1 Earth Cutting 230500 M

3
Excavator of 1 Cu. M bucket capacity, excavates 60 Cu. M / hour
In 12 hours excavation of earth = 720 Cu. M
4 excavators deployment would excavate = 720 X 4 = 2880 Cu. M
Hence, to excavate 105000 Cu. M earth, time reqd.
230500 / 2880 = 80 Days. 20 % for loss time, 96 Days = 3.2 Months Say 4 months
2 Earth cutting & Filling 1651250 M
3
(Lead 2 to 3 K M)
Assumptions:
a) Cutting & Filling time by excavator into 15 Cu. M Hyva 6 Minutes
b) Time taken by Hyva to transport earth from 3 K M distance (Up and down) 22 Minutes
Hence,
One excavator can cut and fill 15 Cu. M Hyva in one hour = 10 Nos. Say 8 Hyvas
Hyva can make 3 trips in one hour (10 + 10 + 2 Minutes for dumping) = 22 Minutes
One set of excavator & Hyva (1 Excavator + 8 Hyva) can transport earth = 8 X 15 = 120 Cu. M
Considering for compaction as 80 % of the transported earth = 120 X 0.80 = 96 Cu. M / Hour
In one shift, Qty. of earth transported = 96 X 6.50 = 624 Cu. M
Hence in 1.5 shift, Qty. of earth transported = 624 X 1.50 = 936 M
3
Total earth to be transported = (1651250 - 230500) = 1420725 M
3
Qty. of earth reqd. to be transported in 6 months = 1420725 / 180 = 7893 M
3
No. of Eqipment set (1 Excavator + 3 Hyva) reqd. to be engaged 0n / day bassis = 7898 / 936 =
7893 / 936 = 8.43 Sets Say, 9 Sets . For breakdown etc. 9 + 3 = 12 Sets are reqd. 6 Months
to meet the requirement on daily basis.
12 Excavators of 60 Cu. / Hour
96 Hyvas of 15 Cu. M capacity
3 Compaction of earth Qty. 1651250 M
3
Using Vibro Roller , Speed = 15 K M / Hour
Assumptions:
In one hour, 300 mm thick soil, 2.50 M wide and 1000 M stretch is compacted
Compacted volume / Hour = 1000 X 2.50 X 0.30 = 750 M
3
So in one shift (6.5 Hours), volume of compacted earth = 4875 M
3
In 1.50 shift volume of compacted earth = 1.5 X 4875 = 7312.50 M
3
No. of days reqd. to compact 1651250 / 7312 = 226 Days
7.50 Months Say 8 Months
4 Blanketting of Morrum over Formation level 174120 M
3
Blanketting 8 / 1651250 X174120 = 0.84 Month Say 1.50 Months
5 Construction of Bridge 22 Nos.
6 For 1 K M Track Length
Assuming, Two gangs of 40 people each
Spreading 100 to 150 mm thick ballast, sleeper and rail over the Formation level
For above job Days Reqd. 12 Days
For Linking job Days Reqd. 12 Days
Total 24 Days
Deployment of 4 gangs will cover 4 K M
Hence, No. of gangs reqd. to cover 27 K M Track Length 27 / 4 = 6.75 Months Say 7 Months
7 Signalling & Telecommunication jobs at Kamradol station yard & In - Plant area Say 5 Months
8 KAMRADOL Station yard jobs ( Buildings, Control rooms etc) Say 6 Months
9 Construction of Control rooms etc. at In - Plant area Say 4 Months