Escolar Documentos
Profissional Documentos
Cultura Documentos
S. Process No. Function (Step) Potential Failure Modes (process defects) (Y's) Potential Failure Effects (Y's)
S E V
Doc. No.:Annxure-2
D E T R P N Recommended Actions Responsible Person & Target Date Actions Taken S E V O C C
O C C
1 Product will fail to meet specification of Product NC at 1.Hardness Homogenity Tensile Strength 5
2 3 4 5 6 7 8 9 10
Kneading
5 5 5 5 5 5 5 5 5
30
30
3 3 4 3 3 2 3 2 3 3 2 3 2 3 3
45 45 40 45 30 20 30 30 30 30 30 45 20 45 30
45 45 40 45 30 20 30 30 30 30 30 45 20 45 30
Operator Trained & qualified Preventive maintenance schedule not followed temperature indicator proper work instruction displayed proper work instruction displayed visual aids displayed receipe chart displayed tc identified each material receipe chart displayed
11 12 13 14 15 16
5 5 5 5 5 5
Doc. No.:Annxure-2
S E V
Controls
D E T
R P N
Actions Taken
S E V
O C C
Operator Trained & qualified Operator Trained & qualified Operator Trained & qualified Operator Trained & qualified Operator Trained & qualified Operator Trained & qualified Preventive maintenance schedule followed Teperature indicator work instruction displayed legible work instruction displayed visual aids for homogenity displayed weighed as per receipe chart Test certificate identified each material proper receipe chart displayed identified each material
30
2 3 4
Mixing
5 5 5
3 2 2 3 2 3 2 2 2 2 3 3 2 2 2 2
3 2 4 3 3 3 2 2 3 3 3 3 2 2 3 3
45 20 40 45 30 45 20 20 30 30 45 45 20 20 30 30
Tensile Strength
5 6 7 8 9 10 11 12
5 5 5 5 5 5 5 5
13 14 15 16 17
5 5 5 5 5
D E T
R P N
S E V
Unawrae of setup instruction untrained man power unaware of working procedure PM schedule not followed Pressure Gauge not working temperature indicator & controller not working
Leakage in machine Blockage of pipe improper set up
Manpower Trained & qualified Manpower Trained & qualified Manpower Trained & qualified Preventive maintenance schedule followed
Periodic inspection of Pressure gauge with PM
54
45
2 3 3 3 3 2 3
4 3 3 3 3 3 4 3 3
48 45 45 45 45 30 60 30 45 30 30 30 30 45 45
Preventive maintenance schedule followed Preventive maintenance schedule followed Preventive maintenance schedule followed
trained man power about set up instruction Temperature indicator
temperature not reaching at 2 desired value use of wrong Die excess material used in block not defined set up instruction wrong material used receipe ratio Poor Gauge R&R poor instrument handling 3 3 3 3 3 3 3
material used as per receipe chart set up instruction defined and displayed identified material receipe chart displayed Gauge R&R Study Trained Man Power is Used
2 2 2 2 3 3
18
D E T
R P N
Doc.No:Annxure-2
O C C
D E T
R P N
Recommen Responsible Actions ded Person & Taken Actions Target Date
S E V
O C C
5 5
use of untrained man power doesnot follow work instruction] unaware of working procedure Low moral Improper setting
2 2
Trained manpower & qualified Trained manpower & qualified Trained manpower & qualified Trained manpower & qualified
Preventive maintenance schedule followed Preventive maintenance schedule followed Preventive maintenance schedule followed Preventive maintenance schedule followed W.I. for set up being used displayed & revieved Trained manpower & qualified calibrated instrument used Inspect and inform to maintenance dept.
4 3
40 30
30
5 5
4 3 3
3 3 3
60 45 45
30
5 5 5 5 5 5 5
not specialised not defined set up instruction work instruction not displayed poor instrument handling uncalibrated instrument used rough tool used hard material improper measuring instrument
3 3 3 3 3 3 3
2 3 3 2 3 3 3
30 45 45 30 45 45 45
1. calibrated Gauge used 2. Gauge R&R done 3. Periodic inspection is done for thickness
45
Doc.No:Annxure-2
O C C
D E T
R P N
Recomme Responsi Actions nded ble Taken Actions Person & Target Date
S E V
O C C
6 7 8 8 8 8 8 6 6 7 7 6 8 8 7 7 7 6 6 8
5 5 4 6 5 6 6 7 5 6 5 6 6 4 5 4 4 3 4 5
Train & Qualified operators Train & Qualified operators Train & Qualified operators Follow PM shedule Follow PM shedule Follow PM shedule clean and maintain the intrument Temperature indicator,pressure gauge Temperature indicator size of component display die list with no. and size Display working instruction weigh as per receipe chart Use as per requirement identify each material Display receipe chart Train & Qualify operators Train & Qualify operators Use calibrated instrument
3 4 4 3 4 3 2 3 2 2 4 4 3 4 3 3 4 3 4 5
90 140 128 144 160 144 96 126 60 84 140 144 144 128 105 84 112 54 96 200
S E V
O C C
D E T
R P N
Actions Taken
S E V
O C C
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 Punching Product NC at Dimension 1. Material rejected by customer. 2. Material reworked/regraded. Use of wrong tool 4 3
Tool identified & tooling management system is in place First & last piece inspection is done First piece inspection is done 3 36
Use of blunt/tool/Die
Improper set up
D E T
R P N
RPN
45 45 45 45 45 40 30 30 30 30 30 30 30 30 20 20
Percent 8 8 8 8 8 7 6 6 6 6 6 6 6 6 4 4
Cum % 8 17 25 33 41 49 54 60 65 71 76 82 87 93 96 100
545
RPN
30 20 10 0
Series2, 4
Xs
45 8 17 45 8 25 45 8 33 45 8 41 40 7 49 30 6 54
Series1, 20
45 8 8
30 6 60
30 6 65
30 6 71
30 6 76
30 6 82
30 6 87
30 6 93
20 4 96
20 4 100