Harris Stratex Networks

Eclipse Terminal Installation and Commissioning Forms


Rev 3 June 07
Introduction

Purpose is to provide:
A prompt for preparing data for new installations.
A datapack for installers.
A data entry form to capture additional as-built data.
An as-built record with sign-off.

Associated forms included in this file are:
Installation Inspection Form
Customer Acceptance Form
Remedial Action Form

Navigation:
The Master Site Data column lists entries required. Click on a
+ tab at the far left of the screen to open up required data
entry rows. Click tab to close.
The Build / As-Built Data column is for data entry. Build data
is data to be entered at the planning (datapack prep) stage. As-
built data is data to be entered at site, mostly from Portal.
The Portal column highlights the data to be entered into Portal
and data to be entered from Portal.
The Comments column is to capture any additional data.

See the Example Form for additional guidance.

Forms can be printed.

Important! Please provide feedback on the use of these forms.
Feedback is needed to provide guidance on what improvements should
be made to assist the application and usability of these forms. Please
send feedback to:
Director Installation Practices
Director of Services, Americas
Global Technical Support manager
Eclipse Terminal Forms: V1.1 June06 Commercial-In-Confidence 1
Harris Stratex Networks
Eclipse Terminal Installation and Configuration Form For Site:
Installer:
Installer Contact Details:
Scheduled Start Date:
Scheduled Completion Date:
New or Existing Site:
Electrical Supply OK yes/no:
Site Grounding OK yes/no:
Antenna Mounts OK yes/no:
Site Security OK yes/no:
Site Plans Included yes/no:
Master Site Data Build / As-Built Data Portal
Entry To
Comments
Terminal
IDU type To
ODU type
Terminal name To
Site name To
Site grid reference To
Tech services contact details To
NOC contact details
Site location
Site access See attached map
Rack number/name
IDU location in rack
Chassis serial number (All serial numbers begin with three letters)
-48Vdc power supply connection
Networking
Terminal IP address To
Subnet mask To
Static or dynamic routing To
Static routing data
DHCP yes/no; address range To
Trap destinations To
Link/Radio
Link name/number To
Remote end site name To
Remote end terminal/node name To
Local antenna type
Local antenna diameter
Antenna serial number
Height on tower / pole mount ID `
Initial pointing (compass/map ref)
Polarization
ODU direct mounting, yes/no
ODU serial number
ODU cable length required
Protected yes/no To
Link protection type To
Trib protection type (TT or TA) To
Tx frequency To
Rx frequency To
T/R spacing To
Tx power To
Detected forward power From
Capacity To
Modulation
ATPC yes/no To
ATPC data
Expected RSL
Indicated RSL From
Expected RSSI
Indicated RSSI From
Expected fade margin
Measured fade margin From
G.826 link check From
Alarms check From
Performance check From
E1 Tributaries
General Instructions:
To = Enter into Portal
From = Enter from Portal
Terminal I+C Form: V1.1 June06 Commercial-In-Confidence 2
Harris Stratex Networks
DS1 Tributaries
STM1/OC3 Tributary
Ethernet Ports
AUX
Auxiliary port
Type, port settings, name To
Circuit name To
Alarm I/O
Alarm actions
Date/Time
(Specify Date/Time setting) To
BER Circuit Checks
Trib-trib BER check
(Specify the trib[s] and period)
From
Alarms exit check
Active alarms yes/no From
Ground checks
Single point bldg ground y/n
Master Ground Bar resistance
Rack to MGB resistance
-48V PSU to MGB resistance
Tower ground resistance(s)
Other resistance readings
Meter used
Site Inspection Report completed
yes/no
Hardware Installation completed
Name:
Signature:
Date:
Node Installation & Tests completed
Name:
Signature:
Date:
Completion Comments
Terminal I+C Form: V1.1 June06 Commercial-In-Confidence 3
Harris Stratex Networks
Eclipse Terminal Installation and Configuration Form For Site: Plaza
Installer: Joeseph Brown
Installer Contact Details: 021 362 700
Scheduled Start Date: 15-Sep-05
Scheduled Completion Date: 18-Sep-05
New or Existing Site: Existing
Electrical Supply OK yes/no: Yes
Site Grounding OK yes/no: Yes
Antenna Mounts OK yes/no: Yes
Site Security OK yes/no: Intruder alarm has been disabled
Site Plans Included yes/no: Yes
Master Site Data Build / As-Built Data Portal
Entry To
Comments
Terminal
IDU type IDU 20x
ODU type ODU 300hp
Terminal name E116 To
Site name Plaza To
Site grid reference Eastxxx Southxxx To
Tech services contact details 021 362 701 To
NOC contact details 021 362 702 To
Site location 10km East of Masterton
Site access Off Murrays Road See attached map
Rack number/name 1A
IDU location in rack Directly under terminal E10
Chassis serial number LES00934567 (All serial numbers begin with three letters)
-48Vdc power supply connection Provide and install 5A Cct Breaker on supply
panel at top of rack
Networking
Terminal IP address 192.168.11.1 To
Subnet mask 225.225.255.0. To
Static or dynamic routing RIP 2 To
Static routing data N/A
DHCP yes/no; address range Yes, 192.168.11.2 to 192.168.11.10 To
Trap destinations N/A To
Link/Radio
Link name/number Plaza-Weston To
Remote end site name Weston To
Remote end terminal/node name E109 To
Local antenna type VHLP2-180-EX
Local antenna diameter 0.6M
Antenna serial number AN35239
Height on tower / pole mount ID 28M `
Initial pointing (compass/map ref) 183 degrees
Polarization Vertical
ODU direct mounting, yes/no Yes
ODU serial number SNA7687988
ODU cable length required 40m
Protected yes/no No To
Link protection type N/A To
Trib protection type (TT or TA) N/A To
Tx frequency 17.85 GHz To
Rx frequency 18.25 GHz To
T/R spacing 400 MHz To
Tx power 17 dBm To
Detected forward power 17.1 dBm From
Capacity 20xE1 To
Modulation 16 QAM To
ATPC yes/no No To
ATPC data
Expected RSL -51 dBm
Indicated RSL -50 dBm From
Expected RSSI 1.25
Indicated RSSI 1.27 From
Expected fade margin 35 dB
Measured fade margin 37 dB From
G.826 link check Zero errors over 14 hours From
Alarms check No active alarms From
Performance check All indications normal From
E1 Tributaries
General Instructions: 4-wheel drive access only. This time of the
year the track will be wet and slippery. Please do a battery check
and run the back-up diesel generator for about 30 mins and check
associated panel lights. Should all be green.
To = Enter into Portal
From = Enter from Portal
Terminal I+C Form V1.1 June06 Commercial-In-Confidence 4
Harris Stratex Networks
Master Site Data Build / As-Built Data Portal
Entry To
Comments
Bal or Unbal Unbal To
No. tribs req. 18 To
Trib names Pla/Wes 1 - 18 To
Circuit names Pla/Wes 1 - 18
Connect to Rack BNC panel: ports 1 to 18
E1 Tributaries
DS1 Tributaries
STM1/OC3 Tributary
Ethernet Ports
AUX
Auxiliary port
Type, port settings, name Sync, default, Aux Plaza/Weston To
Circuit name Bel/Lak To
Alarm I/O
Input 1, active condition Digital input, active high To Wire to intruder alarm: alarm is active when circuit
is broken.
Input 2, active condition To
Output 1, active condition To
Output 2, active condition To
Output 3, active condition To
Output 4, active condition To
Alarm I/O
Alarm actions
Destination IP address, slot, and output.
Trigger(s).
192.168.2.1, slot 4, output 2.
AUX alarm input 1.
To At commissioning check that the destination
output (bell) at Belmont activates when the
intruder alarm is activated. Also check that the
alarm event is raised at the NOC.
Destination IP address, slot, and output.
Trigger(s).
To
Destination IP address, slot, and output.
Trigger(s).
To
Destination IP address, slot, and output.
Trigger(s).
To
Destination IP address, slot, and output.
Trigger(s).
To
Alarm actions
Date/Time
(Specify Date/Time setting) Sync to Portal PC Date/Time To
BER Circuit Checks
Trib-trib BER check
(Specify the trib[s] and period)
BER check completed on trib 2 to Weston. No
errors over 12 hours.
From
Alarms exit check
Active alarms yes/no No active alarms From
Ground checks
Single point bldg ground y/n Yes
Master Ground Bar resistance 0.62 ohms
Rack to MGB resistance 0.15 ohms
-48V PSU to MGB resistance 0.27 ohms
Tower ground resistance(s) Not possible to measure. Cannot get meter jaws
around the ground straps.
Other resistance readings
Meter used Prova clamp-on, model DX Serial number 00458
Hardware Installation completed
Name: Joe Brown
Signature:
Date: 18 September 2005
Node Installation & Tests completed
Name: Joesphine Brown
Signature:
Date: 18 September 2005
Completion Comments Road access is OK.
Terminal I+C Form V1.1 June06 Commercial-In-Confidence 5
Harris Stratex Networks
Master Site Data Build / As-Built Data Portal
Entry To
Comments
Shelter door hinges very corroded.
Checked diesel generator & all OK
Terminal I+C Form V1.1 June06 Commercial-In-Confidence 6
Harris Stratex Networks
Eclipse Terminal Installation Inspection Report For Site:
Check for correct and complete installation of:
Item Pass Fail Comments
Antenna Mounting
Antenna side support (if used)
ODU fastening
ODU grounding
ODU connector weatherproofing
ODU cable fastening
ODU cable grounding
Lightning surge suppressor(s)
IDU location in rack
IDU is labelled (if required)
IDU grounding
IDU power supply wiring
Trib cables are correctly and neatly installed
Trib cables are numbered (if required)
Alarms all-clear
Site left clean and tidy
Site photos taken (if required)
Site ground measurements (if required)
Checked by:
Name:
Signature:
Date:
Additional Comments:
Terminal Inst. Insp. Report: V1.0 Mar04 Commercial-In-Confidence 7
Harris Stratex Networks
Eclipse Terminal Customer Acceptance Form
Site Name:
Eclipse Terminal Name:
Related documents Received Yes/No
Eclipse Installation and Commissioning Form:
Eclipse Installation Inspection Report:
Acceptance Category* Category
Accepted / Conditionally Accepted / Not Accepted:
*If conditionally accepted or not accepted, the action required to
achieve acceptance must be detailed in a Remedial Action Form
Signed By:
Customer
Name:
Signature:
Title:
Date:
Harris Stratex Networks
Name:
Signature:
Title:
Date:
Terminal Acceptance Form V.1.0 Mar04 Commercial-In-Confidence 8