Você está na página 1de 6

Location: Assessor(s):

Definite High Moderate Low Negligible 5 4 3 2 1


Probabili ty & Frequenc y

RISK ASSESSMENT FORM

Terga FRIDI.ALI
5 4 3 2 1 1 Minor 10 8 6 4 2 2 Serious Severity 15 12 9 6 3 3 Major

Date of Assessment: System/Activity:


20 16 12 8 4 4 Catastrophic

24-03-2010

Assessment No:

60

Assembly and adjustment djustment of the metal frames (F01)

Medium Priority (5 days)

Key to Priorities High Priority (2-3 days)

Immediate

INTRODUCTION The table below provides a simplified representation of the methodology used and the processes involved in this Hazard Identification & Risk Analysis Procedure (Risk Management) to be undertaken by OCIA and all Subcontractors in order to initiate, act on, review and effectively manage proje ct-related related risks throughout the Construction Phase.

IDENTIFICATION - Pre planning, Method statement , Job safety analysis.

ASSESSMENT Impact, Risk factor, Mitigation measure, Residual risk

IMPLEMENTATION & COMMUNICATION

REVIEW & UP DATE

Identify activities , Identify hazards

Assess Impacts, Analyze Risk , Establish Mitigation Measures.

Communication & Training

Audit, Inspection & Up dating of Log.

Page 2 of 7


Tasks Hazards Identified (include the exposed groups)
Probability 1-5 1-4

RISK ASSESSMENT FORM

Severity

Risk 1 - 20

Control Measures to be Implemented

Probability 1-5

Severity 1-4

Risk 1 - 20

Residual Risk

Date Action Completed

Transfer equipment

Transfer device collide with other things; Oil leakage

12

Locate the crane

Hitting injury

12

Transport

Traffic risk Collision with person Collision device

Chose a qualified driver before work Check the calibration of all tools Make sure the transport device in good condition Solid the ground Reinforce the pads beneath the outriggers Check the around circumstance before working The trucks must respect: The limited speed in the site The circulation signs The circulation plan (updated) All hose/ropes/cables in use shall be secured to the side of walkways and handrails All unnecessary materials and equipment to be immediately removed from site All exits and walkways to be kept clear for use of personnel High standard of housekeeping to be maintained at all times

Movement of traffic

3 Slip/trip/all

Page 3 of 7


Tasks Hazards Identified (include the exposed groups)
Probability 1-5 1-4

RISK ASSESSMENT FORM


Severity Risk 1 - 20

Control Measures to be Implemented

Probability 1-5

Severity 1-4

Risk 1 - 20

Residual Risk

Date Action Completed

Lifting

Fall from height and hurt workers Component fall down Component collide with other things surrounded

16

collision with person collision between frame and scaffolding collision between the crane and equipments falling materials Poor visibility for the driver

Lifting crane, forklift wires should be regularly calibrated, safe working loads are announced max speed at site is respected for all vehicle It is not allowed to work under loads Handling by qualified riggers worn the related PPE and under supervision Qualified crane operator and qualified rigger to operate lifting work Crane in calibrated period Barricade the lifting area Proper lifting tools Make sure lifting wok operated in good weather mark the area of operations of the crane officer commanding the ship maneuver through regulatory actions to avoid accidents Control of the safety catch hook the slings Ensure the crane on his dashboard that the load weight does not exceed the maximum allowed Ban the person be under a suspended load defining the radius of the rotary crane prohibit the movement of people around the handling stop the lifting operation in strong winds exceed the 50km /h

Page 4 of 7


Tasks Hazards Identified (include the exposed groups)
Probability 1-5 1-4

RISK ASSESSMENT FORM


Severity Risk 1 - 20

Control Measures to be Implemented

Probability 1-5

Severity 1-4

Risk 1 - 20

Residual Risk

Date Action Completed

Work at height (Scaffolding and Man basket) falls from height falling objects

12

the scaffolding should be based on graded soil with good foundation protect a guard with a height of 1.15 m Protection of Persons with safety harnesses protect with an end-board 10 to 15 cm high prohibit work at height if the weather affected the safety of persons Port PPE: Face shield or goggles, gloves, aprons and leggings Respiratory protection Aeration of the workspace Dilution of gas and smoke with ventilation Cleanliness of welding at risk of abrasive particles check valve and Pressure of gas cylinder Leak Detection Gas cylinders and hoses

Welding

Burn Sting Glare Gas and smock Fire and/or Explosion the gas cylinder

16

Page 5 of 7


Tasks Hazards Identified (include the exposed groups)
Probability 1-5 1-4

RISK ASSESSMENT FORM


Severity Risk 1 - 20

Control Measures to be Implemented

Probability 1-5

Severity 1-4

Risk 1 - 20

Residual Risk

Date Action Completed

Electricity

Electrocution

12

Protect electrical equipment from ingress of water Identify equipment risk Warning notices Verification of electric cables before the start of work by an electrician

Fire Explosion

3 Abrasive particles

Check the cleanness of the workplace Site emergency plan to be followed in event fire or explosion. All personnel to be inducted and aware of emergency procedures. Installation of fire extinguishers visible and accessible No smoking or naked lights

Use tools

Hand injuries crushed fingers smooth head against the frame

ensure protection adequate PPE (gloves, helmet, goggles, harness

Page 6 of 7


Tasks Hazards Identified (include the exposed groups)
Probability 1-5

RISK ASSESSMENT FORM

Severity 1-4

Risk 1 - 20

Control Measures to be Implemented

Probability 1-5

Severity 1-4

Risk 1 - 20

Residual Risk

Date Action Completed

Environmental

Pollution the air: Exhaust gas, The dust Leaking oil or diesel machines on soil

Checking the condition of equipments before beginning the work ventilation Workstation

Assessor

Print :

Sign:

Date:

Page 7 of 7

Você também pode gostar