal in order to get burned. Air does not normally conduct electricity however, when a person gets too close to an electrical wire that is not properly insulated, the air can break down and form a conducting path between them to earth. Coils and capacitors store electrical energy and release it after power has been turned off and should, therefore, be discharged before work commences.
5eat %uild up
Heat can build up in wires. A lightweight extension lead gets hot when used for heavy duty service. Avoid using extension leads at all, if possible. If they must be used, ensure they can carry the current without overheating. Do not string them overhead, across aisles and under mats, where heat can build up and fully extend them.
1echanical ha6ards
Electricity is often used to run machinery, rotating machinery and moving parts are always a source of danger, always ensure that guards are in place. Make sure the machine you are working on cannot be turned on without your knowledge.
Electrical design of the on-site generation system (photo by Cummins Power Generation via Flickr)
78er8ie)
The electrical design and planning of the onsite generation system is critical for proper system operation and reliability. This chapter covers installation design of the generator and related electrical systems, their interface with the facility, and topics regarding load and generator protection. One key element for understanding and communication of the electrical system design is a oneline diagram such as the one depicted in Figure 1 below. The electrical installation of the generator set and its accessories must follow the Electrical Code in use by local inspection authorities. Electrical installation should be done by skilled, qualified, and experienced electricians and contractors.
The oneline configuration differences are easy to see. For example, in prime applications the gensets are at the top of the distribution system while in standby and especially in emergency applications the gensets are connected to loads toward the bottom of the distribution system. Power transfer points in prime applications tend to be at the top of the distribution, switching large blocks of load, often with circuit breaker pairs while emergency and standby systems often utilize transfer switches located further down in the system. Other differences are more subtle. Protection in a standby system is minimized in favor of greater reliability while in prime power we tend to move toward greater emphasis on protection of equipment. Coordination is often more of a concern in emergency applications. In standby applications grouping of loads might be commonly done based on location of loads within the facility, while in emergency applications, the grouping is based on priority of service. In any system design, local codes and standards will have a significant impact on the overall system design, hardware, and other application details. Local codes and standards should always be consulted prior to undertaking any design or modification work. This section is intended to cover these major points and other details, to provide general guidance on power system design.
Introduction to IEC 61439 - A new standard on Switchgear and Controlgear Assemblies (photo by ba-online.info)
Introduction
IEC 60439, the standard for low-voltage switchgear and controlgear assemblies , was under restructuring from the last decade. The new series of IEC 61439 standards were published in January 2009. This standard has brought considerable clarity in technical interpretation. The new standard follows the philosophy of IEC 60947 series i.e. IEC 61439-1 is General Rules standard to be referred to by subsidiary product parts of IEC 61439 series. The IEC 60439 standards were ambiguous about how to assess compliance of partially type tested assemblies. As a result manufacturers and testing bodies often treated partially type-tested assemblies differently. One of the main features of IEC 61439-1 is that the discrimination between Type Tested Assemblies (TTA) and Partially Type Tested Assemblies (PTTA) has been eliminated by the verification approach. The three different but equivalent types of verification methods are introduced and these are: 1. Verification by Testing 2. Verification by Calculation/Measurement 3. Verification by Design rules The requirements regarding short circuit performance, temperature rise , dielectric properties and rated diversity factor have been covered in more detail.
Ground Fault Protection Technical Guide (On photo: Schneider Electric ACTI9 wiring devices)
What is 'rounding?
The term grounding is commonly used in the electrical industry to mean both equipment grounding and system grounding. Equipment grounding means the connection of a non-current carrying conductive materials such as conduit, cable trays, junction boxes, enclosures and motor frames to earth ground. System grounding means the connection of the neutral points of current carrying conductors such as the neutral point of a circuit, a transformer, rotating machinery, or a system, either solidly or with a current limiting device to earth ground. Figure 1 illustrates the two types of grounding.
4.
5a6ard scenarios
Consideration of appropriate safety criteria (usually an allowable shock voltage ) is required for all electrical assets that form part of the network. Consideration should be made for substations ( both inside and outside ) and for the accessible portions of the powerlines and cables. As fault current can be coupled to non-power system plant, so it is required to also consider the safety requirements at those locations outside the substations and easements. The specific locations will represent a different risk profile by virtue of the fact that there will be different coincident probabilities of system events and human contacts and different series impedance ( for example, footwear and surface coverings ). Consideration should be given to factors such as:
1. 2. 3. 4.
5. 6.
Probability of multiple simultaneous human contacts ( particularly in public places ), (i.e. touch, step, hand-to-hand or transfer voltage impacts) Susceptible locations (wet areas) Controlled access areas (fenced easements or remote areas ) Series impedance (surface coverings and footwear )
Future possible encroachments upon the electrical network and the effect of system events on those encroachments Conductive and inductive coupling into non-power system plant such as communications infrastructure, telecoms, pipelines and conveyors. Not all risk is imposed by the earthing system. There are external factors that may also impact upon the earthing system resulting in a change in the risk profile of the installation. Figure above summarises the main risk elements in each category. Some external factors that need to be addressed ( during design and installation ) are theft and/or vandalism of earth system components. Consideration should be given to protecting exposed components and/or monitoring key components to ensure an acceptable risk profile. The interaction between the substation or powerline earthing systems and secondary systems ( for example, SCADA) needs also to be considered as those systems can adversely affect each other.
Risk management
All life activities involve some form of inherent risk. The tolerability of injury or death to a member of the public is therefore dependent upon several factors including the types of hazards, the control measures implemented, frequency of occurrence, the likelihood of actions of the individual(s) exposed and the associated consequences. Risk in this context is defined as the chance of something happening that will have an impact on objectives (i.e. a combination of the consequences of an event and their likelihood, frequency or probability). The risk associated with a hazard is determined using a risk assessment process in which hazards are identified, analysed using quantitative methods and qualitatively assessed against specific criteria. Once the risks are evaluated, the appropriate risk treatment process shall be implemented where appropriate to effectively and efficiently manage the risks.
#rounding Systems
Design Considerations
The general purpose of earthing system is to protect life and property in the event of 50/60 Hz faults (short-circuit) and transient phenomena (lightning, switching operations). The question of how a system shall be earthed is governed by the regulation.
The choice of earthing to one point on each system is designed to prevent the passage of current through the earth under normal conditions, and thus to avoid the accompanying risks of electrolysis and interference with communication circuits. Earthing may not give protection against faults which are not essentially earth faults (i.e.: when a phase conductor on an overhead-line breaks ). The earthing of an electrical system depends on several criteria: 1. Location within power generation center 2. Networks 3. Regulations. Several methods exist for system earthing which can be divided into: 1. Insulated 2. Solid earthing 3. Impedance earthing The protection scheme depends on earthing methods.
Insulation Coordination
The earth fault current will induce locally an over voltage which must be compatible with the insulation of low and medium voltage components, to ensure the continuity of supply.