CLAUSE.

NO FIRE FIGHTING SYSTEM


Construct ion of 220 kV S/S and Associ ated
System at Pakri Barwadih
BID DOC NO. : NESCL/ JH (CM&CW)/ CS-PB-818

IE6hd|6kL 5FE6|F|6kI|0d5
v0LNE-||, FkkI - ||


6hkFIEk- N0
Fire Fighting Syst em

Page
1 of 16

1.00.00 SEdEkkL
1.01.00 This section covers the design and performance requirements of the following types of fire
protection system
(a.) Hydrant system
(b.) High Velocity Water (HVW) Spray system for 2 no.s of 220/34.5kV 50MVA Power
Transformers.
(c.) Fire detection system
(d.) Portable fire extinguishers
(e.) Wheel/Trolly mounted fire extinguishers
1.02.00 SEdEkkL 0E5|Sd 6k|IEk|k
1.02.01 The main fire protection system shall consist of a fire water hydrant system serving the
whole substation including Employer's transformer area/control room building and DG Set
area. However, fire detection system inside the Employer's control room is covered under
the scope of another contract.
1.02.02 All equipments/system components of complete fire detection & protection system shall
have the approval from one of the following :
a) Underwriters Laboratories of USA
b) LPCB UK
c) VDS
d) FM-USA
e) BIS (For the approval of pumps and valves).
However, design and installation of complete system and requirements shall be approved
by TAC accredited professional(s) India.
1.02.03 For situations, which are not covered by the standards, system shall be supplied and
installed to ensure effective protection.
1.02.04 The complete fire detection and protection systems shall be as per the
guidelines/codes/standards/rules of the TAC/NFPA/IS :3034/OISD etc and all the systems
/equipments and installation shall be got approved from LPA /TAC accredited professionals
by the bidder to enable Employer to obtain maximum applicable rebate on insurance
premium. The responsibility of getting approval from LPA /TAC accredited professionals
rests exclusively on contractor. Any other additional equipment not specifically mentioned



CLAUSE.NO FIRE FIGHTING SYSTEM
Construct ion of 220 kV S/S and Associ ated
System at Pakri Barwadih
BID DOC NO. : NESCL/ JH (CM&CW)/ CS-PB-818

IE6hd|6kL 5FE6|F|6kI|0d5
v0LNE-||, FkkI - ||


6hkFIEk- N0
Fire Fighting Syst em

Page
2 of 16

in the technical specification but are found necessary to meet the requirements of TAC and
also for safe and sound operation of the plant are to be included at no extra cost to
Employer.
1.03.00 watet supp|y system
1.03.01 Water for hydrant and HVW Spray system shall be supplied by one electrical
motor driven pump with another driven by diesel engine, shall be used as
standby. Two no of underground water storage tanks made of RCC shall be
provided. The Capacity of water storage tanks shall be finalized by the bidder
conforming to TAC Guidelines. Construction of Borewell for fire pump house
water supply as per requirement is in the scope of bidder.
1.04.00 Ftessutisation system
1.04.01 This system consists of two (2) nos. electric motor driven jockey pumps (1 no. working + 1
no. stand-by). In the event of loss of pressure in the hydrant/spray system below a
predetermined value, the jockey pump would start.
Operation of all the pumps shall be automatic and pumps shall be brought
into operation at preset pressure. Fire pumps shall only be stopped manually. Manual
start/stop provision shall be provided in local control
2.00.00 h0kkdI 55IEN
2.01.01 System shall be pressurized continuously to normal working pressure.
2.01.02 System shall consist of Hydrant pumps, pressurisation arrangement, water mains network,
hydrant valves, landing valve, water monitors, hoses, branch pipes, nozzle, hose boxes
etc.
2.01.03 Category of Hazard and minimum terminal pressure shall be as per TAC norms.
2.01.04 Each of the landing valves and external hydrant valves associated with the switchyard area
shall be provided with a hose box. Each hose box shall contain two (2) numbers of 15 m
long hoses, branch pipes, couplings, nozzles, spanners, etc as per TAC guidelines.
2.01.05 Hydrant valves and hose couplings shall be of stainless steel construction confirming to
relevant Indian/International Standard.
2.02.00 5pecilic data
2.02.01 All hydrant valves shall be of stainless steel construction female oblique type conforming to
IS: 5290 or Equivalent.
2.02.02 Hoses shall be of non-percolating flexible type as per IS: 636 (Type-A) and or Equivalent.



CLAUSE.NO FIRE FIGHTING SYSTEM
Construct ion of 220 kV S/S and Associ ated
System at Pakri Barwadih
BID DOC NO. : NESCL/ JH (CM&CW)/ CS-PB-818

IE6hd|6kL 5FE6|F|6kI|0d5
v0LNE-||, FkkI - ||


6hkFIEk- N0
Fire Fighting Syst em

Page
3 of 16

2.02.03 Branch pipes shall be constructed of stainless steel SS-316 at both ends. One end of the
branch pipe will receive the quick coupling while the nozzles will be fixed to the other
end.
2.03.00 hose 6abinets
2.03.01 The external / internal hose cabinets shall be mounted on ground (outdoor /Wall mounted
or column mounted type depending on site conditions.
2.03.02 External & Internal hose cabinets shall have a 6 mm thick glass panel in front door with the
word FIRE painted on it with 150 mm (6) red letters.
2.03.03 External & Internal hose cabinets shall be made of 16 gauge or thicker M.S. Sheets.
2.03.04 The External & Internal hose cabinets shall have rubber bushings to prevent ingress of
water and dust.
3.00.00 hvw 5ptay 5ystem
3.01.00 Seneta|
3.01.01 This specification covers specifications and broad design basis for 220/34.5kV, 2 x 50 MVA
Power Transformers fire detection and protection system.
3.01.02 It shall consist of pressurization arrangements, water mains network, Deluge valves, alarm
valves, flow switches Isolation valves, Y-type strainers, spray nozzles/projectors / spray
nozzles piping network, detection system, instrumentation, local control panels, cables etc.
3.01.03 System shall be pressurized continuously to normal working pressure up to the Deluge
valves and spray nozzles.
3.01.04 The system shall be automatic and shall be activated by a dedicated detection system to
be provided for each of the equipment.
3.02.00 0esign Fhi|osophy (Ninimum kequitements[
3.02.01 Minimum running water pressure at any projector/spray nozzle shall be not less than
3.5kg/Sqcm and not greater than 5.0 kg/Sqcm for HVW spray system.
3.02.02 Design discharge density shall be as per the rules of water spray system of Tariff Advisory
Committee (TAC) and/or NFPA standards.
3.02.03 An isolation valve shall be provided at both upstream and downstream of each of the
deluge valve and alarm valve. The size shall be same as that of the deluge valve and
alarm valve.
3.02.04 The deluge valve (auto-resetting type) assembly shall consist of accessories such as water
motor gong, alarm test valves, drain valves, strainers for these valves, hydraulic releasing
system, solenoid valves, etc.



CLAUSE.NO FIRE FIGHTING SYSTEM
Construct ion of 220 kV S/S and Associ ated
System at Pakri Barwadih
BID DOC NO. : NESCL/ JH (CM&CW)/ CS-PB-818

IE6hd|6kL 5FE6|F|6kI|0d5
v0LNE-||, FkkI - ||


6hkFIEk- N0
Fire Fighting Syst em

Page
4 of 16

3.02.05 A strainer ('Y' type) shall be provided at upstream of deluge valve.
3.02.06 Strainer wire shall be SS (AISI 316), 30 SWG, 30 mesh. Strainer area shall be at least 4
times the pipe cross section at the pipe inlet. Pressure drop across strainer in clean
condition shall not exceed 1.5 kg/cm2 at design flow of deluge valve.
3.02.07 Pressure gauges and pressure switches at upstream and downstream of deluge valves
shall be provided.
2.02.12 The design features and make of all the projectors/ spray nozzles shall be UL/FM or
equivalent approved / listed.
2.02.14 Pressure switches shall be provided in spray and detector piping to exhibit "FIRE" and
"SPRAY ON" annunciations and interlock for tripping of respective equipment wherever
applicable.
2.02.15 Wet type detector network with venting arrangement shall be provided for spray system
using quartzoid bulb detectors.
2.02.16 Remote manual operation of the deluge valves shall be possible from the respective fire
alarm cum control panel through the keyboard operation of PC monitoring station when the
system is selected in remote manual mode. The remote manual selection for the operation
of spray system on any equipment or any zone shall also be through the monitoring station
of the respective panel. Apart from the automatic operation of the deluge valve, the system
shall have provision for manual operation of the deluge valve by means of hand operated
lever close to the deluge valve assembly. There shall also be a provision to operate deluge
valve electrically from a nearby local panel.
4.00.00 F|kE wkIEk FNF5 8 FNF h05E
4.01.00 The Fire water pumps shall be of Horizontal centrifugal type
4.02.00 Maximum speed of all the pumps to be supplied for the Fire Protection System shall be
1500 rpm. However, for jockey pumps, a speed of even upto 3000 rpm is also acceptable.
The motor driven pump and the corresponding diesel engine driven pump shall be
completely interchangeable in respect of speed, impeller, diameter etc.
4.03.00 The Capacity (minimum), discharge pressure (minimum) of pumps shall be designed as
per recommendations of TAC.
4.04.00 The operation of the pressurisation system shall be automatic and required instrumentation
and control shall be provided. Re-circulation line with required valves be provided at for
each set of the Pumps.
4.05.00 In the event of fire, pressure in the hydrant or spray system shall drop due to resulting flow.
In this event, water loss in the system will be replenished by jockey pump. However, if this
is inadequate to meet the demand and results in drop in system pressure further, at preset



CLAUSE.NO FIRE FIGHTING SYSTEM
Construct ion of 220 kV S/S and Associ ated
System at Pakri Barwadih
BID DOC NO. : NESCL/ JH (CM&CW)/ CS-PB-818

IE6hd|6kL 5FE6|F|6kI|0d5
v0LNE-||, FkkI - ||


6hkFIEk- N0
Fire Fighting Syst em

Page
5 of 16

low pressure set point, electric driven pump of the respective system shall start
automatically.
4.06.00 The diesel engine drive of the pump shall conform to the requirements of TAC. Diesel
engine shall be provided with batteries (2x100%) and battery chargers (2x100%).
4.07.00 Battery of the diesel engine shall be lead acid type as per IS and shall be large enough to
crank the engine twelve times successively, each for a duration of 10sec. without any
charging in between.
4.08.00 Each engine shall be provided with fuel oil tank having adequate capacity to hold sufficient
fuel oil for a minimum of twelve (12) hours of full load run. The fuel oil tank shall preferably
be mounted on the engine. No fuel oil tank will be provided by the Employer.
4.09.00 The continuous engine brake horse power rating (after accounting for all auxiliary power
consumption) and correction for temperature and altitude at the site conditions shall be
atleast 20% greater than the requirement at the duty point of pump at rated RPM and in no
case, less than the maximum power requirement at any condition within the operating
range of the pump.
4.10.00 Continuous drive motor rating (at 50 deg.C ambient) shall be at least 10% (ten percent)
above the maximum load demand of the pump in the entire operating range.
4.11.00 The pumps shall comply with the regulations of BIS and shall be approved by LPA /TAC
accredited professionals before installation.
4.12.00 The fire water pump house layout shall have sufficient space for the maintenance of the
pump and diesel engine.
4.13.00 Pumps shall be designed for continuous operation at its best efficiency point to meet the
specific requirements of the system for which it is to be employed.
4.14.00 Pumps shall have continuously rising head characteristic from its operating point towards
shut off without any zone of instability and power capacity characteristic shall be preferably
non-overloading type.
4.15.00 Pump shall be capable of furnishing not less than 150% of rated capacity at a head of not
less than 65% of the rated head. The shut-off head shall not exceed 120% of rated head in
the case of horizontal pumps and 140% in the case of vertical turbine type pumps. Also,
the jockey pumps shall be as per TAC requirements.
5.00.00 F|F|dS kd0 vkLvE5
5.01.00 SEdEkkL
5.01.01 Piping for all fire protection systems shall generally be laid over ground except in locations
such as road/rail crossings where it may not be feasible to route over-ground. At rail/road
crossings, fire water pipes shall be laid inside hume pipes of suitable ratings.



CLAUSE.NO FIRE FIGHTING SYSTEM
Construct ion of 220 kV S/S and Associ ated
System at Pakri Barwadih
BID DOC NO. : NESCL/ JH (CM&CW)/ CS-PB-818

IE6hd|6kL 5FE6|F|6kI|0d5
v0LNE-||, FkkI - ||


6hkFIEk- N0
Fire Fighting Syst em

Page
6 of 16

5.01.02 For calculating friction loss in piping system: WILLIAM & HAZEN formula shall be used with
C value as 100.
5.01.03 Inserts/ Embedments required for all pipe/ valve / equipment supports shall provided by the
agency providing Civil Works. However the Clamps, channels, bolts, nuts etc to
support/mount piping/valves/equipments shall be supplied and erected by the Contractor.
5.02.00 Natetia| ol 6onsttuction
5.02.01 Mild steel as per IS:1239 (Part-I) medium grade (upto 150 NB) & as per IS:3589 Gr 410
(above 200 NB) or Equivalent for pipes normally filled with water.
5.02.02 Pipe thickness:
a. For Pipe sizes upto 150 NB and above: As per IS:1239 Part-I medium grade.
b. For Pipe sizes 200 NB & above shall confirm to IS: 3589 Grade 410.
5.02.03 To prevent soil corrosion buried pipes / pipes in trench shall be properly lagged with
corrosion protective tapes of minimum thickness of 4 mm (in two layers) of coal tar type as
per IS : 15337 or AWWA C 203.
5.02.04 All valves shall be as per applicable IS/BS codes & approved by LPA /TAC accredited
professionals for specific fire protection system and shall be provided with locking
arrangement (with locks) in open or close condition. Further, all gate/butterfly valves of size
200 mm & above shall be provided with spur gear reduction unit.
5.02.05 All the flanges and counter flanges shall conform to ANSI B 16.5 CI 150.
5.02.06 Unless otherwise specified all elbows / bends shall be long radius type.
5.02.07 For pipe fittings the material shall conform to ASTM A 234 Gr WPB or ASTM A 105 or
equivalent and dimensional standard conforming to ANSI B16.11 (socket & threaded type),
ANSI B 16.9 (for butt welded fittings) and ANSI B16.5 (for flanges and flanged fittings) as
the case may be. Further, Galvanised malleable Cast Iron fittings as per IS 1879 or Cast
Iron fittings as per BS-1641 are also acceptable.
5.02.08 The fittings shall be galvanized as per IS:4736 for galvanized pipe application.
5.02.09 In case of branching connections from GI mains for spray piping network, socket may be
welded for more than two pipe reduction instead of standard tees.
5.02.10 Fabricated fittings shall not be acceptable up to pipe size of 300 NB. For sizes 350 NB and
above, fittings may be fabricated as per BS:2633 / BS:534.
5.02.11 Set on set in type fittings shall not be acceptable.
5.02.12 Welding of Galvanised iron pipes/fittings would be permitted provided the same is carried
out by means of special electrodes suitable for the above application and the same shall be



CLAUSE.NO FIRE FIGHTING SYSTEM
Construct ion of 220 kV S/S and Associ ated
System at Pakri Barwadih
BID DOC NO. : NESCL/ JH (CM&CW)/ CS-PB-818

IE6hd|6kL 5FE6|F|6kI|0d5
v0LNE-||, FkkI - ||


6hkFIEk- N0
Fire Fighting Syst em

Page
7 of 16

approved by Employer. After welding, welded portions shall be applied with three coats of
Zinc silicate treatment /rich paint over one coat of suitable primer. Further the Contractor
shall provide proper zinc paint at the point of welding.
5.02.13 Stooved coup|ing : Vendor may also use mechanical grooved couplings type fittings in GI
pipe lines for HVW spray system. All materials and products shall be either Underwriters
Laboratories (UL) Listed or Factory Mutual (FM) Approved and installed in accordance with
NFPA Standard 13 / equivalent Standard.
5.02.14 The fittings shall be galvanized as per IS:4736 for galvanized pipe application.
5.02.15 In case of branching connections from GI mains for spray piping network, socket may be
welded for more than two pipe reduction instead of standard tees.
5.02.16 Fabricated fittings shall not be acceptable up to pipe size of 300 NB. For sizes 350 NB and
above, fittings may be fabricated as per BS:2633 / BS:534.
5.02.17 Set on set in type fittings shall not be acceptable.
5.02.18 Welding of Galvanised iron pipes/fittings would be permitted provided the same is carried
out by means of special electrodes suitable for the above application and the same shall be
approved by Employer. After welding, welded portions shall be applied with three coats of
Zinc silicate treatment /rich paint over one coat of suitable primer. Further the Contractor
shall provide proper zinc paint at the point of welding.
0.00.00 F|kE wkIEk 5I0kkSE 55IEN
6.01.00 Two numbers each of 50% capacity underground fire water storage tanks shall be provided
by the bidder. The fire water storage tanks shall be with RCC. The grade of concrete shall
be 1:1.5:3. Bidder shall ensure that the total capacity of fire water storage shall be as per
the recommendation of TAC.
6.02.00 The discharge pipe each of the tank shall be interconnected through isolation valve. From
the discharge headers, individual suction lines with isolation valve & strainer shall be
provided for each of the pump.
6.03.00 Each tank shall be provided with Level indicators, ultrasonic type level transmitters. The
instrumentation and control shall include annunciations of low-level, very low level, high
level, automatic opening of make up water connection at low level, closure of valves at high
level etc as per system requirement.
7.00.0 NLI|FkF05E d0IILE
The multipurpose nozzle should be such that water under pressure is applied on fire in the
form of a jet, spray or fog. Material of construction for multipurpose nozzle shall be as per
manufacturers standard.
8.00.00 Fk|dI|dS



CLAUSE.NO FIRE FIGHTING SYSTEM
Construct ion of 220 kV S/S and Associ ated
System at Pakri Barwadih
BID DOC NO. : NESCL/ JH (CM&CW)/ CS-PB-818

IE6hd|6kL 5FE6|F|6kI|0d5
v0LNE-||, FkkI - ||


6hkFIEk- N0
Fire Fighting Syst em

Page
8 of 16

8.01.00 All the Equipments shall be protected against external corrosion by providing suitable
painting.
8.02.00 The surfaces of stainless steel, Gunmetal, brass, bronze and non-metallic components
shall not be applied with any painting.
8.03.00 The Contractor shall clean the external surfaces and internal surfaces before Erection by
wire brushing and air blowing. The steel surface to be applied with painting shall be
thoroughly cleaned before applying painting by brushing, shotblasting etc as per the
agreed procedure.
8.04.00 Painting of all equipments /.components of FDPS package shall be as per manufacturers
standard practice or as detailed below whichever is superior in quality.

Envitonment Faint scheme Iota| 0FI
Normal / Mild
Corrosive
Environment
Primer- zinc filled epoxy
Finish Aliphatic Polyurethane (shade
RAL3000)(P.O Red)
Min 125 microns
Corrosive
Environment
(as in coastal
areas)
Primer- zinc filled epoxy
Intermediate Epoxy MIO
Finish Aliphatic Polyurethane (shade
RAL3000)(P.O Red)
Min 200 microns
9.00.00 ELE6Ik|6 N0I0k5
9.01.00 Seneta| kequitements
9.01.01 For the purpose of design of equipment/systems, an ambient temperature of 50 deg.
Centigrade and relative humidity of 95% shall be considered. The equipment shall operate
in a highly polluted environment
9.01.02 All equipments shall be suitable for rated frequency of 50 Hz with a variation of +3% & -5%,
and 10% combined variation of voltage and frequency unless specifically brought out in the
specification.
9.01.03 Contractor shall provide fully compatible electrical system, equipments, accessories and
services.
9.01.04 All the equipment, material and systems shall, in general, conform to the latest edition of
relevant National and international Codes & Standards, especially the Indian Statutory
Regulations.



CLAUSE.NO FIRE FIGHTING SYSTEM
Construct ion of 220 kV S/S and Associ ated
System at Pakri Barwadih
BID DOC NO. : NESCL/ JH (CM&CW)/ CS-PB-818

IE6hd|6kL 5FE6|F|6kI|0d5
v0LNE-||, FkkI - ||


6hkFIEk- N0
Fire Fighting Syst em

Page
9 of 16

9.01.05 It shall be designed to limit voltage variations as given below under worst operating
condition :
415/240V +/- 10%
9.01.06 The voltage level for motors shall be as follows :-
9.01.06.1 Upto 0.2 KW : 240V, Single phase AC, or 415V, Three phase AC
9.01.06.2 Above 0.2KW to 200 KW : 415V, Three phase AC
9.01.07 Fault level shall be 45 KA RMS 1 second for 415V system. 415V system shall be solidly
grounded .
9.01.08 Paint shade shall be RAL 5012 (Blue) for indoor and outdoor equipment.
9.01.09 The responsibility of coordination with other agencies and obtaining all necessary
clearances shall be of the contractor.
9.01.10 Degree of Protection
Degree of protection for various enclosures as per IS:13947 shall be as follows :-
i) Indoor motors IP 54
ii) Outdoor motors IP 55
9.02.00 600E5 kd0 5Ikd0kk05
1.) Three phase induction motors : IS:325, IEC:34
2.) Single phase AC motors : IS:996, IEC:34
9.03.00 IFE
9.03.01 AC Motors:
9.03.01.1 Squirrel cage induction motor suitable for direct-on-line starting.
9.04.00 kkI|dS
9.04.01.1 Continuously rated (S1).
9.04.01.2 maximum continuous motor ratings shall be at least 10% above the maximum load
demand of the driven equipment under entire operating range including voltage and
frequency variations.
9.05.00 IENFEkkIkE k|5E
Air cooled motors



CLAUSE.NO FIRE FIGHTING SYSTEM
Construct ion of 220 kV S/S and Associ ated
System at Pakri Barwadih
BID DOC NO. : NESCL/ JH (CM&CW)/ CS-PB-818

IE6hd|6kL 5FE6|F|6kI|0d5
v0LNE-||, FkkI - ||


6hkFIEk- N0
Fire Fighting Syst em

Page
10 of 16

70 deg. C by resistance method for both class B&F insulation.
9.06.00 0FEkkI|0dkL kEq|kENEdI5
9.06.01 5tatting Iime
9.06.01.1 For motors with starting time upto 20 seconds at minimum permissible voltage during
starting, the locked rotor withstand time under hot condition at highest voltage limit shall be
at least 2.5 second more than starting time .
9.06.01.2 For motors with starting time more than 20 second and upto 45 seconds at minimum
permissible voltage during starting, the locked rotor withstand time under hot condition at
highest voltage limit shall be at least 5 second more than starting time.
9.06.01.3 Speed switches mounted on the motor shaft shall be provided in cases where above
requirements are not met.
9.07.00 Iotque kequitements
9.07.01 Accelerating torque at any speed with the lowest permissible starting voltage shall be at
least 10% motor full load torque.
9.07.02 Pull out torque at rated voltage shall not be less than 205% of full load torque. It shall be
275% for crane duty motors.
9.08.00 5tatting vo|tage tequitement
(a) 85% upto 110KW
(b) 80% from 111KW to 200KW
9.09.00 0E5|Sd kd0 60d5Ik6I|0dkL FEkIkE5
9.09.01 Suitable single phase space heaters shall be provided on motors rated 30KW and above to
maintain windings in dry condition when motor is standstill. Separate terminal box for space
heaters & RTDs shall be provided.
9.09.02 All motors shall be either Totally enclosed fan cooled (TEFC) or Totally enclosed tube
ventilated (TETV) or Closed air circuit air cooled (CACA) type.
9.09.03 Winding and Insulation
(a) Type : Non-hygroscopic, oil resistant, flame resistant
(b) Starting duty : Two hot starts in succession, with motor initially
at normal running temperature.
(d) 415V AC : Class B



CLAUSE.NO FIRE FIGHTING SYSTEM
Construct ion of 220 kV S/S and Associ ated
System at Pakri Barwadih
BID DOC NO. : NESCL/ JH (CM&CW)/ CS-PB-818

IE6hd|6kL 5FE6|F|6kI|0d5
v0LNE-||, FkkI - ||


6hkFIEk- N0
Fire Fighting Syst em

Page
11 of 16

motors
9.09.04 Noise level and vibration shall be limited within the limits prescribed in IS: 12065 & IS:
12075 respectively. Motors shall withstand vibrations produced by driven equipment. Motor
body shall have two earthing points on opposite sides.
9.09.05 All motors shall be so designed that maximum inrush currents and locked rotor and pullout
torque developed by them at extreme voltage and frequency variations do not endanger
the motor and driven equipment.
9.09.06 The motors shall be suitable for bus transfer schemes provided on the 415V systems
without any injurious effect on its life.
9.09.07 The ratio of locked rotor KVA at rated voltage to rated KW shall not exceed the following
(without any further tolerance)
(A) UPTO 110KW 11.0
9.10.00 IFE IE5I
9.10.01 LT MOTORS
9.10.02 LT motors shall be of type tested quality. For each type & rating of LT motors rated above
50 KW, the contractor shall submit for Owners approval the reports of all the type tests as
per relevant standards and carried out within last ten years from the date of bid opening.
These reports should be for the tests conducted on the equipment similar to those
proposed to be supplied under this contract and the test(s) should have been either
conducted at an independent laboratory or should have been witnessed by a client.
9.10.03 In case the Contractor is not able to submit report of the type test(s) conducted within last
ten years from the date of bid opening, or in case the type test report(s) are not found to be
meeting the specification requirements, the Contractor shall conduct all such tests under
this contract free of cost to the Owner and submit the reports for approval.
9.11.00 All acceptance and routine tests as per the specification and relevant standards shall be
carried out. Charges for these shall be deemed to be included in the equipment price.
TABLE - I
DIMENSIONS OF TERMINAL BOXES FOR LV MOTORS
Notot N6k in kw Ninimum distance between centte ol stud and
g|and p|ate in mm
UP to 3 KW As per manufacturer's practice.
Above 3 KW - upto 85



CLAUSE.NO FIRE FIGHTING SYSTEM
Construct ion of 220 kV S/S and Associ ated
System at Pakri Barwadih
BID DOC NO. : NESCL/ JH (CM&CW)/ CS-PB-818

IE6hd|6kL 5FE6|F|6kI|0d5
v0LNE-||, FkkI - ||


6hkFIEk- N0
Fire Fighting Syst em

Page
12 of 16

7 KW
Above 7 KW - upto 13
KW
115
Above 13 KW - upto
24 KW
167
Above 24 KW - upto
37 KW
196
Above 37 KW - upto
55 KW
249
Above 55 KW - upto
90 KW
277
Above 90 KW - upto
125 KW
331
Above 125 KW-upto
200 KW
203
For HT motors the distance between gland plate and the terminal studs shall not
be less than 500 mm.

d0IE: Minimum inter-phase and phase-earth air clearances for LT motors with lugs
installed shall be as follows:
Notot N6k 6|eatance
Upto 110KW 10.0mm
Above 110KW and
Upto 150KW
12.5mm
Above 150KW 19.0mm
10.00.00 60dIk0L kd0 |d5IkNEdIkI|0d
10.01.00 Seneta| kequitements
10.02.00 The Contractor shall provide Independent Control & Instrumentation system for control,
monitoring and operation of associated drives and auxiliaries in all regimes of operation in
safe and most efficient manner including Panels/ Desks, Process Connection and Piping,
charges & batteries, associated Instrumentation Cables etc. as identified in the specification.



CLAUSE.NO FIRE FIGHTING SYSTEM
Construct ion of 220 kV S/S and Associ ated
System at Pakri Barwadih
BID DOC NO. : NESCL/ JH (CM&CW)/ CS-PB-818

IE6hd|6kL 5FE6|F|6kI|0d5
v0LNE-||, FkkI - ||


6hkFIEk- N0
Fire Fighting Syst em

Page
13 of 16

10.03.0 Bidder shall include in his proposal and shall furnish all equipment, devices and services
which may not be specifically stated in the specification but are needed for completeness of
the equipment/systems furnished by the Bidder and for meeting the intent and requirements
of the specification.
10.04.0 The reference ambient temperature outside panel shall be taken as 50
0
C and relative
humidity 100%