Lakebeds (68 Square Miles of Lakebeds)

Paved Roads (284 Miles of Paved Roads)

Unpaved Roads (289 Miles of Unpaved Roads)

Runways (7.8 Miles of Paved Runways)

Unpaved Runways (59 Miles of Lakebed Runways)

Ramp Space (1.3 Million Square Yards Ramp Space)

Buildings (9.5 Million Square Feet Building Space)

Electrical Lines (270 Miles of Electrical Lines)

Wastewater (194 Miles of Wastewater Lines)

Natural Gas (72 Miles of Gas Lines)

POL Storage (3.6 Million Gallons POL Storage)

Deployments (EOD)

Deployments (Our Civilians)

Mr. Ken Harnos EMCS/SCADA

Ms. Becky Goodwin Training Manager

Mr. Robin Hairston Pavements Mr. Christopher Holman Electrical Mr. Hector Aquino-Machuca Electrical Mr. Dave Harrell Energy

Deployments (Family Members)

SrA Ashley Bernhardt

SSgt Michael Harrell

Sgt David LaComb

SrA Steven Harrell

Majs Drew & Seher Judkins

Edwards AFB (Circa 1970)

Edwards AFB (Now)

Edwards AFB (Now)

SunEdisons Projects in the Region

Regulus Solar 60 MW

CSU Bakersfield 1.2 MW Orion Solar 20 MW

Adobe Solar 20 MW Rigel Solar 20 MW

Lancaster State Prison 2.5 MW

Oro Verde Solar 450MW

Bolthouse Farms 1.9 MW Antelope Solar 20 MW

22

Solar Technologies

ParabolicTrough(CSP)

SolarPowerTower(CSP)

Stirling Engine

Photovoltaic

Blueprint for a Secure Energy Future (Private Financing Initiative)


Tehachapi Mojave EdwardsAFB

Lancaster Palmdale

Energy Initiatives (Delivery Point Distances)


Proposed EULLocation
12.5miles

NorthBase Delivery Point AFRL Delivery Point SouthBase Delivery Point

Sustainment/MFH Funding FY13 (dollars in millions)


Annual Average Sustainment Requirements for EAFB = $76.2M
(per UFC 3-701-07)

Total Funding Received = $72.3M

SRM/DEMO/MFH/ARRA/USER FUNDED FY08-FY14 PROJECTS AWARDED


$90,000,000 $80,000,000 $70,000,000 $60,000,000 $50,000,000 $40,000,000 $30,000,000 $20,000,000 $10,000,000 $0
UNAWARDED FUNDED AWARDED

FY08 $66,394,225

FY09 $81,860,480

FY10 $34,814,960

FY11 $34,566,157

FY12 $71,408,654

FY13 $66,578,800

FY14 $15,363,670 $3,055,864

Exciting Times
Oro Verde Solar Project Utility Conservation Program Space Consolidation Program Encroachment Management Civil Engineering Transformation Water Litigation Housing Privatization

MILCON

Sustainment/MFH Funding FY13 (dollars in millions)


Annual Average Sustainment Requirements for EAFB = $76.2M
(per UFC 3-701-07)

Total Funding Received = $72.3M