Escolar Documentos
Profissional Documentos
Cultura Documentos
2007
2
Piling v.3:Layout 2 27/7/07 15:58 Page 3
What this guidance does not cover Pile types in this guidance note are grouped Large displacement piles
This guidance note is only concerned with and described following Tomlinson (1994) (Fig 3). Large displacement piles can be constructed
piling impacts; it does not cover other impacts from concrete, metal or, rarely, wood, and are
associated with pile construction, such as piling Displacement piles installed by hammering, jacking or vibrating the
mats or the excavation of pile caps, or other Displacement piles push the sediment aside piles (or tubes) into the ground (Fig 5). A drop-
aspects of construction.These are covered in as they are installed, compressing the ground hammer simply drops a large weight onto the
study of the Mitigation of Construction Impacts and increasing the bearing capacity of the top of the pile, however, they produce
on Archaeological Remains (Davis et al 2004), foundation. Displacement piles are significant vibration. Hydraulic hammers use a
which provides information on pre- environmentally positive in the sense that controllable powered ram and are quieter and
construction, construction and post- there is no need to remove spoil, no landfill cause less vibration than the drop-hammer. If
construction impacts on archaeological remains. requirements, and reduced vehicle movements.
It is also assumed that the use of piled This is particularly important on contaminated Fig 1 (top left) End bearing pile, where the pile is
foundations as a means of mitigation is a choice sites where the arisings (spoil) would founded in the hard incompressible layer rather than
that is taken in the context of other the soil above.
require remediation.
construction, planning and archaeological There are several forms of displacement Fig 2 (top right) Friction bearing pile, where the
mitigation scenarios, including the refusal of pile (Fig 4). sediment becomes increasingly stiff with depth.
planning permission for the construction of a Fig 3 (middle) Pile types (after Tomlinson 1994, ch 8).
particular development, the use of shallow
foundations, the redesign of any structures to Fig 4 (bottom) Displacement pile types (after
avoid below-ground disturbance or Tomlinson 1994, ch 8).
preservation of the site ‘by record’, through
archaeological excavation.
Piling types
Piling is a method of transferring load from a
structure into the ground.The engineering
objective of a pile is to support a structure by
using the strength of the ground some distance
below the surface that can resist the imposed
force.This can be by direct bearing onto a firm
stratum present at depth below the site or by
using the frictional resistance of the soil against
the pile shaft to develop the load-bearing
capacity. In some cases a combination of these
is used where the pile is founded on a firm
horizon and the sides develop surface friction
(Figs 1 and 2).
3
Piling v.3:Layout 2 27/7/07 15:58 Page 4
Fig 5 (above top) Displacement pile installation: Piles The concrete may be prestressed to enhance
arrive at site, pile located, pile section driven, durability. Hollow piles are often used when
additional section attached, pile driven (image large diameters (>500mm) are needed and are
courtesy of Cementation Foundations Skanska). hollow for ease of handling, or for economy.
Fig 6 (above right) Preformed concrete displacement For hollow steel piles, concrete is poured into
pile being installed, photograph courtesy of Mike Brown.. the hollow section to complete the pile (as for
driven cast in situ), except that in this case the
Fig 7 (above) Illustration of driven cast in situ pile
tubes are not withdrawn.
installation: tube located and driven into ground, filled
with concrete, tube withdrawn leaving completed pile
(image courtesy of Cementation Foundations Skanska). Driven cast in situ
This method is used less often than driven
Fig 8 (right) Cast in situ pile: having been driven, the precast piles (Figs 7 and 8). A tube (steel or
concrete is being poured down the metal tub
precast concrete) with a sacrificial shoe or
(photograph from Cementation Foundations Skanska).
detachable point is driven into the ground,
sediments are soft, preformed piles are jacked displacing and compacting the soil around
rather than hammered in, which has the the tube. Reinforcement is lowered into the
advantage of being quiet and effectively tube and concrete poured into it. As the
vibration-free. concrete is added, the tube is withdrawn
and the concrete may be compacted.This
Driven preformed piles method is normally used to create piles from
Solid piles are usually constructed from precast about 250–500mm diameter with depths
concrete (and occasionally wood) and come as of up to 25m.
specific lengths or sections joined together to
form a longer pile (up to c 40m). Low This method is particularly useful in
headroom rigs can therefore be used in areas contaminated soils, because no arisings are
of restricted access.The normal range of produced; however, removal of the tube can
preformed concrete pile sizes in the UK is cause distortion of the surrounding sediment
2
150 to 300mm .The advantage of using and may allow movement of liquid concrete
preformed concrete piles (Fig 6) is that there is into voids.
no need to wait for concrete to set, nor for
liquid concrete to be transported to, or Auger displacement piles
prepared on, site.The pile sections can be This method uses a spiral auger that displaces
coated before insertion to prevent reaction the spoil laterally into the ground around the
with the surrounding soil and improve hole. Concrete is poured down the auger shaft
concrete durability. as the auger is withdrawn.The displacement
consolidates the ground surrounding the pile,
Hollow piles are tubes generally constructed of resulting in enhanced soil properties and
steel or occasionally precast concrete. therefore shorter pile lengths.
4
Piling v.3:Layout 2 27/7/07 14:52 Page 5
Pile sizes will depend on the individual pile makes this method unsuitable in built-up areas Fig 9 (top) Sheet pile retaining wall along right edge
company’s specific auger design, but diameters and adjacent to fragile historic structures. of site, courtesy Pre-Construct Archaeology Ltd.
of 300mm to 600mm are likely.This type of pile Fig 10 (middle left) Rolled steel tube being installed
is relatively ‘green’, its installation producing very Replacement (bored) piles at Skirbeck Road, Boston.
little spoil, vibration and noise. Replacement piles are installed by boring a
Fig 11 (middle right) Displacement pile being installed
hole, removing the arisings and filling the hole
in Boston.
Small displacement piles with concrete (and often reinforcement) (Fig 12).
Preformed steel The bore tends to consist of a screw-type auger Fig 12 (bottom) Illustration of rotary bored pile
Small metal piles (H-section, sheet, tube or on a piling rig, which augers directly into the construction.The auger is located and begins to remove
box) are hammered, vibrated or jacked into the ground and removes arisings in a series of passes, soil, a temporary casing is installed to prevent the
upper deposits collapsing, further material is
ground. Sheet piles (Fig 9) are often using a ‘flighted’ or bucket auger. Light cable
removed, the concrete and reinforcement are added,
constructed as interlocking piles, used to create percussion bores (shell augers) are also used to the casing is removed and the pile is complete (image
cofferdams or retaining walls, and less often to construct a hole, using a hollow cylinder which courtesy of Cementation Foundations Skanska).
support load from a structure above. Where is hammered into the soil, and then the enclosed
they are used for retaining walls, sheet piles soil removed before another length of cylinder
may also need tie-backs, which will have a is added and pushed further into the ground to
further impact on adjacent deposits. continue deepening the hole. Piles are usually cast
in situ or occasionally constructed using pre-cast
Smaller metal piles include rolled steel sections, concrete ring sections, which are then filled with
screw piles and H-section piles. Rolled steel concrete. Piles can be constructed with diameters
section piles are easily handled and can be of up to 3m, and can be bored to depths of up
driven hard, and in very long lengths; and while to 70m, with under-reamed bases up to three
the pile length can be readily varied, lengths of times the shaft size. Small diameter bored piles
up to 36m can be achieved. are usually less than 600mm diameter and can
reach 30m in most ground conditions. Bored
Screw piles can reach 24m in depth, carry mini-piles are of the order of 200–300mm in
heavy loads and can be successfully anchored diameter and reach up to 15m deep.
in steeply sloping rock surfaces.The piles
are liable to corrosion, which can be treated In some instances a casing is inserted, usually
using cathodic protection, or a pile coating. temporarily, to prevent the collapse of the hole,
Steel screw piles, consisting of a number of and the auger drills inside this. In the case of
curved spirals of steel connected to a central continuous flight-augered (CFA) piles, the
shaft, have been recently used on an arisings are removed at the end of the
archaeological site and this is cited as a case operation when the auger is removed, making
study.They are easily removable, and are likely support unnecessary. With any of the
to cause minimal sub-surface disturbance.
5
Piling v.3:Layout 2 27/7/07 14:54 Page 6
replacement piling methods, there is typically has been formed, although some are left in unstable sediments and the transport, use,
little or no sediment displacement adjacent to place permanently, even though this adds storage and disposal of these materials and
the shaft of the pile. Increased pile capacities significantly to the cost. fluids all need to be taken into account.
can be achieved through the formation of
enlarged pile bases (under-reams) (Fig 13). Unsupported replacement piles
Continuous flight auger (CFA)
Supported replacement piles The CFA technique is one of the most
In unstable soils a casing or a drilling mud/slurry, commonly used piling forms and can be used
such as bentonite, may be used to support the in most soils.The hole is augered out and high
borehole walls.The choice between using metal slump concrete is pumped into the hole
casing or slurry is an engineering decision; through the auger shaft to the base (Figs 14
generally casings are used to line a relatively and 15).
shallow depth of unstable ground to reach a
self-supporting stratum below, while a drilling As the concrete is inserted, the auger is
mud is used to support unstable ground at withdrawn, taking the arisings with it. A
lower levels. reinforcing cage can then be pushed into the
liquid concrete. Practically no vibration or noise
Temporarily supported is created using this piling technique. Pile
A drilling mud such as bentonite would be diameters are usually 0.3–1.2m and they can
used when piling through a deep, unstable reach depths of 25m. Casing is rarely needed
stratum and subsequently pumped out.The use as the sides of the bore do not need
of bentonite has specific implications, including supporting as the arisings are not removed
adverse environmental effects and the large until the concrete is pumped in.
space required for bentonite plants on site.
Additionally it may be classified as controlled Engineering advantages and disadvantages of
waste, in which case disposal requires special replacement piling
precautions and additional expense. Synthetic The benefits of using replacement piles include
polymers may be used instead of bentonite, the variability of length and diameter, the low
although their use is currently less common. risk of ground heave resulting from pile
Pile casings are generally metal tubes inserted installation, and the low noise and vibration.
into the ground by driving, vibration, oscillation
or rotation. Noise and ground vibration can be Disadvantages include the need to bring liquid
high where a casing is installed.These levels, concrete to site, or create concrete/bentonite
however, will generally be much less than for plants on site. A further disadvantage is that
driven pile installation, although tripod-bored CFA piles cannot be inspected once cast. For
piles can also produce significant noise and bored piles where a drilling mud has not been
vibration. Sometimes casings are installed by used, the open pile bore can be inspected
‘mudding in’, the contact between the casing before placing of concrete, so the length, depth,
and soil being lubricated using bentonite.This shaft, and base quality and verticality can be
can significantly reduce the noise and vibration easily verified. Support fluid or casings are
effects. Most casings are removed after the pile usually required to construct bored piles in
6
Piling v.3:Layout 2 27/7/07 14:54 Page 7
Pile-retaining walls construction. Key techniques are vibro aggregate is inserted and vibrated to bond with
Bored pile-retaining walls are created by drilling compaction and the creation of columns using the surrounding soil.Vibro compaction is rarely
a line of holes and forming piles either as displacement and replacement methods, such used in the UK; it requires purely granular soils
contiguous or interlocking (secant) sections (Fig as vibro replacement (Mitchell and Jardine with low silt content.Vibro compaction uses a
17). Secant walls are drilled in two phases – 2002). Dynamic compaction involves dropping vibrating poker (often 300–400mm diameter),
primary piles, then secondary piles that partly a large weight onto the ground and should not inserted into granular soils to agitate and
cut the primary piles.They are often used to be confused with vibro compaction. compact them; water is often used with this
retain the surrounding ground as well as for system to remove very fine particles, and assist
their high stiffness and water-retaining Vibro compaction and vibro replacement – in penetration (Fig 18).
properties. Contiguous pile walls will not retain stone columns
Vibro replacement methods are used in mixed Fig 17 (top) Secant pile wall in background, from
water, but are cheaper than secant walls.These
Gresham Street, London (© MoLAS).
types of pile are generally between 0.45m cohesive, granular or purely cohesive soils,
and 3.0m in diameter and can reach lengths particularly weak soils and fill. A vibrating poker Fig 18 (bottom) Bottom feed vibro replacement
of 60m. In virtually all cases guide trenches is used to create a hole into which stone (images courtesy of Keller Ground Engineering).
are constructed before secant (but not
necessarily contiguous) walls are created in
order to remove obstructions and create the
line.This will therefore remove soil, which
might then need to be taken from site.
Pile-retaining walls are not always used to
support a building, but to contain lateral stress,
for example within basements.
Vibro techniques
Vibro techniques are a form of ground
improvement rather than piling. However, from
the archaeologist’s point of view, vibro methods
present similar problems and so are briefly
considered here.They use densification and/or
the insertion of stone or concrete columns to
provide greater below-ground stability prior to
7
Vibro Concrete Columns [VCC] that disturbance must be understood in order Sites and Monuments Records for reports of
Concrete columns [VCC] can also be constructed that the impact and implications of foundations piling impacts produced only three examples
using vibro techniques. A vibrating poker creates and piling schemes can be assessed.Additionally, (from 17 replies) where piling impacts had
a void, usually through weak soils and is hydrological impacts on the deposits may affect the been recorded (Davies 2004). At the Marefair,
founded on a solid layer. Once the void is deposit/groundwater chemistry and microbiology. Northampton, significant distortion was
created by horizontally and vertically displacing This is not only relevant on waterlogged sites, recorded adjacent to one of the piles (480mm
the soil, a very low slump concrete is pumped as changes in deposit hydrology and chemistry in diameter), with disturbance up to 250mm
into the hole through the poker (Figs 19 and 20). can affect inorganic as well as organic remains. either side.The total area of damage had a
radius of approximately 1.0m and vertical
Engineering advantages and disadvantages of Large displacement pile impacts displacement of over 1.0m, (Northamptonshire
vibro techniques Driven preformed piles: physical impacts Archaeology undated).
As columns of stone or concrete are inserted to Physical impacts of driven preformed piles on
create a support grid within the soil, this increases archaeological remains have been recognised Unfortunately, while the characteristic inverted-
ground-bearing capacity without generating for a number of years (Biddle 1994; Dalwood cone resulting from down-dragging had been
spoil and so is considered environmentally et al 1994). During pile installation, sediment is recorded, little is known about which pile
‘green’. Additionally, although ‘stone’ columns are physically displaced vertically and horizontally, installation technique was used in the past. It is
often aggregate, recycled ballast is now regularly which can cause distortion and damage to therefore impossible to be sure,without going back
used, furthering sustainable development. archaeological deposits, structures and to the original piling records (where they survive),
A high-density grid of vibro columns is particularly artefacts. Such displacement is demonstrated in whether such examples result from driving
useful where increased load-bearing is required. the image from Farrier Street, Worcester preformed piles.The pile excavated in
When stone columns are used as foundations (Dalwood et al 1994), which shows down- Northampton was circular, and may not have
(rather than for ground stabilisation), more dragging of deposits resulting from pile been a preformed displacement pile.The same
columns are usually required than piles. installation (Fig 21). Dalwood et al suggest, (on questions apply to Roman deposits at Vine
the basis of calculations made from excavations Street in Leicester, which demonstrated similar
Piling impacts upon archaeological adjacent to piles in Worcester) that the area of sediment distortion associated with a circular
remains the site affected by piling operations was up to pile (Fig 22).The rough external surface of the
In this section, the impact of each of the pile types six times larger than originally predicted. pile suggests that it was a bored pile rather
is explored, detailing physical and hydrological Although numerous anecdotes of pile damage than a solid preformed pile, although it may
impacts upon archaeological remains. exist, few have been published. A survey of 46 have been driven, then pressure grouted.
All techniques result in damage to or loss of
artefacts, and in sediment deformation equal to at
least the total volume of the pile or vibro-replaced
column.This is the minimum impact that will
result from any piling operation. In many cases,
further disturbance may occur, and the extent of
8
Piling v.3:Layout 2 27/7/07 14:56 Page 9
9
Piling v.3:Layout 2 27/7/07 14:57 Page 10
10
Piling v.3:Layout 2 27/7/07 14:58 Page 11
H-section piles (Hayman et al 1993; Boutwell et obstructions are encountered, and principle, there should be no disturbance of
al 2000).The potential corrosion of these piles archaeological material is dragged down, or the material adjacent to the hole, but this is
and any effects this might have on original orientation of materials is altered. In negated if the auger encounters large cohesive
archaeological deposits are the same as for many cases though, sheet piling will cut through items that are forced outward or dragged
driven sheet piles (see below). archaeological materials.The installation down through significant deposits outside the
techniques used for sheet piling, including intended bore.
Sheet piles also have a limited cross-sectional impact and vibro driving can induce ground
area and the amount of material displaced vibrations that might damage fragile Few published examples exist where
during installation will be significantly lower than archaeological materials or adjacent buildings. archaeological evaluations recorded details of
other pile types. Sediment deformation is replacement piles. In excavations next to new
therefore most likely to occur where A specific concern with steel sheet piles is piles installed at Number 1 Poultry, about 7%
corrosion. A number of studies have been carried of the bored piles caused significant damage at
out on steel piles, which show very limited levels the level of the watertable, with an area twice
of corrosion occurring within the ground, within the diameter of the pile being affected (Nixon
anoxic saturated soils (see for example reviews 1998, 41).This may have occurred during the
in Morley 1978 and in Tomlinson 1994, ch 10, installation of the pile casing as the damage was
particularly 10.4.1). Fewer studies have looked only seen next to (some of) the supported
in detail at the potential corrosion associated replacement piles, but not next to unsupported
with soils above the groundwater table. Where CFA piles (T Nixon pers comm).The impact is
data exist, it is clear that corrosion is enhanced shown in Figure 32, with loss of an area of
in disturbed soils with a constant oxygen beaten earth floor adjacent to the pile
supply, and also on contaminated sites. It is (Rowsome 2000).
possible that corrosion of metal piles may
damage archaeological materials when During the installation of temporary or
corrosion products are transported into other permanent casing vibration may occur, and the
parts of the deposit in solution through surface impact of this, in addition to that of the
water/groundwater percolation, although the installation and removal of the casing, has not
risk is fairly low.The use of plastic sheeting or been fully evaluated.There is a potential risk,
pre-treatment of metal piles would avoid issues highlighted by Nixon (1998), that the
associated with pile corrosion. installation and removal of the casing may
damage an area greater than the diameter of
Where sheet piles are used to create an the casing itself. As temporary casings are
impermeable barrier (such as a cofferdam), then usually installed to support poorly consolidated
de-watering may occur. However, recent deposits, this should reduce any collapse of the
excavations in Bergen, Norway, have shown that bore walls or migration of pile grout into
substantial water flow occurred through a small sediment voids.These concerns should be
hole in the pile (Matthiesen 2005). An investigation discussed by archaeologists and piling engineers
of the state of preservation of material on on a site-by-site basis.
either side of the sheet piling indicated that
there was no significant difference. Other physical impacts may occur where stones,
timber and other materials are not cleanly severed
Steel screw piles will have minimal physical by the bore or casing and are pushed aside or
impact on archaeological deposits (where dragged down (Nixon 1998, 41). It is possible to
obstructions are avoided) and have the added get borers capable of cutting through brick and
benefit that they can be unscrewed when they soft stone and it is essential that the likelihood of
are no longer required, a process that should encountering such sub-surface ground obstacles
also involve little damage to deposits (Fig 31). is clearly addressed in the site evaluation and
The main impact will be the displacement of mitigation strategy, because unforeseen
material during insertion. Additionally, if obstructions may hold up the construction
obstructions became caught between the pile programme, and necessitate excavation to remove
blades, then this could lead to further them.This excavation can be exceptionally
disturbance. Since some compaction of the damaging to archaeological deposits, and can
ground adjacent to the pile will occur, the pile mean that much a greater area of the site is
is unlikely to act as a major conduit for affected than just the pile locations.
migration of water or contamination within
archaeological deposits.There is potential for Where bentonite (or synthetic polymer) is
corrosion of the pile above the groundwater used to support unstable sediments
table, which may have an impact at the time of consideration should be given to the impact of
pile removal if corrosion products have this on archaeological deposits.The complexity
Fig 30 (top) H-section pile test with sand plugged become integrated with the surrounding soil or of the operation means that a compound often
within the flanges of the pile (Hird et al 2006 archaeological material, which may lead to needs to be constructed on site for the slurry
Figure 4.2a). greater disturbance as the pile is removed. processing plant. Bentonite is inert so it should
Fig 31 (middle) Small screw piles in advance of pose no chemical risks to archaeological
installation in Salisbury (see case study) (photograph Supported replacement pile impacts deposits, however, the physical impact on
courtesy of Tim Sheward, Roger Bullivant). Temporarily supported bore: physical impacts archaeological remains has not been fully
Fig 32 (bottom) Loss of material during bored piling An accepted impact associated with considered, so it is recommended that an
operations at the level of the watertable, at Number conventional bored piles is the loss of material impact assessment is carried out before use.
1 Poultry, London (© MoLAS). from within the cross-section of the bore. In Where the site is likely to contain voids or the
11
Piling v.3:Layout 2 27/7/07 14:42 Page 12
Fig 33 (left) Borehole rig with CFA piling rig in the groundwater flow. Sediment and chemical adjacent material can be drawn into the bore
background, during sample retrieval to investigate pile analysis was carried out on each of the (under-flighting), or material within the
cement migration, Slipper Baths, Lincoln (photograph samples, to compare before and after the piling. borehole forced into adjacent deposits.
courtesy of Mark Allen). The samples were analysed for a range of There is still a risk that cement will migrate
Fig 34 (right) Pile installed into pre-augered hole at metals, anions, electrical conductivity and pH. into any voids adjacent to the bore.The
Skirbeck Road, Boston.The installation has not hydrological and geochemical impacts are
deformed the layers, and the edge of the borehole can At both sites, minor variations in the results similar to those discussed for supported
be seen to the left of the pile (image courtesy of APS). between the pre- and post-piling samples were replacement piles (above).
recorded. It is uncertain whether these changes
archaeological deposits are poorly consolidated, were due to the piling or merely represent Vibro Techniques
there is an enhanced risk of the slurry entering natural variability of the burial environment.This Vibro replacement: physical impacts
these areas. In these cases, a temporary casing is still therefore an area where more research One of the principal disadvantages of vibro
should be used for the depth of the is recommended. replacement is that material is forced into the
archaeologically sensitive deposits. ground, displacing sediment (and archaeology).
Unsupported replacement pile impacts As the process involves vibration, the soil
Temporarily supported bore: hydrological Continuous flight auger (CFA): physical impacts adjacent to the column is considerably
impacts Provided cohesive materials are cleanly disturbed during the displacement process and
There is a potential risk that the introduction of severed, CFA piling should not damage deposits this is likely to have a very significant impact on
an alkaline mixture (concrete) will damage outside the area of the auger. adjacent archaeological deposits. Furthermore,
archaeological deposits, particularly This is confirmed by model-scale research columns are usually installed at around 1.5m to
waterlogged ones. Concrete curing is with a fully flighted auger where impacts 3.0m c/c (column centres) so there tend to be
exothermic (Davis et al 2004), the heat outside the diameter of the pile were more replacement columns on a site than if it
potentially acting as a catalyst for further ‘relatively small compared with’ driven were piled, increasing the frequency of any
reactions (cf Edwards 1998).The potential for circular, square- and H-section piles (Hird et al impacts.This is a recent technique, so there
mixing of grout and groundwater and for 2006). Comparison can also be made have been few opportunities for archaeologists
transport of alkaline solution across a greater with field-scale re-excavation of preformed to evaluate its effects.
proportion of the site has yet to be fully driven piles where both direct-driven and
evaluated. Where concrete cures quickly and pre-augered piles were studied to assess Vibro compaction and vibro replacement:
bonds with the sediment of the bore wall, whether pre-augering was an appropriate hydrological impacts
permeability and the potential for transport of mitigation measure to reduce vertical Where vibro replacement stone columns are
alkali materials from the concrete in the sediment displacement (Davies 2003; constructed, although these are extremely
groundwater should be reduced.This is a topic Rayner 2005). In that case it was shown that dense, there is a potential that they could act
where more research is needed, particularly in there was no impact outside the diameter of as conduits for the movement of contaminants,
places where the hydraulic conductivity of the the auger (Fig 34), and this may therefore apply moisture and fluids. In such conditions a
deposits is high, and the movement of in principle to CFA augering. Where concrete plug is generally installed to avoid the
groundwater is therefore fast.Two field-scale archaeological deposits contain structural dispersion of contaminants. Where the hole
tests were carried out (on CFA piles) to look material (bricks, stone, wood) then these created by the vibrating poker is filled with
at the extent of chemical contamination of obstructions may be dragged within the auger concrete rather than stone, the potential for
deposits from pile cement entering into flights and damage adjacent deposits. grout migration will be very limited, as any
solution in the groundwater (Hunter et al voids are likely to have been consolidated by
2006; Langdale-Smith 2006) (Fig 33). At each An additional benefit of CFA piles is that the the initial vibration. Given the extent to which
site, a single pre-piling core sample was taken in soil remains within the auger flights until the the physical impacts from vibration may have
the location of one of the piles. After pile concrete is injected, which significantly reduces disturbed any adjacent archaeological deposits,
installation, two core samples were taken at the potential of pile wall collapse. If, however, consideration of hydrological impacts may be of
distances from the pile, in the direction of an auger is rotated at an incorrect speed, limited consequence.
12
Piling v.3:Layout 2 27/7/07 14:42 Page 13
Pile Type Lateral Sediment Concrete migration Creation of preferential Vibration (noise & Metal Corrosion (of piles)
displacement pathway sediment movement)
Displacement piles Yes No (possibly for Driven Not usually, except in Yes, can be reduced Yes with steel sheet and
(large and small) cast in situ piles) thinly layered ground H section
and with H section piles
Replacement piles Low potential Moderate potential, Low potential Limited, but more likely No
reduced by casing where casing is used
(except for CFA)
Summary of pile impacts on possibly II) are relevant. Historic buildings, which The installation of those driven piles, however,
archaeological deposits and artefacts are built to different specifications than modern is likely to have a greater impact on the
Table 1 contains a summary of the information well-stiffened buildings should be covered by archaeology, with a zone of disturbance at least
outlined above. Methods of mitigating impacts categories II and III. If vibration from piling is one pile-width either side of the pile centreline.
are given in Section 4, below. likely to be an issue on site, a more detailed Furthermore, in cases where it is theoretically
assessment should be made, considering possible to use a large single bored pile,
Other issues to consider frequency of vibration, ground conditions and multiple driven piles (connected by a pile cap)
Vibration the type of building and its foundations (see would usually be needed to provide the same
Vibration from piling can affect above-ground Head and Jardine (1992, 41–6).
structures as well as below-ground
archaeological deposits (Fig 35). Limits on the Vibration can also affect archaeological
acceptable levels of vibration from piling in materials below ground, and intense vibration
relation to above ground structures are given in through soil can damage stratigraphy and
the British Standard (BS) 5228 part 4 (1992, 23). embedded artefacts (Sidell et al 2004). This can
A conservative threshold for minor or cosmetic be caused by pile installation, dynamic pile
damage should be taken as a peak particle testing, and ground improvement techniques
velocity (ppv) of 10 mm/s, for frequencies such as vibro compaction. Additionally, vibro
between 10Hz and 50Hz.These levels relate to piling hammers generate high amplitude
soundly constructed residential properties and vibrations during start-up and close-down.The
similar structures that are in generally good repair. vibrations from the pile travel both laterally and
BS 5228-4 also notes that ‘special consideration vertically (Fig 36).
should be given to ancient ruins and listed
buildings’. An appendix gives summary case Pile size and geometry
history on vibration levels measured on site for Piling requirements on individual sites will relate
a range of piling and ground improvement directly to the structural needs of the building,
techniques, for a range of deposit types. More and the strength and compressibility of the
detailed guidance on vibration from piling on below ground deposits. Since soils behave
above-ground historic structures is provided in differently it is difficult to generalise about
a CIRIA technical note (Head and Jardine ground conditions, or for that matter specific
1992). It summarises a number of other pile design. As such, generic tables, which offset
country codes, including the German DIN pile type against pile size (and therefore loss of
4150, as well as Swiss and Swedish standards archaeology), can be misleading. For example,
and codes.The simplest guidance is given some replacement piles may have a lower
below, after DIN 4150 (1970).This provides loading capacity than driven preformed piles of
levels of vibration for specific types of buildings: a similar diameter or width, and therefore the
For structural monuments, particularly those in area of archaeological deposit damaged would
less than prime condition, category I (and appear to be less for the displacement piles.
13
Piling v.3:Layout 2 27/7/07 14:42 Page 14
14
Piling v.3:Layout 2 27/7/07 14:42 Page 15
the equivalent kentledge and a limited surface Pile testing is covered in detail by the Handbook buildings on the site. Where foundation
footprint. Both dynamic and Statnamic pile on Pile Load Testing, produced by the Federation schemes are designed without adequate
testing should be assessed for vibration impact of Piling Specialists (2006). consideration of potential archaeological
on adjacent structures similar to that required impacts, unnecessary damage and time delays
for driven piling. When positioning a test pile, its Contaminated sites and piling to the construction programme may result.
location in relation to the final construction Many of the piling issues that concern
piles should be considered. Where possible, test archaeologists are similar to those that concern the During the design process, all archaeological
piles and reaction piles should be designed to Environment Agency regarding the effects of piling and engineering information should be shared
form part of the final construction (working on groundwater. Pile installation on contaminated to enable the engineers and architects to
piles) reducing the need for additional piles. On sites that overlie aquifers can give rise to increased design the development and take account of
very sensitive sites, this may affect the type of leaching of pollutants to groundwater through the character and significance of the
pile test chosen. vertical pathways created by the piling archaeological remains and any implications
(Environment Agency 2001; Westcott et al 2003). involved.This will help to ensure that the most
Fig 40 (below) Statnmic pile testing equipment
On sites overlying fractured or fissured rock, or appropriate engineering and mitigation
(photograph courtesy of Mike Brown).
where there has previously been mineral working solutions are identified. It is therefore
Fig 41 (bottom) Whatever the piling technique, piles (ie deep mining), injection of grout (which might paramount that the character and significance
are always likely to damage unknown below-ground impact on shallow archaeological deposits) can of the archaeological deposits are drawn to the
archaeological materials. Even in this instance when also impact further down. At these sites, injection attention of the engineering team at an early
the piles avoided all of the principle walls, damage has
of grout could result in the migration of grout stage so that the associated constraints can be
still occurred (© MoLAS).
away from the bore over a very large area. Where considered as part of the design. As piling can
possible, the archaeological and geotechnical impact significantly on archaeological deposits
investigations should be carried out alongside over a wide area, it may also be appropriate to
each other, to minimise the burden on consider the effects of the proposed works on
developers with respect to site characterisation, deposits adjacent to the site.
risk assessment and risk management design.
Methods to reduce or avoid
Mitigating the impacts of piling – disturbance to archaeological remains
a continuous process The most effective method for mitigating the
impacts of piling on significant archaeological
The archaeological potential of a proposed remains is to adopt an avoidance strategy,
development site is usually assessed with a whereby piles are located away from
desk-based study and impact assessment, archaeologically sensitive areas (Fig 41). In these
followed by field evaluation.This work can be in cases foundations can be designed so that they
response to a development proposal where impact only on the less sensitive areas or on
the impact of the scheme is already known, or areas of existing disturbance. Where significant
to inform a new design. In either case the likely remains are present the possibility of providing
impacts of piling and foundation design should uninterrupted spaces in the most sensitive
be considered at the earliest stage to allow areas should be explored. Where this is not
relevant data to be collected, including possible or feasible then a redesign of the
foundation design of the existing and previous foundations to include raft, ground beam, frame
15
Piling v.3:Layout 2 27/7/07 14:42 Page 16
Table 2 Information relating to new piles that should be stored to ensure that pile re-use can take place the next time the building is developed, from
the RuFUS handbook (Butcher et al 2006a)
Program stage Design stage Construction stage Building operation
Geological information Design philosophy As-built documents As-built drawings
Geotechnical information Design codes Non conformance reports Maintenance records
Groundwater level Design calculations Construction documents Environmental changes
Groundwater quality Necessary bearing capacity Programme of piling works Inspections
Contaminated soil Force combinations applied on each pile Plant and equipment Pile behaviour
Site conditions Pile data Test piling Service life measurements
Settlement limitations Working documents Structural alterations
Protocol for foundation records Site records
Pile installation records
Effects on nearby foundations
and structures
Results from monitoring
16
Piling v.3:Layout 2 27/7/07 14:42 Page 17
Understanding the zone of Local authority planning and archaeological small trenches placed across the site was
disturbance officers need to be mindful of the cumulative limited, and the plan of the friary remains was
Avoidance strategies should be considered on impact of re-development on a site which still difficult to interpret and therefore did not
a site-by-site basis, taking into account the scale makes later interpretation of a site more enable research questions to be fully addressed
and nature of the development and the difficult. In these cases, foundation re-use, both (McDaid 2006a; 2006b). In this case, more
archaeological potential. All piling operations of the existing foundations or their locations extensive area evaluation in advance of the
will result in the physical destruction of would be a beneficial mitigation method. In design of the pile layout might have provided a
archaeology directly in the path of the pile and, other cases, there should be recognition that piling plan which avoided major obstacles and
while it is accepted that destruction will occur, excavation would be better than any further allowed for more interpretation of the
there has been much discussion of what attempts at preservation in situ. archaeology (M McDaid pers comm), although
constitutes an acceptable level. this would have had financial and time
Pre-augering and probing for implications for the developer (M Jones pers
A study into development and archaeology in obstructions comm).
the City of York (Ove Arup and Partners and One method to reduce potential physical
York University in association with Bernard damage to sediments from preformed Locating obstructions is potentially a very
Thorpe 1991) proposed that the use of single displacement piles is to pre-auger the pile damaging stage of construction as, quite
bored (replacement) piles centred on a 6m by locations.This technique has recently been reasonably, developers seek to avoid
6m grid would result in the destruction of trialled on two sites which have subsequently unexpected ground conditions.This may also
between 2% and 5% of the area within the been excavated archaeologically (Davies 2003; not be part of the main piling programme, but
footprint of the construction while still Rayner 2005). In both cases the excavation included within demolition or enabling
maintaining the ‘legibility’ of the deposits.The demonstrated that the impact of the contracts. A methodology detailing steps to be
value of 5% has, inadvertently, gained credence subsequent displacement piling was limited to taken when encountering obstructions should
as the maximum permissible area of the area already disturbed by the pre-augering. be prepared for each site and in some cases it
destruction.This does not take into account the may be appropriate for an archaeologist to be
cumulative effect of successive developments. In order that this technique is successful, it is present to ensure it is adhered to.
Developments on archaeologically sensitive recommended that the auger diameter is equal
sites should strive to achieve lower values. to the diagonal of the pile and augered to Piling and waterlogged deposits
below the depth of known archaeology (Fig Understanding the full impacts of piling on
The York study (ibid 1991) also highlighted the 43).The material disturbed in pre-augering waterlogged deposits is complex, and requires
possibility that disturbance to a zone larger should not be removed from the hole, but left a thorough knowledge of the site hydrology.
than the size of the pile might occur. Recorded in situ while the auger is rotated out in the The chemical impact of pile concrete from
observable impacts from square displacement opposite direction. replacement piles on waterlogged deposits is
piles are extremely variable, ranging from no not yet fully understood, and although two
perceptible change through to distinct zones of When replacement (bored) piles are to be recent field tests did not identify impact
impact where the integrity of the stratigraphy installed on sites where substantial structural beyond 0.5m from the pile, there still remains
equal to at least twice the width of the pile has remains are suspected (stone walls/foundations, the potential that some chemical damage may
been compromised.This is clearly an area etc), then the piling contractor should be made occur. During the time that the pile cures, there
where further study is required. When aware of this issue, and a tool capable of is a potential risk that the migration of
calculating the likely level of impact from cutting through such obstructions should be chemicals from the pile grout/cement will affect
displacement piles, it is suggested that an area used. If CFA or preformed driven piling is the local sub-surface groundwater.The impact
of impact equal to twice the width of the pile undertaken, and obstructions are encountered, of this will to a large degree depend upon the
(ie one pile width either side of the pile two options are available: either the removal of nature of the waterlogged deposits, and the
centreline) is assumed which equates to a four the obstructions through excavation from the rate of groundwater flow. Deposits with a high
fold increase in the area of pile impact and it is surface or the relocation of the pile(s). hydraulic conductivity, such as gravel, may have
this value that must be factored in when Removing obstructions in advance of CFA or fairly rapid groundwater movement, but
calculating ‘loss’ of archaeology. driven piling may involve probing or pre organic-rich, peat-like deposits typically have a
augering with diamond or chisel cutting tips; low hydraulic conductivity, meaning
Fig 43 Recommended diameter for pre-augering however, contractors may more usually engage groundwater movement will be limited and
(circle) shown along with the square pile, with in large-scale machining. Both options result in therefore the potential risk of contaminant
the same distance across the diagonal as the
a collateral loss of archaeological integrity as transport is significantly reduced.This risk could
diameter of the auger hole.
the area around an obstruction is checked be further reduced by the installation of
thoroughly for obstructions. permanent casing.
Two archaeological watching briefs carried out Concerns exist regarding the possibility of piles
during piling at a monastic site known to puncturing impermeable layers that contribute
contain walls demonstrated that locating places to the preservation of waterlogged deposits,
suitable for piles on complex urban sites is particularly in urban environments, such as York,
fraught with difficulties. Although the piling where there are perched water tables.
design for the site had sought to reduce the Mitigation for development where water
impact on archaeological remains to well below logging is known to occur above the natural
5%, unauthorised probing took place, which groundwater level should include an appraisal
was monitored archaeologically. As a result the of the proposed foundation design and a
final disturbance of the uppermost (medieval) consideration of whether an avoidance strategy
deposits was much greater, 17% in one of the can be adopted. Recent research (Hird et al
two cases, which resulted from the need to 2006) indicates that the most important factor
extend the archaeologically recorded areas in is the thickness of the aquitard (the
order to try to understand the remains. impermeable layer restricting groundwater
However, the information gained from these flow). Where piling is the only option on
17
Piling v.3:Layout 2 27/7/07 14:43 Page 18
waterlogged sites with perched water tables, Piling and burial grounds It is also imperative to the success of foundation
then the use of permanent rather than Burial grounds are a good example of where re-use schemes that all available design and
temporary casings on replacement piles should an avoidance strategy should be implemented construction data for current foundations are
be considered, as the removal of these casings or full excavation undertaken (Fig 44). It should stored in a suitable location such as the local
may also disrupt the aquitard. be stressed that the planned use of piled Historic Environment Record. Data would include
foundations on a burial ground will not normally the final pile locations, loading capacity, test
Cofferdams constructed from augered secant be permitted by the Ministry of Justice. results, and as-built drawings. Other information
or driven sheet piles, whether used to control However, while avoidance of disturbance is the such as the engineers design report, contractors
water ingress during construction or in flood preferred option, the archaeological excavation method statements and more detailed designs
defence barriers, may impact indirectly upon of all burials within the footprint of the should form part of the site archive.
waterlogged archaeological remains by altering development will often be necessary. Raft
water levels. Mitigation must include a foundations and ground beams may be feasible Summary
consideration of groundwater flow and possible (see for example case provided by Shilston and A summary of mitigation measures is
effects on the archaeology. Where the barriers Fletcher 1998), although it should be emphasised presented in Table 3.
are long-term, there is every possibility that that further research is needed to evaluate the
waterlogged deposits may effectively be cut off impact of raft foundations, and compression in Case studies
from hydraulic recharge and therefore general. For further information on the
‘preservation by record’ (excavation) would be implications of piling for burial ground Pile pre-augering: JunXion, Lincoln
the only option. archaeology please refer to the Guidance for (see Figs 27 and 28)
Best Practice for Treatment of Human Remains The City Archaeologist originally requested that
Fig 44 Piling in cemeteries is likely to cause
significant damage, as can be seen on the cover Excavated from Christian Burial Grounds in only CFA piles with permanent liners should be
image. In this case, the pile cap has only just avoided England (The Church of England /English used, due to concern about down-dragging of
this skeleton (image courtesy of the University of Heritage 2005). Similar considerations should deposits by driven piles.The requirement for
Leicester Archaeological Services (ULAS)). be given to any non-Christian burial grounds. the permanent liner was due to the high
groundwater level on site. Excavations at an
Reporting adjacent site (Steane et al 2001) had revealed
Our understanding of piling impacts and the best deeply buried and well-preserved timber
mitigation methods comes from experience.The associated with revetting and land reclamation
more sites where previous construction impacts in the form of wattle hurdles and dumped
can be assessed, the more our experience will material dating from the Roman period
grow, but this will only happen with onwards. Deep evaluation was not undertaken
comprehensive dissemination of information. It as no part of the building other than the piles
is therefore recommended that brief was likely to impact on this material, and parts
summaries of the methodology and rationale of the site were also contaminated with oil and
are produced for sites where preservation in diesel fuel (M Jones pers comm).
situ schemes through piling have been
developed. Planning and archaeological officers Despite the foundation recommendations by
may wish to make this part of a condition the City Archaeologist, the developer was keen
relating to the in situ preservation strategy. to use preformed displacement piles, partly
because they would be much cheaper.The
To assist in the dissemination of knowledge, impacts of these piles on archaeological
English Heritage has created a mailbox so deposits was outlined, and it was agreed that it
anyone involved with piling and archaeology would be inappropriate to consider a loss
can submit case studies, images and methods through piling based only on the actual width
which can then be integrated into future of the piles. A figure of twice the width of the
publications (where appropriate).The email piles was used, because it was felt that this
address is: piling@english-heritage.org.uk would take into account the potential
All pile types Adopt ‘avoidance strategy’ and avoid use of piles in areas of archaeological sensitivity where possible. Burial grounds
should not be piled. Where piling is unavoidable, limit extent of physical destruction as far as possible (consider all
ground interventions including ground beams
Large displacement piles Zone of impact is potentially greater than diameter of pile, therefore calculate percentage loss of area in building
footprint using four times the pile area, unless there is evidence of the impact of past piling activity recovered
through excavation.
Small displacement piles Sheet - If waterlogged remains are present, assess potential impacts on groundwater flow and recharge of deposits.
Consider long-term monitoring of water-table and water chemistry.
H-section - Not recommended for waterlogged deposits due to possible migration and oxygen ingress.
Replacement piles Consider use of suitable cutting tools where obstructions are likely to be encountered. For secant walls see above for
sheet piles
CFA - Avoid on sites where structural remains likely
Vibro techniques Require further investigation, but are likely to be extremely damaging to archaeology and should be avoided where
possible.
18
Piling v.3:Layout 2 27/7/07 14:43 Page 19
deformation of adjacent deposits. Calculations it was agreed that it could be used along one sensitive archaeological site in Salisbury
made using this larger figure indicated that the side of the site, providing an evaluation of its (Fig 45).The piles were made up of a number
area of deposit loss was still below 5%, which it impact on archaeology was carried out. of curved spirals of steel of varying diameters
had already been agreed would be acceptable connected to a central shaft.These piles, which
(given the character and importance of the Following excavation, no evidence of had a 250kN capacity (T Sheward pers comm),
archaeological remains on this site). disturbance outside the area of the auger were screwed into the ground to depths of 5m
(ie 350mm) could be identified. Since the (Sheward 2003). Benefits were that it was
The piling contractor believed that the actual potential damage estimated for the driven unnecessary to remove spoil associated with
damage from the use of driven piles would be piles on this site was twice the width of any piling operation, or to bring piling materials
lower if the locations were pre-augered to the pile (c 500mm), this therefore represented to the site through the city’s narrow streets.
below the depth of the archaeology. a reduction in the potential damage that Additionally, the piles can be removed by
They particularly wanted to use this technique might have occurred from driven piling unscrewing at a later date theoretically causing
along one side of the site to reduce piling alone. However, evidence from the pile very limited damage to below-ground deposits.
vibration on the printing presses of the local driven without first pre-augering indicated
newspaper housed in the adjacent building. that down-dragging of material and its Pile re-use: Ramada Encore Hotel,
The methodology entailed pre-augering the pile impact on the deposits was also limited to Mickelgate, York
location with a 350mm diameter auger to a a zone no greater that 350mm. On this basis, The previous building on the site was the
depth of 3–4m then withdrawn whilst rotating for this particular site, it was decided that offices of the Yorkshire Co-operative Society,
in the opposite direction.This left the soil in the there was no need to pre-auger the other constructed in the 1960s.The site was acquired
ground, but disrupted it sufficiently to make the piles on the site (except those adjacent to the by a developer to build a hotel upon. During
insertion of 250mm square piles easier.The printing press). discussions with the City Archaeologist, the
auger size was chosen to match closely the developer was informed of the likely
distance across the pile diagonal (353mm). As Steel screw piles: Salisbury archaeological potential of the site, which was
the technique had not apparently been used This technique, recently adapted from 19th situated within the medieval town walls, not far
before on an archaeological site, century marine engineering, was used on a from the riverside, and therefore likely to
Existing Building
wall 6008
wall 7007 9 11
4
1 8
wall 6001 7
10
5
6 section 1 17 Trench 6 Trench 8
3
2 16
section 3 section 2
Trench 4 Existing
12 13 wall
4006
Building
Trench 5
14 15
core wall
4005 4006
wall
4005
Alignment of new/
New pile foundation existing ground beams
Figure 2 Trench and borehole location
Areas of archaeological
Existing pile foundation observations with designated
area number
19
Piling v.3:Layout 2 27/7/07 14:43 Page 20
contain well preserved organic material. On the substantial piled foundations through river silts • possibilities for the re-use of old piles (or
basis of that discussion, the developer and gravels. Discussions took place on exactly re-drilling old pile locations)
produced a plan to re-use the foundations of which aspects of the Roman archaeology • impacts on deposit hydrology, specifically:
the existing building, thereby reducing the needed to be preserved in situ and what, if • impact of piling on impervious clay
potential need for, and cost of archaeological anything, could be preserved by record. It was layers and water flow
evaluation (Figs 46 and 47).The scheme, which decided that all intact structural elements • impact of concrete/grout upon
included the re-use of all 110 previous piles, needed to be preserved while some spaces groundwater chemistry and
needed a further 17 installed in three discrete between walls could be fully excavated, artefact/ecofact stability
locations.This meant that over most of the rest recorded, backfilled and then piled through.The • impact on hydrology (of
of the site, no ground disturbance occurred. use of detailed digital plans of the archaeology archaeological deposits) of
Any below ground impact was further was extremely important to compare with the adjacent sites
mitigated because the building was constructed proposed foundation plan including pile • impact of piling upon soil microbiology
on the existing ground slab with archaeological locations.The foundations were redesigned to • stability of metal sheet piles within aerobic
recording during the installation of services and allow development while retaining the building deposits
pile caps, none of which were deep enough to intact.The proposed CFA technique was • impact of other foundation types
encounter significant archaeological deposits. retained and no pile dimensions had to be
changed. Piles were relocated to areas between This research will need to be both laboratory-
This scheme was very successful, mainly the Roman walls and hypocaust pilae, with as and field-based.
because the potential for re-use had been much clearance as possible between pile
highlighted early enough in the design phase of locations and the Roman building.The building There is also a need to evaluate areas on sites
the scheme, and was led by the developer, who was backfilled to an agreed specification where past construction activity has impacted
was keen to reduce the risk to the scheme of involving geotextile, inert sand, and then graded upon archaeological deposits and there have
having to deal with archaeological material spoil from the site. CFA piles were then been adverse effects.This will enable an
(Williams and Butcher 2006). carefully located and installed, securing the understanding of actual site-based impacts to
safety of the building. be collated, and is a recommendation included
Pile avoidance and redesign: 43 The in the City of London Corporation Planning
Highway, Shadwell, London Research strategy Advice Note 3, Archaeology Guidance
An exceptionally well-preserved Roman (Corporation of London 2004).
building was discovered during excavation in Since the introduction of PPG16, there has
advance of development (Fig 48). Roman been a need for clear guidance on how to Targeted field evaluations should be carried out
remains had been anticipated following achieve preservation for in situ schemes. During on:
evaluation, but not the quality of the building that time three conferences on ‘Preserving
and extent of its survival. It was considered by Archaeological Remains in situ’ (PARIS) have • CFA piles
the archaeological curator to be a find of taken place (Corfield et al 1998; Nixon 2004). • bored piles, particularly investigating the
national significance and therefore preservation More research is, however, needed to address impact of installation and removal of
in situ was recommended and agreed by all issues including: temporary casing
parties. However, planning permission subject • auger displacement piles
to a condition to archaeologically record and • impact of piles in a range of soil and • removal of existing piles
excavate the site had been granted for a multi- archaeological deposits • vibro techniques
storey residential block of apartments. • impact of piles on hard ‘floor’ levels buried
beneath the ground Parameters that should be recorded are:
The site is located in the Thames floodplain, on • impact of vibration and compressive forces
inherently unstable alluvial sediments, requiring in stratified deposits • depth and lateral extent of physical effects
• accurate sediment description, preferably
including particle size analysis
• moisture and organic content
• number and size of inclusions
• assessment of compression
• distance of grout migration from cast in situ
piles
• any microbiological, chemical or
groundwater impacts from grout migration
20
Piling v.3:Layout 2 27/7/07 14:43 Page 21
21
Piling v.3:Layout 2 27/7/07 14:43 Page 22
22
Piling v.3:Layout 2 27/7/07 14:43 Page 23
statnamic a rapid load testing method for piles situ:. Proceedings of the Conference of 1st–3rd April Northamptonshire Archaeology (undated)
which may be used as an alternative to static or 1996. London: Museum of London Archaeology ‘Archaeological evaluation at Barclaycard, Marefair,
dynamic tests Service, 86–92 Northampton, Stage 2: trial excavation’
tie-back an anchorage or the tie rod connected to Environment Agency 2001 Piling and Penetrative Ove Arup and Partners and York University in
it which may be used to support walls and other Ground Improvement Methods on Land Affected by association with Bernard Thorpe 1991 'York
structures Contamination: Guidance on Pollution Prevention. Development and Archaeology Study’
NGWCLC Report NC/99/73 Rayner, T 2005 ‘Archaeological investigations and
underream an enlarged pedestal cut out of the
soil at the base of a pile.This is usually done with Federation of Piling Specialists (FPS) 2006 watching brief on land at Skirbeck Road, Boston,
a cutting tool, which can be expanded and rotated Handbook on Pile Load Testing. Beckenham: FPS Lincolnshire (BSR04)’. Archaeological Project
Hayman, J W, Adams, R B and Adams, R G 1993 Services (APS) Report No. 20/05: unpublished
at the base of the pile shaft.
‘Foundation piling as a potential conduit for Rowsome, P 2000 Heart of the City: Roman,
unstable soils sands and gravels which are not self-
DNAPL migration', in Proceedings of the Air and Medieval and Modern London Revealed by
supporting and therefore liable to collapse into a
Waste Management Association Meeting. Denver Archaeology at 1 Poultry. London: Museum of
bored hole
Head, J M and Jardine, F M 1992 Ground-borne London Archaeology Service
Vibrations Arising from Piling. London: Construction Sheward, T 2003 ‘Screw piling in Salisbury’. New
References Industry Research and Information Association Steel Construction (November/December): 27–8
Hird, C C, Emmett, K B and Davies, G 2006 Piling Shilston, D T and Fletcher, S L 1998 ‘Geotechnical
Biddle, M. 1994 ‘What Future for British
in Layered Ground: Risks to Groundwater and engineering for the in-situ preservation of
Archaeology’, the opening address at the Eighth
Archaeology. Environment Agency Science Report archaeological remains’, in M Corfield, P Hinton,T
Annual Conference of the Institute of Field
SC020074/SR. Bristol: Environment Agency Nixon and M Pollard (eds) Preserving
Archaeologists, Bradford 13–15 April 1994.
Hird, C C and Moseley, V J 2000 ‘Model study of Archaeological Remains in situ. Proceedings of the
Archaeology in Britain Conference 1994. Oxford:
smear zones around vertical drains in layered soil’. Conference of 1st–3rd April 1996. London: Museum
Oxbow Books
Geotechnique 50, 89–97 of London Archaeological Service, 8–15
Boutwell, G P, Nataraj, M S and McManis, K L
Sidell, E J, Higuchi, T, Allison, RJ and Long, AJ 2004
2000 ‘Deep foundations on brownfield sites’. Hughes, R, Coles, B and Henley, R 2004 ‘The
‘The response of archaeological sediments and
Prague 2000 conference, Prague reuse of pile locations at Governor's House
artefacts to imposed stress regimes as a
British Standard 1992 Noise control on construction development site, City of London’, in T Nixon
consequence of past, present and future
and open sites – Part 4: Code of practice for noise Preserving Archaeological Remains in situ?
anthropogenic activity’, in Nixon, T (ed) Preserving
and vibration control applicable to piling Proceedings of the 2nd Conference, 12–14 Archaeological Remains in situ? Proceedings of the
operations. BS 5228-4 September 2001. London: Museum of London 2nd Conference 12–14 September 2001. London:
Butcher, A P, Powell, J J M and Skinner, H D, Archaeology Service, 98–104 Museum of London Archaeology Service, 42–9
(eds) 2006a Reuse of Foundations for Urban Sites, a Hunter, R, Branch, N P, Swindle, G E, Walsh, N, Steane, K, Darling, M J, Mann, J, Vince, A and
Best Practice Handbook. Bracknall: IHS BRE Press Valcarez, I and Palmer, A 2006 ‘9A Parchment Young, J 2001 The Archaeology of Wigford and the
— 2006b Re-use of Foundations for Urban Sites, Street, Winchester, Hampshire (site code: AY188) Brayford Pool. Oxford: Oxbow Books
Proceedings of the International Conference. Archaeological Monitoring Exercise’. Unpublished
Stockwell, M 1984 ‘Foundation preparation and
Bracknall: IHS BRE Press ArchaeoScape client report
the archaeologist’, in P V Addyman and B V E
Corfield, M, Hinton, P, Nixon, T and Pollard, M Langdale-Smith, T 2006 ‘Appendix 5 – An (eds) Archaeological Papers from York Presented to
(eds) 1998 Preserving Archaeological Remains in assessment of the potential leaching of cement M W Barley. York, 158–62
situ: Proceedings of the Conference of 1st –3rd April material from CFA piles into archaeological
The Church of England/English Heritage 2005
1996. London: Museum of London Archaeology deposits at the Slipper Baths, Waterside North,
Guidance for best practice for treatment of human
Service Lincoln’, in M Allen ‘Archaeological watching brief
remains excavated from Christian burial grounds in
Corporation of London 2004 Planning Advice Note and palaeoenvironmental report: former Slipper
England. London:The Church of England and
3: Archaeology Guidance Baths site, Waterside North, Lincoln. Allen
English Heritage
Archaeological Associates’. Unpublished client
Dalwood, C H, Buteux, V A and Darlington, J Tomlinson, M J 1994 Pile Design and Construction
report
1994 ‘Excavations at Farrier Street and other sites Practice (4 edn). London: E & FN Spon
north of the city wall, Worcester 1988–92’. Trans Matthiesen, H 2005 Influence from piling on cultural
deposits at Bryggen, Bergen. Report to Westcott, F J, Smith, J W N and Lean, C M B
Worcestershire Archaeol Soc 3rd Series 14, 75–114 (2003) Piling in contaminated ground:
Riksantikvaren, Norway. National Museum of
Davies, G 2003 ‘Archaeological Field Evaluation of environmental impacts, regulatory concerns and
Denmark, Department of Conservation, Report
the Impacts of Piling at The JunXion, St Marks effective solutions. Engineering Geology 70:
no 10832-0007-1
Street, Lincoln’. ARCUS: Report No 750.1: 259–268.
unpublished McDaid, M 2006a Lincoln Cathedral Street, Lincoln.
Archaeological Watching Brief. LAS Report 864 Williams, J 2006 ‘Pile re-use at The Collection,
— 2004 ‘Interim Report on the Impact of Piling Lincoln: lessons learnt’, in A P Butcher, J J M Powell
on Archaeological Deposits’. ARCUS Report No — 2006b Lincoln College, Monks Road, Lincoln.
and H D Skinner Reuse of Foundations for Urban
711.1: unpublished Archaeological Watching Brief. LAS Report 902
Sites, Proceedings of the International Conference.
Davis, M J, Gdaniec, K L A, Bryce, M and White, L Mitchell, J and Jardine, F M 2002 A guide to Ground Bracknall: IHS BRE Press, 303–7
2004 Study of the Mitigation of Construction Impacts Treatment. London: CIRIA
Williams, J and Butcher, A P 2006 ‘Foundation
on Archaeological Remains. London: Museum of Morley, J 1978 A Review of the Underground re-use as a mechanism for the preservation of
London Archaeology Service Corrosion of Steel Piling. British Steel Corporation buried cultural heritage in urban centres: how new
Department of Environment 1990 Planning Policy Nixon, T 1998 ‘Practically preserved: observations engineering research helps limit archaeological
Guidance Note 16: Archaeology and Planning. on the impact of construction on urban damage’, in Proceedings of the 7th European
London: HMSO archaeological deposits’, in M Corfield, P Hinton,T Conference 'Sauveur' Safeguarded Cultural Heritage,
DIN (German Standards Institution: Deutsche Nixon and M Pollard (eds) Preserving Understanding and Viability for the Enlarged Europe,
Industrie-Norm, B 1970 ‘Vibrations in buildings’. Archaeological Remains in situ. Proceedings of the Prague 31st May–3rd June 2006: available on-line at
Unpublished draft Conference of 1st–3rd April 1996. London: Museum http://www.arcchip.cz/ec-conference/
of London Archaeology Service, 39–46 programme.php
Edwards, R 1998 ‘The effects of changes in
groundwater on the survival of buried metal Nixon, T (ed) 2004 Preserving Archaeological
artefacts’, in M Corfield, P Hinton,T Nixon and M Remains in situ. Proceedings of the 2nd Conference,
Pollard (eds) Preserving Archaeological Remains in 12–14 September 2001. London: Museum of
London Archaeology Service
23
Piling v.3:Layout 2 27/7/07 14:43 Page 24
Authorship and acknowledgements Published July 2007 English Heritage is the Government’s statutory
This guidance note has been written by Jim advisor on the historic environment. English
Williams (EH), Jane Sidell (EH) and Ian Panter © English Heritage 2007 Heritage provides expert advice to the
(formerly EH, now York Archaeological Trust). It Edited and brought to press by David M Jones, Government about all matters relating to the
has benefited from comments on the three draft English Heritage Publishing historic environment and its conservation.
texts from people working within all aspects of Designed by Amy Slater
engineering and archaeology, to whom the Printed by [PRINTER TO ADD] For further information and copies of this
authors are exceptionally grateful: Mike Collins Printed on recycled paper leaflet, quoting the Product Code, please
(EH, on behalf of AMIG),Tom Cromwell, contact:
Andrew David, Stuart Ellis,Terry Girdler, Jacqui Product Code 51352
Huntley, Edmund Lee, Simon Mays, Lisa Moffett, English Heritage
Dominique de Moulins, Sebastian Payne, Jennie Customer Services Department
Stopford, Roger Thomas, Humphrey Welfare (all PO Box 569
at English Heritage), Rab Fernie and Peter Swindon SN2 2YP
Borne-Webb (Cementation Foundations
Skanska), Michael Brown (University of telephone: 0870 333 1181
Dundee),Tony Butcher (BRE), Mike Corfield, fax: 01793 414926
Glyn Davies (ARCUS), Mat Davis, James Dinn e-mail: customer@english-heritage.org.uk
(Worcester City Council on behalf of ALGAO),
Brian Durham (Oxford City Council and on
behalf of ALGAO), Allan Hall (University of
York / EH), Bob Handley (Aarsleff), Charles
Hird and Adrian Hyde (University of Sheffield),
Richard Hughes (ARUP), Sarah Hughes
(ARUP),Taryn Nixon (MoLAS), Jonathan Smith
(Environment Agency), Kathryn Stubbs (City of
London Corporation),Tony Suckling (Stent
Foundations Ltd), Matthew Warner (Amplus
Ltd), Lee White (Durham County Council),Tim
Bradley (Pre-Construct Archaeology Ltd).